application of robust portfolio modelling to the...
TRANSCRIPT
-
Mat-2.108 Independent Research Project in Applied Mathematics November 20, 2005
Application of Robust Portfolio Modelling to
the Management of Intellectual Property Rights
Helsinki University of Technology Systems Analysis Laboratory Antti Malava 64705M Department of Engineering Physics and Mathematics
-
Contents
CONTENTS .....................................................................................................................2
1. INTRODUCTION..........................................................................................................3
2. PATENTS AS INTELLECTUAL PROPERTY...................................................................5
2.1. Background of Patenting ................................................................................5
2.2. Patent Portfolio Valuation Approaches..........................................................6
3. ROBUST PORTFOLIO MODELLING – A THEORETICAL FRAMEWORK......................8
3.1. Representation of Additive Value....................................................................9
3.2. Incomplete Information.................................................................................10
3.3. Additional Constraints ..................................................................................11
3.4. Non-dominated Portfolios.............................................................................11
3.5. Additional Information .................................................................................12
3.6 Robustness......................................................................................................12
4. CASE STUDY ON PATENT PORTFOLIO ....................................................................14
4.1. Problem Statement ........................................................................................14
4.2. Modelling the Problem .................................................................................14
4.3. Experimental Design.....................................................................................15
4.4. Results ...........................................................................................................15
5. DISCUSSION AND CONCLUSIONS .............................................................................18
6. REFERENCES............................................................................................................20
7. APPENDICES.............................................................................................................22
2
-
1. Introduction
For a company operating in fast-changing, particularly uncertain high-tech market,
systematic management of project portfolio is an important aspect of its strategic
decision-making process. Research and Development (R&D) activities, for example,
represent a typical such environment.
A simple theoretical approach would model the portfolio selection as a single
objective Capital Budgeting Problem that maximises portfolio without violating
resource constraints (e.g. Luenberger 1998). The most used Capital Budgeting
methods include Net Present Value (NPV), Internal Rate of Return (IRR), Discounted
Cash Flow (DCF) and Payback Period (Investopedia, 2005).
In reality, however, this kind of methodology can rarely be applied for several
reasons. Firstly, the value of projects often traces to their performance against several
criteria rather than one (not all of which are necessarily quantitative). Secondly, rather
than considering the portfolio selection as a single objective problem, the company
may have multiple, conflicting and even incommensurate aims (Liesiö et al, 2005)
likewise with their company-wide strategy. Thirdly, and perhaps most importantly, a
standard Capital Budgeting Problem cannot accommodate incomplete information
with regards to criteria weights and criterion-specific performance levels. The
availability of incomplete, uncertain information about project performance against
different criteria, however, is very often a realistic situation – after all, most projects
are novel without reliable historical reference projects to give indication of
performance levels.
Robust Portfolio Modelling (RPM), a recently developed extension of Preference
Programming of the Helsinki University of Technology, takes into account all of the
issues above and provides a flexible framework for mathematical assessment of the
portfolio selection problem. RPM is a decision support framework that makes little
demands on the data and, rather than suggesting a single optimal portfolio, produces a
set of non-dominated (also Pareto-efficient) portfolios and performance measures to
assess the robustness of the portfolio and the proposed projects.
In this paper, RPM methodology is applied to support Intellectual Property Right
(IPR) portfolio management. The study was conducted in co-operation with
Asperation Oy, a joint Research & Development company of Perlos Corporation and
3
-
Aspocomp Group Oyj1 (Asperation Oy, 2005). Asperation’s innovations concentrate
around audio, optical, radio frequency and other technologies connected to
mechanics, and printed circuit board technology (Perlos Oyj, 2005). Management of
the IPRs related to these innovations are of utmost strategic importance for Asperation
to sustain competitive advantage in future. The purpose of the study is to evaluate the
RPM framework in a real case and to present Asperation a theoretical decision
support tool for patent portfolio optimisation and management. These aims are in line
with Asperations’ larger scope of adapting a more systematic methodology for their
project portfolio management practises.
The rest of this paper is structured as follows. Section 2 Discusses Intellectual
Property Rights background, while Section 3 introduces the theoretical framework of
Robust Portfolio Modelling. In section 4, RPM is applied to the case of IPR portfolio
management. Approach to modelling together with practical issues and results are
discussed. Section 5 draws conclusions from the case study.
1 On September 1st, in the middle of the study, the functions of Asperation were divided between
Aspocomp and Perlos (Perlos Oyj, 2005). The study was continued with Perlos.
4
-
2. Patents as Intellectual Property
2.1. Background of Patenting
Patents, trade secrets, trademarks and copyrights are all a form of intellectual property
that can be protected. This paper concentrates on patents. Patents are intangible assets,
whose value lies within their right that prohibits others by law to professionally
exploit the underlying invention. Producing, selling, importing or using the patented
method is regarded as professional exploitation (National Board of Patents and
Registration of Finland, 2005). Patents can be granted for inventions that are new,
innovative and industrially practicable. In other words, just an idea cannot be
patented.
Patents and other intellectual property are objects of international co-operation and
corresponding regulation (Ernst & Young, 2000) administered by World Intellectual
Property Organization (WIPO). Patent applications can be filed nationally with the
country’s patent office, or internationally using systems such as Patent Cooperation
Treaty (PCT) or European Patent Convention (EPC). The prohibition law is
applicable within the geographical area it was granted, and it is usually valid for a
maximum of 20 years, subject to yearly payments for keeping the underlying patent
valid.
The statistics show that the number of nation-wide patens granted in Finland has been
decreasing slightly within the last 10 years from about 2400 to about 2100 (National
Board of Patents and Registration of Finland, 2005). At the same time, however, the
number of European patents granted in Finland has increased from zero-level2 to
about 6000. This rapid increase of European and international patents has prompted
companies to find methods to systematically evaluate and manage patent portfolios as
global entities, part of their larger-scope strategies.
The creation, protection and utilisation of intellectual property are recognised as
issues of all stakeholders, including government and industry (Asian Productivity
Organization, 2004), because they directly affect country’s competitiveness in global
markets. Therefore a number of governmental initiatives around the world have been
2 Finland joined the EPC and the EPO in 1996 and is also a member of WIPO.
5
-
started to not only support the risky process of intellectual property protection, but
also to inform businesses about the importance of systematic management of
intellectual property as part of their strategies. For example, the government of Japan
has established an intellectual property strategic centre that brings together the
government, academia and industry to tackle the problems. Similarly, the Danish
government has addressed the issues of intellectual property in their wider strategy for
improving business development.
2.2. Patent Portfolio Valuation Approaches
The management of tangible assets has a solid basis through many years of research
and the exchange of experience, whereas the management and evaluation of
intangible assets in a strategic way is still not much further than in experimental stage.
Ernst & Young research (2000) revealed, for example, that nine out of ten Danish
companies expected the importance of evaluating the value of their patents and
management of patent portfolio to increase, but only a few could identify actual
methods for doing this. Similarly, although it is estimated that substantially more than
half of the total value of publicly listed US companies arises from intangible assets,
three out of four companies do not assign any value to their intellectual capital (Asian
Productivity Organization, 2004). The core of the problem relates to the difficulties of
valuation, much of which is performed only in connection with purchases, sales,
licensing agreements. The awareness and perceived benefits of IPR are lacking
especially in many small and medium companies that do not see the relevance of IPRs
to their business.
Considering theoretical perspectives, although decision analysis has been widely
accounted for in the literature in connection to different areas of tangible issues such
as healthcare, engineering and project management, very little can be found about
decision analysis methods applied to intangible assets management. Some individual
research contributions exist but there seems to be no clear consensus. The few
mathematical valuation methods used in the field of IPR do come from the field of
decision analysis and relate to evaluating preferences by approximation (such as
PRIME) or through intervals (such as PAIRS) or indirectly by considering
hypothetical alternatives’ value (such as SWING). More quantitative models are some
extensions of Net Present Value or other basic financial methods. Because of the
6
-
difficulties related to capture uncertainty in mathematical models, subjective methods
of valuation such as Delphi technique, expert opinions and are still widely used and
decisions are often made based on “feeling”.
Patenting institutions have begun to notice the need for companies to develop patent
portfolio management methods. For example, as part of Danish Government’s wider
strategy for improving business development, Danish Patent and Trademark Office
recently addressed this issue by developing a software tool to “identify untapped
business potential” (Nielsen, 2003). The tool, IPscore 2.0, presents a systematic
evaluation – both qualitative and quantitative – in the form of financial forecast
estimating the internal net present value (i.e. not market value) of the evaluated
technology. Input is gathered with questionnaires to ensure comprehensive evaluation
(such as evaluations at various stages during the project lifetime), and output is
provided both numerically and graphically.
To take a new, academically orientated approach to patent portfolio valuation and
management, Robust Portfolio Optimisation is presented and applied in this paper.
7
-
3. Robust Portfolio Modelling – a Theoretical Framework
Multiple Criteria Optimisation (also referred to as Multiple Objective Optimisation)
has been and continues to be a classical field of study in Operational Research (Liesiö
et al, 2004). Over the years this area has evolved, and recently the focus has been to
provide easily applicable, user-friendly methods that accommodate the use of
incomplete information with regards to required data (Liesiö, 2004). In other words,
the methods seem to be developing more and more useful to real problems rather than
offering a theoretical consideration that may be of little value to decision makers.
Preference Programming is one such an area of Multiple Criteria Optimisation that
accommodates incomplete information about criterion-specific performance levels
and criteria weights in the selection of a single alternative (Liesiö et al, 2005).
Incomplete information is captured by set inclusion meaning that the ‘true’ value of a
particular parameter is contained within a feasible set derived from the decision
maker’s preferences.
Robust Portfolio Modelling (RPM) is an extension of Preference Programming to the
problem of project portfolio selection. In RPM, the total value of each project and the
project portfolio are modelled by an additive value tree analysis as a weighted average
of the criterion-specific scores. Linear inequalities are used to capture incomplete
information about criteria weights and criterion-specific performance levels are
modelled by using score intervals (Liesiö et al, 2005). The use of incomplete
information leads to a recommendation of multiple non-dominated portfolios rather
than one. Non-dominated portfolios have an overall value not less than any other
portfolio for any combination of feasible weights and scores. To offer concrete
decision recommendations, measures for individual project and project portfolio
robustness are employed.
A graphical representation of RPM (figure 1) gathers together the main ideas and the
multi-step process of the model application. The first phase includes a choice of the
criteria against which the potential projects are evaluated. Incomplete information is
first modelled by reasonably wide score intervals and loose weight statements in order
to take clearly into account the uncertainties. Computation of non-dominated
portfolios follows, together with gradual analysis of projects and project portfolios by
robustness measures. Once the so-called borderline projects have been identified, the
8
-
focus moves on to give additional information, i.e. narrow score intervals and give
more precise weight information with respect to these borderline projects. The final
project selection method is left for the decision maker, but by this phase he or she can
concentrate on analysing the set of remaining borderline projects (i.e. the uncertain
zone), which usually is much smaller in number than the original set of potential
projects. The projects identified as core and exterior project require less attention.
Figure 1. RPM framework. Source: http://www.rpm.tkk.fi/
3.1. Representation of Additive Value
Let { }mxxX ,,1 K= denote a set of m available projects that are evaluated against n criteria. A performance score of project j with regards to I:th attribute (criterion) is
represented by . jiv
In addition, each project j is associated with k:th resource consumption , and the
total amount of resource k is limited by a budget B
jkc
k. The overall value of a project is
the weighted average of its criterion-specific scores, i.e.
9
http://www.rpm.tkk.fi/
-
( ) ∑=
=n
i
jii
j vwxV1
This represents an additive value model in which the weight wi represents the relative
importance of criterion i. The weights of all n criteria form a weight vector
that can be normalised so that it belongs to a set ],,[ 1 nwww K=
⎭⎬⎫
⎩⎨⎧
≥=∈=∈ ∑=
0,1|1
0i
n
ii
nw wwRwSw
that is, weight information is modelled by linear constraints.
3.2. Incomplete Information
One of the most difficult issues of applying mathematical models to support decision-
making is that many of them require complete information in the sense of fixed values
of weights and scores. However, this kind of data is not often available, nor is it
reasonable to always assume that such point estimates are accurate. For example, it is
quite impossible to give a zero-variance point estimate for a completely new project
that has not been started yet. A key feature of RPM methodology is to allow for
incomplete information with regards to weights of the criteria and the criterion-
specific scores of each project.
Incomplete weight information is modelled as a feasible (and convex) weight set
described by linear constraints derived from decision makers’ preference
statements. Incomplete criterion-specific performance information is modelled
through score intervals
0ww SS ⊆
],[ji
ji vv that are assumed to contain the ‘true scores . The
interval for the value of a portfolio p, therefore, is given by
jiv
)],(max),,(min[),,( wpVwpVvwpVww SwSw ∈∈
∈
where
( ) ( )
( ) ( )∑ ∑∑
∑ ∑∑
∈ ∈ =
∈ ∈ =
==
==
px px
n
iiji
j
px px
n
iiji
j
j j
j j
vwwxVwpV
vwwxVwpV
1
1
,,
,,
10
-
3.3. Additional Constraints
The RPM framework allows taking into account additional information such as:
o minimum budget usage
o project synergies
o balanced allocation of resources
and others that can be modelled by adding relevant logical constraints to the set of
constraints.
3.4. Non-dominated Portfolios
Because of using incomplete information, the model does not suggest a single optimal
portfolio but offers a number of non-dominated portfolios that lie within a feasible
information set. Non-dominated portfolios are feasible (i.e. constraint-satisfying)
portfolios whose overall values are higher than any other portfolios’ values for any
combination of feasible weights and scores.
Definition. Portfolio p dominates p’ with regards to information set S if and only if
V(p,w,v) ≥ V(p’,w,v) for all (w,v) ∈ S, (p,p’) ∈ P and
V(p,w,v) > V(p’,w,v) for some (w,v) ∈ S, (p,p’) ∈ P.
Non-dominated portfolios are therefore optimal solutions in some parts of the
information space. A thorough discussion of theory behind dominance structures and
the computation of non-dominated portfolios can be found in Liesiö et al, 2005.
To illustrate the effect of incomplete weight information on non-dominated portfolios,
consider figure 2. It depicts a situation where three portfolios are evaluated against
two criteria of which criterion 1 is more important than criterion 2 (i.e. w1 > w2). The
feasible weight area is therefore delimited to the left-hand side of vertical dotted line,
which means that portfolio 3 can be excluded from the set of non-dominated
portfolios with regards to given information set.
11
-
Figure 2. Additive value of portfolios with preference information w1 > w2
3.5. Additional Information
Should the number of non-dominated portfolios be too large, decision makers can be
asked to reduce the information set by proving narrower score intervals and/or further
weight constraints. It should be noted that while these actions are likely to reduce the
number of non-dominated portfolios, they do not add any new portfolios to it.
3.6 Robustness
The set of non-dominated portfolios itself does not give the decision maker any
straight recommendation about which projects should be included in the chosen
portfolio – after all, there may be a large number of different non-dominated
portfolios. However, one can calculate a core index for each individual project. The
core index simply measures in how many of the non-dominated portfolios each
project was contained. A core index of 100% implies that no matter what the ‘true’
weights and scores are, as long as they lie within the given limits, this project would
be included in all of the non-dominated portfolios and should therefore be selected by
the decision maker in any case. These projects are called core projects. Using the
same logic, a project with 0% core index is not included in any of the non-dominated
portfolios and should therefore be discarded. These projects are referred to as exterior
projects. The projects whose core index lies between these two extremes are so-called
borderline projects.
12
-
The identification of core, exterior and borderline projects facilitates the work of
decision maker greatly because s/he can concentrate on evaluating further the
borderline projects that belong to optimal portfolios for some but not all weight and
score regions. This narrowing of the scope of analysis and further investigation is the
real value of RPM methodology. Even though the computation of non-dominated
portfolios requires a complicated algorithm, the end results are clearly understandable
even without mathematical background and can therefore be easily communicated.
The robustness of a non-dominated portfolio can be measured by maximin and
minimax-regret rules that are employed in Preference Programming (Salo and
Hämäläinen, 2001). Maximin rule by definition recommends the portfolio that
performs the best in the worst-case scenario (i.e. the lower bound of its value defined
by feasible weights and scores). The recommendation is therefore
( )wpVPwn SwPp
,minmaxargmin ∈∈=
Minimax-regret on the other hand recommends a portfolio whose greatest possible
loss of value with regards to some other portfolio over the information set is smallest.
The recommendation is therefore
( ) ( )[ ]wppVwppVPwNn SwPpPp
regret ,'/,/'maxminarg,
maxmin '−=
∈∈∈−
It should be noted that maximin and minimax-regret rules may recommend different
portfolios.
13
-
4. Case Study on Patent Portfolio
4.1. Problem Statement
For a company whose success is closely tight to the innovative Research &
Development activities, systematic managing of Intellectual Property Rights (IPR)
related to these new technologies is vital to ensure positive future perspectives. The
problem is twofold. On micro level, the company needs a methodology to value IPR
in order to assess whether it is profitable to patent a particular IPR in some possible
technological and/or geographical extent. Secondly, because of limited (financial)
resources, not all IPRs can be patented – at least in global scale. Therefore the
company needs a methodology to recommend a selection of individual projects to
form an efficient patent portfolio.
A recent academic study on IPR valuation concentrated on building a methodology
for valuing individual projects (Antila et al, 2005). In this section, RPM methodology
is applied to a problem of supporting patent portfolio management, whereby patents
are considered as projects. Previously Asperation Oy had chosen individual patents to
project portfolio so that they fit within the budget. One of the objectives of this study
is provide comparison for the previous heuristic.
4.2. Modelling the Problem
In the studied case, there are 21 available projects, each of which is evaluated against
5 criteria that are most important to the company. With regards to ordinal preference
order, these criteria are Primary Business Potential, Necessity, Technical Coverage,
Strategic Fit and Secondary Business Potential, respectively. The resource usage cj
represents the cost of securing the patent and the total cost is constrained by a budget
B that is not to be exceeded. The patent-specific costs are constructed so that they
represent the “useful” geographical patenting area for each patent (project). In other
words, for the given cost (i.e. geographical area) of each patent it is profitable to
secure the patent if it is decided to be included in the portfolio. This kind of
formulation helped to keep the number of projects reasonable with regards to
computational time (if patents in different geographical extent were modelled as
mutually exclusive projects, with 5 extents the number of projects would have been
already 105). The criteria weights were obtained both as ordinary preference
14
-
statements (most important, second most important etc) and precise point estimates.
This allowed testing the model with different set-ups to see if and how the results are
affected.
The criterion-specific score estimate intervals were obtained after careful
consideration by the decision makers. The intervals represent an area of assumable
but tolerable variation about uncertain future performances. In other words, from
strategic perspective, it is unrealistic to imagine that a project’s performance with
regards to given criteria would not lie within the suggested interval.
4.3. Experimental Design
A computational study of case was performed with RPM-Solver – a software
developed at the Systems Analysis Laboratory in Helsinki University that uses RPM
framework to calculate non-dominated portfolios and different robustness measures
for individual portfolios. A short description of the software is presented in
www.rpm.tkk.fi.
The first test run was conducted with the data in the exact form it was given (see
appendices, table 1). However, given that the score intervals were rather
homogeneous in width and that levels of scores did not vary much, the computational
time grew unrealistic. Therefore several slightly simplifying experimental designs
were developed to analyse the case in numerical terms. Three different score intervals
representing criterion-specific variation (that is, uncertainty) of 5% (low), 10%
(medium) and 15% (high) were constructed. All cases were run with three different
budgets (low, medium, high). Criteria weights were modelled as ordinary preference
statements (RICH-method), with the restriction that all of the weights were at least
one fifth of the average of the weights.
4.4. Results
The results are analysed mainly by comparing core indices. Although some test runs
produce promising results, in general the recommendations are not so obvious. In fact,
in most cases almost all projects fall into borderline category meaning that the model
is not able to produce many core or exterior projects that would reduce the amount of
further consideration. For example, the results of a “middle case” test run (medium
15
http://www.rpm.tkk.fi/
-
score variation and budget) are presented in figure 2. Only one project appears as so-
called core project and another as exterior project.
Figure 2. Core indeces with a score interval of 10% and a budget constraint of 107.5
In general the projects 23, 26 and 37 perform very well in most of the test runs.
Similarly, projects 13 and 33 fall into exterior project class in most cases. The model
therefore helps to reduce the amount of further investigation by about 25% in general.
Effect of budget constraint
Changing the budget constraint does not seem to change the number of core and
exterior projects meaningfully (see appendices, figures 2 and 3). On the other hand,
borderline projects’ core indices get bigger when increasing the budget.
16
-
Effect of score intervals
Increasing the score intervals seems to have a dramatic effect in not only decreasing
the number of exterior projects but also decreasing the number of core projects. In
fact, regardless of the budget constraint, a score variation of 15% yields neither core
nor exterior projects, (see appendices, figure 3) whereas a score variation of 5%
produces both core and exterior projects (see appendices, figure 4). The reason
translates back to the data being quite homogeneous. For more variable data a 15%
score interval would produce clearly better results.
17
-
5. Discussion and Conclusions
Although the numerical results appear somewhat inconclusive, it should be kept in
mind that the model in this study was somewhat simplified, partly because of lack of
available data and resources needed with regards to the scope of the course. In
addition, the data was perhaps not gathered in the way that would benefit the model
best (that is, the data was not enough variable). Therefore more important than
concentrating on the results of the test runs is to consider how to improve and extend
the model. Some ideas of these ideas are discussed below.
Firstly, the applied model in this paper simplifies the problem from a geographical
perspective. The patent-specific costs (annual payments) were formed to represent a
“useful” patenting area. In other words, the cost of a particular patent, i.e. the sum for
the useful patenting area, is such it that guarantees profitable protection of the patent
should it be patented. In reality, each patent has different cost and criterion-specific
performance level depending on geographically how widely the patent is protected. A
full examination of the geographical issue would be to treat each project in each
geographical area independently and model them as mutually exclusive projects. For
example, if projects 1,2,3,4 and 5 represent the same patent in different geographical
extent, an additional logical constraint tells that only one of these 5 projects can be
selected for any portfolio. However, because this approach would require the
collection of many times the original data it was decided to leave it outside this study.
Another curiosity to consider is the assumption of the applied model that there are no
interdepencies between the individual projects. However, in reality such
interdepencies exist. For example, it is quite likely that two related projects, if both
started, produce together greater overall value than the sum of their individual values.
In other words, these projects have positive synergies. In RPM framework, synergies
can be modelled by adding aditional project for which there are no costs but a value
equal to the supplemental synergy value of the two projects if both started. This
additional “synergy project” is thus started if and only if both (or all) of the
underlying projects are started.
Even further modelling challenge arises from the issue that R&D company may have
rights to patents that they do not own. In other words, one company owns the patents
and another uses them for some cost, and vice versa.
18
-
With regards to numerical results, the study shows that although there is no need to
provide accurate data, too homogenous data leads to results that do not say much.
Emphasising the fact that preference statements about weights and score intervals for
criterion-specific performance levels are enough may lead to a situation where the
given information is not diverse enough. For example, if the score intervals are close
to the same width for many project-criterion combinations, even though the levels of
the intervals vary, the model is not able to find a clear set of core or exterior projects.
This finding is important when communicating how the decision maker should gather
the information needed.
In conclusion, RPM framework provides a flexible, easily understandable but process-
wise challenging framework for portfolio analysis. The real merits of RPM seem to be
its low demand on data and the ability to simply communicate all phases of the
modelling process to all decision makers. The implementation of RPM is a multi-step
challenge that requires careful planning. The study proved a useful introduction to
these challenges and opportunities in applying RPM to real cases.
19
-
6. References
1 Antila, M., Beletski, A., Isola, T., Janhonen, H., Leino, L., (2005). Seminar on
Case Studies in Operational Research, Final Report, Systems Analysis Laboratory,
Helsinki University of Technology, http://www.sal.tkk.fi/Opinnot/Mat-
2.177/projektit2005/Loppuraportti_Asperation.pdf
2 Asian Productivity Organization, (2004). Intellectual Property Rights, Report of
the APO Symposium Intellectual Property Rights 11-14 November 2003,
Bangkok, Thailand, ISBN: 92-833-7020-1.
3 Asperation Oy website, (2005), http://www.asperation.com/.
4 Ernst & Young and Ementor Management Consulting, (2000). Management and
evaluation of patents and trademarks, Consultant’s Analysis Report for the Danish
Patent and Trademark Office.
5 Investopedia website, (2005),
http://www.investopedia.com/terms/c/capitalbudgeting.asp.
6 Liesiö, J., (2004). Robust Multicriteria Optimization of Project Portfolios,
Master’s Thesis, Systems Analysis Laboratory, Helsinki University of
Technology.
7 Liesiö, J., Mild, P., Salminen, L., Ikonen, L., (2004). Final Report, Seminar on
Case Studies in Operational Research, Systems Analysis Laboratory, Helsinki
University of Technology, http://www.sal.tkk.fi/Opinnot/Mat-
2.177/projektit2004/Loppuraportti_Inframan.pdf.
8 Liesiö, J., Mild, P., Salo, A., (2006). Preference Programming for Robust
Portfolio Modeling and Project Selection, manuscript, European Journal of
Operational Research (forthcoming).
9 Luenberger, D., (1998). Investment Science, Oxford University Press.
10 Multiple Criteria Portfolio Analysis research project’s website (2005),
http://www.rpm.tkk.fi/.
11 National Board of Patents and Registration of Finland, (2005), http://www.prh.fi/.
12 Nielsen, P.-E., (2004). Evaluating patent portfolios – a Danish initiative, World
Patent Information, Vol. 26, Issue 2.
20
http://www.sal.tkk.fi/Opinnot/Mat-2.177/projektit2005/Loppuraportti_Asperation.pdfhttp://www.sal.tkk.fi/Opinnot/Mat-2.177/projektit2005/Loppuraportti_Asperation.pdfhttp://www.asperation.com/http://www.investopedia.com/terms/c/capitalbudgeting.asphttp://www.sal.tkk.fi/Opinnot/Mat-2.177/projektit2004/Loppuraportti_Inframan.pdfhttp://www.sal.tkk.fi/Opinnot/Mat-2.177/projektit2004/Loppuraportti_Inframan.pdfhttp://www.rpm.tkk.fi/http://www.prh.fi/
-
13 Perlos Oyj website (2005), http://www.perlos.com/.
14 Salo, A., Hämäläinen, R.P, (2001). Preference Ratios in Multiattribute Evaluation
(PRIME) – Elicitation and Decision Procedures under Incomplete Information,
IEEE Transactions on Systems, Man, and Cybernetics, Vol. 31, pp. 553 – 545.
21
http://www.perlos.com/
-
7. Appendices
Budget limits Importance 80 65 100 50 70 90 125 2 4 1 5 3
Project Annual payment Necessity Strategic fit
Primary business potential
Secondary business potential
Technical coverage
002ab 10 4 4,5 3,5 4,5 3 4,5 3 4 2,5 3,5 007 7,5 4 5 2,5 3,5 2 3 3 4 2 3 011 7,5 3,5 4,5 3 4 2 3 1,5 2 3 4 012 7,5 3,5 4,5 3 4 2 3 1,5 2 3 4 013 10 4 4,5 2,5 3,5 2,5 3,5 2,5 3,5 1,5 2,5 014 10 4 4,5 2,5 3,5 3,5 4,5 3 4 1,5 2,5 020 7,5 4 4,5 3,5 4,5 2 2,5 2 3 1,5 2,5 021 7,5 2 3 3 4 2 3 1,5 2 1,5 2,5 022 5 2,5 3,5 2,5 3,5 2 2,5 1,5 2,5 3,5 4,5 023 7,5 3 4 3 4 3,5 4,5 3 4 2,5 3,5 026 7,5 3 4 3,5 4,5 3 4 1,5 2,5 3 4 027 7,5 4 4,5 3,5 4,5 1,5 2,5 1,5 2,5 3,5 4,5 028 10 4 5 4 4,5 3,5 4,5 3 4 2 3 029 10 4 5 4 4,5 3 4 2,5 3,5 2 3 030 10 4 5 3,5 4,5 2,5 5 2 4,5 3 3,5 033 10 4 4,5 4 4,5 1,5 4,5 2 3 1,5 3 034 5 1,5 2,5 2,5 3,5 1 3,5 1 3,5 1,5 3,5 035 10 4 4,5 2,5 3,5 3 4 3,5 5 3,5 4,5 036 10 4 4,5 3,5 4,5 3,5 4,5 3 4 3,5 4,5 037 5 3 4 2,5 3,5 2 3 2 3 3,5 4,5 038 10 3,5 4,5 3,5 4,5 3 4 2,5 3,5 3,5 4,5
Table 1. Original data. Note that the data was modified for test runs
22
-
Figure 1. Core indeces with a score interval of 5% and a budget constraint of 90
23
-
Figure 2. Core indeces with a score interval of 5% and a budget constraint of 125
24
-
Figure 3. Core indeces with a score interval of 5% and a budget constraint of 107.5
25
-
Figure 4. Core indeces with a score interval of 15% and a budget of 107.5
26
Contents1. Introduction2. Patents as Intellectual Property2.1. Background of Patenting2.2. Patent Portfolio Valuation Approaches
3. Robust Portfolio Modelling – a Theoretical Framework3.1. Representation of Additive Value3.2. Incomplete Information3.3. Additional Constraints3.4. Non-dominated PortfoliosV\(p,w,v\) \( V\(p’,w,v\) for all \
3.5. Additional Information3.6 Robustness
4. Case Study on Patent Portfolio4.1. Problem Statement4.2. Modelling the Problem4.3. Experimental Design4.4. ResultsEffect of score intervals
5. Discussion and Conclusions6. References7. Appendices