ARCHITECT'S FIELD OBSERVATION REPORT Lilburn Library City Hall Library/City Hall Construction 340 Main Street Lilburn, Georgia (US) Report number: A10154GSB-9 Date: September 25, 2015 03:00 PM Work in Progress No work was in progress due to rain. Weather Conditions: Rain and 65 Degrees Contract Date: 07-20-2015 Substantial Completion Date: 09-18-2016 Substantial Completion Date modified by Change Order: 09-18-2016 Contacts and people present Role and company name Name Contact information Present Sent Owner [Gwinnett County ] Gray Booth [email protected] Contractor, Superintendent [Hogan Constuction ] Don Borth [email protected] Contractor, Sr. Project Manager [Hogan Construction] Lisa Tatum [email protected] Contractor, Project Manager [Hogan Construction] Omid Yavari [email protected] Contractor, Project Engineer [Hogan Construction] Zach Limbaugh [email protected] Architect, Project Architect [Precision Planning, Inc.] Jerry Dennis [email protected] The purpose of this field report is to document the project progress and general conformance with the construction documents. Precision Planning, Inc. has not been hired to provide safety inspection services. General Contractor shall be wholly responsible for project safety and, as such, must have all procedures in place to protect workers and public. Precision Planning, Inc. is not responsible for safety procedures for this project and will not be held liable for safety of persons or property while on site or as documented in field report. Observations Report created by Jerry W. Dennis II, AIA [email protected] 1 / 15 Precision Planning, Inc. 400 Pike Boulevard Lawrenceville, Georgia 30046

Upload: others

Post on 26-Jan-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

ARCHITECT'S FIELD OBSERVATION REPORT

Lilburn Library City Hall Library/City Hall Construction340 Main StreetLilburn, Georgia (US)Report number: A10154GSB-9Date: September 25, 2015 03:00 PM

Work in Progress

No work was in progress due to rain.

Weather Conditions: Rain and 65 Degrees

Contract Date: 07-20-2015Substantial Completion Date: 09-18-2016Substantial Completion Date modified by Change Order: 09-18-2016

Contacts and people present

Role and company name Name Contact information Present Sent

Owner [Gwinnett County ]

Gray Booth [email protected]

✔ ✔

Contractor, Superintendent [Hogan Constuction ]

Don Borth [email protected]

✘ ✔

Contractor, Sr. Project Manager [Hogan Construction]

Lisa Tatum [email protected]

✘ ✔

Contractor, Project Manager [Hogan Construction]

Omid Yavari [email protected]

✔ ✔

Contractor, Project Engineer [Hogan Construction]

Zach Limbaugh [email protected]

✔ ✔

Architect, Project Architect [Precision Planning, Inc.]

Jerry Dennis [email protected]

✔ ✔

The purpose of this field report is to document the project progress and general conformance with the construction documents. PrecisionPlanning, Inc. has not been hired to provide safety inspection services. General Contractor shall be wholly responsible for project safety and,as such, must have all procedures in place to protect workers and public. Precision Planning, Inc. is not responsible for safety procedures forthis project and will not be held liable for safety of persons or property while on site or as documented in field report.

Observations

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

Remark Description

General

• Sitework [9.1] Photos show retention pond. There is some silt that is evident at the inlet pipe. Comparison againstprevious photos show that this has been present. It is unclear based on observation if this condition isworsening over time.

• Sitework [9.2] View of North Construction Entrance. The Jobsite trailer is on site, but not yet set up for operations.

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Sitework [9.3] View of North Sediment pond. Stone maintenance is required at inlet.

• Sitework [9.4] View of project site looking southeast toward construction entrance.

Excess suitable soils are being removed from the project site.

• Rock [9.5] View of rock stockpiled on site. This material should be included in the haul off quantites

• Site utilities storedmaterial [9.6]

View of storm utility materials stored on site.

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Sitework [9.7] Photo series shows panoramic view of site looking at library building pad, site looking toward city hallbuilding pad and north toward parking lot.

• Sitework [9.8] View of southeast construction entrance. Erosion control measures are in place and functioning properly

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Roadwork [9.9] ER Snell equipment is on the right of way and work is being performed on curb and gutter in several areas.These photos are included to document work by other forces in the vicinity of our construction limits and arefor information only.

• Sitework [9.10] Photo series shows perimeter erosion control measures along Church street and Main street

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Sitework [9.11] Photo series shows parnoramic view of site looking east toward city hall, and main street

• Erosion control[9.12]

Erosion control measures at the northwest construction entrance. The measures are functioning properly.Howerver, there is heavy silt buildup at the outer fenceline.

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Erosion control[9.13]

Erosion control measures at the bottom of the north slope of the site. There is a small washout that requiresattention in this location.

• Site work [9.14] View of northern sediment traps

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Grassing [9.15] Temporary grassing is being established.

• Erosion control[9.16]

View of north sediment trap. Inlet needs stone maintenance around the east side.

Concrete

• Reinforcement [9.17] View of concrete reinforcement stored on site.

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Foundations [9.18] Foundations for the city hall are in place. Photo of highlighted foundation plan shows all foundations inplace as of the date of this report.

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Foundations [9.19] Foundations for the city hall are in place. Refer to attached exhibit highlighting installed footings to date

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Slab blockouts [9.20] Floor slab block outs are being installed.

Plumbing

• Stored materials[9.21]

Plumbing DIP materials are on site and being installed.

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Under slab roughinG[9.22]

Photo series shows plumbing drains under slab at city hall 1) View of plumbing at Col line B1.6 looking west 2) View of main waste line at Col line B8 looking east 3) View of main waste line at Col line 1.6 looking north 4) View of plumbing at Col line 2.4 5) View of main waste line at Col line B8 looking east 6) View of plumbing west of Col line 3 looking north 7) View of plumbing at Janitor 120

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

• Under slab roughin[9.23]

View of main waste line at Col line B8 looking west

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

Electrical

• Stored matrial [9.24] Electrical materials are stored on site and being installed

• Under slab rough in[9.25]

Photo series shows electrical under slab installation at Col line B

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046

DISCUSSIONS ON SITE

None

General conditions

Disclaimer: Site visits performed by the Architect under this contract have been conducted under the limited conditions as described by siteobservations in the General Conditions of the Contract for Construction, as referenced in the Owner-Architect Agreement.

Information contained in this Field Observation Report by firm name has been prepared to the best of our knowledge according toobservable conditions at the site. This information will be approved record unless written notice to the contrary is received within seven (7)calendar days of the issue date of this document. Written corrections shall be reported to observer at firm name. Oral rebuttals will not beaccepted.

Report created by Jerry W. Dennis II, AIA [email protected] / 15

Precision Planning, Inc.400 Pike Boulevard

Lawrenceville, Georgia 30046