Applying Earned Value Management to Your Project If your project is fairly complex, you may consider using earned-value management (EVM) to help control performance. By providing cost and schedule performance assessments of both the total project and its major parts, EVM allows you to identify the likely problem areas so you can take the most effective corrective actions. The following example presents a realistic illustration of how EVM can support insightful analysis of your project’s performance. Suppose the Acme Company has awarded a contract for the production of two specialized and complex corporate brochures to Copies ‘R’ Us. The contract calls for Copies ‘R’ Us to produce 500 copies of Brochure A and 1,000 copies of Brochure B. It further states that Copies ‘R’ Us will produce Brochure A at the rate of 100 per month and Brochure B at the rate of 250 per month. Production of Brochure A is to start on January 1, and production of Brochure B is to start on February 1. Here's the project plan: Plan for Copies ‘R’ Us to Produce Brochures A and B Activity Star t End Elapsed Time Number of Copies Total Cost Brochure A Jan 1 May 31 5 months 500 £100,000 Brochure B Feb 1 May 31 4 months 1,000 £100,000 Total £200,000 A quick glance reveals that you budgeted £200 a copy for Brochure A (£100,000 / 500 copies) and £100 a copy for Brochure B (£100,000 / 1,000 copies). Suppose it’s the end of March, and you’re three months into the project. Here’s what has happened as of March 31: Project Status as of March 31 Activity Star t Elapsed Time Number of Copies Produced Total Cost Brochure Jan 3 months 150 £45,000

Upload: katie-benson

Post on 20-Nov-2015

14 views

Category:

Documents


8 download

DESCRIPTION

pplying Earned Value Management to Your Project

TRANSCRIPT

Applying Earned Value Management to Your ProjectIf your project is fairly complex, you may consider using earned-value management (EVM) to help control performance. By providing cost and schedule performance assessments of both the total project and its major parts, EVM allows you to identify the likely problem areas so you can take the most effective corrective actions.The following example presents a realistic illustration of how EVM can support insightful analysis of your projects performance.Suppose the Acme Company has awarded a contract for the production of two specialized and complex corporate brochures to Copies R Us. The contract calls for Copies R Us to produce 500 copies of Brochure A and 1,000 copies of Brochure B. It further states that Copies R Us will produce Brochure A at the rate of 100 per month and Brochure B at the rate of 250 per month. Production of Brochure A is to start on January 1, and production of Brochure B is to start on February 1.Here's the project plan:Plan for Copies R Us to Produce Brochures A and B

ActivityStartEndElapsed TimeNumber of CopiesTotal Cost

Brochure AJan 1May 315 months500100,000

Brochure BFeb 1May 314 months1,000100,000

Total200,000

A quick glance reveals that you budgeted 200 a copy for Brochure A (100,000 / 500 copies) and 100 a copy for Brochure B (100,000 / 1,000 copies).Suppose its the end of March, and youre three months into the project. Heres what has happened as of March 31:Project Status as of March 31

ActivityStartElapsed TimeNumber of Copies ProducedTotal Cost

Brochure AJan 13 months15045,000

Brochure BFeb 12 months60030,000

Total75,000

Your job is to figure out your schedule and cost performances to date and to update your forecast of the total amount youll spend for both brochures. Follow these steps:1. Determine the planned value (PV), earned value (EV), and actual cost (AC) for Brochure A through March 31 as follows:PV = 200 per brochure 100 brochures per month 3 months = 60,000EV = 200 per brochure 150 brochures = 30,000AC = 45,0002. Determine the schedule variance (SV), cost variance (CV), schedule performance index (SPI), and cost performance index (CPI) for the production of Brochure A through March 31 as follows:SV = EV PV = 30,000 60,000 = 30,000CV = EV AC = 30,000 45,000 = 15,000SPI = EV / PV = 30,000 / 60,000 = 0.50CPI = EV / AC = 30,000 / 45,000 = 0.67Your analysis reveals that you produced only half of the copies of Brochure A you thought you would and that each brochure cost you 1.5 times the amount you had planned to spend (1 / CPI = 1 / 0.67 = 1.5; also, actual cost per brochure / planned cost per brochure = [45,000 expended / 150 brochures produced] / 200 per brochure = 300 / 200 = 1.5).3. Determine the planned value (PV), earned value (EV), and actual cost (AC) for Brochure B through March 31 as follows:PV = 100 per brochure 250 brochures per month 2 months = 50,000EV = 100 per brochure 600 brochures = 60,000AC = 30,0004. Determine the schedule variance (SV), cost variance (CV), schedule performance index (SPI), and cost performance index (CPI) for the production of Brochure B through March 31 as follows:SV = EV PV = 60,000 50,000 = 10,000CV = EV AC = 60,000 30,000 = 30,000SPI = EV / PV = 60,000 / 50,000 = 1.20CPI = EV /AC = 60,000 / 30,000 = 2.00Your analysis reveals that production of Brochure B is 20 percent ahead of schedule and 50 percent under budget (1 / CPI = 1 / 2 = 0.5; also, [30,000 expended / 600 brochures produced] / 100 per brochure = 50 / 100 = 0.5).5. Forecast the estimate at completion (EAC) for Brochure A.Assume the remaining work is performed at the originally budgeted rate.EAC = BAC + AC EV = 100,000 + 45,000 30,000 = 115,0006. Forecast the estimate at completion (EAC) for Brochure B.Assume the remaining work is performed at the originally budgeted rate.EAC = BAC + AC EV = 100,000 + 30,000 60,000 = 70,0007. Determine the overall status of your project by adding together the schedule variances (SV), the cost variances (CV), and the updated estimates at completion (EAC) for Brochures A and B.Project SV = 30,000 + 10,000 = 20,000Project CV = 15,000 + 30,000 = 15,000Assume the remaining work is performed at the originally budgeted rate.EAC = 115,000 + 70,000 = 185,000If project production rates and costs remain the same until all the required brochures are produced youll finish on budget five months late.