aspera-3 sep. 25, 00 monthly status report aspera monthly status reportmonthly 9_25/ page 1 monthly...

15
ASPERA-3 Sep. 25, 00 Monthly Status Report ASPERA Monthly Status Report Monthly 9_25/ Page 1 Monthly Status Report Report due 9/25/00 Schedule statused as of Sep. 1, 2000

Upload: jemima-reed

Post on 28-Dec-2015

230 views

Category:

Documents


0 download

TRANSCRIPT

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 1

Monthly Status ReportReport due 9/25/00

Schedule statused as of Sep. 1, 2000

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 2

Project Status Summary

Technical

Jul Aug Sep

Detailed Description: (for items identified as yellow or red)

Programmatic

Jul Aug Sep

Schedule

Jul Aug Sep

Resources

Jul Aug Sep

•Over the last period we continued with flight fabrication. We also delivered prototypes of ELS and IMA to Europe as pathfinders for future flight model testing.

•A new concern surfaced over the last month. The MCPs delivered to us from IRF for IMA had several blemishes and stains. We sent these parts back to IRF for further disposition. We are in the process of updating our test flow / delivery to reflect the uncertainty regarding the MCPs.

•The manufacture of the high tolerance ELS parts by an outside subcontractor continues to be a concern. The late delivery of the parts will likely effect final flight unit delivery

• Latest project photos and videos are available on Aspera-3 web site.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 3

Problem and Concern Summary

P=Problem C=Concern R=Resolved

Description Item Month ID'D Jun July Aug SepAssembly process for ELS w/ Coating

March RDelivery of MCPs for ELS from Burle April C C RFine alignment of ELS April <C C C CAlignment of Pogos in IMA June C <C RMCP mount in IMA June C C RHigh background rate in ELS July C RMCPs in IMA Sep C

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 4

Accomplishments of the Last Month -ELS

• Received finished machined sets 1 and 2 from Hyperfine. Parts do not meet spec but may be acceptable as flight spare.

• Hyperfine thinks they have determined the reason for out of spec condition. Process will be modified on set #3.

• Parts were delivered to Walton Plating for UV blackening. We have received the first (which is the better machined) set back. Second set is held up while Walton personnel are on vacation.

• Started rough machining of a third set of parts to supply to Hyperfine.

• Delivered prototype ELS to MSSL to be used as a pathfinder for flight and flight spare sensor calibration.

• Delivered ELS STM to IRF on 8/28/00.• Both amp boards are complete, inspected and bench tested.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 5

Accomplishments of the Last Month –ELS (cont.)

• HVPS #1 is complete, inspected, bench tested and characterized over temperature. HVPS #2 is complete, inspected, bench tested and will be characterized over temperature 9/22-9/25.

• Electronics set #1 has been integrated together and have completed functional and thermal test. Electronics set #2 will be integrated, functionally tested and thermal cycled starting 9/26.

• Met with FMI (DPU and flight software lead) following ASPERA-3 team meeting. We reviewed ELS electrical interface, characterization of the DPU over temperature, flight software and ELS data compression techniques.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 6

Accomplishments of the Last Month - IMA

• Assembled flight and flight spare electronics for thermal test (w/o MCPs). Completed test with no anomalies.

• Inspected flight MCPs in preparation for flight assembly of both units. Identified several blemishes and “stains”. Sent the MCPs back to IRF for their disposition.

• Have started discussions with IRF about potential new plan where we deliver IMA electronics to IRF sans MCPs. IRF assumes the responsibility for MCP installation (with our support) and testing after MCP installation. This change should not effect our delivery date or budget.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 7

Accomplishments of the Last Month - Data Reduction Software

• Began Addressing TBDs in the APAF Software Development Plan (SDP), V1.1– Will Release Version 1.2 November, 2000

• Began Updates to the APAF Project Data Management Plan (PDMP), V1.0 per PDS Comments

– Will Release Version 1.1 December, 2000

• Delivered APAF Data System Interface Document (DSID), V1.0 to PDS– Waiting for Feedback

• APAF Software Requirements Documentation is Currently on Hold Due to Lack of Information Concerning ASPERA-3 Packet Definitions

• Continued Providing Technical Assistance for EPO Web Information• Continued Defining and Implementing IDFS Web Tools• Provided Software Support for ELS Characterization• Held monthly ASPERA-3 Software Status Meeting (September 22, 2000)

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 8

Planned Activities for the Next Month - ELS

• (Hopefully) receive MCP flight set 5 to complete the order.

• Finish rough machining set #3 parts. Deliver parts to Hyperfine. Receive high tolerance parts from Hyperfine.

• Deliver parts to England for UV coating.

• Finish flight electronics #2 thermal test.

• Assemble flight spare unit.

• Begin flight spare unit characterization and high voltage testing.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 9

Planned Activities for the Next Month - IMA

• Assemble flight and flight spare units with dummy MCPs.

• Perform vibe test on both units.

• Start vacuum testing beginning with high voltage breakdown tests.

• Begin characterization testing.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 10

Planned Activities for the Next Month - Data Reduction Software

Tasks

• Continue Providing Technical Assistance for EPO Web Information

• Continue Defining and Implementing IDFS Web Tools

• Continue Addressing TBDs in the APAF Software Development Plan (SDP), V1.1

• Continue Updates to the APAF Project Data Management Plan (PDMP), V1.0

• Begin Defining Packet Definitions for ELS

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 11

Problem and Concern Status

Alignment of ELS :• This remains our biggest concern. We have received two sets of parts from

Hyperfine. None of the parts meet spec though they may be acceptable as flight spare. We are rough machining another set of parts for Hyperfine per their new directions and process.* The parts will then be sent to Hyperfine for precision machining. Walton Plating is shut down until Oct 10. We are shooting to have set #3 to Walton at that time for UV blackening. The problems with the machining and blackening will likely cause us to slightly slip delivery of ELS. We have discussed this with IRF & MSSL. They do not see any problems with slipping the delivery. We will be discussing this officially with them and NASA in the coming week.

*Hyperfine’s theory on why the parts are out of spec is that too little material was left for the precision machining operation. The rough machining since it was to near final dimensions effected the grain structure of the part making it impossible for Hyperfine to precision machine the part to the specified tolerance. The rough machining of the next set of parts will leave much more material so that the grain structure is not disturbed.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 12

Problem and Concern Status (cont.)

IMA MCPs :• A new concern: we inspected the IMA MCPs during the last

month and identified several blemishes and stains. These plates were procured and provided as CFE by IRF. We sent the plates back to IRF for IRF to disposition. At IRF’s suggestion, we are looking at modifying our test and delivery plan to deliver IMA to IRF without MCPs. This places the responsibility for the MCPs solely on IRF and protects our schedule and budget. The proposed test plan (which will be discussed with IRF and NASA) still has us performing vibration, high voltage, and characterization testing of both IMA units. We will also support IRF post-delivery for MCP installation and testing. The proposed plan does not effect our delivery schedule or budget.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 13

Schedule Summary

ELS: The manufacture of the high precision parts to spec and the subsequent UV blackening is the critical path on the schedule for delivery of the flight unit.

• We are currently updating the schedule to reflect the latest knowledge about availability of personnel and current plan for testing and delivery.

• Discussions with IRF / NASA / MSSL will continue and will be finalized in the coming weeks.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 14

Schedule Summary (cont.)

IMA: Likewise, we are in the process of updating our schedule to reflect the new proposed plan for delivery of IMA. We feel confident that we can still make the current delivery date under the new plan and are still planning on a Pre-ship Review the week of Nov. 13. The new schedule / plan will be reported upon at the upcoming Monthly Status Telcon.

• Software activities continue to be on schedule. • The full-up schedule is available on the ASPERA-

3 Web site.

ASPERA-3

Sep. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 9_25/ Page 15

ASPERA-3 PHASE B/C/D MASTER SCHEDULEJ J A S O N D2003

J J A S O N D J F M A M2002

J J A S O N D J F M A M2001

J J A S O N D J F M A M2000

J J A S O N D J F M A M

MAJOR MILESTONES / REVIEWS

Southwest Research Institute Approval: John Scherrer, Project Mgr.

Orig Approval: 6/25/99 Last Change: 8/13/99 Status As Of: 9/01/00

MA1999

INSTRUMENT DEVELOPMENTELS

Rev: A - ELS STM Delivery Revised to 9/05/00

ESA LAUNCH

- Electron Spectrometer Imager

MCPs Avail

ELSPDR

Denotes a Change/Slip

MechanicalDesignDetail DesignMechanical FabricationMicrochannel Plates (MCP’s)

MCP ProcurementMCP Characterization

Structural Thermal Model (STM) FabricationSTM Test & Delivery

IRF ELS & IMADelivery to ESA

CDRKEY

MAJOR MILESTONE

SCHEDULED START

SCHEDULED COMPLETION

EARLY START/COMPLETIONLATE START/COMPLETION

RESERVES

CRITICAL PATH

SUMMARY

STM

STM DeliveryElectrical

HVPS DesignHVPS LayoutHVPS FabricationHVPS Testing

HV Power Supply (HVPS)

Anode Board Design ModificationsAnode PWA LayoutAnode FabricationAnode Testing

Anode Assemby

Sensor Integration & TestSensor Assembly

Sensor Bench TestSensor Testing & Characterization (@ SwRI)

ELS FM/Flt. SpareDelivery to IRF

ELS Calibration (@ IRF) & Delivery to ESA

IMA- Ion Mass Analyzer ImagerIMAPDR

Prototype Development

IMA Definition

CDR

SwRI ELS FM/FS Delivery

Prototype DesignPrototype LayoutPrototype Fabrication & Testing

Flt. Model / Flt. Spare DevelopmentFM/FS Design ModificationFM/FS LayoutFM/FS Fabrication & AssemblyMCP Need Date MCP’s

Req’dIMA FM/FS Deliveryto ASPERA / ESA

SwRI IMA FM/FSDelivery

FM Sensor Characterization (@ SwRI)IMA Calibration (@ IRF) & Delivery to ESA

Processing SoftwareSoftware Concept & RequirementsVirtual Instrument DesignVirtual Instrument S/W CodingVirtual Instrument S/W Testing

S/W Integration w/Sensor Calibration

SwRI ELS &IMA Delivto IRF

Instrument SupportEngineering SupportScience Planning & SupportSoftware Development & Support

IMA FM/FS I&T

FP

F

FP

P

P

FP

FP

FSP

FSP

FP

FP

FP

P

F

F

P PROTOTYPE

F FLIGHT

P

Deliver IMA Prototype

F

ASPERAICDR

ASPERAPDR

ELS FM/FS Deliveryto ASPERA / ESA

IMA FM/Flt. SpareDelivery to IRF

9/30/07

P

P

F

MCP’s Returned to IRF for Rework