asi chap004

43
Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved Whitten Bentley Dittm SYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition 4 C H A P T E R PROJECT MANAGEMENT

Upload: putra-tidore

Post on 10-May-2015

236 views

Category:

Education


0 download

DESCRIPTION

Analisis Sistem Informasi

TRANSCRIPT

Page 1: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

4C H A P T E R

PROJECT MANAGEMENT

Page 2: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Chapter Four Project Management

• Define the terms project and project management, and differentiate between project and process management.

• Describe the causes of failed information systems and technology projects.• Describe the basic competencies required of project managers.• Describe the basic functions of project management.• Differentiate between PERT and Gantt charts as project management tools.• Describe the role of project management software as it relates to project

management tools.• Describe eight activities in project management.• Define joint project planning and its role in project management.• Define scope and a write a statement of work to document scope.• Use a work breakdown structure to decompose a project into tasks.• Estimate tasks’ durations, and specify intertask dependencies on a PERT chart.• Assign resources to a project and produce a project schedule with a Gantt chart.• Assign people to tasks and direct the team effort.• Use critical path analysis to adjust schedule and resource allocations in response to

schedule and budget deviations.• Manage user expectations of a project and adjust project scope.

Page 3: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Chapter Map

Page 4: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Project and Project Management

A project is a [temporary] sequence of unique, complex, and connected activities having one goal or purpose and that must be completed by specific time, within budget, and according to specification.

Project management is the process of scoping, planning, staffing, organizing, directing, and controlling the development of an acceptable system at a minimum cost within a specified time frame.

Page 5: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Project versus Process Management

Project management is the process of scoping, planning, staffing, organizing, directing, and controlling the development of an acceptable system at a minimum cost within a specified time frame.

Process management is an ongoing activity that documents, manages the use of, and improves an organization’s chosen methodology (the “process”) for system development. Process management is concerned with the activities, deliverables, and quality standards to be applied to all projects.

Page 6: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Measures of Project Success

– The resulting information system is acceptable to the customer.

– The system was delivered “on time.”

– The system was delivered “within budget.”– The system development process had a

minimal impact on ongoing business operations.

Page 7: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Causes of Project Failure

• Failure to establish upper-management commitment to the project

• Lack of organization’s commitment to the system development methodology

• Taking shortcuts through or around the system development methodology

• Poor expectations management• Premature commitment to a fixed budget and schedule• Poor estimating techniques• Overoptimism• The mythical man-month (Brooks, 1975)• Inadequate people management skills• Failure to adapt to business change• Insufficient resources• Failure to “manage to the plan”

Page 8: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Project Manager Competencies

• Business awareness

• Business partner orientation

• Commitment to quality

• Initiative

• Information gathering

• Analytical thinking

• Conceptual thinking

• Interpersonal awareness

• Organizational awareness

• Anticipation of impact

• Resourceful use of influence

• Motivating others

• Communication skills

• Developing others

• Monitoring and controlling

• Self-confidence

• Stress management

• Concern for credibility

• Flexibility

(Adapted from Wysocki, Beck, and Crane, Effective Project Management: How to Plan, Manage, and Deliver Projects on Time

and within Budget.)

Page 9: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Project Management Functions

– Scoping

– Planning

– Estimating

– Scheduling

– Organizing

– Directing      

– Controlling

– Closing

Page 10: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Project Management Tools & Techniques

A PERT chart is a graphical network model that depicts a project’s tasks and the relationships between those tasks.

A Gantt chart is a simple horizontal bar chart that depicts project tasks against a calendar. Each bar represents a named project task. The tasks are listed vertically in the left-hand column. The horizontal axis is a calendar timeline.

Page 11: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

PERT Chart

5-3-2001 5-12-2001

5-3-2001 5-11-2001

Preliminary Investigation

5-12-2001 6-12-2001

5-12-2001 6-14-2001

Problem Analysis

5-28-2001 7-15-2001

5-30-2001 7-18-2001

Requirements Analysis

6-13-2001 7-30-2001

6-13-2001 8-3-2001

Decision Analysis

9-10-2001 12-14-2001

TBD TBD

Implementation

7-19-2001 11-13-2001

7-20-2001 In Progress

Construction

7-3-2001 9-25-2001

7-5-2001 10-9-2001

Design

5-3-2001 N/A

5-3-2001 N/A

Project Initiation

ScheduledStart

ScheduledFinish

Actual Start ActualFinish

Task

ScheduledStart

ScheduledFinish

Actual Start ActualFinish

Task

intertaskdependency

Legend

Page 12: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Gantt Chart

Incomplete Task

Complete Task

Legend

ID

1

2

3

4

5

6

7

Preliminary investigation

Problem analysis

Requirements analysis

Decision analysis

Design

Construction

Implementation

May Jun Jul Aug Sep Oct Nov Dec

2001Task Name

Today

Page 13: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Microsoft Project Gantt Chart

Page 14: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Microsoft Project PERT Chart

Page 15: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Project Management Life Cycle

Page 16: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Joint Project Planning Strategy

Joint project planning (JPP) is a strategy wherein all stakeholders in a project (meaning system owners, users, analysts, designers, and builders) participate in a one-to-three day project management workshop, the result of which is consensus agreement on project scope, schedule, resources, and budget. (Of course, subsequent workshops or meetings may be required to adjust scope, budget, and schedule.)

Page 17: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Activity 1: Negotiate Scope

Scope defines the boundaries of a project—What part of the business is to be studied, analyzed, designed, constructed, implemented, and ultimately improved?

– Product – Quality – Time – Cost – Resources

A statement of work is a narrative description of the work to be performed as part of a project. Common synonyms include scope statement, project definition, project overview, and document of understanding.

Page 18: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Statement of Work

I. PurposeII. Background

A. Problem, opportunity, or directive statementB. History leading to project requestC. Project goal and objectivesD. Product description

III. Scope(notice the use of your information system building blocks)A. StakeholdersB. DataC. ProcessesD. Locations

IV. Project ApproachA. RouteB. Deliverables

V. Managerial ApproachA. Team building considerationsB. Manager and experienceC. Training requirementsD. Meeting schedulesE. Reporting methods and frequencyF. Conflict managementG. Scope management (continued)

Page 19: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Statement of Work (concluded)

VI. ConstraintsA. Start dateB. DeadlinesC. BudgetD. Technology

VII. Ballpark EstimatesA. ScheduleB. Budget

VIII. Conditions of SatisfactionA. Success criteriaB. AssumptionsC. Risks

IX. Appendices

Page 20: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Activity 2: Identify Tasks

A work breakdown structure (WBS) is a hierarchical decomposition of the project into phases, activities, and tasks.

Milestones are events that signify the accomplishment or completion of major deliverables during a project.

Page 21: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Work Breakdown Structures

1 Phase 1 of the project …2 Phase 2 of the project …

2.1 Activity 1 of Phase 2 …

2.2 Activity 2 of Phase 22.2.1 Task 1 of Activity

2.2 in Phase 22.2.2 Task 2 of Activity

2.2 in Phase 22.2.3 Task 3 of Activity

2.2 in Phase 22.3 Activity 3 of Phase 2

…3 Phase 3 of the project …

=

PROJECTGOAL

0

PHASE

2

PHASE

3

PHASE

1

ACTIVITY

2.2

ACTIVITY

2.1

ACTIVITY

2.3

TASK

2.2.2

TASK

2.2.1

TASK

2.2.3

Page 22: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Activity 3: Estimate Task Durations

1.  Estimate the minimum amount of time it would take to perform the task. We'll call this the optimistic duration (OD).

2.  Estimate the maximum amount of time it would take to perform the task. We'll call this the pessimistic duration (PD).

3.  Estimate the expected duration (ED) that will be needed to perform the task.

4.  Calculate the most likely duration (D) as follows:

D = (1 x OD) + (4 x ED) + (1 x PD) 6

Page 23: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Activity 4: Specify Intertask Dependencies

• Finish-to-start (FS)—The finish of one task triggers the start of another task.

• Start-to-start (SS)—The start of one task triggers the start of another task.

• Finish-to-finish (FF)—Two tasks must finish at the same time.

• Start-to-finish (SF)—The start of one task signifies the finish of another task.

Page 24: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Entering Intertask Dependencies

Page 25: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Scheduling Strategies

Forward scheduling establishes a project start date and then schedules forward from that date. Based on the planned duration of required tasks, their interdependencies, and the allocation of resources to complete those tasks, a projected project completion date is calculated.

Reverse scheduling establishes a project deadline and then schedules backward from that date. Essentially, tasks, their duration, interdependencies, and resources must be considered to ensure that the project can be completed by the deadline.

Page 26: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

A Project Calendar

Page 27: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Activity 5: Assign Resources

• People—inclusive of all the system owners, users, analysts, designers, builders, external agents, and clerical help that will be involved in the project in any way, shape, or form.

• Services—a service such as a quality review that may be charged on a per use basis.

• Facilities and equipment—including all rooms and technology that will be needed to complete the project.

• Supplies and materials—everything from pencils, paper, notebooks, toner cartridges, etc.

• Money—A translation of all of the above into the language of accounting—budgeted dollars!

Page 28: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Defining Project Resources

Page 29: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Assigning Project Resources

Page 30: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Resource Leveling

Resource leveling is a strategy used to correct resource overallocations by some combination of delaying or splitting tasks.

There are two techniques for resource leveling:

• task delaying• task splitting

Page 31: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Task Splitting and Delaying

• The critical path for a project is that sequence of dependent tasks that have the largest sum of most likely durations. The critical path determines the earliest possible completion date of the project.

– Tasks that are on the critical path cannot be delayed without delaying the entire project schedule. To achieve resource leveling, critical tasks can only be split.

• The slack time available for any noncritical task is the amount of delay that can be tolerated between the starting time and completion time of a task without causing a delay in the completion date of the entire project.

– Tasks that have slack time can be delayed to achieve resource leveling

Page 32: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Activity 6: Direct the Team Effort

• Supervision resources– The DEADLINE – A Novel

About Project Management – The One Minute Manager– The Care and Feeding of

Monkeys

• Stages of Team Maturity (see figure to the right)

Ÿ Establish structure and rulesŸ Clarify team member relationshipsŸ Identify responsibilitiesŸ Develop a plan to achieve goals

ORIENTATION STAGE

Ÿ Resolve interpersonal conflictŸ Further clarify rules and goalsŸ Develop a participative climate

INTERNAL PROBLEM-SOLVING STAGE

Ÿ Direct team activity toward goalsŸ Provide and get feedbackŸ Share ideas–growing cohesionŸ Individuals feel good about each other

GROWTH AND PRODUCTIVITY STAGE

Ÿ More feedback and evaluationŸ Adherence to team normsŸ Roles of team strengthenedŸ Strong team motivation to share goals

EVALUATION AND CONTROL STAGE

FORMING

STORMING

NORMING

PERFORMING

Page 33: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Activity 7: Monitor and Control Progress

• Progress reporting

• Change management

• Expectations management

• Schedule adjustments—critical path analysis (CPA)

Page 34: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Sample Outline for a Progress Report

I. Cover PageA. Project name or identificationB. Project managerC. Date or report

II. Summary of progressA. Schedule analysisB. Budget analysisC. Scope analysis (describe any changes that may have an impact on future progress)D. Process analysis (describe any problems encountered with strategy or methodology)E. Gantt progress chart(s)

III. Activity analysisA. Tasks completed since last reportB. Current tasks and deliverablesC. Short term future tasks and deliverables

IV. Previous problems and issuesA. Action item and statusB. New or revised action items 1. Recommendation 2. Assignment of responsibility 3. Deadline

(continued)

Page 35: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Sample Outline for a Progress Report (concluded)

V. New problems and issuesA. Problems (actual or anticipated)B. Issues (actual or anticipated)C. Possible solutions 1. Recommendation 2. Assignment of responsibility 3. Deadline

VI. Attachments(include relevant printouts from project management software)

Page 36: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Progress on a Gantt Chart

Page 37: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Expectations Management

An expectations management matrix is a rule-driven tool for helping management understand the dynamics and impact of changing project parameters such as cost, schedule, scope, and quality.

Page 38: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Lunar Project Expectations Management

Page 39: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Typical, Initial Expectations for a Project

Page 40: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Adjusting Expectations

Page 41: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Changing Priorities

Page 42: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Critical Path Analysis (and Slack Time)

1. Using intertask dependencies, determine every possible path through the project.

2. For each path, sum the durations of all tasks in the path.

3. The path with the longest total duration is the critical path.– The critical path for a project is that sequence of

dependent tasks that have the largest sum of most likely durations. The critical path determines the earliest completion date of the project.

– The slack time available for any noncritical task is the amount of delay that can be tolerated between the starting time and completion time of a task without causing a delay in the completion date of the entire project.

Page 43: Asi Chap004

Irwin/McGraw-Hill Copyright © 2000 The McGraw-Hill Companies. All Rights reserved

Whitten Bentley DittmanSYSTEMS ANALYSIS AND DESIGN METHODS 5th Edition

Critical Path

The critical path is highlighted in red

TASK C

Fri 2/9/01 2 days

Fri 2/9/01 0 days

TASK D

Tue 2/20/01 7 days

Tue 2/20/01 0 days

TASK I

Tue 2/27/01 5 days

Tue 2/27/01 0 days

TASK E

Mon 2/19/01 6 days

Tue 2/20/01 1 day

TASK B

Wed 2/7/01 2 days

Wed 2/7/01 0 days

TASK A

Mon 2/5/01 3 days

Mon 2/5/01 0 days

TASK H

Thu 2/15/01 1 day

Tue 2/20/01 3 days

TASK F

Wed 2/14/01 3 days

Fri 2/16/01 2 days

TASK G

Fri 2/16/01 2 days

Tue 2/20/01 2 days

Duration

Slack Time