attachment f - brevard public schools
TRANSCRIPT
Facilities Services2700 Judge Fran Jamieson WayViera, Florida 32940-6601
Campus Capital Needs Sales Surtax Funded
Attachment F
Estimate
Detail ReportCondition CodeFacility
Challenger 7 1.29 $638,802District School Security $97,7221.00
Perimeter/Entry Fencing and Gates $70,742Pedestrian Access and Safety (Fencing) 1.00 $70,742
Building Access Security Equipment $26,980Public Access Control 1.00 $26,980
Educational Technology $189,2321.40
Technology Equipment Renewal $89,180Computer Replacement 3.00 $35,704Server Replacement 1.00 $25,002Telephone System Replacement 1.00 $16,795Wireless Access Points Replacement 1.00 $11,680
Classroom Technology Infrastructure (Electrical, HVAC and Data) $100,051Student Stations Power/ Technology HVAC 1.00 $100,051
Facility Renewal $351,8481.29
Fire Alarm System Renewal $51,243Fire Alarm System 2.00 $51,243
Cooling and Heating Control System Renewal $183,240Building Automation System 1.00 $183,240
Exterior Door/Window/Louver System Renewal $3,284Main Entry Hardware 2.00 $3,284
Electrical Distribution System Renewal $43,540TSS Surge Suppression 1.00 $43,540
Electrical System Components (Lightning Protection, Intercom and Generators) Renewal $37,939Lightning Protection 1.00 $37,939
Air Supply and Exhaust System Renewal $32,601Exhaust Fans Art Kiln Room, Locker Rooms, Restrooms, Science 1.00 $32,601
July 22, 2014
Exhibit B ‐‐ Sales Surtax Summary Form
Challenger 7 Elementary School Construction Manger Firm Name: Wharton SmithDate: February 15, 2020
DISTRICT SCHOOL SECURITY60 01 Perimeter/Entry Fencing and Gates60 02 Building Access and Security Equipment
EDUCATIONAL TECHNOLOGY65 01 Technology Building Cabling65 02 Technology Equipment Renewal65 03 Classroom Technology Infrastructure (Electrical, HVAC, Data) $60,000.00 $100,051.00 $1,428.00 $38,623.00
FACILITY RENEWAL50 00 Facility Renewal (design and preconstruction) $196,372.00 ‐$196,372.0051 01 Safety and Building Code Deficiency Corrections51 02 ADA Code Deficiency Correction51 03 Fire Alarm System Renewal $0.00 $51,243.00 $51,243.0052 04 Central Mechanical Plant Renewal $2,052,653.00 ‐$2,052,653.0052 05 Cooling and Heating Control System Renewal $303,901.00 ‐$303,901.0052 06 Air Conditioning and Air Distribution Equipment Renewal $648,000.00 $183,240.00 ‐$464,760.0053 07 Roofing System Renewal53 08 Exterior Building Wall Finish System Renewal53 09 Exterior Door/Window/Louver System Renewal $0.00 $3,284.00 $3,284.0052 10 Building Water and Sanitary Piping System Renewal52 11 Water Heating System Renewal54 12 Electrical Supply System (Transformers, Switchgear, Wiring) Renewal $42,000.00 ‐$42,000.0054 13 Electrical Distribution System Renewal $74,400.00 $43,540.00 ‐$30,860.0054 14 Electrical Components (Lightning Protection, Intercom, Generator) Renewal* $37,939.00 $37,939.0054 15 Interior and Exterior Lighting Equipment Renewal52 16 Air Supply and Exhaust System Renewal $57,000.00 $32,601.00 ‐$24,399.0052 17 Site Utility Systems (Gas, Electric, Storm, Water, Sanitary) Renewal
Contingency previously applied Reserve for covered walkwaysAdditional administration and permitting $5,000.00 ‐$5,000.00Sales surtax supplement ‐$3,027,500.00 $3,027,500.00
Total $3,237,954.00 $451,898.00 ‐$2,824,700.00 $38,644.00
Facility Renewal Only $3,177,954.00 $351,847.00 ‐$2,826,128.00 $21.00
Educational Technology Only $60,000.00 $100,051.00 $1,428.00 $38,623.00
BalanceAttachment F Spent & EncumberedGroup/Category Description Proposed Price
Month Year Revenue Cumulative Security 50% ET 15% Facilities 35% Total
August 2019 $1,294,012 $1,294,012 $647,006 $194,102 $452,904 $1,294,012September 2019 $3,474,204 $4,768,216 $1,737,102 $521,131 $1,215,971 $3,474,204October 2019 $3,440,101 $8,208,317 $1,720,051 $516,015 $1,204,035 $3,440,101November 2019 $4,526,234 $12,734,551 $2,263,117 $678,935 $1,584,182 $4,526,234December 2019 $3,425,373 $16,159,924 $1,712,687 $513,806 $1,198,881 $3,425,373January 2020 $3,477,814 $19,637,738 $1,738,907 $521,672 $1,217,235 $3,477,814February 2020 $5,420,075 $25,057,813 $2,710,038 $813,011 $1,897,026 $5,420,075March 2020 $3,315,493 $28,373,306 $1,657,747 $497,324 $1,160,423 $3,315,493April 2020 $3,355,854 $31,729,160 $1,677,927 $503,378 $1,174,549 $3,355,854May 2020 $5,389,791 $37,118,951 $2,694,896 $808,469 $1,886,427 $5,389,791June 2020 $3,554,107 $40,673,058 $1,777,054 $533,116 $1,243,937 $3,554,107July 2020 $3,574,694 $44,247,752 $1,787,347 $536,204 $1,251,143 $3,574,694August 2020 $4,954,442 $49,202,194 $2,477,221 $743,166 $1,734,055 $4,954,442September 2020 $3,474,204 $52,676,398 $1,737,102 $521,131 $1,215,971 $3,474,204October 2020 $3,440,101 $56,116,499 $1,720,051 $516,015 $1,204,035 $3,440,101November 2020 $4,526,234 $60,642,733 $2,263,117 $678,935 $1,584,182 $4,526,234December 2020 $3,425,373 $64,068,106 $1,712,687 $513,806 $1,198,881 $3,425,373January 2021 $3,477,814 $67,545,920 $1,738,907 $521,672 $1,217,235 $3,477,814February 2021 $5,420,075 $72,965,995 $2,710,038 $813,011 $1,897,026 $5,420,075
Total $72,965,995 $35,835,992 $10,750,797 $25,085,194 $72,965,995Estimated based on prior year receipts
Approved/Requested Allocations: Security ET Facilities Total Original Amount Reduction
Repayment of temporary transfer ‐ security to facilities 9,332,130.58$ 9,332,130.58$ Allocation to security previously approved but not used) 280,144.46$ 280,144.46$ Building Automation System plan (Board approved September 24, 2019) ‐ under study ‐ defer 200,000$ 200,000.00$ Columbia, McAuliffe, Challenger 7 HVAC (Board approved September 24, 2019) 7,000,000$ 7,000,000.00$ Board agenda 3/10Computer replacement (Board approved September 24, 2019) 500,000$ 500,000.00$ Longleaf Elementary facility renewal ‐ GMP pending ICOC Approved 12/11/2019 250,000$ 250,000.00$ Board agenda 3/10Cocoa Beach High facility renewal ‐ GMP pending ICOC Approved 12/11/2019 1,000,000$ 1,000,000.00$ Satellite High facility renewal ‐ GMP pending ICOC Approved 12/11/2019 1,200,000$ 1,200,000.00$ Mims Elementary facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,200,000$ 1,200,000.00$ Board agenda 1/28McNair Elementary facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 950,000$ 950,000.00$ Board agenda 3/10 $1,000,000 50,000$ Edgewood Jr./Sr. High facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,550,000$ 1,550,000.00$ Board agenda 3/10 $1,600,000 50,000$ Additional allocation Columbia, McAuliffe, Challenger 7 HVAC ICOC Approved 12/11/2019 2,000,000$ 2,000,000.00$ Board agenda 3/10Cambridge Elementary facility renewal ‐ supplemental request ICOC Approved 01/09/2020 700,000$ 700,000.00$ Board agenda 1/14Enterprise Elementary facility renewal ‐ supplemental request ICOC Approved 01/09/2020 650,000$ 650,000.00$ Board agenda 1/14Titusville High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 770,000$ 770,000.00$ Board agenda 1/14Imperial Estates facility renewal ‐ supplemental request ICOC Approved 01/09/2020 520,000$ 520,000.00$ Board agenda 1/14Astronaut High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 460,000$ 460,000.00$ Board agenda 1/28Space Coast Jr./Sr. High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 300,000$ 300,000.00$ Board agenda 1/28 $450,000 150,000$ Suntree Elementary ICOC Approved 01/09/2020 ‐$ ‐$ Board agenda 2/11 $240,000 240,000$ Manatee Elementary ‐ supplemental request ICOC Approved 01/09/2020 400,000$ 400,000.00$ Board agenda 1/28 $460,000 60,000$ Sunrise Elementary ICOC Approved 01/09/2020 230,000$ 230,000.00$ Board agenda 2/11 $270,000 40,000$ Gardendale Alternative Learning Center ‐ GMP pending ICOC Approved 01/09/2020 200,000$ 200,000.00$ Clearlake Adult Education Center ICOC Approved 01/09/2020 300,000$ 300,000.00$ Cocoa Beach Jr./Sr. High AHU 8.2 ICOC Approved 01/09/2020 200,000$ 200,000.00$ Board agenda 1/14Bayside High structural repair ‐ GMP pending ICOC Approved 01/09/2020 400,000$ 400,000.00$ Jupiter Elementary ‐ GMP pending ICOC Approved 01/09/2020 100,000$ 100,000.00$ Board agenda 3/10Riviera Elementary ‐ GMP pending ICOC Approved 01/09/2020 250,000$ 250,000.00$ Board agenda 3/10 $300,000 50,000$ Palm Bay High (roof top AHUs Building 7 and elevator) ICOC Approved 01/09/2020 500,000$ 500,000.00$ Board agenda 2/11Palm Bay High (3 new chillers) ‐ pending further investigation ICOC Approved 01/09/2020 1,400,000$ 1,400,000.00$
Gardendale (additional allocation) ICOC Approved 2/19/2020 100,000$ Longleaf (additional allocation) ICOC Approved 2/19/2020 200,000$ Board agenda 3/10Satellite High School (additional allocation) ICOC Approved 2/19/2020 200,000$ Cambridge building automation system ICOC Approved 2/19/2020 340,000$ Board agenda 3/10 350,000$ 10,000$ Riviera (additional allocation) ICOC Approved 2/19/2020 ‐$ Board agenda 3/10 40,000$ 40,000$ Jupiter (additional allocation) ICOC Approved 2/19/2020 5,000$ Board agenda 3/10 40,000$ 35,000$ Viera High School ‐ supplemental request ICOC Approved 2/19/2020 680,000$ Board agenda 3/10 700,000$ 20,000$ Creel (security request) ICOC Approved 2/19/2020 400,000$ Educational technology ‐ computer refreshment ICOC Approved 2/19/2020 1,500,000$ Palm Bay High ‐ defer chiller replacement pending further investigation ICOC Approved 2/19/2020 (1,000,000)$ Building automation system study (defer) ICOC Approved 2/19/2020 (200,000)$ Edgewood drainage ICOC Approved 2/19/2020 305,000$ Board agenda 3/10 $320,000 15,000$
Total Allocation 10,012,275$ 2,000,000$ 23,360,000$ 35,372,275$ $760,000
Net Remaining Allocation 25,823,716$ 8,750,797$ 1,725,194$ 37,593,720$
February 19, 2020 ICOC agendaChanges from prior approved allocation
Projected Revenue over $198 Million Preliminary Recommended Distribution
Updated 02/23/2020
GMP Amendment – Exhibit C – Challenger 7 Elementary School/RFP#20-147-P-DR Page 1 of 4
EXHIBIT C
GUARANTEED MAXIMUM PRICE AMENDMENT
TO
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES
BY AND BETWEEN
WHARTON-SMITH, INC.
AND
SCHOOL BOARD OF BREVARD COUNTY
2700 JUDGE FRAN JAMIESON WAY
VIERA, FL 32940
PHONE: (321) 633-1000
FAX: (321) 633-4646
FOR THE CONSTRUCTION OF:
CHALLENGER 7 ELEMENTARY SCHOOL
FACILITY RENEWAL
RFP #20-147-P-DR
February 20, 2020
GMP Amendment – Exhibit C – Challenger 7 Elementary School/RFP#20-147-P-DR Page 2 of 4
ARTICLE 1. GUARANTEED MAXIMUM PRICE (GMP) 1.1 Guaranteed Maximum Price (GMP): Construction Manager guarantees that it shall not
exceed a Guaranteed Maximum Price (GMP) of Three Million, Two Hundred Thirty-Seven
Thousand, Nine Hundred Fifty-Four Dollars ($3,237,954.00) for the identified Sub-Project. 1.2 Basis of the GMP:
1.2.1 Construction Documents: The Scope of Work for the GMP shall be as defined in the Contract
Construction Documents.
1.2.2 List of Construction Documents identified in Article 7 of this Guaranteed Maximum Price
Amendment.
1.2.3 Exceptions, Clarifications and Exclusions: The Scope of Work defined in the Construction
Contract Documents and/or Design Criteria package shall be modified and/or clarified as identified
in Article 8 of this Guaranteed Maximum Price Amendment.
ARTICLE 2. PROJECT TIME 2.1 Substantial Completion Date: Substantial Completion of the Work shall be achieved in
accordance with the CPM schedule attached hereto.
2.2 Final Completion Date: Final completion of the Work shall be achieved in accordance with
the CPM schedule attached hereto.
2.3 Project Schedule: Attached to this Amendment will be a schedule identifying the above
noted completion times and intermediate milestone dates estimated for the Project. The
proposed schedule shall be integrated into the Construction Manager’s Schedule upon
approval of this Guaranteed Maximum Price Amendment.
ARTICLE 3. CONSTRUCTION MANAGER FEE 3.1 Construction Manager Fee: The Construction Manager Fee for the Project shall be a Lump
Sum of One Hundred Forty-Seven Thousand, Four Hundred Forty-Four ($147,444.00).
Note: All allowances will be on a Not-To-Exceed basis. All unused funds will be returned
to the School District at the time of construction close-out. Fee will be paid only on cost
of work for these items.
ARTICLE 4. REIMBURSABLE GENERAL CONDITIONS COSTS 4.1 General Conditions: General Conditions costs for the Project shall not exceed Three
Hundred Twenty-Nine Thousand, Seven Hundred Fifty-Seven Dollars ($329,757.00).
General Conditions costs shall be reimbursed at Construction Manager’s actual cost.
General Conditions costs shall be in compliance with the General Conditions to the
Agreement for Construction Management Services (Exhibit A) and are identified in the
attached document prepared by the Construction Manager.
Note: Labor rates are subject to project audit and will be paid at Construction Manager’s
current rate verification.
GMP Amendment – Exhibit C – Challenger 7 Elementary School/RFP#20-147-P-DR Page 3 of 4
ARTICLE 5. LIQUIDATED DAMAGES 5.1 Substantial Completion: Construction Manager shall pay Owner One Thousand Dollars
($1,000.00) as liquidated damages for each day that Substantial Completion extends
beyond the Substantial Completion Date.
5.2 Final Completion: Construction Manager shall pay Owner Five Hundred Dollars ($500.00)
as liquidated damages for each day that Final Completion extends beyond the Final
Completion Date.
ARTICLE 6. PROJECT REPRESENTATIVES 6.1 Owner’s Representative: Owner designates the individual listed below as its Owner’s
Project Manager to provide direct interface with Construction Manager with respect to
Owner’s responsibilities.
Art Johnson Owner’s Project Manager 6.2 Construction Manager’s Representative: Construction Manager designates the individual listed
below as its Construction Manager’s Representative to provide direct interface with Owner with
respect to Construction Manager’s responsibilities.
Nick Hare Construction Manager’s Project Manager
ARTICLE 7. LIST OF CONSTRUCTION CONTRACT DOCUMENTS 7.1 Drawings: Listed below are the contract documents and their issue date which is the basis
of this Guaranteed Maximum Price Amendment:
See attached proposal dated February 18, 2020.
7.2 Specifications: Listed below are the specification sections and their issue date which is
the basis of this Guaranteed Maximum Price Amendment:
See attached proposal dated February 18, 2020.
ARTICLE 8. EXCEPTIONS, EXCLUSIONS AND CLARIFICATIONS 8.1 Exceptions and Exclusions: Listed below are specific Exceptions and Exclusions identified
by the Construction Manager during the development of this Project Design and Bidding:
See attached proposal dated February 18, 2020.
8.2 Clarifications: Listed below are specific Clarifications identified by the Construction
Manager during the development of this Project Design and Bidding:
See attached proposal dated February 18, 2020.
GMP Amendment – Exhibit C – Challenger 7 Elementary School/RFP#20-147-P-DR Page 4 of 4
SIGNATURE PAGE:
THE SCHOOL BOARD OF CONSTRUCTION MANAGER:
BREVARD COUNTY, FLORIDA: WHARTON-SMITH, INC.
By:_____________________________ By:___________________________
Misty Belford, Chairperson
Print Name: ___________________
ATTEST (WITNESS):
Title: _________________________
By:_____________________________ Date:_________________________
Mark W. Mullins, Ed.D.
Superintendent
Date:___________________________ ATTEST (WITNESS):
By:___________________________
Print Name:____________________ Title: ________________________ Approved as to form: ___________________________
General Counsel
END OF EXHIBIT C
Darin A. Crafton
Executive Vice President
02/21/20
Kimberly A. Murray
Administrative Manager
TABLE OF CONTENTS
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services, REP #20-147-P-DRChallenger 7 Elementary School Facility RenewalThe School Board of Brevard County
Section Item Reference
Section 1a: Guaranteed Maximum Price (GMP) (Article 1.1)Schedule of ValuesDirect Costs
Section 1b: Scope of Work (Article 1.2-1.3)List of Contract Documents included in Section 7 Exceptions, Clarifications & Exclusions included in Section 8
Section 2: Project Time (Article 2.1-2.3)
Section 3: Construction Manager Fee (Article 3.1)
Section 4: Reimbursable General Conditions Costs (Article 4.1)
Section 5: Liquidated Damages (Article 5.1-5.2)
Section 6: Project Representatives (Article 6..1-6.2)
Section 7: List of Construction Contract Documents (Article 7.1-7.2)
Section 8: Exceptions, Exclusions & Clarifications (Article 8.1-8.2)
SBBC Challenger 7 ES Page 1 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 1aGuaranteed Maximum Price (GMP)
Attachments: Schedule of ValuesDirect Costs
SBBC Challenger 7 ES Page 2 of 42 02/18/2020
LINE Spec DESCRIPTION TOTAL
1 020000 Sitework Allowance 17,063
2 021000 Demolition 31,150
3 028200 Fencing 2,056
4 030000 CIP Concrete Allowance 36,055
5 040000 Masonry Allowance 6,000
6 050000 Structural Steel Allowance 20,265
7 061000 Rough Carpentry - N/A 0
8 075000 Roofing Allowance 750
9 079000 Sealant Allowance 1,500
10 081000 Doors, Frames & Hardware 8,000
11 092000 Drywall - N/A 0
12 092100 Stucco Allowance 6,468
13 095000 Acoustical Ceiling Allowance 28,361
14 099100 Finishes Allowance 33,300
15 151000 Plumbing - N/A 0
16 155000 HVAC 1,924,225
17 158000 Test & Balance 27,500
18 159000 Controls 253,251
19 16000 Electrical 284,400
20 TOTAL DIRECT COSTS 2,680,343
21 General Requirements 49,984
22 General Conditions 218,545
23 General Liability Insurance 9,713
24 Builder's Risk Insurance 1,677
25 Subcontractor Bonds 26,041
26 P&P Bond 23,797
27 SUBTOTAL 3,010,100
28 Fee (5% - Directs/GRs/GCs) 147,444
29 Contingency (3% - Directs) 80,410
30 Guaranteed Maximum Price 3,237,954
Exhibit C – Guaranteed Maximum Price (GMP) Amendment
to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
The School Board of Brevard County
Section 1a
Schedule of Values
SBBC Challenger 7 ES Page 3 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
1 020000 Sitework Allowance
2
3
4 Regrade/Sod @ Disturbed Areas 6,000 sf 10,500
5 Repair Asphalt 875 sf 6,563
6 Construction Fence 0 ft 0
7 0 0
8 0 0
9 Bond 17,063 $ 0 WSI Estimate
10 Adjustment from WSI estimate to subcontractor LS 0 17,063
11
12
13
14 Subtotal - Sitework Allowance 17,063
15 021000 Demolition
16
17
18 Cut & Remove Concrete Sidewalk 2,230 SF 11,150
19 Cut & Remove Asphalt 875 SF 5,250
20 Cut Opening in Gyp Wall for Door @ Stage 32 SF 320
21 Cut Opening in Masonry Wall for 8" Pipe 16 EA 12,000
22 Demo CMU Opening for Door 6' x 7' 168 SF 1,680
23 Demo HMD & Frame 5 EA 750
24 0 0
25 0 0
26 Bond 31,150 $ 0 WSI Estimate
27 Adjustment from WSI estimate to subcontractor LS 0 31,150
28
29
30
31 Subtotal - Demolition 31,150
32 028200 Fencing
33
34 Fence Chain Link 8' 48 LF 1,056
35 Gate 6' Dbl 1 EA 1,000
36 0 0
37 Bond 2,056 $ 0 WSI Estimate
38 Adjustment from WSI estimate to subcontractor LS 0 2,056
39
40
41 Subtotal - Fencing 2,056
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
SBBC Challenger 7 ES Page 4 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
42 030000 CIP Concrete Allowance
43
44
45
46 032000 Formwork 0 0
47 033000 Concrete 0 0
48 035000 Finishing 0 0
49 0 0
50 Replace Concrete Sidewalk 2,230 SF 33,450
51 Repair Mortar @ Door Frame 6 x 7 Access Door 4 1,000
52 Concrete Housekeeping Pad 107 SF 1,605
53 0 0
54 Bond 0 $ 0 WSI Estimate
55 Adjustment from WSI estimate to subcontractor LS 0 36,055
56
57
58
59 Subtotal - CIP Concrete Allowance 36,055
60 040000 Masonry Allowance
61
62
63
64 0 0
65 Match/Patch Brick @ New Access Doors 4 LS 6,000
66 0 0
67 0 0
68 Bond 6,000 $ 0 WSI Estimate
69 Adjustment from WSI estimate to subcontractor LS 0 6,000
70
71
72
73 Subtotal - Masonry Allowance 6,000
74 050000 Structural Steel Allowance
75
76
77 051000 Structural Steel
78 053000 Miscellaneous Metals 0 0
79 0 0
80 Steel Lintel 8' 4 LS 6,000
81 Structural Beam HDG @ Cooling Tower 17 LF 765
82 Modifications to Catwalks 7 Locations 9 LS 13,500
83 0 0
84 Bond 20,265 $ 0 WSI Estimate
85 Adjustment from WSI estimate to subcontractor LS 0 20,265
86
87
88
89 Subtotal - Structural Steel Allowance 20,265
SBBC Challenger 7 ES Page 5 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
90 061000 Rough Carpentry - N/A
91
92
93
94 061100 Rough Carpentry 0 0
95 0 0
96 0 0
97 0 0
98 Bond 0 $ 0 WSI Estimate
99 Adjustment from WSI estimate to subcontractor LS 0 0
100
101
102
103 Subtotal - Rough Carpentry - N/A 0
104 075000 Roofing Allowance
105
106
107 075010 Demo Roof Curb@Boiler Stack 0 LS 0
108 Patch Roof @ Boiler Stack 1 LS 750
109 0 0
110 0 0
111 Bond 750 $ 0 WSI Estimate
112 Adjustment from WSI estimate to subcontractor LS 0 750
113
114
115
116 Subtotal - Roofing Allowance 750
117 079000 Sealant Allowance
118
119
120 Misc Caulk@ Roof Curb/Door Frames 5 LS 1,500
121 0 0
122 0 0
123 Bond 1,500 $ 0 WSI Estimate
124 Adjustment from WSI estimate to subcontractor LS 0 1,500
125
126
127
128 Subtotal - Sealant Allowance 1,500
SBBC Challenger 7 ES Page 6 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
129 081000 Doors, Frames & Hardware
130
131
132 081010 Doors & Frames 0 0
133 0871000 Hardware 0 0
134 0 0
135 Door 3 x 3 Sgl HM Insulation 2 EA 700
136 Door 6 x 7 Dbl HM Insulation 4 EA 2,200
137 Door Frame 3 x 3 HM 2 EA 400
138 Door Frame 6 x 7 HM 4 EA 800
139 Door Hardware Set 6 EA 3,000
140 Installation 6 LS 600
141 Safety Chain @ Doorway 4 EA 300
142 0 0
143 Bond 2,900 $ 0 WSI Estimate
144 Adjustment from WSI estimate to subcontractor LS 0 8,000
145
146
147
148 Subtotal - Doors, Frames & Hardware 8,000
149 092000 Drywall - N/A
150
151
152 054000 Engineered Metal Studs 0 0
153 072000 Insulation 0 0
154 091010 Metal Studs 0 0
155 092500 Drywall 0 0
156 0 0
157 0 0
158 Bond 0 $ 0 WSI Estimate
159 Adjustment from WSI estimate to subcontractor LS 0 0
160
161
162
163 Subtotal - Drywall - N/A 0
164 092100 Stucco Allowance
165
166
167 0 0
168 Demo Stucco For Pipe Supports 539 SF 1,078
169 Repair Stucco For Pipe Supports 539 SF 5,390
170 0 0
171 0 0
172 Bond 6,468 $ 0 WSI Estimate
173 Adjustment from WSI estimate to subcontractor LS 0 6,468
174
175
176
177 Subtotal - Stucco Allowance 6,468
SBBC Challenger 7 ES Page 7 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
178 095000 Acoustical Ceiling Allowance
179
180
181 0
182 095100 Suspended Acoustic Ceilings 0 0
183 Remove and replace Drop Ceilings x 10' 10,450 sf 31,350
184 0 0
185 0 0
186 Scope Adjustment 0 0
187 Missing Scope-Additional Ceiling Areas 0 sf 0
188 0 0
189 Bond 31,350 $ 0 WSI Estimate
190 Adjustment from WSI estimate to subcontractor 1 LS (2,989) 31,350
191
192
193
194 Subtotal - Acoustical Ceiling Allowance 28,361
195 099000 Finishes Allowance
196
197
198 099100 Finishes 0 0
199 Finishes Allowance 1 LS 29,500
200 Scope Inclusions 0 0
201 Misc Touchup Paint @ Walls 6 LS 3,000
202 Paint New Doors & Frames Dbl 4 EA 600
203 Paint New Doors & Frames Sgl 2 EA 200
204 0 0
205 Bond 33,300 $ 0 WSI Estimate
206 Adjustment from WSI estimate to subcontractor LS 0 33,300
207
208
209 Subtotal - Finishes Allowance 33,300
210 151000 Plumbing - N/A
211
212
213 151000 Pipe Materials & Systems 0 0
214 152000 Valves & Pipe Accessories 0 0
215 153000 Ductile Pipe 0 0
216 154000 PVC Pipe 0 0
217 155000 Steel & SS Pipe 0 0
218 0 0
219 Bond 0 $ 0 WSI Estimate
220 Adjustment from WSI estimate to subcontractor LS 0 0
221
222
223 Subtotal - Plumbing - N/A 0
SBBC Challenger 7 ES Page 8 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
224 155000 HVAC
225
226
227 155000 HVAC System 0 0
228 0 0
229 15.1 Demo 0 0 133,719
230 Demo HP Unit, Flr Mtd 47 EA 70,500
231 Demo HP Unit, Ceiling Hung 15 EA 18,750
232 Demo Pkg A/C Flr Mtd 1 EA 1,500
233 Demo Exhaust Fan 14 EA 3,500
234 Demo Ductwork 12 - 6 786 FT 3,929
235 Demo Ductwork 24 - 14 309 FT 1,856
236 Demo Diffuser 25 EA 1,250
237 Demo Piping A/G 2" - 3/4" 2,082 FT 15,614
238 Demo Piping A/G 4" - 6" 138 FT 2,070
239 Demo Air Compressor 1 EA 500
240 Demo Boiler Pkg 1 EA 1,500
241 Demo Boiler Stack 1 EA 250
242 Demo Cooling Tower 1 EA 7,500
243 Demo Heat Exchanger Plate & Frame 1 EA 1,500
244 Demo Pumps End Suction Centrifugal Frame Mtd 3 EA 3,000
245 Demo Wall Fan 1 EA 500
246 0 0
247 15.2 Equipment 0 0 789,650
248 AHU CHW 1200 CFM 3.5 Ton 3 EA 15,300
249 AHU CHW 1600 CFM 4 Ton 0 EA 0
250 AHU CHW 3000 CFM 10 Ton 1 EA 11,300
251 AHU CHW 3500 CFM 10 Ton 1 EA 13,200
252 AHU CHW 5500 CFM 10 Ton 6 EA 104,400
253 AHU CHW 6000 CFM 10 Ton 1 EA 21,400
254 AHU CHW 7000 CFM 10 Ton 1 EA 23,300
255 AHU CHW 8000 CFM 15 Ton 1 EA 26,700
256 Air Cond Split System 2.5 Ton 1 EA 2,850
257 Air Cond Split System 3.5 Ton 1 EA 3,825
258 Air Cond Split System 5 Ton 2 EA 11,250
259 Ext Condenser Unit 2.5 Ton 1 EA 1,075
260 Ext Condenser Unit 3.5 Ton 1 EA 1,350
261 Ext Condenser Unit 5.0 Ton 2 EA 3,250
262 A/C Packaged Flr Mtd 10 Ton 1 EA 17,300
263 OAU CHW 1600 CFM 1 EA 8,500
264 Air Purification System 59,000 CFM 20,650
265 Drain Pan SS w/Float Switch Med 18 EA 13,500
266 Drain Pan SS w/Float Switch Lg 13 EA 13,000
267 Concrete Pad Precast 5 x 5 4 EA 2,000
268 Fan Ceiling RR 50 CFM 20 Watt 2 EA 260
269 Fan Ceiling RR 80 CFM 20 Watt 8 EA 1,440
270 Fan In-Line Centrifugal 200 CFM 1/4 HP 1 EA 1,800
271 Fan In-Line Centrifugal 400 CFM 1/4 HP 1 EA 2,000
SBBC Challenger 7 ES Page 9 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
272 Fan In-Line Centrifugal 500 CFM 1/4 HP 1 EA 2,150
273 Fan In-Line Centrifugal 820 CFM 1/4 HP 2 EA 4,600
274 Fan In-Line Centrifugal 1050 CFM 1/4 HP 1 EA 2,400
275 Fan In-Line Centrifugal 6300 CFM 1/2 HP 1 EA 5,000
276 Fan Wall 325 CFM 1/4 HP 1 EA 650
277 Fan Wall 2300 CFM 1/4 HP 1 EA 2,200
278 Fan Wall Mtd 3150 CFM 1/3 HP 1 EA 2,500
279 Flex Hanger Assy 4 Ea Springs & Rods HD 10 EA 10,000
280 Flex Hanger Assy 4 Ea Springs & Rods LD 68 EA 51,000
281 VAV Box 6" 15 EA 22,500
282 VAV Box 8" 6 EA 9,900
283 VAV Box 10" 34 EA 58,650
284 0 0
285 Air Separator 6" 1 EA 4,400
286 Chiller Rotary Screw 251 Tons 1 EA 205,000
287 Cooling Tower SS Evapco AT 750 GPM 15 HP 1 EA 60,000
288 Pump End Suction Cent Frame Mtd 530 GPM @ 88' TDH 15 HP 2 EA 15,300
289 Pump End Suction Cent Frame Mtd 957 GPM @ 40' TDH 10 HP 2 EA 13,000
290 Refrigerant Monitor Panel 1 EA 750
291 0 0
292 15.3 Grilles & Registers 0 0 33,870
293 Louver 26 x 18 1 EA 872
294 Louver 36 x 24 1 EA 1,105
295 Louver 48 x 16 2 EA 2,100
296 Return Grill 24 x 24 Lay In 14 EA 1,512
297 Return Grill 24 x 24 Side Wall 39 EA 6,396
298 Return Grill 30 x 24 Side Wall 0 EA 0
299 Supply Diffuser 12 x 12 Sidewall 6" 9 EA 585
300 Supply Diffuser 12 x 12 Lay In 6" 45 EA 15,975
301 Supply Diffuser 24 x 24 Lay In 6" 1 EA 355
302 Supply Diffuser 24 x 24 Lay In 8" 6 EA 2,130
303 Supply Diffuser 24 x 24 Lay In 10" 6 EA 2,130
304 Supply Diffuser 24 x 24 Lay In 12" 2 EA 710
305 0 0
306 15.4 Ductwork 0 0
307 Ductwork Total 17,026 lbs 161,750 215,152
308 Supply LP 4,075 lbs 0
309 Supply MP 5,246 lbs 0
310 Return 7,600 lbs 0
311 Exhaust 105 lbs 0
312 Sheet Metal Closure Panel 18GA 36' H 84 SF 420
313 Damper Manual 6" Dia 39 EA 2,360
314 Damper Manual 8" Dia 15 EA 990
315 Damper Manual 10" Dia 13 EA 949
316 Damper Manual 12" Dia 5 EA 395
317 Damper Manual 8" x 8 2 EA 115
318 Damper Manual 10" x 6 1 EA 60
319 Damper Manual 10" x 10 10 EA 635
320 Damper Manual 12" x 6 2 EA 126
SBBC Challenger 7 ES Page 10 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
321 Damper Manual 12" x 10 1 EA 65
322 Damper Manual 12" x 12 3 EA 201
323 Damper Manual 14" x 12 49 EA 3,528
324 Damper Manual 20" x 12 1 EA 95
325 Damper Manual 24" x 12 1 EA 120
326 Damper Manual 26" x 18 1 EA 175
327 Damper Manual 28" x 12 1 EA 13
328 Damper Manual 48" x 16 2 EA 468
329 Damper Motorized Rd 8" Dia 0 EA 0
330 Damper Motorized Rd 12" Dia 1 EA 133
331 Damper Motorized 6" x 6 1 EA 175
332 Damper Motorized 10" x 10 2 EA 380
333 Damper Motorized 12" x 6 1 EA 185
334 Damper Motorized 14" x 12 8 EA 1,520
335 Damper Motorized 22" x 10 1 EA 225
336 Damper Motorized 24" x 14 1 EA 255
337 Damper Motorized 25" x 14 3 EA 930
338 Damper Motorized 30" x 24 0 EA 0
339 Duct Flex Supply 6" 198 FT 1,993
340 Duct Flex Supply 8" 100 FT 1,339
341 Duct Flex Supply 10" 97 FT 1,731
342 Duct Flex Supply 12" 12 FT 276
343 Tie In 6 x 6 3 EA 450
344 Tie In 8 x 8 4 EA 720
345 Tie In 10 x 10 4 EA 800
346 Tie In 12 x 6 12 EA 2,700
347 Tie In 12 x 12 13 EA 2,925
348 Tie In 14 x 6 2 EA 500
349 Tie In 14 x 12 61 EA 15,250
350 Tie In 18 x 12 2 EA 550
351 Tie In 20 x 10 2 EA 550
352 Tie In 20 x 12 10 EA 2,750
353 Tie In 24 x 14 11 EA 3,300
354 Tie In 24 x 24 3 EA 900
355 Tie In 26 x 12 0 EA 0
356 Tie In 26 x 18 2 EA 650
357 Cut Opening For Louver 3 EA 1,500
358 15.5 Piping 0 0 588,584
359 Coil Connection 1" 1 EA 3,800
360 Coil Connection 1 1/4" 4 EA 16,000
361 Coil Connection 1 1/2" 2 EA 8,000
362 Coil Connection 2" 4 EA 18,000
363 Coil Connection 2 1/2" 3 EA 15,000
364 Coil Connection 3" 1 EA 5,000
365 Freon Piping A/G 410 FT 51,259
366 Insulate Exist Piping 1 1/4" 357 FT 9,643
367 Insulate Exist Piping 2" 223 FT 7,591
368 Insulate Exist Piping 2 1/2" 61 FT 2,257
369 Pipe Cover Plate 18 S/M Painted 100 FT 3,502
SBBC Challenger 7 ES Page 11 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
370 Piping A/G CU Insulation CHW 1 1/4" 60 FT 2,106
371 Piping A/G CU Insulation CHW 1 1/2" 66 FT 2,520
372 Piping A/G CU Insulation CHW 2" 115 FT 5,252
373 Piping A/G CU Insulation CHW 2 1/2" 451 FT 27,532
374 Piping A/G CS Insulation CHW 3" 279 FT 22,878
375 Piping A/G CS Insulation CHW 4" 534 FT 49,384
376 Piping A/G CS Insulation CHW 6" 553 FT 83,420
377 Piping A/G PVC Cond 3/4" 65 FT 1,285
378 Piping A/G PVC Cond 1" 113 FT 2,944
379 Piping A/G PVC Cond 1 1/2" 122 FT 3,913
380 Piping U/G CS Insulation CHW 1 1/2" 0 FT 0
381 Piping U/G CS Insulation CHW 2 1/2" 134 FT 20,747
382 Piping U/G CS Pre-Insulation CHW 3" 125 FT 20,625
383 Piping U/G CS Pre-Insulation CHW 6" 712 FT 131,720
384 0 0
385 Valve Ball Brnz Scrd 1/2" 4 EA 152
386 Valve Ball Brnz Scrd 1" 5 EA 349
387 Valve Ball Brnz Scrd 1 1/4" 1 EA 96
388 Valve Ball Brnz Scrd L/O 1 1/2" 0 EA 0
389 Valve Ball Brnz Scrd 2" 1 EA 148
390 Valve BFY Lug L/O 2 1/2" 0 EA 0
391 Valve BFY Lug L/O 3" 0 EA 0
392 Valve BFY Lug L/O 4" 4 EA 2,910
393 Valve BFY Lug L/O 6" 30 EA 29,491
394 Valve Backflow Preventer RP 1 1/4" 1 EA 1,250
395 Valve Balancing CI Flgd 6" 4 EA 11,000
396 Valve Check Wafer CI Fldg 6" 6 EA 5,220
397 Valve Flow Control CI Flgd Labor Only 6" 2 EA 700
398 Valve Pressure Reducing Brnz 1 1/4" 1 EA 425
399 Valve Pressure Relief Brnz Scrd 3/4" 1 EA 255
400 Valve Box CI w/Lid 4 EA 600
401 Flex Conn SS Flgd 6" 12 EA 4,800
402 Flow Meter CI Flgd Labor Only 2 EA 700
403 Pressure Gauge 8 EA 1,000
404 Suction Diffuser CI Flgd 6" 4 EA 9,000
405 T-Meter 4 EA 700
406 TOL for Inst Conn 1" 6 EA 510
407 0 0
408 Piping Tie In 1" 14 FT 2,100
409 Piping Tie In 1 1/4" 2 FT 400
410 Piping Tie In 2" 4 FT 1,400
411 Piping Tie In 3" 2 FT 1,000
412 0 0
413 15.8 Insulation 0 0
414 Ductwork Total 14,245 SF 85,467 85,467
415 Supply LP 3,559 0
416 Supply MP 3,863 0
417 Return 6,726 0
418 Exhaust 97 0
SBBC Challenger 7 ES Page 12 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
419 0 0
420 15.8 T & B 0 0 See Below
421 0 0
422 15.9 Controls 0 0 See Below
423 0 0
424 0 0
425 Bond 1,846,442 $ 36,929 WSI Estimate
426 Adjustment from WSI estimate to subcontractor 1 LS 60,096 1,883,371
427
428
429 Subtotal - HVAC 1,943,467
430 158000 Test & Balance
431
432
433 158000 T & B 66,867 sf 23,403
434 0 0
435 0 0
436 Bond 23,403 $ 0 WSI Estimate
437 Adjustment from WSI estimate to subcontractor 1 LS 4,097 23,403
438
439
440
441 Subtotal - Test & Balance 27,500
442 159000 Controls
443
444
445 15.9 Controls 0 0 291,375
446 H-Stat 5 EA 1,500
447 Static Pressure Sensor 65 EA 22,750
448 T-Stat 67 EA 18,425
449 EMS Control Panel 1 EA 15,000
450 Control Points Water Side 66 EA 62,700
451 Control Points Air Side 0
452 AHU 18 EA 13,500
453 VAV's 179 EA 89,500
454 Fans 136 EA 68,000
455 Dampers 1 8,500
456 0 0
457 Scope Adjustments 0 0
458 Demo Tstat 67 EA 3,350
459 Demo DDC Controller 7 EA 1,050
460 0 0
461 Bond 304,275 $ 6,086 WSI Estimate
462 Adjustment from WSI estimate to subcontractor 1 LS (54,578) 310,361
463
464
465
466 Subtotal - Controls 255,783
SBBC Challenger 7 ES Page 13 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
467 16000 Electrical
468
469
470 Power 0 0
471 Lighting 0 0
472 Low Voltage 0 0
473 0 0
474 16.1 Demo 0 0 41,404
475 Demo Conduit Back to Panel 5,046 FT 15,139
476 Demo Exhaust Fan RR Type 15 EA 1,950
477 Remove and Reinstall Exhaust Fan RR Type 3 EA 780
478 Remove Light Fixture 7 EA 595
479 Demo Panel 175 Amp120/208V 1 EA 520
480 Demo Panel 400 Amp120/208V 1 EA 615
481 Demo Smoke Detectors 18 EA 2,340
482 Demo Disconnect 3 EA 225
483 Disconnect Make Safe HP Unit 67 EA 17,420
484 Disconnect Make Safe A/C DX Package Unit 1 EA 260
485 Disconnect Make Safe Boiler 1 EA 260
486 Disconnect Make Safe CH Pumps 4 EA 1,040
487 Disconnect Make Safe Cooling Tower 1 EA 260
488 0 0
489 16.3 Equipment 0 0 145,955
490 Circuit Breaker 600V 1 Pole 20 A 129 EA 8,708
491 Circuit Breaker 600V 1 Pole 30 A 48 EA 3,240
492 Circuit Breaker 600V 2 Pole 20 A 3 EA 312
493 Circuit Breaker 600V 2 Pole 50 A 3 EA 312
494 Circuit Breaker 600V 2 Pole 60 A 3 EA 312
495 Circuit Breaker 600V 3 Pole 20 A 16 EA 2,816
496 Circuit Breaker 600V 3 Pole 25 A 1 EA 176
497 Circuit Breaker 600V 3 Pole 30 A 26 EA 4,576
498 Circuit Breaker 600V 3 Pole 35 A 1 EA 176
499 Circuit Breaker 600V 3 Pole 40 A 1 EA 176
500 Circuit Breaker 600V 3 Pole 45 A 1 EA 176
501 Circuit Breaker 600V 3 Pole 60 A 1 EA 176
502 Circuit Breaker 600V 3 Pole 70 A 4 EA 704
503 Circuit Breaker 600V 3 Pole 90 A 1 EA 475
504 Circuit Breaker 600V 3 Pole 100 A 1 EA 475
505 Circuit Breaker 600V 3 Pole 600 A 1 EA 7,200
506 Disconnect Fused 600 V 3 Pole 30 Amp NEMA 1 57 EA 23,085
507 Disconnect Fused 600 V 3 Pole 60 Amp NEMA 1 12 EA 6,360
508 Disconnect Fused 600 V 3 Pole 60 Amp NEMA 3R 3 EA 1,875
509 Install VFD's 5 EA 1,125
510 Power Panel ML 120/208V 125 A NEMA 1 1 EA 1,100
511 Power Panel ML 120/208V 175 A NEMA 1 2 EA 3,800
512 Power Panel ML 120/208V 600 A NEMA 1 1 EA 2,925
513 SPD Surge Protection Device 23 EA 71,875
514 Transformer Dry Type 480/120/208V 50KVA 1 EA 3,800
515 0 0
SBBC Challenger 7 ES Page 14 of 42 02/18/2020
LINE Specification DESCRIPTION QTY UNIT TOTALS COMMENTS
Number
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
Section 1a
The School Board of Brevard County
Direct Costs
516 16.5 Light Fixtures 0 0
517 Light Fixture LED 1 x 4 Chain Mtd 10 EA 3,250 3,250
518 0 0
519 0 0
520 0 0
521 16.6 Power Dist 0 0 182,077
522 Conduit A/G 3/4'' w/ 2 # 8 & 1 #10 Gd 197 FT 3,819
523 Conduit A/G 3/4'' w/ 2 #10 & 1 #10 Gd 4,233 FT 78,649
524 Conduit A/G 3/4'' w/ 2 #12 & 1 #12 Gd 529 FT 9,565
525 Conduit A/G 3/4'' w/ 3 # 6 & 1 #10 Gd 77 FT 1,787
526 Conduit A/G 1'' w/ 3 #6 & 1 #10 Gd 66 FT 1,732
527 Conduit A/G 1'' w/ 3 #8 & 1 #10 Gd 77 FT 1,943
528 Conduit A/G 1'' w/ 3 #10 & 1 #10 Gd 318 FT 7,490
529 Conduit A/G 1'' w/ 3 #12 & 1 #12 Gd 1,335 FT 30,589
530 Conduit A/G 11/2'' w/ 3 #3, & 1 #8 G 84 FT 2,828
531 Conduit A/G 1 1/2'' w/3 #4 & 1 #8 G 34 FT 1,110
532 Conduit A/G 2'' w/4 #2/0, & 1 # 4 G 157 FT 7,777
533 Conduit A/G 21/2'' w/ 3-#250 KCM & 2 #2 G X 2 94 FT 7,727
534 Conduit A/G 4'' w/4 #600 MCM & 1 #3 G 27 FT 4,785
535 Conduit U/G 3/4'' w/ 2 # 8 & 1 #10 Gd 51 FT 2,610
536 Conduit U/G 3/4'' w/ 3 #10 & 1 #10 Gd 12 FT 83
537 Conduit U/G 1'' w/ 3 #6 & 1 #10 Gd 8 FT 82
538 Junction Box 22 EA 6,600
539 Reconnect Exhaust Fans 15 EA 3,750
540 Power Outlet G 120V 20A 26 EA 4,550
541 Adjust Exist Smoke Detector for New Ductwork 16 EA 4,000
542 Data Outlet 3 EA 600
543 0 0
544 Fire Alarm Modifications 66,867 SF 33,433 33,433
545 0 0
546 0 0
547 Bond 406,119 $ 8,122 WSI Estimate
548 Adjustment from WSI estimate to subcontractor 1 LS (125,575) 414,241
549
550
551
552 Subtotal - Electrical 288,666
553SUBTOTAL DIRECT COST 2,706,384
554 Remove Direct Cost Bonding -26,041
555TOTAL DIRECT COST 2,680,343
SBBC Challenger 7 ES Page 15 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 1bScope of Work
Attachments: Scope of Work
Note: List of Contract Documents included in Section 7 Exceptions, Clarifications & Exclusions included in Section 8
SBBC Challenger 7 ES Page 16 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment
to Agreement for CM Services, REP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
The School Board of Brevard County
Section 1b
Scope of Work
The Facility Renewal Project at Challenger 7 Elementary School primarily consists of Electrical & Mechanical
renewals throughout the campus. Guaranteed Maximum Price (GMP) encompasses electrical and mechanical
improvements and extensive BAS control improvements. A large portion of electrical work has been captured
to support the mechanical activities. The mechanical scope of work includes major modifications to the
Central Energy Plant including new chiller, cooling tower chilled water and condenser pumps. The existing
building air conditioning units are replaced with new water-cooled AHU’s and VAV boxes, tied into the existing
ductwork. Additional work includes new exhaust fans, new piping and valves, new motorized dampers and
miscellaneous HVAC equipment shall be replaced as required per plans and specifications.
The Education Technology scope consists of new charging cart receptacles in every classroom. The new circuits
will be fed from existing panels in the mechanical rooms.
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 2Project Time
Summary:Substantial Completion Date July 31, 2020Final Completion Date October 12, 2020
Attachments: Project Schedule
SBBC Challenger 7 ES Page 18 of 42 02/18/2020
Activity Name Start Finish
SBBC Challenger 7 ES - Facility Renewal 10-Feb-20 12-Oct-20
Preconstruction 10-Feb-20 29-May-20
HVAC Equipment Submittals 10-Feb-20 21-Feb-20
Electrical Equipment Submittals 10-Feb-20 21-Feb-20
Subcontractor LOI 10-Feb-20 10-Feb-20
Mechanical Engineer / Owner Review 24-Feb-20 28-Feb-20
Electrical Engineer / Owner Review 24-Feb-20 28-Feb-20
Mechanical Submittal Approval 02-Mar-20 02-Mar-20
Electrical Submittal Approval 02-Mar-20 02-Mar-20
NTP 11-Mar-20 11-Mar-20
Subcontracts Issued 11-Mar-20 13-Mar-20
Owner Direct Purchase 11-Mar-20 17-Mar-20
Spring Break Mobilization 16-Mar-20 16-Mar-20
HVAC CEP Equipment 18-Mar-20 27-May-20
Electrical Equipment Procurement 18-Mar-20 28-Apr-20
HVAC AHU Equipment Procurement 18-Mar-20 28-Apr-20
Summer Mobilization 29-May-20 29-May-20
Building 1 01-Jun-20 18-Jun-20
Remove & Save Ceiling Tile & Grid 01-Jun-20 01-Jun-20
Resupport Light Fixtures 01-Jun-20 01-Jun-20
Disconnect Electrical to Mechanical Equipment 01-Jun-20 01-Jun-20
Rough-In New BAS Controls 01-Jun-20 05-Jun-20
Remove Existing Heat Pumps 02-Jun-20 02-Jun-20
Remove Existing Duct Work 02-Jun-20 02-Jun-20
Remove All Wiring / Piping to Units 02-Jun-20 02-Jun-20
Remove Exisitng Exhaust Fans 02-Jun-20 02-Jun-20
Install New Transformer / Panel & Feeders 02-Jun-20 03-Jun-20
Modify / Flush Condenser Water Pipes 03-Jun-20 03-Jun-20
Remove / Replace Thermostats in Rooms 03-Jun-20 09-Jun-20
Modify All Condensate Drains / Cap Unused 03-Jun-20 04-Jun-20
Install New Subpanel & Feeders 04-Jun-20 05-Jun-20
Install New Exhaust Fans 05-Jun-20 05-Jun-20
Reconnect Power to Exhaust Fans 08-Jun-20 08-Jun-20
Install New Main Chilled Water Piping 10-Jun-20 12-Jun-20
Install New Condensate Piping 10-Jun-20 11-Jun-20
Install BAS Controls to Equipment 11-Jun-20 17-Jun-20
Tie-In Existing Electrical 15-Jun-20 15-Jun-20
Pressure Test Piping 15-Jun-20 15-Jun-20
Insulate Piping 15-Jun-20 16-Jun-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
12-Oct-20, SBBC Challenger 7 ES - Facility Renewal
29-May-20, Preconstruction
HVAC Equipment Submittals
Electrical Equipment Submittals
Subcontractor LOI
Mechanical Engineer / Owner Review
Electrical Engineer / Owner Review
Mechanical Submittal Approval
Electrical Submittal Approval
NTP
Subcontracts Issued
Owner Direct Purchase
Spring Break Mobilization
HVAC CEP Equipment
Electrical Equipment Procurement
HVAC AHU Equipment Procurement
Summer Mobilization
18-Jun-20, Building 1
Remove & Save Ceiling Tile & Grid
Resupport Light Fixtures
Disconnect Electrical to Mechanical Equipment
Rough-In New BAS Controls
Remove Existing Heat Pumps
Remove Existing Duct Work
Remove All Wiring / Piping to Units
Remove Exisitng Exhaust Fans
Install New Transformer / Panel & Feeders
Modify / Flush Condenser Water Pipes
Remove / Replace Thermostats in Rooms
Modify All Condensate Drains / Cap Unused
Install New Subpanel & Feeders
Install New Exhaust Fans
Reconnect Power to Exhaust Fans
Install New Main Chilled Water Piping
Install New Condensate Piping
Install BAS Controls to Equipment
Tie-In Existing Electrical
Pressure Test Piping
Insulate Piping
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 19 of 42 02/18/2020
Activity Name Start Finish
Test & Balance Water System 15-Jun-20 15-Jun-20
Inspection - Mechanical Rough-In 15-Jun-20 15-Jun-20
Inspection - Electrical Rough-In 16-Jun-20 16-Jun-20
Inspection - Pressure Test CHW Piping 16-Jun-20 16-Jun-20
Inspection - Mechanical Insulation 17-Jun-20 17-Jun-20
Inspection - Above Ceiling 17-Jun-20 17-Jun-20
Reinstall Ceiling Tile & Grid 17-Jun-20 18-Jun-20
AHU-1A 03-Jun-20 10-Jun-20
Install AHU-1A 03-Jun-20 03-Jun-20
Reconnect AHU-1A to Existing Piping / Install New 04-Jun-20 04-Jun-20
Install VAVs / New Ductwork 05-Jun-20 09-Jun-20
Connect Electrical to AHU / GPS 10-Jun-20 10-Jun-20
AHU-1B 05-Jun-20 11-Jun-20
Install AHU-1B 05-Jun-20 05-Jun-20
Reconnect AHU-1B to Existing Piping 08-Jun-20 08-Jun-20
Install VAVs / New Ductwork 09-Jun-20 10-Jun-20
Connect Electrical to AHU / GPS 11-Jun-20 11-Jun-20
AC-1A 03-Jun-20 09-Jun-20
Install AC-1A 03-Jun-20 03-Jun-20
Install Condenser Unit 04-Jun-20 04-Jun-20
Install Condenser Linesets 05-Jun-20 05-Jun-20
Install New Ductwork / Tie-in Existing 08-Jun-20 08-Jun-20
Connect Electrical to AHU / GPS / Condenser 09-Jun-20 09-Jun-20
AC-1B 04-Jun-20 10-Jun-20
Install AC-1B 04-Jun-20 04-Jun-20
Install Condenser Unit 05-Jun-20 05-Jun-20
Install Condenser Linesets 08-Jun-20 08-Jun-20
Install New Ductwork / Tie-in Existing 09-Jun-20 09-Jun-20
Connect Electrical to AHU / GPS / Condenser 10-Jun-20 10-Jun-20
AC-1C 05-Jun-20 11-Jun-20
Install AC-1C 05-Jun-20 05-Jun-20
Install Condenser Unit 08-Jun-20 08-Jun-20
Install Condenser Linesets 09-Jun-20 09-Jun-20
Install New Ductwork / Tie-in Existing 10-Jun-20 10-Jun-20
Connect Electrical to AHU / GPS / Condenser 11-Jun-20 11-Jun-20
AC-1D 08-Jun-20 12-Jun-20
Install AC-1D 08-Jun-20 08-Jun-20
Install Condenser Unit 09-Jun-20 09-Jun-20
Install Condenser Linesets 10-Jun-20 10-Jun-20
Install New Ductwork / Tie-in Existing 11-Jun-20 11-Jun-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
Test & Balance Water System
Inspection - Mechanical Rough-In
Inspection - Electrical Rough-In
Inspection - Pressure Test CHW Piping
Inspection - Mechanical Insulation
Inspection - Above Ceiling
Reinstall Ceiling Tile & Grid
10-Jun-20, AHU-1A
Install AHU-1A
Reconnect AHU-1A to Existing Piping / Install New
Install VAVs / New Ductwork
Connect Electrical to AHU / GPS
11-Jun-20, AHU-1B
Install AHU-1B
Reconnect AHU-1B to Existing Piping
Install VAVs / New Ductwork
Connect Electrical to AHU / GPS
09-Jun-20, AC-1A
Install AC-1A
Install Condenser Unit
Install Condenser Linesets
Install New Ductwork / Tie-in Existing
Connect Electrical to AHU / GPS / Condenser
10-Jun-20, AC-1B
Install AC-1B
Install Condenser Unit
Install Condenser Linesets
Install New Ductwork / Tie-in Existing
Connect Electrical to AHU / GPS / Condenser
11-Jun-20, AC-1C
Install AC-1C
Install Condenser Unit
Install Condenser Linesets
Install New Ductwork / Tie-in Existing
Connect Electrical to AHU / GPS / Condenser
12-Jun-20, AC-1D
Install AC-1D
Install Condenser Unit
Install Condenser Linesets
Install New Ductwork / Tie-in Existing
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 20 of 42 02/18/2020
Activity Name Start Finish
Connect Electrical to AHU / GPS / Condenser 12-Jun-20 12-Jun-20
Building 2 16-Mar-20 19-Jun-20
Install New Classroom Charging Cart Receptacle 17-Mar-20 30-Mar-20
Remove & Save Ceiling Tile & Grid 02-Jun-20 02-Jun-20
Demo New Wall Penetration for Ductwork 03-Jun-20 03-Jun-20
Install New Ductwork in Teacher Planning Rooms 04-Jun-20 05-Jun-20
Install New Supply Diffuser in Adjacent Storage Rooms 08-Jun-20 08-Jun-20
Inspection - Mechanical Rough-In 15-Jun-20 15-Jun-20
Inspection - Mechanical Insulation 15-Jun-20 15-Jun-20
Inspection - Pressure Test CHW Piping 15-Jun-20 15-Jun-20
Reinstall Ceiling Tile & Grid 18-Jun-20 18-Jun-20
Inspection - Electrical Rough-In 18-Jun-20 18-Jun-20
Inspection - Above Ceiling 18-Jun-20 18-Jun-20
Mezzanine 16-Mar-20 19-Jun-20
Install & Insulate New Chilled Water Piping 23-Mar-20 27-Mar-20
Rough-In BAS Controls 31-Mar-20 06-Apr-20
Install New High Duct Work 02-Apr-20 15-Apr-20
Disconnect Electrical to Existing Equipment 03-Jun-20 03-Jun-20
Relocate / Install New Light Fixtures 03-Jun-20 03-Jun-20
Install New Thermo-Ply Sheathing 03-Jun-20 09-Jun-20
Demo Existing Mechanical Equipment 04-Jun-20 05-Jun-20
Install New AHUs 08-Jun-20 08-Jun-20
Install New VAVs / Lower Ductwork 08-Jun-20 12-Jun-20
Connect Power to New Mechanical Equipment 15-Jun-20 16-Jun-20
Install BAS Controls to Equipment 15-Jun-20 19-Jun-20
Connect Power to Exhaust Fans 17-Jun-20 17-Jun-20
Structural 16-Mar-20 20-Mar-20
Cut Opening in Mezzanine Wall 16-Mar-20 16-Mar-20
Modify Existing Interior Structural Wall Openings 17-Mar-20 17-Mar-20
Install New Structural Support 18-Mar-20 18-Mar-20
Cap Unfinished Edges 19-Mar-20 19-Mar-20
Install New Door 20-Mar-20 20-Mar-20
Building 3 24-Mar-20 26-Jun-20
Install New Classroom Charging Cart Receptacle 31-Mar-20 13-Apr-20
Remove & Save Ceiling Tile & Grid 03-Jun-20 03-Jun-20
Demo New Wall Penetration for Ductwork 04-Jun-20 04-Jun-20
Install New Ductwork in Teacher Planning Rooms 05-Jun-20 08-Jun-20
Install New Supply Diffuser in Adjacent Storage Rooms 09-Jun-20 09-Jun-20
Inspection - Mechanical Rough-In 16-Jun-20 16-Jun-20
Inspection - Mechanical Insulation 16-Jun-20 16-Jun-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
Connect Electrical to AHU / GPS / Condenser
19-Jun-20, Building 2
Install New Classroom Charging Cart Receptacle
Remove & Save Ceiling Tile & Grid
Demo New Wall Penetration for Ductwork
Install New Ductwork in Teacher Planning Rooms
Install New Supply Diffuser in Adjacent Storage Rooms
Inspection - Mechanical Rough-In
Inspection - Mechanical Insulation
Inspection - Pressure Test CHW Piping
Reinstall Ceiling Tile & Grid
Inspection - Electrical Rough-In
Inspection - Above Ceiling
19-Jun-20, Mezzanine
Install & Insulate New Chilled Water Piping
Rough-In BAS Controls
Install New High Duct Work
Disconnect Electrical to Existing Equipment
Relocate / Install New Light Fixtures
Install New Thermo-Ply Sheathing
Demo Existing Mechanical Equipment
Install New AHUs
Install New VAVs / Lower Ductwork
Connect Power to New Mechanical Equipment
Install BAS Controls to Equipment
Connect Power to Exhaust Fans
20-Mar-20, Structural
Cut Opening in Mezzanine Wall
Modify Existing Interior Structural Wall Openings
Install New Structural Support
Cap Unfinished Edges
Install New Door
26-Jun-20, Building 3
Install New Classroom Charging Cart Receptacle
Remove & Save Ceiling Tile & Grid
Demo New Wall Penetration for Ductwork
Install New Ductwork in Teacher Planning Rooms
Install New Supply Diffuser in Adjacent Storage Rooms
Inspection - Mechanical Rough-In
Inspection - Mechanical Insulation
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 3 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 21 of 42 02/18/2020
Activity Name Start Finish
Inspection - Pressure Test CHW Piping 16-Jun-20 16-Jun-20
Reinstall Ceiling Tile & Grid 19-Jun-20 19-Jun-20
Inspection - Electrical Rough-In 19-Jun-20 19-Jun-20
Inspection - Above Ceiling 19-Jun-20 19-Jun-20
Mezzanine 24-Mar-20 26-Jun-20
Install & Insulate New Chilled Water Piping 30-Mar-20 03-Apr-20
Rough-In BAS Controls 07-Apr-20 13-Apr-20
Install New High Duct Work 09-Apr-20 22-Apr-20
Disconnect Electrical to Existing Equipment 04-Jun-20 04-Jun-20
Relocate / Install New Light Fixtures 04-Jun-20 04-Jun-20
Install New Thermo-Ply Sheathing 04-Jun-20 10-Jun-20
Demo Existing Mechanical Equipment 05-Jun-20 08-Jun-20
Install New AHUs 09-Jun-20 09-Jun-20
Install New VAVs / Lower Ductwork 09-Jun-20 15-Jun-20
Connect Power to New Mechanical Equipment 16-Jun-20 17-Jun-20
Connect Power to Exhaust Fans 18-Jun-20 18-Jun-20
Install BAS Controls to Equipment 22-Jun-20 26-Jun-20
Structural 24-Mar-20 31-Mar-20
Cut Opening in Mezzanine Wall 24-Mar-20 24-Mar-20
Modify Existing Structural Wall Openings 25-Mar-20 26-Mar-20
Install New Structural Support 27-Mar-20 27-Mar-20
Cap Unfinished Edges 30-Mar-20 30-Mar-20
Install New Door 31-Mar-20 31-Mar-20
Building 4 14-Apr-20 24-Jun-20
Rough-In BAS Controls 14-Apr-20 20-Apr-20
Resupport Light Fixtures 01-Jun-20 01-Jun-20
Disconnect Existing Mechanical Equipment 01-Jun-20 01-Jun-20
Install New Transformer / Panel & Feeders 02-Jun-20 03-Jun-20
Remove & Save Ceiling Tile & Grid 04-Jun-20 05-Jun-20
Install New Subpanel & Feeders 04-Jun-20 05-Jun-20
Remove Existing Heat Pumps 08-Jun-20 08-Jun-20
Remove Existing Duct Work 08-Jun-20 08-Jun-20
Remove All Wiring / Piping to Units 08-Jun-20 08-Jun-20
Remove Exisitng Exhaust Fans 08-Jun-20 08-Jun-20
Modify / Flush Condenser Water Pipes 09-Jun-20 09-Jun-20
Remove / Replace Thermostats in Rooms 09-Jun-20 15-Jun-20
Modify All Condensate Drains / Cap Unused 09-Jun-20 10-Jun-20
Install New Exhaust Fans 11-Jun-20 11-Jun-20
Reconnect Power to Exhaust Fans 12-Jun-20 12-Jun-20
Install New Main Chilled Water Piping 16-Jun-20 18-Jun-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
Inspection - Pressure Test CHW Piping
Reinstall Ceiling Tile & Grid
Inspection - Electrical Rough-In
Inspection - Above Ceiling
26-Jun-20, Mezzanine
Install & Insulate New Chilled Water Piping
Rough-In BAS Controls
Install New High Duct Work
Disconnect Electrical to Existing Equipment
Relocate / Install New Light Fixtures
Install New Thermo-Ply Sheathing
Demo Existing Mechanical Equipment
Install New AHUs
Install New VAVs / Lower Ductwork
Connect Power to New Mechanical Equipment
Connect Power to Exhaust Fans
Install BAS Controls to Equipment
31-Mar-20, Structural
Cut Opening in Mezzanine Wall
Modify Existing Structural Wall Openings
Install New Structural Support
Cap Unfinished Edges
Install New Door
24-Jun-20, Building 4
Rough-In BAS Controls
Resupport Light Fixtures
Disconnect Existing Mechanical Equipment
Install New Transformer / Panel & Feeders
Remove & Save Ceiling Tile & Grid
Install New Subpanel & Feeders
Remove Existing Heat Pumps
Remove Existing Duct Work
Remove All Wiring / Piping to Units
Remove Exisitng Exhaust Fans
Modify / Flush Condenser Water Pipes
Remove / Replace Thermostats in Rooms
Modify All Condensate Drains / Cap Unused
Install New Exhaust Fans
Reconnect Power to Exhaust Fans
Install New Main Chilled Water Piping
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 4 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 22 of 42 02/18/2020
Activity Name Start Finish
Install New Condensate Piping 16-Jun-20 17-Jun-20
Install BAS Controls to Equipment 18-Jun-20 24-Jun-20
Pressure Test Piping 19-Jun-20 19-Jun-20
Insulate Piping 19-Jun-20 22-Jun-20
Test & Balance Water System 19-Jun-20 19-Jun-20
Inspection - Mechanical Rough-In 19-Jun-20 19-Jun-20
Tie-In Existing Electrical 22-Jun-20 22-Jun-20
Inspection - Pressure Test CHW Piping 22-Jun-20 22-Jun-20
Inspection - Electrical Rough-In 23-Jun-20 23-Jun-20
Inspection - Mechanical Insulation 23-Jun-20 23-Jun-20
Inspection - Above Ceiling 23-Jun-20 23-Jun-20
Reinstall Ceiling Grid & Tile 23-Jun-20 24-Jun-20
AHU-4A 09-Jun-20 15-Jun-20
Install AHU-4A 09-Jun-20 09-Jun-20
Reconnect AHU-4A to Existing Piping / Install New 10-Jun-20 10-Jun-20
Install VAVs / New Ductwork 11-Jun-20 12-Jun-20
Connect Electrical to AHU / GPS 15-Jun-20 15-Jun-20
AHU-4B 10-Jun-20 16-Jun-20
Install AHU-4B 10-Jun-20 10-Jun-20
Reconnect AHU-4B to Existing Piping / Install New 11-Jun-20 11-Jun-20
Install VAVs / New Ductwork 12-Jun-20 15-Jun-20
Connect Electrical to AHU / GPS 16-Jun-20 16-Jun-20
AHU-4C 11-Jun-20 17-Jun-20
Install AHU-4C 11-Jun-20 11-Jun-20
Reconnect AHU-4C to Existing Piping / Install New 12-Jun-20 12-Jun-20
Install VAVs / New Ductwork 15-Jun-20 16-Jun-20
Connect Electrical to AHU / GPS 17-Jun-20 17-Jun-20
AHU-4D 12-Jun-20 18-Jun-20
Install AHU-4D 12-Jun-20 12-Jun-20
Reconnect AHU-4D to Existing Piping / Install New 15-Jun-20 15-Jun-20
Install VAVs / New Ductwork 16-Jun-20 17-Jun-20
Connect Electrical to AHU / GPS 18-Jun-20 18-Jun-20
AC-4 09-Jun-20 15-Jun-20
Install AC-4 09-Jun-20 09-Jun-20
Install Condenser Unit 10-Jun-20 10-Jun-20
Install Condenser Linesets 10-Jun-20 10-Jun-20
Install New Ductwork / Tie-in Existing 11-Jun-20 12-Jun-20
Connect Electrical to AHU / GPS / Condenser 15-Jun-20 15-Jun-20
OAU-4 15-Jun-20 19-Jun-20
Install OAU-4 15-Jun-20 15-Jun-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
Install New Condensate Piping
Install BAS Controls to Equipment
Pressure Test Piping
Insulate Piping
Test & Balance Water System
Inspection - Mechanical Rough-In
Tie-In Existing Electrical
Inspection - Pressure Test CHW Piping
Inspection - Electrical Rough-In
Inspection - Mechanical Insulation
Inspection - Above Ceiling
Reinstall Ceiling Grid & Tile
15-Jun-20, AHU-4A
Install AHU-4A
Reconnect AHU-4A to Existing Piping / Install New
Install VAVs / New Ductwork
Connect Electrical to AHU / GPS
16-Jun-20, AHU-4B
Install AHU-4B
Reconnect AHU-4B to Existing Piping / Install New
Install VAVs / New Ductwork
Connect Electrical to AHU / GPS
17-Jun-20, AHU-4C
Install AHU-4C
Reconnect AHU-4C to Existing Piping / Install New
Install VAVs / New Ductwork
Connect Electrical to AHU / GPS
18-Jun-20, AHU-4D
Install AHU-4D
Reconnect AHU-4D to Existing Piping / Install New
Install VAVs / New Ductwork
Connect Electrical to AHU / GPS
15-Jun-20, AC-4
Install AC-4
Install Condenser Unit
Install Condenser Linesets
Install New Ductwork / Tie-in Existing
Connect Electrical to AHU / GPS / Condenser
19-Jun-20, OAU-4
Install OAU-4
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 5 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 23 of 42 02/18/2020
Activity Name Start Finish
Install Condenser Unit 16-Jun-20 16-Jun-20
Install Condenser Linesets 16-Jun-20 16-Jun-20
Install New Ductwork / Tie-in Existing 17-Jun-20 18-Jun-20
Connect Electrical to AHU / GPS / Condenser 19-Jun-20 19-Jun-20
Building 5 16-Mar-20 06-Jul-20
Install New Classroom Charging Cart Receptacle 14-Apr-20 27-Apr-20
Remove & Save Ceiling Tile & Grid 08-Jun-20 08-Jun-20
Demo New Wall Penetration for Ductwork 09-Jun-20 09-Jun-20
Install New Ductwork in Teacher Planning Rooms 10-Jun-20 11-Jun-20
Install New Supply Diffuser in Adjacent Storage Rooms 12-Jun-20 12-Jun-20
Inspection - Mechanical Rough-In 19-Jun-20 19-Jun-20
Inspection - Mechanical Insulation 19-Jun-20 19-Jun-20
Inspection - Pressure Test CHW Piping 19-Jun-20 19-Jun-20
Reinstall Ceiling Tile & Grid 24-Jun-20 24-Jun-20
Inspection - Electrical Rough-In 24-Jun-20 24-Jun-20
Inspection - Above Ceiling 24-Jun-20 24-Jun-20
Mezzanine 16-Mar-20 06-Jul-20
Install & Insulate New Chilled Water Piping 06-Apr-20 10-Apr-20
Install New High Duct Work 16-Apr-20 29-Apr-20
Rough-In BAS Controls 21-Apr-20 27-Apr-20
Disconnect Electrical to Existing Equipment 09-Jun-20 09-Jun-20
Relocate / Install New Light Fixtures 09-Jun-20 09-Jun-20
Install New Thermo-Ply Sheathing 09-Jun-20 15-Jun-20
Demo Existing Mechanical Equipment 10-Jun-20 11-Jun-20
Install New AHUs 12-Jun-20 12-Jun-20
Install New VAVs / Lower Ductwork 12-Jun-20 18-Jun-20
Connect Power to New Mechanical Equipment 19-Jun-20 22-Jun-20
Connect Power to Exhaust Fans 23-Jun-20 23-Jun-20
Install BAS Controls to Equipment 29-Jun-20 06-Jul-20
Structural 16-Mar-20 23-Mar-20
Cut Opening in Mezzanine Wall 16-Mar-20 16-Mar-20
Modify Existing Structural Wall Openings 17-Mar-20 18-Mar-20
Install New Structural Support 19-Mar-20 19-Mar-20
Cap Unfinished Edges 20-Mar-20 20-Mar-20
Install New Door 23-Mar-20 23-Mar-20
Building 6 24-Mar-20 13-Jul-20
Install New Classroom Charging Cart Receptacle 28-Apr-20 11-May-20
Remove & Save Ceiling Tile & Grid 09-Jun-20 09-Jun-20
Demo New Wall Penetration for Ductwork 10-Jun-20 10-Jun-20
Install New Ductwork in Teacher Planning Rooms 11-Jun-20 12-Jun-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
Install Condenser Unit
Install Condenser Linesets
Install New Ductwork / Tie-in Existing
Connect Electrical to AHU / GPS / Condenser
06-Jul-20, Building 5
Install New Classroom Charging Cart Receptacle
Remove & Save Ceiling Tile & Grid
Demo New Wall Penetration for Ductwork
Install New Ductwork in Teacher Planning Rooms
Install New Supply Diffuser in Adjacent Storage Rooms
Inspection - Mechanical Rough-In
Inspection - Mechanical Insulation
Inspection - Pressure Test CHW Piping
Reinstall Ceiling Tile & Grid
Inspection - Electrical Rough-In
Inspection - Above Ceiling
06-Jul-20, Mezzanine
Install & Insulate New Chilled Water Piping
Install New High Duct Work
Rough-In BAS Controls
Disconnect Electrical to Existing Equipment
Relocate / Install New Light Fixtures
Install New Thermo-Ply Sheathing
Demo Existing Mechanical Equipment
Install New AHUs
Install New VAVs / Lower Ductwork
Connect Power to New Mechanical Equipment
Connect Power to Exhaust Fans
Install BAS Controls to Equipment
23-Mar-20, Structural
Cut Opening in Mezzanine Wall
Modify Existing Structural Wall Openings
Install New Structural Support
Cap Unfinished Edges
Install New Door
13-Jul-20, Building 6
Install New Classroom Charging Cart Receptacle
Remove & Save Ceiling Tile & Grid
Demo New Wall Penetration for Ductwork
Install New Ductwork in Teacher Planning Rooms
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 6 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 24 of 42 02/18/2020
Activity Name Start Finish
Install New Supply Diffuser in Adjacent Storage Rooms 15-Jun-20 15-Jun-20
Inspection - Mechanical Rough-In 22-Jun-20 22-Jun-20
Inspection - Mechanical Insulation 22-Jun-20 22-Jun-20
Inspection - Pressure Test CHW Piping 22-Jun-20 22-Jun-20
Reinstall Ceiling Tile & Grid 25-Jun-20 25-Jun-20
Inspection - Electrical Rough-In 25-Jun-20 25-Jun-20
Inspection - Above Ceiling 25-Jun-20 25-Jun-20
Mezzanine 24-Mar-20 13-Jul-20
Install & Insulate New Chilled Water Piping 13-Apr-20 17-Apr-20
Install New High Duct Work 23-Apr-20 06-May-20
Rough-In BAS Controls 28-Apr-20 04-May-20
Disconnect Electrical to Existing Equipment 10-Jun-20 10-Jun-20
Relocate / Install New Light Fixtures 10-Jun-20 10-Jun-20
Install New Thermo-Ply Sheathing 10-Jun-20 16-Jun-20
Demo Existing Mechanical Equipment 11-Jun-20 12-Jun-20
Install New AHUs 15-Jun-20 15-Jun-20
Install New VAVs / Lower Ductwork 15-Jun-20 19-Jun-20
Connect Power to New Mechanical Equipment 22-Jun-20 23-Jun-20
Connect Power to Exhaust Fans 24-Jun-20 24-Jun-20
Install BAS Controls to Equipment 07-Jul-20 13-Jul-20
Structural 24-Mar-20 30-Mar-20
Cut Opening in Mezzanine Wall 24-Mar-20 24-Mar-20
Modify Existing Structural Wall Openings 25-Mar-20 25-Mar-20
Install New Structural Support 26-Mar-20 26-Mar-20
Cap Unfinished Edges 27-Mar-20 27-Mar-20
Install New Door 30-Mar-20 30-Mar-20
Building 8 / Chiller Plant 05-May-20 17-Jul-20
Rough-In BAS Controls 05-May-20 18-May-20
Demo Existing Mechanical Equipment 01-Jun-20 05-Jun-20
Pressure Wash Walls / Floor 08-Jun-20 09-Jun-20
Place Housekeeping Pads 10-Jun-20 12-Jun-20
Install New Electrical for Mechanical Equipment 10-Jun-20 23-Jun-20
Install New Piping 10-Jun-20 30-Jun-20
Install New Pumps / HVAC Equipment 15-Jun-20 19-Jun-20
Install New Cooling Tower 15-Jun-20 17-Jun-20
Install New Chiller 15-Jun-20 17-Jun-20
Install New Relief Fan 15-Jun-20 16-Jun-20
Install New Lighting / Receptacles 24-Jun-20 25-Jun-20
Install New Panel / Tie-in to Existing 24-Jun-20 25-Jun-20
Install BAS Controls to Equipment 25-Jun-20 09-Jul-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
Install New Supply Diffuser in Adjacent Storage Rooms
Inspection - Mechanical Rough-In
Inspection - Mechanical Insulation
Inspection - Pressure Test CHW Piping
Reinstall Ceiling Tile & Grid
Inspection - Electrical Rough-In
Inspection - Above Ceiling
13-Jul-20, Mezzanine
Install & Insulate New Chilled Water Piping
Install New High Duct Work
Rough-In BAS Controls
Disconnect Electrical to Existing Equipment
Relocate / Install New Light Fixtures
Install New Thermo-Ply Sheathing
Demo Existing Mechanical Equipment
Install New AHUs
Install New VAVs / Lower Ductwork
Connect Power to New Mechanical Equipment
Connect Power to Exhaust Fans
Install BAS Controls to Equipment
30-Mar-20, Structural
Cut Opening in Mezzanine Wall
Modify Existing Structural Wall Openings
Install New Structural Support
Cap Unfinished Edges
Install New Door
17-Jul-20, Building 8 / Chiller Plant
Rough-In BAS Controls
Demo Existing Mechanical Equipment
Pressure Wash Walls / Floor
Place Housekeeping Pads
Install New Electrical for Mechanical Equipment
Install New Piping
Install New Pumps / HVAC Equipment
Install New Cooling Tower
Install New Chiller
Install New Relief Fan
Install New Lighting / Receptacles
Install New Panel / Tie-in to Existing
Install BAS Controls to Equipment
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 7 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 25 of 42 02/18/2020
Activity Name Start Finish
Inspection - Electrical Rough-In 26-Jun-20 26-Jun-20
Insulate Chilled Water Piping 01-Jul-20 15-Jul-20
Inspection - Mechanical Rough-In 01-Jul-20 01-Jul-20
Inspection - Pressure Test CHW Piping 01-Jul-20 01-Jul-20
Flush & Treat Chilled Water System 01-Jul-20 08-Jul-20
Inspection - Mechanical Insulation 16-Jul-20 16-Jul-20
Factory Start-Up of Chiller 16-Jul-20 17-Jul-20
Sitework 01-Jun-20 23-Jun-20
Sawcut Existing Sidewalk / Asphalt 01-Jun-20 02-Jun-20
Excavation 03-Jun-20 04-Jun-20
Install New Underground Piping 05-Jun-20 11-Jun-20
Inspection - Underground 12-Jun-20 12-Jun-20
Tie-in Undergound to New Mezzanine Pipiing 12-Jun-20 18-Jun-20
Insulate Underground Piping 19-Jun-20 19-Jun-20
Inspection - Pressure Test 19-Jun-20 19-Jun-20
Backfill & Compact 22-Jun-20 22-Jun-20
Patch Sidewalk / Asphalt 23-Jun-20 23-Jun-20
Close-out 03-Jun-20 12-Oct-20
25% Close-out Meeting 03-Jun-20 03-Jun-20
50% Close-out Meeting 02-Jul-20 02-Jul-20
Test Building Controls 14-Jul-20 27-Jul-20
Inspection - Mechanical Final 20-Jul-20 21-Jul-20
Inspection - Electrical Final 20-Jul-20 21-Jul-20
Test & Balance 20-Jul-20 31-Jul-20
Inspection - Building Final 23-Jul-20 27-Jul-20
Substantial Completion 31-Jul-20 31-Jul-20
75% Close-out Meeting 31-Jul-20 31-Jul-20
Punchlist 03-Aug-20 04-Sep-20
Owner Training 03-Aug-20 21-Aug-20
Third Party Commissioning 17-Aug-20 12-Oct-20
Final Completion 12-Oct-20
26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15
January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020
Inspection - Electrical Rough-In
Insulate Chilled Water Piping
Inspection - Mechanical Rough-In
Inspection - Pressure Test CHW Piping
Flush & Treat Chilled Water System
Inspection - Mechanical Insulation
Factory Start-Up of Chiller
23-Jun-20, Sitework
Sawcut Existing Sidewalk / Asphalt
Excavation
Install New Underground Piping
Inspection - Underground
Tie-in Undergound to New Mezzanine Pipiing
Insulate Underground Piping
Inspection - Pressure Test
Backfill & Compact
Patch Sidewalk / Asphalt
12-Oct-20, Close-out
25% Close-out Meeting
50% Close-out Meeting
Test Building Controls
Inspection - Mechanical Final
Inspection - Electrical Final
Test & Balance
Inspection - Building Final
Substantial Completion
75% Close-out Meeting
Punchlist
Owner Training
Third Party Commissioning
Final Completion
SBBC Challenger 7
Facility Renewal
Final Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 8 of 8 TASK filter: All Activities
© Oracle Corporation
SBBC Challenger 7 ES Page 26 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 3Construction Manager Fee
Please see Section 1a, GMP.
SBBC Challenger 7 ES Page 27 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 4General Conditions
Summary: General Requirements $49,984General Conditions $218,545General Liability Insurance $9,713Builder's Risk Insurance $1,677Subcontractor Bonds $26,041P&P Bond $23,797___________________________________Subtotal: $329,757
Attachments: General Conditions General Requirements
SBBC Challenger 7 ES Page 28 of 42 02/18/2020
150 dy BASE LABOR RATE: 2/18/2020
22 wk
5 mo
LINE DESCRIPTION BASE TOTAL TOTALS COMMENTS
ITEM QTY UNIT RATE MH
1 Project Management Team $196,258
2 Project Executive 0.50 mo 90.30 86.60 7,820
3 Project Manager 1.83 mo 70.70 317.30 22,433
4 Assistant Project Manager 4.00 mo 53.90 692.80 37,342
5 General Superintendent 0.50 mo 75.60 86.60 6,547
6 Superintendent 5.00 mo 57.05 866.00 49,405
7 Craft Foreman 3.75 mo 34.65 649.50 22,505
8 Project Engineer 2.50 mo 40.60 433.00 17,580
9 Field Engineer 0.00 mo 0.00 0.00 0
10 Project Assistant 2.50 mo 31.50 433.00 13,640
11 Project Accountant 1.00 mo 24.50 173.20 4,243
12 Safety Engineer 0.40 mo 50.40 69.28 3,492
13 Scheduler 0.80 mo 81.20 138.56 11,251
14 Staffing Check OK
15 Total Months of Staff 22.78 mo
16 Project Staffing Support Costs $22,287
17 Vehicles 19 mo 919.00 0 17,720
18 Phones 19 mo 62.00 0 1,195
19 Computers for Staff 23 mo 148.00 0 3,372
20 TOTAL GENERAL CONDITIONS 3,946 218,545
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
The School Board of Brevard County
Section 4
General Conditions
SBBC Challenger 7 ES Page 29 of 42 02/18/2020
150 dy22 wk
5 mo18-Feb-20
LINE UNIT TOTALS COMMENTSITEM DESCRIPTION QTY UNIT PRICE
1 Project Documentation 10,600
2 Informational signage 1 ea 600.00 600
3 Plan & specification reproduction cost 1 ls 500.00 500
4 Surveyor services 2 days 1,500.00 3,000
5 Ground Penetrating Radar 2 days 2,500.00 5,000
6 Progress Photo Documentation/3D 1 ls 1,500.00 1,500
7 8 Trailer Facilities $1,700
9 Field office supplies 5 mo 80.00 400
10 Internet Access 5 mo 200.00 1,000
11 Telephone - monthly charges - W/S 0 mo 0
12 Field office furnishings & equipment - purchase 1 ls 300.00 300
13 14 Temporary Facilities for Construction $650
15 Temporary toilets ( 1 / 40 tradesmen) 5 mo 130.00 650
16 17 Construction Equipment & Tools $6,750
18 Small tools & supplies 5 mo 450.00 2,250
19 Dust partitions 35' x 15' @ 20 Ea 5,000 sf 0.50 2,500
20 Existing surfaces protection - Drape Plastic 10,000 sf 0.20 2,000
21 22 Safety & Security $29,534
23 Construction Fencing - Panelized 500 ft 10.00 5,000
24 Barricades - Orange Fence 250 ft 3.00 750
25 Clean-up at end of project 30,000 sf 0.25 7,500
26 Clean-up throughout duration of project 22 wk 522.00 11,484
27 Dumpsters:
28 Dumpsters during project 10 pulls 450.00 4,500
29 Fire Extinguishers 4 ea 75.00 300
30 31 Project Start Up $750
32 Start up electric consumption charges 0 sf 0
33 Additional labor for 24/7 start-up 0 ls 0
34 As-built drawings 1 ls 500.00 500
35 Operation & maintenance manuals 1 ls 250.00 250
36 Final site survey 0 ea 0
37 TOTAL GENERAL CONDITIONS $49,984 49,984
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, REP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
The School Board of Brevard County
Section 4
General Requirements
SBBC Challenger 7 ES Page 30 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 5Liquidated Damages
To be provided upon acceptance of GMP Amendment.
SBBC Challenger 7 ES Page 31 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 6Project Representative:
Attachments:Representative InformationResume – Darin A. Crafton, Executive Vice PresidentResume - Nick Hare, Project Manger
SBBC Challenger 7 ES Page 32 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, REP #20-147-P-DR Challenger 7 Elementary School Facility Renewal
The School Board of Brevard County
Section 6Project Representatives
Owner’s Representatives: David Lindemann, Director of Planning and Project Management, Facilities Services 2700 Judge Fran Jamieson Way, Viera, FL 32940, (321) 633-1000 ext. 11463
Chris Gerber, Project Manager, Facilities Services 2700 Judge Fran Jamieson Way, Viera, FL 32940, (321) 633-3580 ext. 13048
Construction Manager’s Representatives:
Darin A. Crafton, Executive Vice President750 Monroe Road, Sanford, FL 32771, (407) 321-8410Resume Attached
Nick Hare, CGC, Project Manager750 Monroe Road, Sanford, FL 32771, (407) 321-8410Resume Attached
SBBC Challenger 7 ES Page 33 of 42 02/18/2020
Darin CraftonExecutive Vice President, Commercial Division
KEY QUALIFICATIONS
24 years of senior level experience with hospitality and commercial construction
EDUCATION
B.S., Construction, Bradley University, 1994
YEARS OF EXPERIENCE
4—Wharton-Smith24—Total
REGISTRATIONS / LICENSES / CERTIFICATIONS
OSHA 10-Hour
PROFESSIONAL AFFILIATIONS
ABC (Associated Builders & Constructors)
AGC (Associated General Contractors-US/Orlando/Charlotte
NAIOP (National Association of Industrial & Office Properties)
PCEA (Professional Construction Estimators Association-Southeast Division)
SAME (Society of American Military Engineers)
Darin Crafton is a senior construction executive with more than 24 years of experience in the construction industry and a proven track record of successfully completing high profile multi-million dollar projects on time and on budget. Darin will establish strong working relationships with our clients, his team members, and the communities where we live and work.
Project Experience
EDUCATION
• Innovation Middle School (Lake Nona), Orange County Public Schools, Orlando, FL ($26.5 million)
• Windermere High School (West Orange Area Relief High School), Orange County Public Schools, Orlando, FL ($70.2 million)
• Addition/Renovation to Tuskawilla Middle School, Seminole County Public Schools, Winter Springs, FL ($16 million)
• New 15,000 Seat Football Stadium, Expandable to 35,000 Seats for the University of North Carolina (UNC) 49er’s Football Team, Charlotte, NC, 2010 ($40 million)
• New High School ($37 million); Addition and Renovation ($10 million), Libertyville School District #28, Chicago, IL
• Two Identical Three-Story Elementary Schools located across town from each other, Cicero School District #99, Chicago, IL ($25 million)
• Westbrook Elementary School Renovation and Lincoln Jr. High School Renovation Phase I & II, Mount Prospect District #57, Chicago, IL ($2 million & $1 million)
• Lions Park Elementary School, Mount Prospect District #59, 68,000 SF, Chicago, IL, ($7 million)
• Fairview Elementary School, 68,000 SF, Mount Prospect District #59, Chicago, IL ($7 million)
• University of Southern Mississippi – Marine Research Facility, Mississippi State Port Authority, Gulfport, MS ($11 million)
MUNICIPAL
• USSSA Space Coast Complex – Viera, Melbourne, FL ($12.6 million)
• Seminole County Sports Complex, Seminole County, Sanford, FL ($27 million)
• Soldier’s Creek Sports Complex, Seminole County, Longwood, FL ($7.2 million)
• Austin Tindall Regional Park Expansion, Osceola County, Kissimmee, FL ($5.5 million)
RELIGION
• St. Luke’s Lutheran Church, Fellowship Hall and Gymnasium, Oviedo, FL
SBBC Challenger 7 ES Page 34 of 42 02/18/2020
($4.4 million)
HOSPITALITY
• Eight-Story, 119 Guestroom Hotel, Aloft Hotel, Orlando, FL ($12 million)
• Renovation of 450 Guestrooms and four Restaurants Completed in Nine Weeks, Ritz Carlton, Naples, FL ($23 million)
• 16,000-acre, 305,000-SF, and 228 Luxury Guestrooms, Streamsong Resort, FL ($80 million)
• 395-Guest Room, Lobby and Fitness/Pool Renovation, Sheraton Hotel Renovation, Indianapolis, IN, 2010 ($5 million)
• New 12-story Hotel Tower and Phase II Casino, Hardrock Tampa Hotel & Casino, Tampa, FL ($85 million)
COMMERCIAL
• Mixed-Use, High-End Retail, Hotel and Water Park, American Dream Development, Rutherford, NJ ($2 billion)
• 65-story Condo at 1151 West Georgia Condo (Precon), Vancouver, BC ($250 million)
• Five-Building Mixed-Use Facility on the Historic Biltmore Property, Biltmore Winery Antler Village, Asheville, NC, 2009 ($12 million)
• Thirty-Four-story, 1.1-million SF building, 55 West, Orlando, FL ($170 million)
• New Design-Build Clubhouse/Casino/Horse Racetrack, MEC Gulfstream Clubhouse, Hallandale, FL ($66 million)
• Themed Dinner and Horse Show Attraction, Dixie Stampede Dinner & Show Theater, Orlando, FL ($20 million)
• New Themed Mixed-use Attraction Consisting of Restaurants, 4-D Theater and Retail Stores, Crossroads at Stone Mountain, Atlanta, GA ($25 million)
• New Prototype Resort Consisting of a three hotel complex of a five story, 388 room Fairfield Inn, five story, 400 room Courtyard Marriott and five story, 312 room Springhill Suites, Marriott International, Orlando, FL ($75 million)
• Emergency Operations Center, Mobil County Commission, Mobile, AL ($10.7 million)
RESIDENTIAL
• Six-story, 246 Apartments and 399 Space Garage, 899 North Orange Avenue, Orlando, FL ($32 million)
• New Eight-Story Apartment Tower and Parking Deck, Parkcrest at Harbor Island, Tampa, FL ($35 million)
OTHER
• Two-Story Command Center for NAVFAC Cherry Point Naval Base, NAVFAC Cherry Point Command Center, Havelock, NC, 2009 ($22 million
• New Design-Build Flight Simulation Training Facility, Jet Blue, Orlando, FL ($16 million)
• New 70,000 SF Recreation Complex, Oak Brook Park District, Chicago, IL ($10 million)
Darin CraftonExecutive Vice President, Commercial Division
SBBC Challenger 7 ES Page 35 of 42 02/18/2020
Nick Hare Project Manager
KEY QUALIFICATIONS
EDUCATIONB.S. in Building Construction, Auburn University, 2007
YEARS OF EXPERIENCE
< 1—Wharton-Smith13—Total
REGISTRATIONS / LICENSES / CERTIFICATIONS
OSHA 30-Hour
Florida General Contractors Licence CGC1521147
CPR/First Aid Certified
PROFESSIONAL AFFILIATIONS
Member
Member
As Project Manager, Nick is responsible for providing daily leadership to the project team and for the successful completion of all preconstruction and construction phases of the project. He will develop schedules, perform constructability reviews, value engineering and site logistics. During construction, he assists with all construction activities, including quality control, cost control, change orders, and close-out.
Project Experience
• Johnson Middle School Facility Renewal, Brevard Public Schools, Melbourne, FL ($2.8 million)
• Gemini Elementary School Facility Renewal, Brevard Public Schools, Melbourne Beach, FL ($978 K)
• Cypress West WRF Ops Building, Toho Water Authority, Kissimmee, FL ($832,500)*
• Rockledge High School Technology Infrastructure Upgrade, Brevard Public Schools, Rockledge, FL ($1,520,800)*
• Andersen Elementary School Air Handler Unit Replacement, Brevard Public Schools, Rockledge, FL ($593,000)*
• Rockledge High School Buildings 12 & 15 Restroom Remodels, Brvard Public Schools, Rockledge, FL ($330,000)*
• Fixed Seating Replacement, University of Central Florida ($275,500)*
• Port Canaveral Enterprise Rent-A-Car, Enterprise Holdings LLC ($270,000)*
• Jefferson Middle School Facility Renewal, Brevard Public Schools ($3,600,000)*
SBBC Challenger 7 ES Page 36 of 42 02/18/2020
Name Title
• Andersen Elementary School MEP Systems Upgrade, Brevard Public Schools, Rockledge, FL ($1,073,000)*
• Atlantis Elementary School Technology, Fire Alarm, and Intercom Infrastructure Upgrades, Brevard Public Schools, Port St. John, FL ($1,013,000)*
• Longleaf Elementary School Technology and Fire Alarm Infrastructure Upgrades, Brevard Public Schools, Melbourne, FL ($731,000)*
• Meadowlane Primary Technology Infrastructure Upgrades, Brevard Public Schools, West Melbourne, FL ($620,000)*
• Southwest and Turner Facility Renewal, Brevard Public Schools ($4,023,000)*
• Trevor Colbourn Hall, University of Central Florida, Orlando, FL ($24,000,000)*
*Denotes previous experience
SBBC Challenger 7 ES Page 37 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 7Construction Documents List
Attachments: Documents List including Drawings, Specifications, RFI’s, WSI’s
SBBC Challenger 7 ES Page 38 of 42 02/18/2020
Number Sheet Name Issue Date
G-1 Cover Sheet 1/14/20
A-1 Architectural Detail 1/14/20
M-1 Mechanical Legends & Abbreviations 1/14/20
M-2 Mechanical Site Plan 1/14/20
M-3 Mechanical Plan - Bldg. 1 1/14/20
M-4 Mechanical Plan - Bldg. 2 1/14/20
M-5 Mechanical Plan - Bldg. 3 1/14/20
M-6 Mechanical Plan - Bldg. 4 1/14/20
M-7 Mechanical Plan - Bldg. 5 1/14/20
M-8 Mechanical Plan - Bldg. 6 1/14/20
M-9 Mechanical Plan - Bldg. 9 1/14/20
M-10 Mechanical Schedules 1/14/20
M-11 Mechanical Schedules 1/14/20
M-12 Mechanical Schedules 1/14/20
M-13 Mechanical Details 1/14/20
M-14 Mechanical Controls - Water Side 1/14/20
M-15 Mechanical Controls - Air Side 1/14/20
E-1 Electrical Legend and Abbreviations 1/14/20
E-2 Electrical Site Plan 1/14/20
E-3 Electrical Demolition Plans - Bldg. 1 & 4 1/14/20
E-4 Electrical Plans - Bldg. 1 & 4 1/14/20
E-5 Electrical Plans - Bldg. 2 & 3 1/14/20
E-6 Electrical Plans - Bldg. 5 & 6 1/14/20
E-7 Electrical Plans - Bldg. 8 1/14/20
E-8 Electrical Schedules 1/14/20
E-9 Electrical Schedules 1/14/20
E-10 Electrical Schedules 1/14/20
E-11 Electrical Risers 1/14/20
Drawings
Challenger 7 Facility Renewal 100 % Bid Set, DDC Engineering
List of Construction Contract Documents
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
The School Board of Brevard CountyChallenger 7 Elementary School Facility Renewal
Section 7
SBBC Challenger 7 ES Page 39 of 42 02/18/2020
List of Construction Contract Documents
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for CM Services, RFP #20-147-P-DR
The School Board of Brevard CountyChallenger 7 Elementary School Facility Renewal
Section 7
Number Sheet Name Issue Date
Table of Contents 1/14/20
221116 Domestic Water Piping 1/14/20
230513 Motors 1/14/20
230519 Meters and Gauges 1/14/20
230523 Valves 1/14/20
230529 Hangers and Supports 1/14/20
230553 Mechanical Identification 1/14/20
230593 Testing, Adjusting, and Balancing 1/14/20
230713 Duct Insulation 1/14/20
230716 Equipment Insulation 1/14/20
230719 Pipe Insulation 1/14/20
230923 Direct Digital Control System 1/14/20
232116 Hydronic Piping 1/14/20
232123 Hydronic Pumps 1/14/20
232300 Refrigerant Piping 1/14/20
233113 Metal Ducts 1/14/20
233300 Duct Accessories 1/14/20
233416 Power Ventilators 1/14/20
234100 Air Filters 1/14/20
236426 Water Cooled Chillers 1/14/20
236514 Cooling Towers 1/14/20
237313 Indoor Air-Handling Units 1/14/20
260010 Basic Electrical Requirements 1/14/20
260519 Conductors and Cables 1/14/20
260526 Grounding and Bonding 1/14/20
260529 Hangers and Supports for Electrical Systems 1/14/20
260533 Raceways and Boxes 1/14/20
260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 1/14/20
260553 Electrical Identification 1/14/20
262213 Low-Voltage Transformers 1/14/20
262416 Panelboards 1/14/20
262726 Wiring Devices 1/14/20
262813 Fuses 1/14/20
262816 Enclosed Switches and Circuit Breakers 1/14/20
262913 Enclosed Controllers 1/14/20
262923 Variable Frequency Controllers 1/14/20
264313 Surge Protection for Low-Voltage Electrical Power Circuits 1/14/20
RFI 001
WSI 001
WSI 001
Request for Information (RFI)
Specifications
DDC Engineering Inc, Response Received 1/30/2020
Wharton-Smith, Inc. Supplemental Instruction (WSI)
Scope & Schedule, Sent to bidders 2/3/2020
Photos, Sent to bidders 2/3/2020
Brevard Public Schools, Challenger 7 Elementary Master Specifications, Dated January 14, 2020
SBBC Challenger 7 ES Page 40 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment to Agreement for Construction Management Services
Challenger 7 Elementary School (2131) Facility RenewalRFP #20-147-P-DR
Section 8Exceptions & Exclusions and Clarifications
Attachments:Assumptions & Clarifications and Exclusions
SBBC Challenger 7 ES Page 41 of 42 02/18/2020
Exhibit C – Guaranteed Maximum Price (GMP) Amendment
to Agreement for CM Services, REP #20-147-P-DR
Challenger 7 Elementary School Facility Renewal
The School Board of Brevard County
Section 8
Exceptions & Exclusions and Clarifications
Assumptions & Clarifications:
1. Impacted existing finish surfaces shall be repaired in a manner to match existing conditions as closely as
possible.
2. The cost of staff identified in the General Conditions shall not all be stationed on site, but working
exclusively on the project, shall be reimbursed by the SBBC as shown in the attached General
Conditions exhibit.
3. Overtime hourly rates shall only apply to hourly field staff personnel working on the project above and
beyond forty (40) hours per week or more than 10 hours per day and shall be consistent with the
audited overtime hourly rate.
4. Modifications to Existing Catwalks need additional review and may require additional engineering and
design. The values carried are to be considered an allowance.
5. The roof penetration at the Boiler in Bldg 8 is assumed to include a roof curb. When the stack is
removed, the curb will be capped with a sheet-metal plate and made weather-tight.
6. Floor Coating at Building 8 shall be similar to Tred-Plex Epoxy and shall be roller applied.
7. Makeup Water for the Cooling Towers is assumed to use the exiting piping and extend as required for
the new equipment.
8. Existing Water Treatment system shall be reconnected to the new condenser water piping and tested.
No repairs or replacement of components for this system are included.
9. Temporary Cooling and Dehumidification shall consist of portable units, moved from space to space as
required. The value carried is to be considered an allowance.
10. AHU’s on the existing Mezzanine will be set on Structural Steel Rails in lieu of concrete housekeeping
pads.
11. Electrical renovations do not include any modifications to the existing voice/data or security/access
control systems.
Exceptions & Exclusions:
1. ACM Abatement, if required.
2. Repair or replacement of any existing conditions not shown on the contract documents or identified
specifically within the scope of this contract.
3. Cleaning of existing Ductwork is excluded.
4. Painting of Mechanical Rooms is excluded.
5. New Thermo-Ply Sheathing & Insulation repairs at Mezzanine walls is excluded.
SBBC Challenger 7 ES Page 42 of 42 02/18/2020