Atlantic Yards

Construction Summary Report for Week ending 3/07/2014 Weather: Very cold at beginning/slowly warming through week: temps 12-44.

B2 o Only the final 3 3rd floor mods were installed during the week, bringing the total

number of mods installed to date up to 54, 5.8% of the 930 total; 18 dwelling units out of 350.

o In the basement and ground floor levels plumbing piping, ductwork, electrical

conduit work, block wall and door installation continued. No further spray-on fireproofing was performed at the ground floor level due to the cold and other on-site factors. There was no further work related to finishing the connections between the B2 and Arena basements. Both knockout panel areas still need to be completed.

o The latest project schedule transmitted to STV in late November, 2013

forecasted a TCO in January, 2015, based on regular module delivery starting on 12/31/13. Mod installation was to have reached the 9th Floor (240+ mods) by 3/7/14. The delay in mod installation could impact the 1/2015 TCO date down the road. If lost time is to be made up it requires mod production at the Navy Yard to somehow accelerate. A new schedule was requested from Skanska the end of January but STV was told it was under revision and would then be shared. STV will request a revised schedule again next week.

o On the 10/16/13 ESD/Consultant site visit to Building 293 at the Navy Yard, FC

Skanska stated its goal was to reduce module manufacturing time from one month per floor to one week per floor. However, the B2 11/25/13 schedule assumes at least 2 weeks production timeframe per floor. The number of mods per floor will increase from 27 (Floors 2-4) to 36 (Floors 5-19), then decrease to 29 (Floors 20-23), then to 20 (Floors 24-32) and then 8 mods for Floor 33 and 5 mods for Floor 34. Mod production began on 7/24/13. Production of the 2nd

floor mods were earlier reported by FC Skanska to have been completely finished the week of 1/17/14 when the 3rd floor mods were also to have been finished. However, walk-throughs of the 2nd floor mods installed at the B2 site beginning on 2/6/14 revealed that many were in fact incomplete with appliances, sinks and toilets and in some cases flooring and wall work not yet installed. This work on the 2nd floor will have to be completed on site in addition to on-site leak damage

repair/replacement of water-damaged ceilings, walls and floors and possibly

Page 2: Atlantic Yards B2 FOIL, AY STV Report - 3-7-14 - Proposed Redactions_Redacted

other elements such as electrical. Other work including carpeting and hung ceiling work in the east-west corridor of each floor was always planned to be done on site after utility mate-line work (and water damage repair) is completed. No walk-through of the 3rd floor mods installed was undertaken as Skanska had not yet ‘broken through’ the protective paper outer wrapping of the mods, indicating that they will once the 4th floors are installed.

o Hirani was not on site this week to perform a weekly detailed site inspection so

no report is attached.