Summary of Rosemont Copper Aquifer Protection StudiesTRANSCRIPT
10 rosemont copper - a bridge to a sustainable future
Aquifer Protection
Agency CorrespondenceTITLE: Initial Hydrology for Rosemont Copper
OperationsRELEASE DATE: October 2009PREPARED BY: Arizona Department of Environmental
Quality
TITLE: Rosemont Copper Co NADS 1 090408RELEASE DATE: April 2009PREPARED BY: Arizona Department of Environmental
Quality
TITLE: Rosemont Copper Co RAIS 041410RELEASE DATE: April 2010PREPARED BY: Arizona Department of Environmental
Quality
TITLE: Incomplete Response to Substantive Deficiencies
RELEASE DATE: December 2010PREPARED BY: Arizona Department of Environmental
Quality
Aquifer Protection Permit ApplicationTITLE: Rosemont Copper APP Appl . Volumes . 1-4cRELEASE DATE: February 2009PREPARED BY: Tetra Tech for submission to ADEQ
Rosemont ResponseTITLE: Response to Notice of Administrative
Deficiencies Letter (Transmittal of documents requested in letter April 4, 2009)
RELEASE DATE: May 2009PREPARED BY: Rosemont Copper
TITLE: Incomplete Response to Substantive Deficiencies, Inventory Number 106100
RELEASE DATE: January 2010PREPARED BY: Rosemont Copper
Aquifer protection studies looked at the flow of water at the Rosemont project site to determine potential long-term impact on the quality and quantity of water in the area .
Aquifer Protection
10 rosemont copper - a bridge to a sustainable future
rosemont copper - a bridge to a sustainable future 11
Technical Response Part 1TITLE: Comprehensive Request for Additional
Information (Response to ADEQ)RELEASE DATE: July 2010PROVIDED BY: Kimberlite Water Quality Permitting and
Compliance ServicesBrief Summary: This July 2010 letter from Kimberlite
Water Quality Permitting and Compliance Services (Rosemont’s engineering consultants) responds to an ADEQ letter from April 2010 that made specific requests for additional technical information about the Rosemont operations. The April 2010 ADEQ letter was part of the technical review of Rosemont’s application for an Aquifer Protection Permit, submitted in March 2009.
TITLE: Site Water Management Update, Volumes 1 - 5RELEASE DATE: April 2010PREPARED BY: Tetra Tech
TITLE: Infiltration, Seepage, Fate and Transport Modeling Report
RELEASE DATE: February 2010PREPARED BY: Tetra TechBrief Summary: The projected amounts and quality of
water entering (infiltration) and leaving (seepage) three of Rosemont’s facilities have been thoroughly scrutinized. This report from Tetra Tech presents the results of infiltration and seepage, and fate (altered chemistry) and transport modeling for the proposed Waste Rock Storage Area, the Heap Leach Facility, and the Dry Stack Tailings Facility. Detailed laboratory studies and predictive modeling (including waste rock, heap leach residuals, and dry stack tailings residuals) for the three Rosemont facilities show that they will have little or no impact on the quality or quantity of water within the regional groundwater system. Another site-wide particle tracking model (fate and transport analysis) has been completed by Tetra Tech to confirm that these three facilities will not impact the regional system.
TITLE: Tailings GeochemistryRELEASE DATE: March 2009PREPARED BY: Tetra TechBrief Summary: Rosemont’s geochemistry studies
evaluated the potential impact to the regional aquifer from water emerging from the project site, especially from the Waste Rock Storage Area, Heap Leach Facility and Dry Stack Tailings Facility. This report from Tetra
Tech covers four samples of tailings material that were generated and tested for acid-generation capacity and release of metals. Tests conclude that water outflow will be no more acidic than present groundwater and concentrations of most specific metals were below detection in all of the samples. Overall, the geochemistry studies found little to no probability of pollution of the area aquifers.
TITLE: POC Well Diagram RPI-WSRELEASE DATE: July 2010
TITLE: Revisions to Figure 23 of APP ApplicationRELEASE DATE: July 2010PREPARED BY: Tetra Tech
TITLE: Rosemont Well Inventory UpdateRELEASE DATE: January 2010PREPARED BY: Tetra Tech
TITLE: Water Level Hydrographs 2007-2010RELEASE DATE: July 2010PREPARED BY: Montgomery & Associates
TITLE: Groundwater Level Contours and Depth to Water 2010RELEASE DATE: July 2010PREPARED BY: Montgomery & Associates
TITLE: Summary of Groundwater Level Measurements for Wells, Piezometers and Drill Holes
RELEASE DATE: July 2010PREPARED BY: Montgomery & Associates
TITLE: Site Surface Soils GeochemistryRELEASE DATE: January 2010PREPARED BY: Tetra Tech
TITLE: Surface Water Sample Sites, Cienega Creek and Davidson Canyon
RELEASE DATE: July 2010PREPARED BY: Montgomery & Associates
TITLE: Geochemical Sample Composite MethodRELEASE DATE: November 2009PREPARED BY: Tetra Tech
Technical Response Part 2TITLE: Attachment 1: Groundwater Flow Modeling
Conducted for Simulation of Proposed Rosemont Pit Dewatering and Post-Closure Revised Report
RELEASE DATE: August 2010PREPARED BY: Montgomery & Associates
TITLE: Attachment 2: Rosemont Groundwater Flow Model Summary
RELEASE DATE: August 2010PREPARED BY: Montgomery & Associates
TITLE: Attachment 3: SRK Consulting Technical Review of Montgomery’s 2009 Groundwater Flow Model
RELEASE DATE: August 2010PREPARED BY: SRK Consulting
TITLE: Attachment 4: Rosemont Geochemical Pit Lake Predictive Model Summary
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 5: Rosemont Area-Wide Fate and Transport and DIA Summary
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 6: Rosemont Infiltration, Seepage, Fate and Transport Modeling Report Update
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 7: Technical Review of Tetra Tech’s Feb . 2010 Infiltration, Seepage, and Fate and Transport Modeling Report
RELEASE DATE: April 2010PREPARED BY: SRK Consulting
TITLE: Attachment 8: Physical and Mechanical Properties of Tailing and Waste Rockfill Materials
RELEASE DATE: August 2010PREPARED BY: AMEC
TITLE: Attachment 9: Rosemont Tailing Geochemistry Sample Sources
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 10: Rosemont Heap Leach Design Responses
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
12 rosemont copper - a bridge to a sustainable future
TITLE: Attachment 11: Rosemont Flow-Through Drain Design Summary
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 12: PWTS Pond and Settling Basin Design Revisions
RELEASE DATE: August 2010PREPARED BY: M3 Engineering & Technology
TITLE: Attachment 13: Rosemont BADCT Analysis for the PWTS Pond
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 14: Rosemont Settling Basin BADCT Analysis
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 15: Rosemont Waste Rock Segregation Plan
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 16: Rosemont APP-Regulated Facility Locations
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 17: Rosemont APP-Regulated Facility Depth to Groundwater
RELEASE DATE: August 2010PREPARED BY: Tetra Tech
TITLE: Attachment 18: Non-Municipal Solid Waste Landfill Application Revised
RELEASE DATE: August 2010PREPARED BY: Civil and Environmental Consultants, Inc.
TITLE: Comprehensive Request for Additional Information RELEASE DATE: August 2010PREPARED BY: Kimberlite Water Quality Permitting and
Compliance ServiceBrief Summary: This report from Kimberlite provides
responses and supporting information to the remaining comments from the ADEQ April 2010 letter that contained 52 specific requests for additional technical information about the Rosemont project. The August 2010 letter includes the following supplemental
information:• Tetra Tech Groundwater Flow Model summary, dated
August 31, 2010.• Tetra Tech Geochemical Pit Lake Predictive Model
Summary, dated August 24, 2010.• Tetra Tech Area-Wide Fate and Transport and DIA
Summary, dated August 31, 2010.•Civil and Environmental Consultants, Inc. (CEC) Non-
Municipal Solid Waste Landfill Application, dated August 2010.