approved as to content - st. petersburg, florida · 1.22 work in streets and highways ... sib-3...

69

Upload: trandieu

Post on 11-Jun-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

APPROVED AS TO CONTENT

TABLE OF CONTENTS

SUPPLEMENTAL CONTRACT STANDARDS 1

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

SUPPLEMENTAL INSTRUCTIONS TO BIDDERS

SIB-1 Contract Completion Time SIB-2 Subletting of Contract SIB-3 Applicable SBE Percentage

SUPPLEMENTAL EXECUTION OF THE CONTRACT

SEC-1 Builder’s Risk Insurance

TABLE OF CONTENTS TS-1

Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

Technical Specifications

SECTION 1 – GENERAL

1.01 LOCATION OF THE WORK SITE AND ACCESS 1.02 SCOPE OF WORK 1.03 ESTIMATED QUANTITIES 1.04 PLANS AND SPECIFICATIONS 1.05 FIELD ENGINEERING 1.06 SAFEGUARDING SURVEY MARKS 1.07 INSPECTION AUTHORITY 1.08 PROJECT SCHEDULE 1.09 PROJECT START TIME 1.10 STORM PREPAREDNESS 1.11 MATERIALS AND EQUIPMENT 1.12 MANUFACTURER 1.13 SAMPLES 1.14 EQUIVALENT QUALITY 1.15 MATERIAL AND EQUIPMENT DELIVERY AND STORAGE 1.16 SERVICE OF MANUFACTURER’S REPRESENTATIVE 1.17 CONTAMINANTS CONTAINMENT/DISPOSITION 1.18 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION 1.19 MAINTENANCE OF STORM DRAINAGE SYSTEM 1.20 SPILL OR DISCHARGE OF WASTEWATER OR RECLAIMED WATER 1.21 SEQUENCE OF OPERATION 1.22 WORK IN STREETS AND HIGHWAYS 1.23 WORK IN PRIVATE PROPERTY 1.24 PERMITS 1.25 FIELD OFFICE AND APPURTENANT STRUCTURES 1.26 PROJECT SIGN 1.27 MOBILIZATION

TABLE OF CONTENTS TS-2

Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

1.28 WATER PURCHASE 1.29 TREE PROTECTION 1.30 TREE REMOVAL AND REPLACEMENT OR TREE REMOVAL, REPLACEMENT AND RELOCATION 1.31 UTILITIES 1.32 SHOP, FIELD AND LABORATORY TESTING 1.33 SOIL BORING DATA 1.34 SOILS DENSITY TESTS 1.35 SALVAGED MATERIALS 1.36 AS-BUILT DRAWINGS

SECTIONS 2 THROUGH 19 – NOT USED

SECTION 20 – PAY ITEM DESCRIPTIONS

20.01 EXPLANATION AND DEFINITIONS 20.02 PAY ITEM DESCRIPTIONS

DIVISION 1 – GENERAL REQUIREMENTS

01100 SUMMARY

DIVISION 2 – EXISTING CONDITIONS

02411 SELECTIVE DEMOLITION

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

07920 JOINT SEALANTS

DIVISION 8 – OPENINGS

08511 ALUMINUM WINDOWS 08800 GLAZING

DIVISION 9 – FINISHES

09910 PAINTING

DIVISION 10 – SPECIALTIES

10710 HURRICANE SCREENS

CONTRACT STANDARDS: SUPPLEMENTAL

SUPPLEMENTAL INSTRUCTIONS

TO BIDDER

Contract Standards Supplemental Instructions to Bidders

SUPPLEMENTAL INSTRUCTIONS TO BIDDERS In cases where this section and the standard Contract Standards Instruction to Bidders do not agree, this section, the Supplemental Instructions to Bidders will govern. SIB-1 Article I-2.4 - Contract Completion Time Add the following text to this Article: “Construction time will be a total of twenty (20) calendar days. Work must be coordinated with Sunken Gardens staff. The Turner House will be available during that period. The contractor will perform and complete all the work, including final inspection, during this period of time.” SIB-2 Article I-13, 13.2 - Subletting of Contract Delete the text contained in this article and include the following text:

“It is a requirement of this Contract that the Contractor must perform at least 25% of the Work called for under this contract with the Contractor’s own forces. It is also required that subcontractor’s utilized under this Contract must perform at least 25% of the Work subcontracted to them with their own forces. Prior to final payment for the Work, the Contractor will be required to furnish an affidavit substantiating the above.”

SIB-3 Article I-14, 14.4 - Applicable SBE Percentage Article I-14 Small Business Enterprise Program; Sub Article 14.4 Participation by SBE Contractors and Subcontractors; fourth line Delete “SBE: ______%” and Replace with “SBE: N/A”.

SUPPLEMENTAL EXECUTION

OF CONTRACT

Contract Standards Supplemental Execution of the Contract

SUPPLEMENTAL EXECUTION OF THE CONTRACT In cases where this section and the standard Contract Standards Instruction to Bidders do not agree, this section, the Supplemental Instructions to Bidders will govern. SEC-1 Article E-2, 2.6 - Builder’s Risk Insurance Article E-2- Insurance and Indemnification, Sub Article 2.6 Builder’s Risk Insurance; Builder’s Risk Insurance IS NOT applicable for this project.

TECHNICAL SPECIFICATIONS

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-1

SECTION 1 – GENERAL

1.01 LOCATION OF THE WORK SITE AND ACCESS The Project is for the Turner House Window Replacement at Sunken Gardens Garden located at 1825 4th Street North, St. Petersburg, Florida. Access to the Work site shall be over public streets and rights-of-way. Any damage to existing pavement or other surface improvements, attributable to the Contractor's activities, shall be restored to like-new condition by the Contractor at the Contractor's expense. 1.02 SCOPE OF WORK The essential portions of the proposed Work for the Project are summarized as follows: Single award contract for the complete construction work; including civil, architectural, structural, plumbing, mechanical, electrical and all other work shown in the Contract Documents. Estimated quantities and Contract Pay Items are listed in the Proposal. 1.03 ESTIMATED QUANTITIES The estimated quantities listed in the Proposal for the various Contract Pay Items shall be used for the purposes of comparing bids and determining amounts for which the bid and performance bonds shall be furnished. Certain estimated quantities listed are greater than the quantities required to complete the Work as shown on the Plans. The greater quantities and quantities of work items not shown may be for contingent work; compensation for contingent work will be made if required and approved by the Engineer. The City reserves the right to vary the estimated quantities or to delete the Work and the corresponding Contract Pay Items from the Contract. The Contractor will be compensated for Work actually performed as indicated on the Plans, in the Specifications, or authorized by the Engineer, all in accordance with the unit prices and lump sum prices contained in the Proposal. The bidder shall quote in the Proposal a unit or lump sum price for which he will perform the Work for each of the Contract Pay Items. 1.04 PLANS AND SPECIFICATIONS Technical Specifications Section 1 and Technical Specification2 by ARC3 Architecture, Inc., Division 2 through Division 26 have been prepared specifically for this Project. Other Technical Specifications sections are City Standards and only the applicable portions of them govern the Work to be performed. Where the Plans and Specifications are not in agreement, the Plans shall govern. Where a specifically prepared Technical Specifications section is not in agreement with City Standards Technical Specifications, the specifically prepared section shall govern. The Contractor shall furnish all labor, equipment, and materials to construct the Project and all miscellaneous and appurtenant work complete in place as specifically described and included under each Contract Pay Item as shown, specified, or directed by the Engineer in accordance with the obvious or expressed intent of the Contract. The list of drawings comprising the Plans for Project No. 15211-019 is shown on Sheet 1 of the Plan Drawing Nos. 11054-1 and 11054-2.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-2

1.05 FIELD ENGINEERING The Contractor shall establish and provide all vertical and horizontal control points for this Project including benchmarks. The Contractor shall provide the field layout surveying necessary to properly construct the Work from City-furnished control points or reference points indicated on the Plans. All field layout surveying shall be performed under the supervision of a Professional Land Surveyor (Chapter 472, Florida Statutes). The Contractor shall submit the name and registration number of said Surveyor as directed by the Engineer. The Engineer reserves the right to check all survey staking and to require adjustments or re-staking by the Contractor in the event that conflicts or errors are detected. Water pressure pipelines that are 8-inch or less diameter shall be installed with the required cover using horizontal control stakes provided by the Contractor. Storm drains, sanitary sewers, sanitary pressure pipelines, and water pressure pipelines greater than 8-inch diameter shall be installed using an approved method for line and grade control. Methods for line and grade control shall be submitted to the Engineer for approval, as specified for shop drawings. Sketches shall be provided by the Contractor showing vertical adjustment necessary for pressure pipelines to adequately clear storm drains and other utilities, unless otherwise shown on the Plans. 1.06 SAFEGUARDING SURVEY MARKS The Contractor shall safeguard all existing property monuments, benchmarks, and other survey marks adjacent to and within the Project limits, and shall bear the cost of re-establishing them if disturbed or destroyed. 1.07 INSPECTION AUTHORITY The Engineer has ultimate responsibility for Contract administration and inspection for this Project. The Engineer may assign field inspection responsibilities to a Design Professional and/or City Inspector. Each step of construction is subject to approval by the Engineer prior to proceeding with a subsequent step in accordance with the General Conditions article headed "Tests and Inspections" and as supplemented herein. During the progress of the Work and up to the date of final acceptance, the Contractor shall at all times afford representatives of the City, the County, the State, the Department of Environmental Protection, the Department of Labor, or any other agency with jurisdiction, a reasonable, safe, and proper facility for observation of the Work done or being done at the site and also of the manufacture or preparation of materials and equipment at the place of such manufacture or preparation. The Project line of authority will be presented at the Preconstruction Conference. 1.08 PROJECT SCHEDULE The Contractor shall submit a Project schedule in accordance with General Conditions articles headed "Project Schedule" and "Progress Charts" and as supplemented herein.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-3

Scheduling and progress reporting shall be accomplished by the use of a bar chart to provide a clear and concise comparison of progress. 1.09 PROJECT START TIME

Charging of Contract Time will begin on the first (1st) calendar day after issuance of the Notice to Proceed or on the actual day that the Contractor commences Work at the site, whichever is the earlier. Suspension of Contract Time shall be requested in the manner set forth in the General Conditions article headed "Changes in the Work," subsection headed "Changes in Contract Time," and shall include:

1. Manufacturer's signed affidavit. 2. Number of calendar days requested (not to exceed above maximum). 3. Reasons Contract Time must be extended. 4. Stipulation of all Work, including Schedule, which is to be performed during the grace

period. 5. Indication of what insurance and bonds will be active.

A. Documentation shall be presented to the City prior to, or during, the Preconstruction

Conference. B. It may be possible that certain Work items can be accomplished by the Contractor prior to

receipt of the custom equipment or materials if, in the opinion of the Engineer, City use of the facility is not impacted.

C. Failure of the Contractor to substantively obtain the custom equipment or materials, if

through no fault of the City, will not be justification for extending the Contract Time extension beyond the above maximum duration.

1.10 STORM PREPAREDNESS PLAN Within 15 days of the date of Notice to Proceed, the Contractor shall file with the Engineer a Storm Preparedness Plan. The plan shall outline the necessary measures the Contractor proposes to perform at no additional cost to the City upon the issuance of an official storm warning issued by the National Weather Service. In the event of inclement weather, or at the Engineer's direction, the Contractor shall carefully protect the Work, private property affected by the Work, and stored materials against damage or injury from the weather. If, in the opinion of Engineer, any portion of the Work or materials is damaged or injured by reason of failure on the part of the Contractor to protect the Work, such Work and materials shall be removed and replaced at the Contractor's expense. 1.11 MATERIALS AND EQUIPMENT All materials, appurtenances, and types of construction shall be in accordance with the Technical Specifications and shall in no event be less than that necessary to conform to the requirements of all applicable laws and regulations.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-4

All materials and equipment to be incorporated into the Work shall be new, unused, and correctly designed. They shall be of standard first grade quality, produced by expert workmen, and be intended for the use for which they are offered. Materials or equipment which, in the opinion of the Engineer, are inferior or of a lower grade than indicated, specified, or required, will not be accepted.

Only "Asbestos-Free" materials shall be incorporated into the Work, unless the Technical Specifications specifically call for otherwise. Material suspected of being Regulated Asbestos Containing Material (RACM), includes but is not limited to: thermal and acoustic insulation, joint compound, mastic, adhesive, vinyl floor tile and sheeting, ceiling tile, plaster, wall board, roofing felt, and shingle. Shop drawings for material or equipment suspected of being RACM shall list all contents, shall be noted "Asbestos-Free," and shall be screened by the Contractor prior to submittal to confirm that it is "Asbestos-Free." All materials delivered to the Project site shall have been approved through the shop drawing procedure and shall be in their original labeled and unopened containers. In the event that asbestos-containing material installed by the Contractor is discovered either during construction, following completion of construction, or following acceptance of the Contract Work by the City and closeout of the Contract, it will be the responsibility of the Contractor to pay all costs incurred to remove and replace those materials, including repair or replacement of all adjacent materials which are affected by the abatement process. 1.12 MANUFACTURER The names of proposed manufacturers, manufacturers' representatives, suppliers, and dealers who are to furnish materials, fixtures, equipment, appurtenances, or other fittings, shall be submitted by the Contractor to the Engineer for approval in accordance with the General Conditions article headed "Shop Drawings and Submittals" to afford proper investigation and checking. No manufacturer will be approved for any materials, fixtures, equipment, appurtenances, or other fittings to be furnished under this Contract unless the manufacturer is of good reputation and has a plant of ample capacity. The Contractor shall, upon the request of the Engineer, be required to submit evidence that the manufacturer has manufactured a product similar to the one specified and that the product has been used for a like purpose for a sufficient length of time to demonstrate its satisfactory performance. All transactions with the manufacturer and subcontractors shall be through the Contractor. Any two or more pieces of material or equipment of the same kind, type, or classification and being used for identical types of service, shall be made by the same manufacturer. 1.13 SAMPLES The Contractor shall, when required, submit to the Engineer for approval, typical samples of material and appurtenances. The samples shall be properly identified by tags and shall be submitted sufficiently in advance of the time when they are to be incorporated into the Work so that rejections thereof will not cause delay. A letter of transmittal from the Contractor requesting approval shall accompany all such samples.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-5

1.14 EQUIVALENT QUALITY In the Contract Documents, whenever an article, material, apparatus, equipment, or process is called for by trade name or by name of a patentee, manufacturer, or dealer, or by reference to catalog of a manufacturer or dealer, it shall be understood as intending to mean and specify the article, material, apparatus, equipment, or process designated, or, upon approval of the Engineer, any equal thereto in quality, finish, design, efficiency, and durability, and equally serviceable for the purposes for which it is intended. Whenever material or equipment is submitted for approval as being equal to that specified, the submittal shall include sufficient information and data to demonstrate that the material or equipment conforms to the Contract requirements. The decision as to whether or not such material or equipment is equal to that specified shall be made by the Engineer. Upon rejection of any material or equipment submitted as the equivalent of that specifically named in the Contract, the Contractor shall immediately proceed to furnish the designated material or equipment. Neither the approval by the Engineer of alternate material or equipment as being equivalent to that specified, nor the furnishing of the material or equipment specified, shall in any way relieve the Contractor of responsibility for failure of the material or equipment, due to faulty design, material, or workmanship, to perform the functions required of them by the Contract Documents. 1.15 MATERIAL AND EQUIPMENT DELIVERY AND STORAGE In conformance with the General Conditions article headed "Material and Equipment Delivery" the Contractor shall deliver materials in ample quantities to ensure the most speedy and uninterrupted progress of the Work to complete the Work within the allotted time. The Contractor shall also coordinate deliveries in order to avoid delay in, or impediment of, the progress of the Work of any related contractor. The Contractor shall provide space for storage of materials and equipment. Pipe strung along roads and rights-of-way shall be placed in a manner that will not endanger or restrict pedestrian or vehicular traffic. 1.16 SERVICE OF MANUFACTURER'S REPRESENTATIVE The Contract amount shall include the cost of furnishing a competent and experienced representative of the equipment manufacturer who shall assist the Contractor, when required, to install, adjust, test, and place in operation the equipment in conformity with the Contract Documents. After the equipment is placed in operation, the representative shall make all adjustments and tests required by the Engineer to prove that the installed equipment is in proper and satisfactory operating condition. The representative shall instruct personnel designated by the Engineer in the proper operation and maintenance of such equipment. 1.17 CONTAMINANTS CONTAINMENT/DISPOSITION A. Prior to the installation of well points for dewatering, the Contractor shall visually inspect the

Work area for indications of existing ground water monitoring, wells, or metal caps at grade. The Contractor shall review the Work area for monitoring wells or abandoned fuel tanks, and shall notify the Engineer in writing if any of the above items exist.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-6

B. If during the dewatering activities the spoil water becomes odorous (excluding sulfur odor)

or the spoil water is discolored (excluding tannic acid or iron), the Contractor shall stop the dewatering activities and shall notify the Engineer in writing of such, and request direction.

C. When Work activities encounter or expose any abnormal condition that may indicate the

existence of a hazardous or toxic waste, Work activities shall stop in the vicinity of the abnormal condition and the Contractor shall notify the Engineer immediately. The presence of tanks or barrels; discolored earth, metal, wood, or groundwater; visible fumes; abnormal odors; excessively hot earth; smoke; or other conditions that appear abnormal, may be signs of hazardous or toxic wastes and shall be treated with extraordinary caution.

Every effort shall be made by the Contractor to minimize the spread of any hazardous or toxic waste into uncontaminated areas.

The Contractor's operations shall not resume until directed in writing by the Engineer.

Disposition of the hazardous or toxic waste will be made in accordance with the requirements and regulations of any City, County, State, or Federal agency having jurisdiction. Where the Contractor performs work necessary to dispose of hazardous or toxic waste, and the Contract does not include Pay Items for disposal, payment may be made as provided in the Contract Standards: General Conditions article headed "Unforeseen Subsurface Conditions."

1.18 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION The Contractor shall be responsible for prevention, control, and abatement of erosion, siltation, and water pollution resulting from construction of the Project until final acceptance of the Project. The Contractor shall implement all appropriate turbidity management practices at the point of discharge into a storm drainage system, gutter, or other conveyance to ensure that state water quality standards are not violated at the point where the storm drain, gutter, or other conveyance discharges into a surface water. All necessary provisions shall be taken to ensure compliance with the water quality standards of the State of Florida. Attention is called to Chapter 62-302, Florida Administrative Code, and in particular, the requirements that turbidity shall not exceed 29 NTUs above background level. Adequate silt containment procedures and equipment shall be used to control turbidity, at no additional cost to the City. 1.19 MAINTENANCE OF STORM DRAINAGE SYSTEM The Contractor shall be responsible at all times to maintain the operation of existing stormwater facilities, or, when existing stormwater facilities are removed, to provide equivalent capacity alternate forms of stormwater removal adequate to prevent upstream flooding in excess of existing conditions. This responsibility shall include the installation of temporary connections, bypass pumping, or other temporary means necessary until the new drainage system is fully operational.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-7

1.20 SPILL OR DISCHARGE OF WASTEWATER OR RECLAIMED WATER The discharge of wastewater or effluent (reclaimed water) into waters of the State and/or into canals, ditches, and ponds that are connected to waters of the State is prohibited. Any spill or discharge of wastewater or reclaimed water shall be immediately reported to the Engineer, the City’s Wastewater Collection System Manager (892-5612), and the City’s Emergency Dispatch Center (893-7261). In the event of a spill or discharge, the Contractor shall immediately control, contain, and stop the spill or discharge and shall repair any damage to the City’s facilities. The Contractor shall be responsible for any penalties and costs charged to the City by the FDEP and for all costs incurred by the City as a result of the Contractor’s actions or as a result of the Contractor’s negligence. 1.21 SEQUENCE OF OPERATION A. General

It is essential that any Project Work be sequenced to minimize obstruction of normal daily activities.

The Contractor shall include in the Project Schedule a Sequence of Operations conforming to the following order:

1. Store equipment and materials at locations and in a manner approved by the Engineer. 2. Confine work and personnel to designated areas in accordance with the Specifications. 3. Clean up work areas daily so as to present a safe and neat appearing work site.

B. Utility Companies may be present on the Work site adjusting their facilities and installing new facilities. The Contractor's work shall be scheduled in such a manner as to minimize conflicts with various utility companies.

C. The Contractor shall clean up the site for each phase of Work in accordance with the Contract Documents before proceeding to a subsequent phase of Work, unless otherwise approved by the Engineer.

D. No Time Extension- If the Engineer orders the construction, or a phase of construction, to be stopped due to the Contractor's neglect to adhere to the Sequence of Operations as outlined herein, the Stop Work Order shall not constitute a basis for extension of time. E. Sequence of Construction- To be determined by Contractor for the approval of the City Engineer. 1.22 WORK IN STREETS AND HIGHWAYS All Work within streets and highways shall be subject to the regulations and requirements of the appropriate agencies. .

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-8

Methods and materials of construction used in restoration within such streets and highways shall conform to the requirements, inspection, and approval of the duly authorized representatives of the appropriate agency having jurisdiction. Restoration Work shall include: removal and replacement of pavement, sidewalk, curb, and gutter; replacement of storm drainage facilities; excavation and backfilling; and storage of materials and equipment. 1.23 WORK IN PRIVATE PROPERTY In the event that, in the opinion of the Contractor, obtaining a temporary construction easement outside the limits of the right-of-way, of City-owned property, or of the easement(s) obtained by the City is necessary or desirable, it shall be the sole responsibility of the Contractor to obtain such temporary easement from the owner of the property. If such easement is obtained by the Contractor it shall contain provision to hold the City harmless from any operations of the Contractor within the easement limits. The Contractor shall not conduct construction operations on private property outside the limits of the right-of-way, of City-owned property, or of the easement(s) obtained by the City unless a copy of the Temporary Construction Easement Agreement is filed with the Engineer. Upon completion of Work in easements, the Contractor shall restore the property, including all fences or other structures disturbed by his operations, to as good as or better than the condition in which he found it. 1.24 PERMITS Construction projects performed for the City will require licenses and permits in the same manner as private construction projects within the City. City permit will be required for tree removal. The Contractor shall secure such permit(s) at his own expense (the City's Urban Forester can be contacted at 893-7472). The Contractor shall secure, at his expense, all licenses and permits, and shall comply with all applicable laws, regulations, and codes as required by the State of Florida and/or the City of St. Petersburg. The permit fee schedule for the general construction, grounds improvement, electrical, plumbing, mechanical, and other Work is on file at the City Construction Services and Permitting Division, Municipal Services Center, One Fourth Street North, St. Petersburg, Florida, (727/893-7231). City Building Permit No. TBD will be required for the Project; the cost will be reimbursed to the contractor from the Permit Allowance. City permits for this Project will include:

Building 1.25 FIELD OFFICE AND APPURTENANT STRUCTURES General: All structures for use by the Contractor or Engineer shall be temporary. Permanent facilities shall not be used for field offices or for storage. Structures may be new or used, but must be serviceable, adequate for the required purpose, and shall be in compliance with all applicable codes or regulations. All security requirements for such facilities shall be provided and maintained by the Contractor.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-9

Before the Final Payment will be paid, and as directed by the Engineer, the Contractor shall clean up the area, remove any temporary facilities, finish grade, and restore the area to its original condition as determined by the Engineer. 1.26 PROJECT SIGN The City shall furnish the Project sign. The Contractor shall erect the sign and maintain it for the duration of the Project. The Contractor shall mount the sign using 4-inch pressure treated lumber or as approved by the Engineer, and other supports as required, at a location mutually agreed by the Engineer and the Contractor. If the sign becomes unusable due to damage, vandalism, or any means other than Contractor activity, the City will furnish a replacement sign at no cost to the Contractor. If the sign is damaged by Contractor activity, the Contractor shall replace the sign in-kind at no additional cost to the City. Payment for installing and maintaining the Project sign shall be incidental to construction costs of the Project for the duration of the Contract. The sign will remain the property of the City upon completion of the Project. No sign other than as shown on the Plans and/or as specified, either by the Contractor, any subcontractor, or any material supplier, will be allowed on the Project site. 1.27 MOBILIZATION Mobilization shall include all preparatory work and operations necessary to begin the Project, including moving of personnel, equipment, plant, and all else necessary to commence work. The cost of bonds, insurance, shop drawings, and preconstruction expenses shall also be included. If a separate Pay Item is included for mobilization, payment will be as specified for that Pay Item. If no Pay Item is included, costs for mobilization shall be included with the costs for the major Work items included in the Proposal. 1.28 WATER PURCHASE Water used in connection with this Project may be purchased from the Water Resources Department, 1650 Third Avenue North, in accordance with the provisions of applicable ordinances, procedures, and regulations. 1.29 TREE PROTECTION Particular care shall be taken by the Contractor to protect trees during construction by erecting approved barricades to prevent unnecessary damage to trunk and roots during construction. Such barriers shall protect the area within the dripline. The Contractor shall prune all branches that interfere with construction in accordance with American Forestry Association Standards. Roots over 2-inch diameter shall be preserved wherever possible. If root pruning is required, roots shall be cut cleanly.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-10

Temporary soil deposits, concrete block, concrete wash, or solvents shall not be placed within the dripline. The grade within the dripline shall be preserved. If adjacent grade is altered, protective measures such as those described in the Florida State Division of Forestry "Tree Protection Manual for Builders and Developers" shall be constructed to protect the tree(s) from deleterious effects of the grade change. 1.30 TREE REMOVAL AND REPLACEMENT/TREE REMOVAL, REPLACEMENT, AND

RELOCATION

As required by St. Petersburg City Code “Chapter 16. Article XV. Division 5. Tree and Mangrove Protection” a permit is required to remove any native tree or palm greater than 2-inch diameter measured 4.5 feet above the ground. The Contractor shall obtain any necessary tree removal permit, shall furnish and replace trees as required, and shall perform this Work in a manner conforming to all applicable provisions of said regulations or permit. The cost of tree removal and obtaining the tree removal permits shall be included in the cost of the appropriate associated Contract Pay Item under which the Work is to be performed. The Contractor shall remove trees as required and approved by the Engineer whether or not said trees are shown on the Plans. Trees that have to be removed, except for Australian pine, Brazilian pepper, punk, and other exempt species, shall be replaced as directed. Replacement trees shall be of native species at least 8 feet tall and at least 3-inch caliper diameter. If the cost of removing and disposing of a desirable species of tree exceeds the cost of relocating the tree to a point not in conflict with the proposed construction, the City may order that the tree be relocated within the right-of-way, or to the abutting property owner's desired location or immediately adjoining the right-of-way. This applies to trees of a transplantable size and condition, greater than 2-inch diameter measured 4.5 feet above the ground, and generally less than 12 feet tall. 1.31 UTILITIES Prior to construction, the Contractor shall familiarize himself with the location of all existing utilities and facilities within the Project Site and with the applicable provisions of the General Conditions article headed "Public Convenience and Safety." The Contractor shall notify utility companies at least 48 hours, excluding Saturdays, Sundays, and legal holidays, prior to excavation. Utility companies shall be contacted by calling the utility notification center "Sunshine" at 1-800-432-4770. The City will furnish to the Contractor the available records of City utilities. The Contractor shall locate and mark all City utilities for his reference and for use by utility companies. The Contractor shall act as the City’s agent for locating and marking City underground utilities within the Project limits, in accordance with the Florida Underground Facilities Damage Prevention and Safety Act (FS 556). In all cases where existing utility lines may be interfered with by the Work, the Contractor shall give a minimum of 48 hours notice to the owners of such utilities to permit them to relocate the lines prior to construction. Existing utilities have been shown on the Plans insofar as information is reasonably available. However, it will be the Contractor's responsibility to preserve all existing utilities whether shown on the Plans or not.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-11

1.32 SHOP, FIELD, AND LABORATORY TESTING The Engineer may require testing by certified personnel of certain materials to be incorporated in the Work, such as: soils density, pavement, concrete pipe and appurtenances, and welds. In the event any such testing is required by the Engineer, a detailed description will be found in these Technical Specifications concerned with the specific item of Work. Where reference is made in the DOT-SSRBC for design mixes, tests of materials, or work performed, or where in the opinion of the Engineer, tests are required to ascertain compliance with the Specifications, the Contractor shall have such tests made by an approved testing laboratory. No additional payment will be made for these tests. 1.33 SOIL BORING DATA Soil boring data, including groundwater elevations or conditions, are available for Bidder's inspection at the offices of the City Engineering & Capital Improvements Department. These data are presented only as information that is available which indicates certain conditions found and is limited to the exact locations on the dates indicated. 1.34 SOILS DENSITY TESTS Soils density testing shall be performed by the City at no cost to the Contractor. Retesting of failed tests, in excess of 10 percent of tests performed, shall be at the expense of the Contractor. The Contractor may have independent soils compaction tests performed, at no cost to the City; however, the results of these tests may not constitute a basis for acceptance or rejection of the Work. All soils used in backfill shall be compacted with suitable equipment in layers as specified. Maximum density shall be defined as the oven-dried density in pounds per cubic foot of the soil at optimum moisture content as determined by the latest revision of AASHTO T180. Prior to any backfill operation, a representative sample of the backfill material shall be taken by certified personnel, and tested in a certified laboratory as approved by the Engineer, to determine the relationship between the moisture content and density of the material when compacted in accordance with AASHTO T180. When the densities and corresponding moisture contents for the sample material have been plotted as specified, a curve shall be produced. The moisture content corresponding to the peak of the curve shall be termed the "optimum moisture content" of the sample under the above described compaction. At least one representative sample, as described above, shall be taken thereafter for every significant observed change in soil characteristics or as ordered by the Engineer. The maximum density of the representative sample as herein specified shall become the basis for determining the in-place percentage of maximum density required in the Technical Specification for the specific item of Work.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-12

In-place density testing shall employ the use of nuclear equipment in accordance with the latest revision of AASHTO T238 Method B "Density of Soil and Soil-Aggregate in Place by Nuclear Methods." In-place density shall be taken upon completion of each compaction layer or more often as ordered by the Engineer. 1.35 SALVAGED MATERIALS The Contractor shall not proceed with demolition of existing materials or equipment without prior written approval from the Engineer for the method of disposal. All materials which are not returned to the City yard shall be disposed in an approved disposal site. The Engineer may request confirmation of the site's approval for disposal of the specific materials. Salvaged materials shall be loaded on Contractor trucks and returned to the City Utilities Complex Yard, 1635 Third Avenue North. The City will designate the specific location at the yard for placement of salvaged materials by the Contractor. The following materials shall be removed and returned by the Contractor: A. Fire hydrants, manhole frames and covers, inlet grates, and concrete catch basin covers

shall be salvaged and each placed in a designated location at the City yard. B. Granite curb shall be salvaged, individually unloaded, and neatly placed at a designated

location in the City yard. C. Red paving brick (free of asphalt) and sidewalk hexblock shall be palletized on

City-furnished pallets and delivered to the City yard. D. Asphalt millings shall be transported to the City yard and dumped in a pile at a designated

location in the City yard. 1.36 AS-BUILT DRAWINGS A. General For all elements of construction, the Contractor shall furnish the Engineer one set of

marked-up Contract Plans blueline prints showing as-built conditions, as specified in the General Conditions article headed "As-Built Drawings."

The drawings shall show the name, address, and phone number of the Contractor. Each drawing shall be certified by a responsible representative of the Contractor and dated.

The as-built drawings shall reflect any differences from the original Contract Plans in the same level of detail and units of dimension as the Plans.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-13

B. Electrical and Control Wiring

The as-built drawings shall include all changes to the original Contract Plans. The as-built drawings shall also include the size, color, and number of wires and conduit. For Projects where this information is too voluminous to be contained on the blueline prints, the Contractor shall prepare supplemental drawings, on same size sheets as the blueline prints, showing the additional conduit runs, 1-line diagrams, ladder diagrams, and other information. The wiring schematic diagrams shall show termination location and wiring identification at each point on the ladder diagram.

Technical Specifications Section 1 – General

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

1-14

NO TEXT THIS PAGE

Technical Specifications Sections 2 through 19

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

SECTIONS 2 THROUGH 19 -- NOT USED

Technical Specifications Sections 2 through 19 Sunken Gardens Improvements FY15 – Turner House Window Replacement Project No. 15211-019

NO TEXT THIS PAGE

Technical Specifications Section 20 – Pay Item Descriptions

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

20-1

SECTION 20 - PAY ITEM DESCRIPTIONS

20.01 EXPLANATION AND DEFINITIONS The following explanation of the measurement and payment for the Bid form items is made for information and guidance. The omission of reference to any item in this description shall not, however, alter the intent of the Bid form or relieve the Contractor of the necessity of furnishing such as part of the “Contract. The City will not allow for additional compensation beyond those Pay Items included in the Proposal. It is important therefore that all Bidders fully acquaint themselves with all Plans, Specifications, City Standard Details, and other details pertaining to the Work. Work not shown or called out in either the Plans or the Specifications, but necessary in carrying out the intent of the Project or in the complete and proper execution of the Work, is required and shall be performed by the Contractor as though it were specifically delineated or described. No additional compensation will be considered for this associated and necessary Work. 20.02 PAY ITEM DESCRIPTIONS Pay Item No. 1 – All construction work for Turner House Window Replacement at Sunken Gardens Project No. 15211-019 No measurement shall be made for this Pay Item. Payment will be made at the lump-sum price indicated in the Proposal to provide a complete task that includes all required mobilization/demobilization, labor, material, equipment, rentals, services, bonds, insurances, staging, on-site and off-site cleaning/sweeping, preparations, and incidentals, complete as shown on the Plans, as specified and as directed by the Engineer to complete the required portions of the proposed Work for the Project as summarized in SECTION1 – GENERAL of the Technical Specifications. Pay Item No. 2 – Allowance for Permit Costs The Proposal includes an allowance for reimbursement of permit costs to the General Contractor. Any amount of extra work and/or alterations to the proposed Work charged to the allowance shall be fully documented and authorized by the Engineer. Pay Item No. 3 – Allowance for Unforeseen Conditions The proposal includes an allowance for unforeseen or unanticipated conditions that were not specifically identified in the Contract Documents. Any amount of extra Work and/or alteration the proposed Work charged to the allowance shall be fully documented and authorized by the Engineer as follows. A. The Contractor shall include in the Contact Total Price the allowance so named in the

Proposal form.

B. The Contractor shall not proceed on any additional Work to be covered by the allowance until authorized in writing by the Engineer.

Technical Specifications Section 20 - Pay Item Descriptions

Sunken Gardens Improvements FY15 – Turner House Window Replacement

Project No. 15211-019

20-2

C. The Contractor shall cause the Work so covered to be done by such subcontractors or

suppliers, and for such sum within the limit of the allowance as authorized by the Engineer.

D. The allowance shall not be used for incidental Work shown on the Plans or specified in

the Contract Documents, or for other work required to render the Project complete.

Technical Specifications Division 1 – General Requirements

Section 01100 – Summary Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

SECTION – 01100 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Specification and drawing conventions.

1.2 PROJECT INFORMATION

A. Project Identification: Sunken Gardens Turner House. 1. Project Location: 1825 4th Street North.

B. Owner: City of St. Petersburg.

1. Owner's Representative: Jean Totti.

C. Architect: ARC3 Architecture

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following: 1. Demolition and removal of designated aluminum awning windows, replacement

with impact rated aluminum projected out windows and the addition of hurricane impact screens to the existing wood framed fixed clerestory windows. Repair of any damage to adjacent finishes. Application of joint sealants to interior and exterior perimeter of windows. Repainting of adjacent surfaces affected by construction to match existing.

B. Type of Contract. 1. Project will be constructed under a single prime contract.

1.4 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows: 1. Imperative mood and streamlined language are generally used in the

Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

01100-1

Technical Specifications Division 1 – General Requirements

Section 01100 – Summary Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2. Specification requirements are to be performed by Contractor unless specifically

stated otherwise.

PART 2 - PRODUCTS – NOT USED

PART 3 - EXECUTION – NOT USED

01100-2

Technical Specifications Division 2 – Existing Conditions

Section 02411 – Selective Demolition Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

SECTION 02411 – SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: 1. Demolition and removal of designated aluminum awning windows.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.

B. Existing to Remain: Existing items of construction that are not to be permanently removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.3 INFORMATIONAL SUBMITTALS

A. Pre-demolition Photographs or Video: Submit before Work begins.

1.4 CLOSEOUT SUBMITTALS

A. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.

1.5 FIELD CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. 1. If suspected hazardous materials are encountered, do not disturb; immediately

notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Storage or sale of removed items or materials on-site is not permitted.

02411-1

Technical Specifications Division 2 – Existing Conditions

Section 02411 – Selective Demolition Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

F. Utility Service: Maintain existing utilities indicated to remain in service and protect

them against damage during selective demolition operations.

PART 2 - PRODUCTS

2.1 PEFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Architect.

D. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems and protect them against damage.

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

02411-2

Technical Specifications Division 2 – Existing Conditions

Section 02411 – Selective Demolition Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows: 1. Neatly cut openings and holes plumb, square, and true to dimensions required.

Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

5. Dispose of demolished items and materials promptly.

B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.5 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Except for items or materials indicated to be reused, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill. 1. Do not allow demolished materials to accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent

surfaces and areas.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.

3.6 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

02411-3

Technical Specifications Division 2 – Existing Conditions

Section 02411 – Selective Demolition Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

NO TEXT THIS PAGE

02411-4

Technical Specifications Division 7 – Thermal and Moisture Protection

Section 07920 – Joint Sealants Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

SECTION 07920 – JOINT SEALANTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: 1. Silicone joint sealants. 2. Latex joint sealants.

1.2 PRECONSTRUCTION TESTING

A. Preconstruction Field-Adhesion Testing: Before installing sealants, field test their adhesion to Project joint substrates. Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

1.3 ACTION SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Joint-Sealant Schedule: Include the following information: 1. Joint-sealant application, joint location, and designation. 2. Joint-sealant manufacturer and product name. 3. Joint-sealant formulation. 4. Joint-sealant color.

1.4 INFORMATIONAL SUBMITTALS

A. Preconstruction field-adhesion test reports.

B. Warranties.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. VOC Content of Interior Sealants: Sealants and sealant primers used inside the weatherproofing system shall comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24): 1. Architectural Sealants: 250 g/L. 2. Sealant Primers for Nonporous Substrates: 250 g/L. 3. Sealant Primers for Porous Substrates: 775 g/L.

07920-1

Technical Specifications Division 7 – Thermal and Moisture Protection

Section 07920 – Joint Sealants Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

B. Stain-Test-Response Characteristics: Where sealants are specified to be non-staining

to porous substrates, provide products that have undergone testing according to ASTM C 1248 and have not stained porous joint substrates indicated for Project.

C. Suitability for Contact with Food: Where sealants are indicated for joints that will come in repeated contact with food, provide products that comply with 21 CFR 177.2600.

2.2 SILICONE JOINT SEALANTS

A. Silicone Joint Sealant: ASTM C 920. 1. Manufacturers: Subject to compliance with requirements, available

manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. BASF Building Systems. b. Dow Corning Corporation. c. GE Advanced Materials - Silicones. d. May National Associates, Inc. e. Pecora Corporation. f. Polymeric Systems, Inc. g. Schnee-Morehead, Inc. h. Sika Corporation; Construction Products Division. i. Tremco Incorporated.

2. Type: Single component (S) 3. Uses Related to Exposure: Nontraffic (NT) 4. Locations: Exterior perimeter of storefront window assemblies.

2.3 LATEX JOINT SEALANTS

A. Latex Joint Sealant ASTM C 834, Type OP, Grade NF. 1. Manufacturers: Subject to compliance with requirements, available

manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following] a. BASF Building Systems. b. Bostik, Inc. c. May National Associates, Inc. d. Pecora Corporation. e. Schnee-Morehead, Inc. f. Tremco Incorporated.

2. Locations: Interior perimeter of storefront window assemblies.

2.4 JOINT SEALANT BACKING

A. Cylindrical Sealant Backings: ASTM C 1330, Type C (closed-cell material with a surface skin), Type O (open-cell material), Type B (bicellular material with a surface skin), or any of the preceding types, as approved in writing by joint-sealant manufacturer for joint application indicated, and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.

07920-2

Technical Specifications Division 7 – Thermal and Moisture Protection

Section 07920 – Joint Sealants Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

B. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant

manufacturer.

2.5 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials.

C. Masking Tape: Non-staining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

PART 3 - EXECUTION

3.1 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions. 1. Remove laitance and form-release agents from concrete. 2. Clean nonporous joint substrate surfaces with chemical cleaners or other means

that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.

B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

3.2 INSTALLATION

A. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

B. Install sealant backings of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability. 1. Do not leave gaps between ends of sealant backings.

07920-3

Technical Specifications Division 7 – Thermal and Moisture Protection

Section 07920 – Joint Sealants Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2. Do not stretch, twist, puncture, or tear sealant backings. 3. Remove absorbent sealant backings that have become wet before sealant

application and replace them with dry materials.

C. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.

D. Install sealants using proven techniques that comply with the following and at the same time backings are installed: 1. Place sealants so they directly contact and fully wet joint substrates. 2. Completely fill recesses in each joint configuration. 3. Produce uniform, cross-sectional shapes and depths relative to joint widths that

allow optimum sealant movement capability.

E. Tooling of Non-sag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint. 1. Remove excess sealant from surfaces adjacent to joints. 2. Use tooling agents that are approved in writing by sealant manufacturer and that

do not discolor sealants or adjacent surfaces. 3. Provide concave joint profile per Figure 8A in ASTM C 1193, unless otherwise

indicated.

F. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

3.3 FIELD QUALITY CONTROL

A. Field-Adhesion Testing: Field test joint-sealant adhesion to joint substrates as follows: 1. Test Method: Test joint sealants according to Method A, Field-Applied Sealant

Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

B. Evaluation of Field-Adhesion Test Results: Sealants not evidencing adhesive failure from testing or noncompliance with other indicated requirements will be considered satisfactory. Remove sealants that fail to adhere to joint substrates during testing or to comply with other requirements. Retest failed applications until test results prove sealants comply with indicated requirements.

07920-4

Technical Specifications Division 8 – Openings

Section 08511 – Aluminum Windows Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

SECTION 08511 – ALUMINUM WINDOWS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes aluminum windows for exterior locations.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: Include plans, elevations, sections, hardware, accessories, insect screens, operational clearances, and details of installation, including anchor, flashing, and sealant installation.

C. Product Schedule: For aluminum windows. Use same designations indicated on Drawings.

1.3 INFORMATIONAL SUBMITTALS

A. Product test reports.

B. Sample warranties.

1.4 WARRANTY

A. Manufacturer's Warranty: Manufacturer agrees to repair or replace aluminum windows that fail in materials or workmanship within specified warranty period. 1. Warranty Period:

a. Window: 10 years from date of Substantial Completion. b. Glazing Units: Five years from date of Substantial Completion. c. Aluminum Finish: 10 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Basis-of-Design Product: Subject to compliance with requirements, provide Series 250-V Top Hinged Projected Out windows as manufactured by Sum Metals Systems or comparable product by one of the following: 1. EFCO Corporation; a Pella company. 2. Kawneer North America; an Alcoa company.

08511-1

Technical Specifications Division 8 – Openings

Section 08511 – Aluminum Windows Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

3. Thermal Windows, Inc. 4. TRACO. 5. Winco. 6. YKK AP America Inc.

2.2 WINDOW PERFORMANCE REQUIREMENTS

A. Product Standard: AAMA/WDMA/CSA 101/I.S.2/A440. 1. Minimum Performance Class: HC. 2. Minimum Performance Grade: 100.

B. Thermal Transmittance: NFRC 100 maximum whole-window U-factor of 0.60 Btu/sq. ft.

x h x deg F.

C. Solar Heat-Gain Coefficient (SHGC): NFRC 200 maximum whole-window SHGC of 0.27.

D. Windborne-Debris Impact Resistance: Pass missile-impact and cyclic-pressure tests when tested according to ASTM E 1886 and testing information in ASTM E 1996.for an Ultimate Design Wind Speed of 147mph. 1. Large-Missile Test: For glazed openings located within 30 feet of grade.

2.3 ALUMINUM WINDOWS

A. Operating Types: Top Hinged Projected Out.

B. Frames and Sashes: Non-thermal aluminum extrusions complying with AAMA/WDMA/CSA 101/I.S.2/A440.

C. Glass: Reference Specifications Section 08800 Glazing for glass requirements.

D. Glazing System: Manufacturer's standard factory-glazing system that produces weather tight seal.

E. Projected Window Hardware: 1. Gear-Type Rotary Operators: Complying with AAMA 901 when tested according

to ASTM E 405, Method A. Provide operators that function without requiring the removal of interior screens or using screen wickets. a. Type and Style: As selected by Architect from manufacturer's full range of

types and styles. 2. Hinges: Non-friction type, not less than two per sash. 3. Lock: Manufacturer’s standard locking mechanism 4. Limit Devices: Manufacturer’s standard stainless steel limit stop device.

F. Weather Stripping: Provide full-perimeter weather stripping for each operable sash

unless otherwise indicated. 08511-2

Technical Specifications Division 8 – Openings

Section 08511 – Aluminum Windows Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

G. Fasteners: Noncorrosive and compatible with window members, trim, hardware, anchors, and other components. 1. Exposed Fasteners: Do not use exposed fasteners to the greatest extent

possible. For application of hardware, use fasteners that match finish hardware being fastened.

2.4 ACCESSORIES

A. Subsills: Non-thermal, extruded-aluminum subsills in configurations indicated on Drawings.

B. Column Covers: Extruded-aluminum profiles in sizes and configurations indicated on Drawings.

C. Interior Trim: Extruded-aluminum profiles in sizes and configurations indicated on Drawings.

D. Panning Trim: Extruded-aluminum profiles in sizes and configurations indicated on Drawings.

E. Receptor System: Two-piece, snap-together, thermally broken, extruded-aluminum receptor system that anchors windows in place.

2.5 INSECT SCREENS

A. General: Fabricate insect screens to integrate with window frame. Provide screen for each operable exterior sash. Screen wickets are not permitted. 1. Type and Location: Full, inside for project-out sashes.

B. Aluminum Frames: Complying with SMA 1004 or SMA 1201.

C. Glass-Fiber Mesh Fabric: 20-by-20 mesh complying with ASTM D 3656.

1. Mesh Color: Manufacturer's standard.

2.6 FABRICATION

A. Fabricate aluminum windows in sizes indicated. Include a complete system for assembling components and anchoring windows.

B. Glaze aluminum windows in the factory.

C. Weather strip each operable sash to provide weather tight installation.

D. Provide weep holes and internal passages to conduct infiltrating water to exterior.

08511-3

Technical Specifications Division 8 – Openings

Section 08511 – Aluminum Windows Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

E. Provide mullions and cover plates, matching window units, complete with anchors for

support to structure and installation of window units. Allow for erection tolerances and provide for movement of window units due to thermal expansion and building deflections, as indicated. Provide mullions and cover plates capable of withstanding design wind loads of window units.

F. Complete fabrication, assembly, finishing, hardware application, and other work in the factory to greatest extent possible. Disassemble components only as necessary for shipment and installation.

2.7 ALUMINUM FINISHES

A. Anodic Finish: Class I complying with AAMA 611. 1. Color: Clear.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with manufacturer's written instructions for installing windows, hardware, accessories, and other components. For installation procedures and requirements not addressed in manufacturer's written instructions, comply with installation requirements in ASTM E 2112.

B. Install windows level, plumb, square, true to line, without distortion or impeding thermal movement, anchored securely in place to structural support, and in proper relation to wall flashing and other adjacent construction to produce weather tight construction.

C. Install windows and components to drain condensation, water penetrating joints, and moisture migrating within windows to the exterior.

D. Separate aluminum and other corrodible surfaces from sources of corrosion or electrolytic action at points of contact with other materials.

E. Adjust operating sashes and hardware for a tight fit at contact points and weather stripping for smooth operation and weather tight closure.

F. Clean exposed surfaces immediately after installing windows. Avoid damaging protective coatings and finishes. Remove excess sealants, glazing materials, dirt, and other substances.

G. Remove and replace glass that has been broken, chipped, cracked, abraded, or damaged during construction period.

08511-4

Technical Specifications Division 8 - Openings

Section 08800 - Glazing Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

SECTION 08800 - GLAZING PART 1 - GENERAL

1.1 SUMMARY

A. Section includes glazing for the following products and applications, including those specified in other Sections where glazing requirements are specified by reference to this Section: 1. Storefront framing.

1.2 PERFORMANCE REQUIREMENTS

A. Provide glass and glazing materials for continuity of building enclosure vapor retarder and air barrier: 1. To utilize the inner pane of multiple pane units for the continuity of the air barrier

and vapor retarder seal.

B. Structural Design: Design in accordance with applicable code for most critical combination of wind, seismic and dead loads as well as required live impact loads for glass walls.

C. Size glass to withstand dead and live loads caused by positive and negative wind pressure acting normal to the plane of the wall, including building corners. 1. Design Wind Loads: As calculated in accordance with applicable code and ASCE

7, with basic wind speed exposure as indicated on Drawings.

D. Wind-Borne Debris Loads: Design and size glass located less than 60 feet above grade to withstand the following: 1. Glass Within 30 feet of Grade: ASTM 1996; large missile impact test. 2. Glass Within 60 feet of Grade: ASTM 1996; small missile impact test.

E. Seismic Loads: Design and size components to withstand seismic loads and sway

displacement as calculated in accordance with applicable code.

F. Limit Glass Deflection: Maximum differential deflection for two adjacent unsupported edges less than thickness of glass when 50 plf force applied to one panel at any point up to 42 inches above finished floor.

G. Thermal and Solar Optical Performance: Measured or calculated in accordance with the following: 1. U-Value: NFRC 100. 2. Solar Heat Gain Coefficients: NFRC 200. 3. Solar Optical Properties: NFRC 300.

08800-1

Technical Specifications Division 8 - Openings

Section 08800 - Glazing Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

1.3 ACTION SUBMITTALS

A. Product Data: For each glass product and glazing material indicated.

B. Glass Samples: For each type of glass product other than clear monolithic vision glass; 12 inches square.

C. Glazing Schedule: List glass types and thicknesses for each size opening and location. Use same designations indicated on Drawings.

D. Delegated-Design Submittal: For glass indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.4 QUALITY ASSURANCE

A. Glazing Publications: Comply with published recommendations of glass product manufacturers and organizations below, unless more stringent requirements are indicated. Refer to these publications for glazing terms not otherwise defined in this Section or in referenced standards. 1. GANA Publications: GANA's "Laminated Glazing Reference Manual"

and GANA's "Glazing Manual."

B. Safety Glazing Labeling: Where safety glazing labeling is indicated, permanently mark glazing with certification label of the SGCC or another certification agency acceptable to authorities having jurisdiction. Label shall indicate manufacturer's name, type of glass, thickness, and safety glazing standard with which glass complies.

1.5 WARRANTY

A. Manufacturer's Special Warranty on Laminated Glass: Manufacturer's standard form in which laminated-glass manufacturer agrees to replace laminated-glass units that deteriorate within specified warranty period. Deterioration of laminated glass is defined as defects developed from normal use that are not attributed to glass breakage or to maintaining and cleaning laminated glass contrary to manufacturer's written instructions. Defects include edge separation, delamination materially obstructing vision through glass, and blemishes exceeding those allowed by referenced laminated-glass standard. 1. Warranty Period: Five years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 GLASS PRODUCTS, GENERAL

A. Thickness: Where glass thickness is indicated, it is a minimum. Provide glass lights in thicknesses as needed to comply with requirements indicated.

08800-2

Technical Specifications Division 8 - Openings

Section 08800 - Glazing Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2.2 LAMINATED GLASS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. ACH Glass. 2. AFG Industries. 3. Guardian Industries. 4. Oldcastle Glass. 5. PPG Industries. 6. Viracon.

B. Windborne-Debris-Impact-Resistant Laminated Glass: ASTM C 1172, and complying

with testing requirements in 16 CFR 1201 for Category II materials, with "Windborne-Debris-Impact Resistance" Paragraph in "Glass Products, General" Article, and with other requirements specified. Use materials that have a proven record of no tendency to bubble, discolor, or lose physical and mechanical properties after fabrication and installation. 1. Construction: Laminate glass with one of the following to comply with interlayer

manufacturer's written recommendations: a. Polyvinyl butyral interlayer. b. Polyvinyl butyral interlayer’s reinforced with polyethylene terephthalate film. c. Ionoplast interlayer. d. Cast-in-place and cured-transparent-resin interlayer. e. Cast-in-place and cured-transparent-resin interlayer reinforced with

polyethylene terephthalate film. 2. Interlayer Thickness: Provide thickness not less than that indicated and as

needed to comply with requirements. 3. Interlayer Color: Clear unless otherwise indicated.

2.3 GLAZING GASKETS

A. Dense Compression Gaskets: Molded or extruded gaskets of profile and hardness required to maintain watertight seal, made from one of the following: 1. Neoprene 2. EPDM complying with ASTM C 864. 3. Silicone complying with ASTM C 1115.

B. Soft Compression Gaskets: Extruded or molded, closed-cell, integral-skinned

neoprene, EPDM, or silicone gaskets complying with ASTM C 509, Type II, black; of profile and hardness required to maintain watertight seal. 1. Application: Use where soft compression gaskets will be compressed by inserting

dense compression gaskets on opposite side of glazing or pressure applied by means of pressure-glazing stops on opposite side of glazing.

08800-3

Technical Specifications Division 8 - Openings

Section 08800 - Glazing Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2.4 MISCELLANEOUS GLAZING MATERIALS

A. Cleaners, Primers, and Sealers: Types recommended by sealant or gasket manufacturer.

B. Setting Blocks: Elastomeric material with a Shore, Type A durometer hardness of 85, plus or minus 5.

C. Spacers: Elastomeric blocks or continuous extrusions of hardness required by glass manufacturer to maintain glass lights in place for installation indicated.

D. Edge Blocks: Elastomeric material of hardness needed to limit glass lateral movement (side walking).

PART 3 - EXECUTION

3.1 GLAZING, GENERAL

A. Comply with combined written instructions of manufacturers of glass, sealants, gaskets, and other glazing materials, unless more stringent requirements are indicated, including those in referenced glazing publications.

B. Adjust glazing channel dimensions as required by Project conditions during installation to provide necessary bite on glass, minimum edge and face clearances, and adequate sealant thicknesses, with reasonable tolerances.

C. Protect glass edges from damage during handling and installation. Remove damaged glass from Project site and legally dispose of off Project site. Damaged glass is glass with edge damage or other imperfections that, when installed, could weaken glass and impair performance and appearance.

D. Apply primers to joint surfaces where required for adhesion of sealants, as determined by preconstruction testing.

E. Install setting blocks in sill rabbets, sized and located to comply with referenced glazing publications, unless otherwise required by glass manufacturer. Set blocks in thin course of compatible sealant suitable for heel bead.

F. Do not exceed edge pressures stipulated by glass manufacturers for installing glass lights.

G. Provide spacers for glass lights where length plus width is larger than 50 inches.

H. Provide edge blocking where indicated or needed to prevent glass lights from moving sideways in glazing channel, as recommended in writing by glass manufacturer and according to requirements in referenced glazing publications.

08800-4

Technical Specifications Division 8 - Openings

Section 08800 - Glazing Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

3.2 GASKET GLAZING (DRY)

A. Cut compression gaskets to lengths recommended by gasket manufacturer to fit openings exactly, with allowance for stretch during installation.

B. Insert soft compression gasket between glass and frame or fixed stop so it is securely in place with joints miter cut and bonded together at corners.

C. Installation with Drive-in Wedge Gaskets: Center glass lights in openings on setting blocks and press firmly against soft compression gasket by inserting dense compression gaskets formed and installed to lock in place against faces of removable stops. Start gasket applications at corners and work toward centers of openings. Compress gaskets to produce a weather tight seal without developing bending stresses in glass. Seal gasket joints with sealant recommended by gasket manufacturer.

D. Installation with Pressure-Glazing Stops: Center glass lights in openings on setting blocks and press firmly against soft compression gasket. Install dense compression gaskets and pressure-glazing stops, applying pressure uniformly to compression gaskets. Compress gaskets to produce a weather tight seal without developing bending stresses in glass. Seal gasket joints with sealant recommended by gasket manufacturer.

E. Install gaskets so they protrude past face of glazing stops.

3.3 CLEANING AND PROTECTION

A. Protect exterior glass from damage immediately after installation by attaching crossed streamers to framing held away from glass. Do not apply markers to glass surface. Remove nonpermanent labels and clean surfaces.

B. Protect glass from contact with contaminating substances resulting from construction operations. If, despite such protection, contaminating substances do come into contact with glass, remove substances immediately as recommended in writing by glass manufacturer.

C. Examine glass surfaces adjacent to or below exterior concrete and other masonry surfaces at frequent intervals during construction, but not less than once a month, for buildup of dirt, scum, alkaline deposits, or stains; remove as recommended in writing by glass manufacturer.

D. Remove and replace glass that is broken, chipped, cracked, or abraded or that is damaged from natural causes, accidents, and vandalism, during construction period.

08800-5

Technical Specifications Division 8 - Openings

Section 08800 - Glazing Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

NO TEXT THIS PAGE

08800-6

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

SECTION 09910 - PAINTING

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes surface preparation and field painting of exposed exterior and interior items and surfaces.

B. Paint exposed surfaces, except where these Specifications indicate that the surface or material is not to be painted or is to remain natural. If an item or a surface is not specifically mentioned, paint the item or surface the same as similar adjacent materials or surfaces. If a color of finish is not indicated, Architect will select from standard colors and finishes available. 1. Painting includes field painting of exposed bare and covered pipes and ducts

(including color coding), hangers, exposed steel and iron supports, and surfaces of mechanical and electrical equipment that do not have a factory-applied final finish.

C. Do not paint prefinished items, concealed surfaces, finished metal surfaces, operating parts, and labels. 1. Prefinished items include the following factory-finished components:

a. Architectural woodwork. b. Acoustical wall panels. c. Metal toilet enclosures. d. Metal lockers. e. Unit kitchens. f. Elevator entrance doors and frames. g. Elevator equipment. h. Finished mechanical and electrical equipment. i. Light fixtures.

2. Concealed surfaces include walls or ceilings in the following generally inaccessible spaces: a. Foundation spaces. b. Furred areas. c. Ceiling plenums. d. Utility tunnels. e. Pipe spaces. f. Duct shafts. g. Elevator shafts.

3. Finished metal surfaces include the following: a. Anodized aluminum. b. Stainless steel. c. Chromium plate. d. Copper and copper alloys. e. Bronze and brass.

09910-1

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

4. Operating parts include moving parts of operating equipment and the following: a. Valve and damper operators. b. Linkages. c. Sensing devices. d. Motor and fan shafts.

5. Labels: Do not paint over UL, FMG, or other code-required labels or equipment name, identification, performance rating, or nomenclature plates.

1.2 DEFINITIONS

A. General: Standard coating terms defined in ASTM D 16 apply to this Section. 1. Flat refers to a lusterless or matte finish with a gloss range below 15 when

measured at an 85-degree meter. 2. Eggshell refers to low-sheen finish with a gloss range between 20 and 35 when

measured at a 60-degree meter. 3. Semi-gloss refers to medium-sheen finish with a gloss range between 35 and

70 when measured at a 60-degree meter. 4. Full gloss refers to high-sheen finish with a gloss range more than 70 when

measured at a 60-degree meter.

1.3 SUBMITTALS

A. Product Data: For each paint system indicated. Include block fillers and primers. 1. Material List: An inclusive list of required coating materials. Indicate each

material and cross-reference specific coating, finish system, and application. Identify each material by manufacturer's catalog number and general classification.

2. Manufacturer's Information: Manufacturer's technical information, including label analysis and instructions for handling, storing, and applying each coating material.

B. Samples for Initial Selection: For each type of finish-coat material indicated. 1. After color selection, Architect will furnish color chips for surfaces to be coated.

C. Samples for Verification: For each color and material to be applied, with texture to simulate actual conditions, on representative Samples of the actual substrate. 1. Provide stepped Samples, defining each separate coat, including block fillers

and primers. Use representative colors when preparing Samples for review. Resubmit until required sheen, color, and texture are achieved.

2. Provide a list of materials and applications for each coat of each Sample. Label each Sample for location and application.

D. Qualification Data: For Applicator.

09910-2

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

1.4 QUALITY ASSURANCE

A. Applicator Qualifications: A firm or individual experienced in applying paints and coatings similar in material, design, and extent to those indicated for this Project, whose work has resulted in applications with a record of successful in-service performance.

B. Source Limitations: Obtain block fillers and primers for each coating system from the same manufacturer as the finish coats.

C. Benchmark Samples (Mockups): Provide a full-coat benchmark finish sample for each type of coating and substrate required. Duplicate finish of approved sample Submittals. 1. Architect will select one room or surface to represent surfaces and conditions

for application of each type of coating and substrate. a. Wall Surfaces: Provide samples on at least 50 sq. ft.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to Project site in manufacturer's original, unopened packages and containers bearing manufacturer's name and label and the following information: 1. Product name or title of material. 2. Product description (generic classification or binder type). 3. Manufacturer's stock number and date of manufacture. 4. Contents by volume, for pigment and vehicle constituents. 5. Thinning instructions. 6. Application instructions. 7. Color name and number. 8. VOC content.

B. Store materials not in use in tightly covered containers in a well-ventilated area at a minimum ambient temperature of 45 deg F. Maintain storage containers in a clean condition, free of foreign materials and residue. 1. Protect from freezing. Keep storage area neat and orderly. Remove oily rags

and waste daily.

C. Take precautionary measures to prevent fire hazards and spontaneous combustion.

1.6 PROJECT CONDITIONS

A. Apply waterborne paints only when temperatures of surfaces to be painted and surrounding air are between 50 and 90 deg F.

B. Do not apply paint in rain, fog, or mist; or when relative humidity exceeds 85 percent; or at temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.

09910-3

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

1. Painting may continue during inclement weather if surfaces and areas to be

painted are enclosed and heated within temperature limits specified by manufacturer during application and drying periods.

1.7 EXTRA MATERIALS

A. Furnish extra paint materials from the same production run as the materials applied and in the quantities described below. Package with protective covering for storage and identify with labels describing contents. Deliver extra materials to Owner. 1. Label each container with color, texture, sheen and location/room, in addition to

the manufacturer’s label. 2. Quantity: Furnish Owner with an additional 5 percent, but not less than 1 gal or

1 case, as appropriate, of each material and color applied.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers' Names: Shortened versions (shown in parentheses) of the following manufacturers' names are used in other Part 2 articles: 1. Benjamin Moore & Co. (Benjamin Moore). 2. Coronado Paint Company (Coronado). 3. Duron Paints and Wallcoverings (Duron). 4. PPG Industries, Inc. (Pittsburgh Paints). 5. Sherwin-Williams Co. (Sherwin-Williams).

B. For purpose of designating type and quality of paint required, "Painting Schedule" specified in this section is based on paints manufactured by Sherwin Williams Company.

1. "Paint Schedule" specifies the minimum number of primer and finish coats acceptable, which establishes the paint "system" required for the work.

2.2 PAINT MATERIALS, GENERAL

A. Material Compatibility: Provide block fillers, primers, and finish-coat materials that are compatible with one another and with the substrates indicated under conditions of service and application, as demonstrated by manufacturer based on testing and field experience.

B. Material Quality: Provide manufacturer's best-quality paint material of the various coating types specified that are factory formulated and recommended by manufacturer for application indicated. Paint-material containers not displaying manufacturer's product identification will not be acceptable.

C. Colors: As indicated in Finish Schedule or drawings provided for the Project.

09910-4

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2.3 EXTERIOR FINISH COATS

A. Exterior Flat Acrylic Paint: Factory-formulated flat acrylic-emulsion latex paint for exterior application. 1. Sherwin-Williams; Resilience Exterior Latex Flat, K42 Series: Applied at a dry

film of not less than 1.56 mils.

B. Exterior Semi-gloss Acrylic Enamel: Factory-formulated satin acrylic-emulsion latex paint for exterior application. 1. Sherwin-Williams; Resilience Exterior Satin Latex, K43 Series: Applied at a dry

film of not less than 1.52 mils.

C. Exterior Gloss Acrylic Paint: Factory-formulated gloss acrylic-latex gloss for exterior application. 1. Sherwin-Williams; Resilience Exterior Satin Latex, K44 Series: Applied at a dry

film of not less than 1.6 mils.

D. Exterior Gloss Acrylic Enamel for Ferrous and Other Metals: Factory-formulated full-gloss waterborne acrylic-latex enamel for exterior application. 1. Sherwin-Williams; Pro Industrial Enamel Alkyd Urethane B54 Series: Applied at

a dry film thickness of not less than 2.0 mils.

E. Exterior Semi-Gloss Acrylic Paint: Factory-formulated waterborne semi-gloss for exterior application. 1. Sherwin-Williams; Pro Industrial HP Acrylic Semi-Gloss B66 Series: Applied at

a dry film thickness of not less than 2.5 mils.

F. Exterior Gloss Acrylic Paint: Factory-formulated waterborne semi-gloss for exterior application. 1. Sherwin-Williams; Pro Industrial HP Acrylic Gloss B66 Series: Applied at a dry

film thickness of not less than 2.5 mils.

G. Exterior Gloss Polyamide Epoxy: Factory-formulated polyamide gloss epoxy for exterior application to ferrous metals. 1. Sherwin-Williams; Macropoxy 646 HS FC Epoxy B58 Series: Applied at a dry

film thickness of not less than 5.0 mils.

H. Exterior Waterproof Coating: Factory-formulated acrylic waterproof coating for above grade masonry surfaces. 1. Sherwin-Williams; Loxon XP Waterproof Coating A24 Series: Applied at a dry

film thickness of not less than 6.4 mils.

09910-5

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2.4 INTERIOR FINISH COATS

A. Interior Flat Acrylic Paint: Factory-formulated flat acrylic-emulsion latex paint for interior application. 1. Sherwin-Williams; Harmony Interior Latex Flat Wall Paint, B5 Series: Applied

at a dry film thickness of not less than 1.5 mils.

B. Interior Eg-Shell Acrylic Paint: Factory-formulated eg-shell acrylic-emulsion. 1. Sherwin-Williams; Harmony Eg-Shell Wall Paint B9 Series: Applied at a dry

film thickness of not less than 1.7 mils.

C. Interior Semi-gloss Acrylic: Factory-formulated semi-gloss acrylic-latex for interior application. 1. Sherwin-Williams; Harmony Interior Latex Semi-Gloss Enamel B10 Series:

Applied at a dry film thickness of not less than 1.6 mils.

D. Interior Full-Gloss Acrylic Enamel: Factory-formulated full-gloss acrylic-latex interior enamel. 1. Sherwin-Williams; ProClassic Interior Latex Gloss Enamel B21: Applied at a

dry film thickness of not less than 1.5 mils.

E. Interior Semi-gloss Alkyd Enamel: Factory-formulated semi-gloss alkyd enamel for interior application. 1. Sherwin-Williams; ProClassic Interior Alkyd Semi-Gloss Enamel B34 Series:

Applied at a dry film thickness of not less than 1.6 mils.

F. Interior Semi-Gloss Epoxy for Gypsum Board and Plaster: Factory-formulated waterborne epoxy for interior application. 1. Sherwin-Williams; ProIndustrial Pre-Catalyzed Epoxy Semi-Gloss K46 Series:

Applied at a dry film thickness of not less than 1.5 mils.

G. Interior Eg-Shell Multi-Purpose Coating: Factory-formulated waterborne acrylic multi-purpose coating. 1. Sherwin-Williams; ProIndustrial Multi-Surface Acrylic Eg-Shell B66 Series:

Applied at a dry film thickness of not less than 1.5 mils.

H. Interior Gloss Multi-Purpose Coating: Factory-formulated waterborne acrylic multi-purpose coating. 1. Sherwin-Williams; ProIndustrial Multi-Surface Acrylic Gloss B66 Series:

Applied at a dry film thickness of not less than 1.5 mils.

09910-6

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2.5 PRIMERS

A. Exterior Chalky Surface Conditioner. 1. Sherwin-Williams; Loxon Masonry Conditioner A24 Series: Applied at 200-300

square feet per gallon.

B. Exterior/Interior Waterborne Rust-Inhibitive Primer. 1. Sherwin-Williams; ProIndustrial ProCryl Universal Metal Primer B66-300

Series: Applied at a dry film thickness of not less than 2 mils.

C. Exterior Ferrous Metal Polyamide Epoxy Primer. 1. Sherwin-Williams; Macropoxy HS FC Epoxy B58 Series: Applied at a dry film

thickness of not less than 5.0 mils.

D. MultiPurpose Waterbased Acrylic Latex Primer. 1. Sherwin-Williams; MultiPurpose Interior/Exterior Latex Primer/Sealer

B51W451: Applied at a dry film thickness of not less than 1.4 mils.

2.6 REPAIR MATERIALS

A. Texture Coating-Sherwin Williams; UltraCrete Acrylic Texture Coating; A44 Series. Applied at 50-80 square feet per gallon. Finishes applicable are Fine, Medium and Extra Coarse.

B. Elastomeric Patching Compound-Sherwin Williams; Concrete & Masonry Patching Compound; A5 Series.

2.7 Sealants;

A. Polyurethane-Sherwin Williams; Stampede IH Polyurethane Sealant; 1638758.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Applicator present, for compliance with requirements for paint application. 1. Proceed with paint application only after unsatisfactory conditions have been

corrected and surfaces receiving paint are thoroughly dry. 2. Start of painting will be construed as Applicator's acceptance of surfaces and

conditions within a particular area.

B. Coordination of Work: Review other Sections in which primers are provided to ensure compatibility of the total system for various substrates. On request, furnish information on characteristics of finish materials to ensure use of compatible primers.

09910-7

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

3.2 PREPARATION

A. General: Remove hardware and hardware accessories, plates, machined surfaces, lighting fixtures, and similar items already installed that are not to be painted. If removal is impractical or impossible because of size or weight of the item, provide surface-applied protection before surface preparation and painting. 1. After completing painting operations in each space or area, reinstall items

removed using workers skilled in the trades involved.

B. Cleaning: Before applying paint or other surface treatments, clean substrates of substances that could impair bond of the various coatings. Remove oil and grease before cleaning. 1. All surfaces to be painted shall be cleaned and prepared as specified. The

painting contractor is responsible for the finish of his work. Should any surface be found unsuitable to produce a proper paint or sealant finish, the Owner or Owner's agent shall be notified, in writing, and no materials shall be applied until the unsuitable surfaces have been made satisfactory. Coating performance is affected by proper product selection, application, and surface preparation. Coating integrity and service life will be reduced because of improperly prepared surfaces. The selection and implementation of proper surface preparation ensures coating adhesion to the substrate and prolongs the service life of the coating system.

2. Maintenance painting will frequently not permit or require complete removal of all old coatings prior to repainting. However, ALL surface contamination such as oil, grease, loose and marginally adhering paint, mill scale, dirt, foreign matter, rust, mold, mildew, mortar, efflorescence and sealers must be removed to assure sound bonding to the tightly adhering old paint. In addition, glossy surfaces of old paint films must be clean and dull before repainting. Spot prime all bare areas with the appropriate primer. Recognize that any surface preparation short of total removal of the old coatings may compromise the service length of the system. Always check for compatibility of the previously painted surface with the new coating by applying a test patch of 2-3 square feet. Allow to dry thoroughly, check adhesion.

3. All exterior surfaces must be thoroughly pressure cleaned using a pressure washer at 2500 PSI and a 15 degree tip held no more than 12" from the surface to insure the surface is cleaned free of all loose, scaling, and marginally adhering paint, all chalk, mildew, stains, dirt, grease or other foreign material. Surface must be firm, clean and dry before proceeding. All loose and scaling paint not removed by pressure cleaning shall be removed by wire brushing or other suitable power tool cleaning. Remove mildew using a solution of chlorine bleach and water mixed to a ratio of 1 part chlorine bleach and 3 parts water. Taking extreme care not to get solution on adjacent vegetation. Allow solution to remain on the surface for 10 minutes before rinsing thoroughly with clean water.

09910-8

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

CAUTION: DO NOT ADD HOUSEHOLD DETERGENTS OR AMMONIA TO THE BLEACH SOLUTION. Wear protective glasses or goggles, waterproof gloves, and protective clothing. Quickly wash off with soap and clean water any solution that touches the skin. Wet any shrubbery in the area where cleaning prior to use of any bleach and water mixture rinse completely after area cleaned.

C. Surface Preparation: Clean and prepare surfaces to be painted according to manufacturer's written instructions for each particular substrate condition and as specified. 1. Provide barrier coats over incompatible primers or remove and reprime. 2. Cementitious Materials: Prepare concrete, concrete unit masonry, cement

plaster, and mineral-fiber-reinforced cement panel surfaces to be painted. Remove efflorescence, chalk, dust, dirt, grease, oils, and release agents. Roughen as required to remove glaze. If hardeners or sealers have been used to improve curing, use mechanical methods of surface preparation. a. Use abrasive blast-cleaning methods if recommended by paint

manufacturer. b. Determine alkalinity and moisture content of surfaces by performing

appropriate tests. If surfaces are sufficiently alkaline to cause the finish paint to blister and burn, correct this condition before application. Do not paint surfaces if moisture content exceeds that permitted in manufacturer's written instructions.

c. Clean concrete floors to be painted with a 5 percent solution of muriatic acid or other etching cleaner. Flush the floor with clean water to remove acid, neutralize with ammonia, rinse, allow to dry, and vacuum before painting.

3. Wood: Clean surfaces of dirt, oil, and other foreign substances with scrapers, mineral spirits, and sandpaper, as required. Sand surfaces exposed to view smooth and dust off. a. Scrape and clean small, dry, seasoned knots, and apply a thin coat of

white shellac or other recommended knot sealer before applying primer. After priming, fill holes and imperfections in finish surfaces with putty or plastic wood filler. Tint fillers to match wood. Sand smooth when dried.

b. Prime, stain, or seal wood to be painted immediately on delivery. Prime edges, ends, faces, undersides, and back sides of wood, including cabinets, counters, cases, and paneling.

c. Backprime paneling on interior partitions where masonry, plaster, or other wet wall construction occurs on back side.

4. Ferrous Metals: Clean un-galvanized ferrous-metal surfaces that have not been shop coated; remove oil, grease, dirt, loose mill scale, and other foreign substances. Use solvent or mechanical cleaning methods that comply with SSPC's recommendations. a. Blast steel surfaces clean as recommended by paint system

manufacturer. b. Treat bare and sandblasted or pickled clean metal with a metal treatment

wash coat before priming.

09910-9

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

c. Touch up bare areas and shop-applied prime coats that have been

damaged. Wire-brush, clean with solvents recommended by paint manufacturer, and touch up with same primer as the shop coat.

5. Galvanized Surfaces: Clean galvanized surfaces with nonpetroleum-based solvents so surface is free of oil and surface contaminants. Remove pretreatment from galvanized sheet metal fabricated from coil stock by mechanical methods.

D. Material Preparation: Mix and prepare paint materials according to manufacturer's written instructions. 1. Maintain containers used in mixing and applying paint in a clean condition, free

of foreign materials and residue. 2. Stir material before application to produce a mixture of uniform density. Stir as

required during application. Do not stir surface film into material. If necessary, remove surface film and strain material before using.

3. Use only thinners approved by paint manufacturer and only within recommended limits.

3.3 APPLICATION

A. General: Apply paint according to manufacturer's written instructions. Use applicators and techniques best suited for substrate and type of material being applied. 1. Paint colors, surface treatments, and finishes are indicated in the paint

schedules. 2. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or

conditions detrimental to formation of a durable paint film. 3. Provide finish coats that are compatible with primers used. 4. The term "exposed surfaces" includes areas visible when permanent or built-in

fixtures, grilles, convector covers, covers for finned-tube radiation, and similar components are in place. Extend coatings in these areas, as required, to maintain system integrity and provide desired protection.

5. Paint surfaces behind movable equipment and furniture the same as similar exposed surfaces. Before final installation of equipment, paint surfaces behind permanently fixed equipment or furniture with prime coat only.

6. Paint interior surfaces of ducts with a flat, non-specular black paint where visible through registers or grilles.

7. Paint back sides of access panels and removable or hinged covers to match exposed surfaces.

8. Finish exterior doors on tops, bottoms, and side edges the same as exterior faces.

B. Scheduling Painting: Apply first coat to surfaces that have been cleaned, pretreated, or otherwise prepared for painting as soon as practicable after preparation and before subsequent surface deterioration.

09910-10

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

1. The number of coats and film thickness required are the same regardless of

application method. Do not apply succeeding coats until previous coat has cured as recommended by manufacturer. If sanding is required to produce a smooth, even surface according to manufacturer's written instructions, sand between applications.

2. Omit primer over metal surfaces that have been shop primed and touchup painted.

3. If undercoats, stains, or other conditions show through final coat of paint, apply additional coats until paint film is of uniform finish, color, and appearance. Give special attention to ensure that edges, corners, crevices, welds, and exposed fasteners receive a dry film thickness equivalent to that of flat surfaces.

4. Allow sufficient time between successive coats to permit proper drying. Do not recoat surfaces until paint has dried to where it feels firm, and does not deform or feel sticky under moderate thumb pressure, and until application of another coat of paint does not cause undercoat to lift or lose adhesion.

C. Application Procedures: Apply paints and coatings by brush, roller, spray, or other applicators according to manufacturer's written instructions. 1. Brushes: Use brushes best suited for type of material applied. Use brush of

appropriate size for surface or item being painted. 2. Rollers: Use rollers of carpet, velvet-back, or high-pile sheep's wool as

recommended by manufacturer for material and texture required. 3. Spray Equipment: Use airless spray equipment with orifice size as

recommended by manufacturer for material and texture required.

D. Minimum Coating Thickness: Apply paint materials no thinner than manufacturer's recommended spreading rate to achieve dry film thickness indicated. Provide total dry film thickness of the entire system as recommended by manufacturer.

E. Mechanical and Electrical Work: Painting of mechanical and electrical work is limited to items exposed in equipment rooms and occupied spaces.

F. Mechanical items to be painted include, but are not limited to, the following: 1. Un-insulated metal piping. 2. Pipe hangers and supports. 3. Tanks that do not have factory-applied final finishes. 4. Visible portions of internal surfaces of metal ducts, without liner, behind air

inlets and outlets. 5. Duct, equipment, and pipe insulation having "all-service jacket" or other

paintable jacket material. 6. Mechanical equipment that is indicated to have a factory-primed finish for field

painting.

G. Electrical items to be painted include, but are not limited to, the following: 1. Switchgear. 2. Panelboards. 3. Electrical equipment that is indicated to have a factory-primed finish for field

painting.

09910-11

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

H. Block Fillers: Apply block fillers to concrete masonry block at a rate to ensure complete coverage with pores filled.

I. Prime Coats: Before applying finish coats, apply a prime coat, as recommended by manufacturer, to material that is required to be painted or finished and that has not been prime coated by others. Recoat primed and sealed surfaces where evidence of suction spots or unsealed areas in first coat appears, to ensure a finish coat with no burn-through or other defects due to insufficient sealing.

J. Pigmented (Opaque) Finishes: Completely cover surfaces as necessary to provide a smooth, opaque surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections will not be acceptable.

K. Completed Work: Match approved samples for color, texture, and coverage. Remove, refinish, or repaint work not complying with requirements.

3.4 CLEANING

A. Cleanup: At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from Project site. 1. After completing painting, clean glass and paint-spattered surfaces. Remove

spattered paint by washing and scraping without scratching or damaging adjacent finished surfaces.

3.5 PROTECTION

A. Protect work of other trades, whether being painted or not, against damage from painting. Correct damage by cleaning, repairing or replacing, and repainting, as approved by Architect.

B. Provide "Wet Paint" signs to protect newly painted finishes. After completing painting operations, remove temporary protective wrappings provided by others to protect their work. 1. After work of other trades is complete, touch up and restore damaged or

defaced painted surfaces. Comply with procedures specified in PDCA P1.

3.6 EXTERIOR PAINT SCHEDULE

A. EPS-1 Concrete, Stucco, and Masonry: Provide the following finish systems over existing exterior concrete, stucco, CMU and brick masonry substrates: 1. Flat Acrylic Finish: Two finish coats over a primer.

a. Primer: Loxon Masonry Conditioner, Clear or Pigmented, A24 Series. b. Finish Coats: Resilience Exterior Latex Flat, K42 Series.

2. Satin Acrylic Finish: Two finish coats over a primer. a. Primer: Loxon Masonry Conditioner, Clear or Pigmented, A24 Series. b. Finish Coats: Resilience Exterior Latex Satin, K43 Series.

09910-12

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

3. Gloss Acrylic Finish: Two finish coats over a primer.

a. Primer: Loxon Masonry Conditioner, Clear or Pigmented, A24 Series. b. Finish Coats: Resilience Exterior Latex Gloss, K44 Series.

B. EPS-2 Wood: Provide the following finish systems over smooth wood siding, wood trim, and other smooth exterior wood surfaces: 1. Flat Acrylic Finish: Two finish coats over a primer.

a. Primer: Exterior wood primer for acrylic enamels. b. Finish Coats: Exterior flat acrylic paint.

2. Semi-gloss Acrylic-Enamel Finish: Two finish coats over a primer. a. Primer: Exterior wood primer for acrylic enamels. b. Finish Coats: Exterior semi-gloss acrylic enamel.

C. EPS-4 Ferrous Metal: Provide the following finish systems over existing exterior ferrous metal. 1. Eg-Shell Acrylic Finish: Two finish coats over a rust-inhibitive primer.

a. Primer: ProIndustrial ProCryl Universal Metal Primer, B66 Series. b. Finish Coat: ProIndustrial High Performance Acrylic Eg-Shell, B66

Series. 2. Semi-gloss Acrylic-Enamel Finish: Two finish coats over a rust-inhibitive

primer. a. Primer: ProIndustrial ProCryl Universal Metal Primer, B66 Series. b. Finish Coat: ProIndustrial High Performance Acrylic Eg-Shell, B66

Series. 3. Gloss Acrylic-Enamel Finish: Two finish coats over a rust-inhibitive primer.

a. Primer: ProIndustrial ProCryl Universal Metal Primer, B66 Series. b. Finish Coat: ProIndustrial High Performance Acrylic Eg-Shell, B66

Series.

D. EPS-5 Ferrous Metal: Provide the following finish systems over exterior exposed metal surfaces: 1. Semi-Gloss Polyurethane Finish: Two finish coats over an epoxy primer.

a. Primer: Macropoxy 646 HS FC Epoxy, B58 Series. b. Finish Coat: Acrolon 218 HS Polyurethane, B65 Series.

2. Gloss Polyurethane Finish: Two finish coats over an epoxy primer. a. Primer: Macropoxy 646 HS FC Epoxy, B58 Series. b. Finish Coats: Acrolon 218 HS Polyurethane, B65 Series.

E. EPS-6 Aluminum: Provide the following finish systems over existing exterior aluminum surfaces: 1. Eg-Shell Acrylic Finish: Two finish coats over a primer.

a. Primer: Loxon Masonry Conditioner Clear or Pigmented, A24 Series. b. Finish Coats: ProIndustrial High Performance Acrylic Eg-Shell, B66

Series.

09910-13

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

2. Semi-gloss Acrylic-Enamel Finish: Two finish coats over a primer. a. Primer: Loxon Masonry Conditioner Clear or Pigmented, A24 Series. b. Finish Coats: ProIndustrial High Performance Acrylic Semi-Gloss, B66

Series. 3. Gloss Acrylic-Enamel Finish: Two finish coats over a primer.

a. Primer: Loxon Masonry Conditioner Clear or Pigmented, A24 Series. b. Finish Coats: ProIndustrial High Performance Acrylic Semi-Gloss, B66

Series.

3.7 INTERIOR PAINT SCHEDULE

A. IPS-1 Concrete and Masonry: Provide the following paint systems over existing interior concrete, CMU and brick masonry substrates: 1. Flat Acrylic Finish: Two finish coats over a primer.

a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: Harmony Interior Latex Flat Wall Paint, B5 Series.

2. Eg-Shell Acrylic Finish: Two finish coats over a primer. a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: Harmony Interior Latex Eg-Shell Wall Paint, B9 Series.

3. Semi-gloss Acrylic-Enamel Finish: Two finish coats over a primer. a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: Harmony Interior Latex Semi-Gloss, B10 Series.

B. IPS-2 Epoxy on Concrete Unit Masonry: Provide the following finish system over existing concrete unit masonry surfaces. 1. Semi-Gloss Finish: Two finish coats over a primer.

a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: ProIndustrial Pre-Catalyzed Epoxy Semi-Gloss, K46

Series.

C. IPS-3 Gypsum Board: Provide the following finish systems over existing interior gypsum board surfaces: 1. Flat Acrylic Finish: Two finish coats over a primer.

a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: Harmony Interior Latex Flat Wall Paint, B5 Series.

2. Eg-Shell Acrylic Finish: Two finish coats over a primer. a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: Harmony Interior Latex Flat Wall Paint, B9 Series.

3. Semi-Gloss Acrylic Finish: Two finish coats over a primer. a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: Harmony Interior Latex Flat Wall Paint, B10 Series.

D. IPS-4 Epoxy on Gypsum Board: Provide the following finish system over existing gypsum board surfaces:

09910-14

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

1. Semi-Gloss Finish: Two finish coats over a primer. a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: ProIndustrial Pre-Catalyzed Epoxy Semi-Gloss, K46

Series.

E. IPS-5 Wood and Hardboard: Provide the following paint finish systems over existing interior wood surfaces: 1. Waterborne Acrylic Gloss: Two finish coats over a primer.

a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: ProClassic Interior Latex Gloss Enamel B21 Series.

2. Alkyd Semi-Gloss: Two finish coats over a primer. a. Primer: Multipurpose Interior/Exterior Primer/Sealer, B51W450. b. Finish Coats: ProClassic Interior Alkyd Semi-Gloss Enamel B34 Series.

F. IPS-6 Ferrous Metal: Provide the following finish systems over existing ferrous metal: 1. Eg-Shell Acrylic Finish: Two finish coats over a rust inhibitive primer.

a. Primer: ProIndustrial ProCryl Universal Metal Primer, B66 Series. b. Finish Coats: ProIndustrial High Performance Acrylic Eg-Shell, B66

Series. 2. Semi-gloss Acrylic-Enamel Finish: Two finish coats over a rust inhibitive

primer. a. Primer: ProIndustrial ProCryl Universal Metal Primer, B66 Series. b. Finish Coats: ProIndustrial High Performance Acrylic Semi-Gloss, B66

Series. 3. Gloss Acrylic-Enamel Finish: Two finish coats over a rust inhibitive primer.

a. Primer: ProIndustrial ProCryl Universal Metal Primer, B66 Series. b. Finish Coats: ProIndustrial High Performance Acrylic Gloss, B66 Series.

09910-15

Technical Specifications Division 9 - Finishes

Section 09910 - Painting Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

NO TEXT THIS PAGE

09910-16

Technical Specifications Division 10 - Specialties

Section 10710 – Hurricane Screens Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

SECTION 10710 – HURRICANE SCREENS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. All aluminum screen frames with stainless steel wire mesh units covered under this specification shall be of the fixed type, consisting of a main frame and wire cloth. No plastic, steel or galvanized steel parts shall be accepted. Screens shall be permanently installed. Screens with hinges and locking systems shall not be accepted.

1.2 ACTION SUBMITTALS

A. Product Data: For aluminum frames and screen material.

B. Fabrication Drawings: Include the following information:

1. Elevation drawings of each screen assembly. 2. Installation details including fastener size, spacing and embedment.

1.3 INFORMATIONAL SUBMITTALS

A. Warranties.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Mainframe:

1. Hollow extruded aluminum alloy minimum 6063 T6 with a minimum 2 3/8” face, 1 ¼” thick and .062 wall thickness. .

2. Minimum tensile strength: 22,000 lbs. per square inch. 3. Finish: Frame and sash profiles to be standard Kynar Powder Coated,

electrostatic applied, and baked on. Standard color White.

B. Wire Lock retainers:

1. Screen wire lock retainers shall be of solid extruded aluminum alloy of 6063 T6 with a minimum wall thickness of .062 and having a minimum tensile strength of 22,000 lbs. per square inch.

10710-1

Technical Specifications Division 10 - Specialties

Section 10710 – Hurricane Screens Sunken Gardens Improvements FY15 –

Turner House Window Replacement Project No. 15211-019

C. Screen Wire

1. High tensile 304 stainless steel mesh with 12 x 12 strands per inch at 0.028 diameter. Screen wire mesh shall be one continuous piece with 1” wide, 90 degree bends on all four sides.

2. Screen wire to be corrosion pre-treated and powder coated with standard Kynar Powder Coat, electrostatic applied, and baked on, black only.

D. Hardware.

1. All fasteners, screws and other miscellaneous fastening hardware components shall be of aluminum, stainless steel or salt sprayed coated galvanized steel.

2.2 MANUFACTURERS

A. Basis of Design Product: Subject to compliance with requirements, provide Storm Safe Fixed Impact Screens as manufactured by QMI and distributed by Roll-A-Way.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with manufacturer's written instructions for installing hurricane screens, hardware, accessories, and other components.

B. Install hurricane screens level, plumb, square, true to line, without distortion, anchored securely in place to structural support, and in proper relation window opening and other adjacent construction.

C. Timber Frame Typhoon Installation: Fasteners for installation to wood framing shall be ¼” lag wood screw anchors of sufficient length to achieve a minimum embedment of 1-5/16” into wood framing. Spacing screws per approval documents.

D. The exposed surfaces of all aluminum members, screen material, and screws shall be clean and free from serious surface blemishes. Clean exposed surfaces immediately after installing windows. Avoid damaging protective coatings and finishes. Remove excess sealants, glazing materials, dirt, and other substances.

E. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

10710-2

CERTIFICATE OF INSURANCE