Azgard9 - Colorado

Azgard9 - ColoradoIssues Related to Sampling & ProductionChanges made in Tech Pack, Trims Layout, styling, measurements after PO placement till PP stage.

Requirement of Bay City to dispatch PP with complete trims for the production approval.

Metal trims lead time 4 weeks Delay in getting comments 1 week minimum

Flexibility to understand limitations

Parcel misplacement

Delays from Nominated suppliers

Delays in making commercial decision regarding shipments Thank You!