background information document › wp-content › uploads › 2012 › 06 ›...
TRANSCRIPT
Government of Montserrat
Background Information Document
Environment and Social Impact Assessment For
Geothermal – Drilling of Exploratory Production Wells
Prepared and Submitted By
September 2012
Contents Page
1.0 Introduction ..............................................................................................................................................3
1.1 Brief Description .....................................................................................................................................3 1.2 Purpose of Document ...........................................................................................................................3 1.3 Audience ...................................................................................................................................................3
2.0 The Project ...............................................................................................................................................4 2.1 Project Background ...............................................................................................................................4 2.2 Project Description ................................................................................................................................7 2.3 Project Purpose ......................................................................................................................................9 2.4 Project Technical information ..........................................................................................................10 2.5 Project Location....................................................................................................................................11
3.0 The Environmental and Social Impact Assessment ..................................................................12 3.1 Project Team ..........................................................................................................................................12 3.2 Environmental Impact Assessment (EIA) .....................................................................................13
3.2.1 EIA Scoping ..................................................................................................................................13 3.2.2 Environmental Stakeholder Engagement............................................................................16 3.2.4 Environmental Baseline Data ..................................................................................................17 3.2.5 Environmental Impacts .............................................................................................................17 3.2.6 Development of an Environmental Impact Management Plan (EIMP) ........................18
3.3 Social Impact Assessment (SIA)......................................................................................................19 3.3.1 SIA Scoping ..................................................................................................................................20 3.3.2 Social Stakeholder Engagement ............................................................................................23 3.3.3 Social Stakeholder Feedback..................................................................................................24 3.3.4 Socioeconomic Baseline Data ................................................................................................24 3.3.5 Social Impacts .............................................................................................................................25 3.3.6 Development of a Social Impact Management Plan (SIMP) ...........................................26
3.4 Review Institutional Capacity and Feedback ...............................................................................26 References ............................................................................................................................................................27
Montserrat Geothermal ESIA
Page 3
1.0 Introduction
1.1 Brief Description
Atom Solutions Inc. has been contracted to provide specialist environmental
services to the Government of Montserrat for the effective management of
geothermal test drilling and related activities on the Island. The assignment
comprises an Environmental and Social Impact Assessment (ESIA) for the
proposed drilling of two production wells, including Environmental and Social
Management Plans to guide and monitor the performance of the drilling
contractor.
1.2 Purpose of Document
This document is intended to be the main source of information about the test
drilling project. Its purpose is to:-
Introduce the proposed project
Explain the ESIA process
Be a source of reference for the project
1.3 Audience
The primary audience for this document will be:
Stakeholder Ministries
Businesses
Non-Government Organizations (NGOs)
General Public
Montserrat Geothermal ESIA
Page 4
2.0 The Project
2.1 Project Background
The island of Montserrat is a UK Overseas Territory, located in the Leeward
Islands of the Eastern Caribbean, part of the Lesser Antilles Island Chain.
Montserrat is approximately 16 km long and 11 km wide, with a total surface area
of approximately 40 km2 and a population of 4,922 (2011 Census). The island is
the most mountainous of the Leeward Islands and is dominated by the Soufrière
Hills Volcano.
The GDP per capita is approximately U$ 8,400 (2006 data). There is limited
economic activity on the island including mining and quarrying, construction,
financial and professional services and tourism. Volcanic eruptions in 1995
destroyed the capital city and enforced the permanent relocation of inhabitants
from two-thirds of the island. Since then the territory has been dependent on UK
aid, with DFID currently providing 54% of Montserrat's recurrent budget in the
form of budget support. Montserrat's economy is 100% fossil fuel based with the
Government of Montserrat spending £ 1.7 million annually on fuel imports. This is
unsustainable from an environmental, climate change and economic perspective.
Given its volcanic origins, Montserrat has the potential for geothermal electrical
power generation as an alternative to a power supply based on imported fossil
fuels.
Montserrat Geothermal ESIA
Page 5
The exploration and exploitation of Montserrat's potential geothermal resource is
one of the Government of Montserrat's highest development priorities. However,
it is an innovative area for energy development with high up front cost.
Several studies have been undertaken to identify potentially exploitable
geothermal sources on the island. The most recent of these (including that
undertaken by EGS) have concentrated on an area which lies within the Weekes
Valley area between Garibaldi Hill and St George’s Hill, in a zone that is in the
volcanic risk area (but considered safe from direct volcanic threat) where day
time access is now possible. However, mud slides in the Belham River may
interrupt access into the potential development area if there is heavy rainfall.
See location map for proposed drilling below.
Montserrat Geothermal ESIA
Page 6
Figure 1 - Drilling Location
Montserrat Geothermal ESIA
Page 7
In 2010 a DFID funded study assessed the geothermal potential of Montserrat.
This built on the findings of other research commissioned since 1997 and
concluded that there is high probability that Montserrat has considerable
geothermal resources. The most conservative research suggests that there is a
75-80% chance of at least 5 MW of power available.
In 2011 DFID commissioned an economic assessment that assessed the
commercial viability for resources of different sizes e.g. 2-5 MW, <25 MW and
>50 MW. This assessment determined that a 2 MW production capacity had the
most favourable economic rate of return and would be sufficient for Montserrat’s
immediate and medium-term requirements.
2.2 Project Description
Recognising the high cost of mobilisation of drilling equipment to Montserrat, it is
proposed to proceed directly to the drilling of two production size wells rather
than smaller pre-production exploration ‘slim holes’ that would then need to be
followed by production wells. Given the very small area able to be explored within
the accessible zone, the drilling of slim holes before the production wells is not
expected to influence the well locations and may unreasonably delay what is an
already relatively costly development.
Montserrat Geothermal ESIA
Page 8
Each well will be drilled to a depth of 2000 ft. The target area is sited on St.
George’s Hill. Well #1 will be drilled to the bottom of the clay cap at the boundary
between the high and low resistivity zones. The zone targeted is the intersection
between orthogonal fault/fracture systems as indicated by resistivity data and
high MEQ activity in 1995 as well as surface fault mapping. It is proposed that
this area has the highest probability of having both hot fluid and locally high
permeability. Well #2 is planned to test the areal extent of the resource within the
accessible area around St George’s Hill.
The Government of Montserrat (GoM) is establishing a Geothermal Project
Management Unit (PMU) to oversee the proposed drilling of the two production
sized wells. It is anticipated that the PMU will draw technical support through a
number of associated tenders for drilling management, well site preparation and
specialist support services for well logging, analysis and testing. The services
under this tender are seen essentially as a “turnkey” delivery of two production
wells as specified by the GoM. The Drill Services Contractor (DSC) will supply all
equipment, materials, consumables and services for the completion of the drilling
programme.
The Drilling Services Contractor will provide a suitably sized drilling rig and
associated equipment and operational personnel. In addition, the Drilling
Services Contractor will be required to arrange and manage, either from within its
own resources or through competent and recognised service companies, the
provision of all materials required to complete the drilling programme as
Montserrat Geothermal ESIA
Page 9
described in these documents, mud engineering, casing and cementing services
and the provision of all pipe work, silencer and appropriate structures from well
head to test pit for production testing.
Drilling water supply requirements are estimated at 3500 litres per minute with
backup storage available through “ponding” at one or both drilling sites.
2.3 Project Purpose
The purpose of this consultancy is to ensure that:
Any potential negative environmental and social impacts associated with
drilling activities are clearly identified.
All geothermal test drilling activities are managed in order to avoid or
minimise negative environmental and social impacts.
Opportunities are identified for creating/enhancing beneficial
environmental and social effects/benefits, where possible.
Stakeholders have opportunities to contribute to the process of
environmental assessment and management and are kept informed of its
progress.
The proposed drilling is an exploratory phase for a potential geothermal
development and any power plant installation will be dependent on the outcome.
The location of the drilling operation is in a volcanic exclusion zone where there
are currently no inhabitants and into which access is restricted.
Montserrat Geothermal ESIA
Page 10
2.4 Project Technical information
Technical information for the production wells as proposed is given below.
Location St Georges Bay Hill Well A01 Coordinates Eastings 376295.3604 Northings
1848341.1684 Well B01 Coordinates Eastings 376382.7624 Northings
1848844.2617
Drilling and Casing Programme Section Depth Casing Details
Open Hole Metres 26” 40 to 60 20" 94 lb/ft, H-40, BT &C
casing cemented back to the surface
17 ½ “ 250 to 350 13 3/8" 68 lb/ft, K-55, BT &C casing cemented back to the surface.
12 ¼ “ 800 to 1000 9 5/8" 47 lb/ft, K-55, BT&C casing cemented back to the surface.
9 5/8 “ 1500 to 2000 7" 26 lb/ft, K-55, BT&C slotted liner. This casing shall extend from approximately three joints above the 9 5/8” production casing shoe to the final well depth.
Wellhead Completion Test Pressure 13 3/8” 3000 wellhead flange with adaptor spool 10” to 13 3/8”
1000 psi
10” 900 Master Valve with 2 x 1 3/8” 900 side valves
1000 psi
Montserrat Geothermal ESIA
Page 11
2.5 Project Location
The area between St. Georges Hill and Garibaldi Hill is considered the most
practical place to test for a geothermal system from a geologic, logistics and
safety perspective. Two major morphological features dominate the prospect
area. Garibaldi Hill is located south of the Old Road Bay, filled with mudflows
since the last eruption, and north of the Fox’s Bay. St George’s Hill is located
east of Garibaldi Hill, surrounded on its east and south part by the pyroclastic
flows of the most recent eruptions. This area will be the primary focus of the
ESIA, which should be carried out in accordance with the requirements of the
Physical Planning Act 2002 (Cap. 8.03) in order to identify the potential
environmental and social of the drilling activities and develop appropriate
mitigation measures in the form of an Environmental and Social Management
Plan.
The potential impact zones will be the drilling location itself and surrounding
areas; the extent of the impact zone beyond the drilling site will be determined by
the ESIA consultant. As the site is in an area where only day time access is
allowed, the impact on local communities is likely to be relatively limited.
Montserrat Geothermal ESIA
Page 12
3.0 The Environmental and Social Impact Assessment
3.1 Project Team
The team structure for this project is shown below. The resources utilized in the
execution of such roles are shown in the table.
Project Manager
(Atom)
EnvironmentalSpecialist
(Atom)
Communications Specialist
(Montserrat)
Hydro-Geologist
(Atom)
Social/Legal Specialist
(Atom)
BiodiversitySpecialist
(Government)
Resources Roles
Dr. Erwin Edwards (EE) Project Management
Energy/Climate Change Specialist
Socio-economic Impact
Communications
Mr. Cathal Healy-Singh (CH) Environmental Impact Specialist
Ms. Paula Bourne (PB) Social Impact Specialist
Montserrat Geothermal ESIA
Page 13
Environmental Impact Specialist
Legal Services
Government Resource (GOV) Biodiversity Specialist
Mr. Pramenath Narinesingh (PN) Hydro-geologist
3.2 Environmental Impact Assessment (EIA)
3.2.1 EIA Scoping
A preliminary desktop assessment undertaken by the Government of Montserrat
in March 2012, generated a provisional list of impacts and issues to be assessed
in the impact assessment. See list below:
Impacts on surface water
Impacts on groundwater
Solid and liquid wastes
Air quality
Stakeholder perceptions
Noise and vibration
Transport
Impacts on fauna
Impacts on flora
Impacts that may occur due to accidental events
Impacts on social activities during normal access times
Impact of community traditions/culture
Potential economic disruptions
Impact on legal land right
Health and Safety
Montserrat Geothermal ESIA
Page 14
The proposed drilling sites are within a restricted zone with limited access. They
were selected because of its geothermal potential and because it is relatively
safe from pyroclastic flows, being shielded by St. George’s Hill. The closest
distance to residents is 1,600m. All drill fluids will be stored adjacent to the well in
dedicated waterproof concrete structures with 960 m3 capacity. On completion of
drilling it is proposed that the liquid component is re-injected into the well. The
solid component can be left in the concrete tank, capped and integrated into
future geothermal extraction if the well yield proves viable.
The drill sites are downwind of the volcano. Baseline SO2 (sulphur dioxide), acid
rain and seismic activity are regularly monitored by the MVO. Because of these
conditions the following impacts are not expected to be significant:
Greenhouse gas emissions
Atmospheric heat pollution
Soil and land contamination
Land use conflicts
Land take
Erosion from water discharge
Marine impacts
Subsidence
Induced landslides
Induced seismicity
Visual
Public health and safety
Tourism
Archaeological
Montserrat Geothermal ESIA
Page 15
However, all relevant impacts will be assessed during the scoping phase and a
definitive list prepared to include any areas not currently identified.
Scoping is a critical, early step in the preparation of an EIA. The scoping process
identifies the issues that are likely to be of most importance during the EIA and
eliminates those that are of little concern. Typically, this process concludes with
the establishment of Terms of Reference for the preparation of an EIA. In this
way, scoping ensures that EIA studies are focused on the significant effects and
time and money are not wasted on unnecessary investigations. A detailed
understanding of the logistics for landing, transporting and mobilizing the drill rig
for the drilling operation, the materials used, duration and occupational risks will
also be part of the scoping exercise.
The purpose of scoping is to identify:
The important issues to be considered in an EIA
The appropriate time and space boundaries of the EIA study
The information necessary for decision-making
The significant effects and factors to be studied in detail.
Meetings were held with the focal point in the Contracting Ministry. This is the
Director of the Public Works Department in the Ministry of in the Ministry of
Communications, Works and Labour. Meetings were also held with the
Montserrat Volcano Observatory, the Water and Wastewater Division of the
Utilities Company and the Departments of Environment and Planning in the
Ministry of Agriculture, Land, Housing and Environment. Meetings will also be
Montserrat Geothermal ESIA
Page 16
held with key Government entities. Site visits also formed part of the Scoping
exercise. The purpose is to view and characterize the proposed drill sites as well
as the drill rig transport route from the jetty, the drainage catchment in which the
drilling will take place, key infrastructure and other activities which may be taking
place within the study in order to establish the Study Boundary.
Key to the scoping exercise is to establish risks to the project because of its
proximity to the volcano. Emergency response and evacuation routes will also be
documented.
3.2.2 Environmental Stakeholder Engagement
Meetings will be facilitated between the public, stakeholders, government and the
project team. Internal meetings and interviews will also be held with stakeholders
from critical ministries including but not limited to those with responsibility for
development, planning, transport and tourism.
Other Key institutional stakeholders in the drilling operations include the selected
drilling Contractor, Public Works Department in the Ministry of Communications,
Works and Labour, the Montserrat Volcano Observatory, the Water and
Wastewater Division in the Utilities Company, the department of Environment in
the Ministry of Agriculture, land Housing and Environment and the Royal
Montserrat Police Service (RMPS). The RMPS is responsible for security of the
current unsafe zone and for supervising access to the zone
Montserrat Geothermal ESIA
Page 17
3.2.3 Environmental Stakeholder Feedback
Feedback will be actively solicited from all attendees at our scheduled meetings
and those who are interested in the project. Electronic media will be used where
appropriate to facilitate easy communication with the project team. All findings
will be compiled in a report and used as input to the final Environmental
Management Plans to manage the drilling period. Comments may be sent to
3.2.4 Environmental Baseline Data
Atom will execute all the studies necessary to explore the selected potential
impacts of the environmental factors. A number of potential impacts have been
identified for baseline data. However given the selected location, several impacts
may be insignificant. All impacts will be considered initially to ensure the
assessment is thorough and control/reference data is documented. All such data
will be collected on-site and analysed to determine significance.
3.2.5 Environmental Impacts
The consultancy will clearly identify any potential negative and positive
environmental impacts associated with drilling activities. Having identified any
potential negative impacts, the Atom team will develop specific strategies and
actions to enhance potential environmental benefits and minimise or mitigate
Montserrat Geothermal ESIA
Page 18
negative impacts. It will also include a monitoring component which will allow
government to monitor the drilling process and the execution of specific actions
in relation to minimisation, mitigation or enhancement. It will focus primarily on
drilling activities.
For any potential opportunities to create or enhance beneficial environmental
effects, strategies and plans will be developed to maximize such benefits if
possible.
It is recognized that action plans required to support the drilling operations will
also address the emergency response to possible increased volcanic activity
including an emergency evacuation plan to the shore line to a stand by marine
vessel.
3.2.6 Development of an Environmental Impact Management Plan (EIMP)
Framework
The EIMP will present a framework for the control, mitigation, monitoring and
auditing if necessary, to prevent or limit potentially adverse environmental
impacts from the drill operations. In addition to the monitoring of environmental
mitigation measures directly associated with the drilling, the monitoring and
communication of risks associated with volcanic activity is critical because the
Montserrat Geothermal ESIA
Page 19
drill site is located in a ‘controlled access’ area. An emergency prevention,
response and evacuation plan will form part of the EIMP framework.
Management System
The EMP will identify a management system where defined resources have
specific roles and responsibilities. The EIMP must be integrated into all activities
of the drilling contractor. It is the shared responsibility of the stakeholders to
ensure that all persons associated with the drilling operations are orientated and
familiar with the EMP and follow all its recommendations.
3.3 Social Impact Assessment (SIA)
Planners, decision makers and technocrats alike have increasingly recognised
the importance of the social impact assessment process as critical to better
understanding the social issues which may arise from major development and
the consequences of programmes, and policies. Consequently, a Social Impact
Assessment has now become an important part of the project preparation
process. Goldman and Baum (2000) define Social Impact Assessment (SIA) as
a method of analyzing what impact actions may have on the social aspects of the
environment.
The IOCPGSIA (2003) defines social impacts as “the consequences to human
populations of any public or private actions that alter the ways in which people
live, work, play, relate to one another, organize to meet their needs, and
Montserrat Geothermal ESIA
Page 20
generally cope as members of society”. The term also includes cultural impacts
involving changes to the norms, values, and beliefs that guide and rationalize
their cognition of themselves and their society.” Social Impacts can be positive or
negative.
There are several steps which are necessary to undertake the Social Impact
Assessment process. These are defined in the context of this specific project
which involves the drilling of two Geothermal Testing Holes.
3.3.1 SIA Scoping
Atom has compiled a list of preliminary impacts and issues to be examined in the
impact assessment. See list below:
Stakeholder perceptions
Transport
Impacts that may occur due to accidental events
Impacts on social activities during normal access times
Stress on social support systems
Impact of community traditions/culture
Potential economic disruptions
Impact on legal land rights
Health and Safety concerns for workers
Loss of access to Government/other buildings to conduct business
Change in the supply/cost of utilities
Loss of housing or community resources
Health and Safety
Montserrat Geothermal ESIA
Page 21
In order to complete the scoping exercise a number of steps were necessary.
Defining the Impact Area
The impact area is a well-defined area which is expected to be affected by the
project activities. In this specific case, the location for the drilling of test holes
has already been identified. The impact zone will therefore be the area
immediately surrounding the drilling location including the Volcano Exclusion
Zone and where access is restricted. It is an area which is already prohibited to
the general public. Discussions with the local authorities will provide further
information on the level of access to the project location and this accompanied by
some community level discussions and a physical study of the surrounding
communities will help to determine the full extent of impact area.
Available Data/Information
A thorough review of information available on similar types of projects often
offers an initial basis for the identification of potential impacts. It is therefore an
instrumental exercise and a great deal of preliminary effort will be put into this
process. This process is usually most beneficial if baseline conditions are similar
to those of the present project. Therefore, where actual impact data on similar
projects within Montserrat or the region can be identified, they would be helpful in
the assessment process.
Montserrat Geothermal ESIA
Page 22
Screening
The Screening exercise requires the examination of the potential impacts from a
neutral perspective. This helps in determining the scope of detailed SIA that
would be subsequently carried out. In this process, the potential impacts can be
scanned to determine which can be classified as having no impact. These will be
eliminated in the screening process, leaving the opportunity to focus on the
impacts which are relevant to the project
Field Surveys
This Scoping exercise will involve field work. It is critical to undertake surveying
of the local environment to validate the issues which have been borne out in the
screening exercise. This part of the process will involve the review of the social
activities of the potentially affected population, inclusive of the movement of
persons, community activity, economic activity within the community and
activities within the Volcano Exclusion Zone. The methods that will be
incorporated into this Scoping Exercise will include a review of:
Official Census
Land Title Records
Official Socioeconomic Reports
Other administrative records
Key Informant discussions with Government Ministries
Key Informant Questionnaires
Public Consultations
Montserrat Geothermal ESIA
Page 23
3.3.2 Social Stakeholder Engagement
Stakeholders are persons in the community, groups or institutions which are
likely to be affected by a proposed intervention (either negatively or positively), or
those which can affect the outcome of the intervention. After defining the impact
zone, these groups become clearer. However, not only those in the impact zone
may be affected since there are those persons who also have an interest as a
result of benefits to be derived. The various stakeholders will be identified
through a process of consultation within the community. The process of
identification will include determining:
Who are the direct beneficiaries of the project
Who are adversely affected by the project
Groups whose support would be helpful in the successful completion of the
drilling exercise
Groups whose opposition would be detrimental to the successful completion
of the drilling exercise
Vulnerable groups within the immediate community
Hence included in this group may be persons likely to find work, persons who
may traverse the immediate surroundings of the project location or those who
may have property in the immediate surrounds, along with those who may stand
to gain indirectly from an economic point of view.
Montserrat Geothermal ESIA
Page 24
3.3.3 Social Stakeholder Feedback
Feedback will be actively solicited from all attendees at our scheduled meetings.
It would also involve interaction with special interest groups and stakeholders,
government officials and relevant community organisations. A canvassing of the
potentially affected community is required to ensure that all concerned interest
groups are given a voice. Social issues can often be qualitative in nature,
involving feelings, norms and patterns of a community. Therefore, examination,
observation and open discussion all form part of this process. Electronic media
will be used where appropriate to facilitate easy communication with the project
team. All findings will be compiled in a report and used as input to the final Social
Management Plans to manage the drilling period. Comments may be sent to
3.3.4 Socioeconomic Baseline Data
A socio-economic review is required in order to determine the level of economic
activity within the affected community. Economic indicators from local economic
and social reports will be utilized to develop a profile of the state of the
Montserrat economy. There is no community within the Exclusion Zone, but if
the surrounding area has residential and economic activity as determined by the
Screening Process, the socio-economic profile of this area will be studied. In
addition, the drilling activities are likely to have some impact on the employment
situation within the country in the short-term. However temporary, the impact of
Montserrat Geothermal ESIA
Page 25
this activity must still be examined and measured and incorporated into the
Management Plan.
3.3.5 Social Impacts
The identification and assessment of the impacts can be conducted once all of
the preceding information is gathered and a solid picture of the project, issues
and potential impacts have been identified. A probability assessment on the
extent and consequences of those impacts on social values will be undertaken.
Based upon the severity of the impact (from high to low) the impact may be
deemed unacceptable or appropriate mitigation measures may be recommended
to reduce the extent of the impact or to soften the impact.
Because of the qualitative nature of some social impacts, a comparative ranking
methodology may not always be possible. It is therefore very important to
consult the affected groups in determining which impacts likely affect them more
severely since the SIA specialist must be most concerned with provision of relief
to the community. Impacts which are classified as positive also need to be
managed in order to ensure that maximum benefit results from them. The
importance of the Management Plan cannot be overstated since that is the tool
for controlling the stated impacts.
Montserrat Geothermal ESIA
Page 26
3.3.6 Development of a Social Impact Management Plan (SIMP)
Once the severity of the impacts is identified, the development of a Social Impact
Management Plan (SIMP) or a mitigation plan will be undertaken. This Plan will
identify all of the impacts which need to be managed, the corresponding levels
and the recommendation for mitigation. It would also include a monitoring facility
and indicators to measure both the impact and the success of the recommended
mitigation measures. Impacts are however dynamic in nature, consequently the
Plan will be a living document and allow for continuous changes where
necessary.
3.4 Review Institutional Capacity and Feedback
Draft documents will be reviewed by selected stakeholders, DfID and other key
persons. It will also be necessary to review the institutional capacity to ensure
resources and the required skill sets exist to implement and monitor the two
management plans.
Montserrat Geothermal ESIA
Page 27
References
Goldman, Laurence and Scott Baum 2000 “Introduction” in Laurence R Goldman (ed)
2000 Social Impact Analysis: An Applied Anthropology Manual Oxford/New York: Berg
IOCPG (Interorganizational Committee on Principles and Guidelines for Social Impact
Assessment) 2003 “Principles and Guidelines for Social Impact Assessment in the
USA” Impact Assessment and Project Appraisal, volume 21, number 3, September
2003 (pg 231)
Government of Montserrat 2010 “Final Report Geothermal Exploration in Montserrat,
Caribbean” GOM
Government of Montserrat 2012 “Terms of Reference for Montserrat Geothermal Test
Drilling”, GOM
Government of Montserrat 2002 “PHYSICAL PLANNING ACT and Subsidiary
Legislation, Revised Edition” , GOM