assembly line balancing jaime joo mba 530 – section 1 brigham young university

28
Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Upload: howard-singleton

Post on 20-Jan-2016

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Assembly Line Balancing

Jaime Joo

MBA 530 – Section 1

Brigham Young University

Page 2: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Outline• What is Assembly Line Balancing?

• How can Assembly Line Balancing benefit your operations?

• Classic approach to ALB

• Let’s practice!

• ALB in the real world

• Conclusions

Page 3: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

What is Assembly Line Balancing (ALB)?

ALB is the procedure to assign tasks to workstations so that:

•Precedence relationship is complied with

•No workstation takes more than the cycle time to complete

•Operational idle time is minimized

Page 4: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

How can Assembly Line Balancing benefit your operations?

A balanced line:• Promotes one piece flow• Avoids excessive work load in some stages

(overburden)• Minimizes wastes (over-processing, inventory,

waiting, rework, transportation, motion)• Reduces variation

Page 5: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Unbalanced Line

Work Station 1

Work Station 4

Work Station 3

Work Station 2

!? Zzz Zzz

10 sec 40 sec! 20 sec 15 sec

Overproduction!

Generates waste

Undesirable waiting

Page 6: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Balanced Line

Work Station 1

Work Station 4

Work Station 3

Work Station 2

25 sec 25 sec 20 sec 15 sec

•Promotes one piece flow

•Avoids overburden

•Minimizes wastes

•Reduces variation

Page 7: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Line Balancing prerequisitesPrior to balancing a line we must:

• Determine the required workstation cycle time (or TAKT time), matching the pace of the manufacturing process to customer demand

• Standardize the process

Page 8: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Classic approach to ALB

Also known as SALBP* (Simple Assembly Line Balancing Problem), the classic approach to ALB is an heuristic process to optimize assembly lines simplifying the problem to a basic level of complexity

*Dubbed SALBP by Becker and Scholl (2004)

Page 9: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example The next table shows the tasks performed in a

production line. Our goal is to combine them into workstations. The assembly line operates 8 hours per day and the expected customer demand is 1000 units per day. Balance the line and calculate the efficiency and theoretical minimum number of workstations.

Page 10: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)Task Task Time

(sec)Preceding Task

A 13 -

B 11 A

C 15 A

D 20 B

E 12 B

F 13 C

G 13 C

H 18 D, E

I 17 F, G

J 15 H, I

K 9 J

Total Time: 156

Page 11: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)• Step 1: Draw a precedence diagram according to the given sequential relationship

K

9 sec

J

15 sec

I

17 sec

H

18 sec

G

13 sec

F

13 sec

E

12 sec

D

20 sec

C

15 sec

B

11 sec

A

13 sec

Page 12: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)• Step 2: Determine Takt time or Workstation Cycle Time

C=Production time per day / Customer demand (or output per day)

C= 28800 sec (8 hours) / 1000 units = 28.8

• Step 3: Determine the theoretical number of workstations required

N= Total Task Time / Takt time

N= 156 / 28.8 = 5.42 (~6 workstations)

Page 13: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)• Step 4: Define your assignment rules. For

this example our primary rule will be “number of following tasks” and the secondary rule will be “longest operation time”

Page 14: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)• Step 5: Assign tasks to workstations following the assignment rules

and meeting precedence and cycle time requirements

To form Workstation 1:

A

13 sec B

C

Following tasks: 5

Following tasks: 5

11 sec

15 secLot: 15>11!

WS1: A+C=28 sec

Cycle Time met!

Page 15: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)• Forming Workstation 2:

A

13 sec B

C

11 sec

15 sec

G

13 sec

F

13 sec

E

12 sec

D

20 sec

B+D>Cycle time!

LOT:_F&G>E

Arbitrarily choose F

WS2: Operation time=24 sec (<C)

Page 16: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)• Following the same criteria we achieve our balancing with

7 workstations

Workstation Task Task TimeRemaining Unassigned Time

Feasible Remaining Tasks

Task withmost followers

Task withLOT

A 13 15.8 B, C B, C CC 15 0.8 -B 11 17.8 E, F, G E, F, G F, GF 13 4.8 -

3 D 20 8.8 -G 13 15.8 E E 12 3.8 -

5 H 18 10.8 -6 I 17 11.8 -

J 15 13.8 KK 9 4.8 -

1

2

4

7

Page 17: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Example (cont.)• Step 6: Calculate Efficiency

– Efficiency= Total Task Time / (Actual number of workstations * Takt Time)

– Efficiency= 156 / (7*28.8) = 77%

How to interpret this efficiency?

Is this the best efficiency achievable?

Page 18: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Let’s Practice• We have found a new market for our

product. This market is less demanding so we have decided not to include a particular feature, specifically the feature added by task I. As a consequence, task time in F drops to 5 seconds and task time in G drops to 8 seconds. Balance the line according to the other conditions.

Page 19: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Let’s practice (cont.)Task Task Time

(sec)Preceding Task

A 13 -

B 11 A

C 15 A

D 20 B

E 12 B

F 13 5 C

G 13 8 C

H 18 D, E

I 17 F, G

J (new I) 15 H, F, G

K (new J) 9 I

Total Time: 156 126

Page 20: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Let’s practice (cont.)• Let’s take some time to solve this new

problem. This time we will calculate keeping the primary and secondary rules as in the original problem.

Page 21: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Let’s practice (solution)• Precedence diagram

J*

9 sec

I*

15 sec

H

18 sec

G

8 sec

F

5 sec

E

12 sec

D

C

15 sec

B

11 sec

A

13 sec

20 sec

*Previously J & K respectively

Page 22: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Let’s practice (solution)• Takt time

C = 28,800 sec / 1000 units = 28.8

• Theoretical number of workstations

N = 126/28.8 = 4.38 (~5 workstations)

• Primary rule: number of following tasks

• Secondary rule: longest operation time

Page 23: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Let’s practice (solution)• Following the rules and observing cycle time and precedence

we obtain:

Workstation Task Task TimeRemaining Unassigned Time

Feasible Remaining Tasks

Task withmost followers

Task withLOT

A 13 15.8 B, C BB 11 4.8 -C 15 13.8 E, F, G EE 12 1.8 -

3 D 20 8.8 -4 H 18 10.8

G 8 20.8 FF 5 15.8 II 15 0.8 -

6 J 9 19.8 -

1

2

5

Page 24: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Let’s practice (solution)• Efficiency = 126/(6*28.8) = 73%

Challenge: Is this the best efficiency achievable? Try to solve with LOT as the primary rule and you will obtain a 5 workstations balance, increasing efficiency to 87%

Page 25: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

ALB in the real worldThe simple ALB problem approach is limited by some

constraints:

• Balance on existing and operating lines– Workstations have spatial constraints

– Some workstations cannot be eliminated

– Need to smooth workload among workstations

• Multiple operators per workstation– Different paces among operators, different lead times within the

same workstation

Page 26: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

ALB in the real world (cont.)• Operator spatial constraints

– Different workstation imposed working positions– More than one task to be performed in what should be the space for

one task

• Multiple Products– Coping with different products, some operations are needed for

some products but not for others– Some products can introduce “peak times” in some workstations

• Different task times performed in different shifts– Particularly when introducing new employees or workers with some

degree of incapacity

Page 27: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

Conclusion• Simply Assembly Line Balancing is a valid

method to optimize assembly lines. However, many variables found in real operating lines increase the complexity of the problem. More complex algorithms have been developed to solve the difficult task of balancing large scale industrial lines. Some of them are commercially available in software.

Page 28: Assembly Line Balancing Jaime Joo MBA 530 – Section 1 Brigham Young University

References• F. Robert Jacobs & Richard B. Chase “Operations and

Supply Management, The Core” McGraw-Hill/Irwin First Edition

• Emanuel Falkenauer “Line Balancing in the real world” Optimal Design

• Paul Swift. http://www.beyondlean.com/line-balancing.html