  • 8/11/2019 Auditing PSM Systems

    1/20

    Auditing Process SafetyManagement Systems

    David E. Downs, CIH, CSPPresident

    EHS Management Partners, Inc.

  • 8/11/2019 Auditing PSM Systems

    2/20

    Copyright - EHS Management Partners,Inc.

    Process Safety Management -A Brief Review

    Rationale for Process Safety Management Structure of OSHAs PSM Standard Requirement for PSM Audit PSM Audit as a Management System Component

  • 8/11/2019 Auditing PSM Systems

    3/20

    Copyright - EHS Management Partners,Inc.

    Bhopal, India

  • 8/11/2019 Auditing PSM Systems

    4/20

    Copyright - EHS Management Partners,Inc.

    Chemical CompanyMustang, Nevada

    Downloaded from the U.S. Chemical Safety and Hazard Investigation Board Web Site

  • 8/11/2019 Auditing PSM Systems

    5/20

    Copyright - EHS Management Partners,Inc.

    Chemical Plant Explosion

    Downloaded from the U.S. Chemical Safety and Hazard Investigation Board Web Site

  • 8/11/2019 Auditing PSM Systems

    6/20

    Copyright - EHS Management Partners,Inc.

    Process Safety Management Structure Employee Involvement Process Safety Information Process Hazard Analysis Operating Procedures Employee Training

    Contractors Pre-Startup Safety Mechanical Integrity Hot Work Permits Management of Change

    Incident Investigation Emergency Preparedness

    Compliance Audits!

  • 8/11/2019 Auditing PSM Systems

    7/20

    Copyright - EHS Management Partners,Inc.

    PSM Audit Requirements

    Certify compliance every three years procedures are adequate are being followed

    Conducted by at least one person familiar with process Report of findings Document response to findings Retain last two audit reports

  • 8/11/2019 Auditing PSM Systems

    8/20

    Copyright - EHS Management Partners,Inc.

    PSM in the Context of an EHSManagement System

    Covered process - usually rates as a significant EHSaspect

    Objectives relate to risk reduction

    Significant implementation issues Responsibilities; Training; Process Documentation; ... PSM Audit is part of Checking and Corrective Action Goal needs to be Continuous Improvement

  • 8/11/2019 Auditing PSM Systems

    9/20

    Copyright - EHS Management Partners,Inc.

    Design of a PSM Audit

    Start with OSHA Guidance Document OSHA Instruction CPL 2-2.45A CH-1

    Appendix A Essentially a workbook and checklist for the OSHA

    Compliance Officer

    Includes Program Summaries by section Record Review Guidelines On-site Conditions to Review Interview Questions

  • 8/11/2019 Auditing PSM Systems

    10/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

    Develop Implementation Criteria Level 1- Issue or criteria has not been addressed Level 2- Addressed in cursory or ad hoc manner, little

    coordination or management Level 3- Most elements addressed; some areas need

    completion, documentation or communication Level 4- Criteria has been effectively and consistently

    implemented

    Level 5- Addressed in particularly effective manner; bestmanagement practices in industry or company.

  • 8/11/2019 Auditing PSM Systems

    11/20

    Copyright - EHS Management Partners,Inc. 1

    Example Question & Implementation Levels

    Q: Have appropriate checks and inspections been made to assureequipment is installed properly and consistent with designspecifications and manufacturer's instructions?

    L evel 1- There is no evidence of a process for installation verification.

    L evel 2- Some staff report that inspections are done, but there is no consistentdocumentation or process.

    L evel 3- There is evidence of a procedure for equipment installation checks andinspections, based on review of documentation. Not all new equipment is

    consistently reviewed; or, reviews may not be complete.

  • 8/11/2019 Auditing PSM Systems

    12/20

    Copyright - EHS Management Partners,Inc. 1

    Example Question & Implementation Levels

    Q: Have appropriate checks and inspections been made to assureequipment is installed properly and consistent with designspecifications and manufacturer's instructions?

    L evel 4- There is an effective and consistent review process which verifies that new

    equipment is installed properly and in accordance with specifications. Reviews aredocumented.

    L evel 5- The process for new equipment installation has been designed andimplemented in a particularly effective manner and represents best practices for thisindustry or organization.

  • 8/11/2019 Auditing PSM Systems

    13/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

  • 8/11/2019 Auditing PSM Systems

    14/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

  • 8/11/2019 Auditing PSM Systems

    15/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

  • 8/11/2019 Auditing PSM Systems

    16/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

  • 8/11/2019 Auditing PSM Systems

    17/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

  • 8/11/2019 Auditing PSM Systems

    18/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

  • 8/11/2019 Auditing PSM Systems

    19/20

    Copyright - EHS Management Partners,Inc. 1

    Design of a PSM Audit

  • 8/11/2019 Auditing PSM Systems

    20/20

    Copyright - EHS Management Partners,Inc. 2

    Conclusions

    Need to comply with OSHA Audit Requirements Recognize the reality of incremental

    improvements

    Institute a Continuous Improvement Process