    ENSCO 84 STRUCTURAL WORK COMPLETION STATUS

    JOB DESCRIPTION BALANCE ACTIVITIES PERCENTAGE

    COMPLETION

    SCHEDULED

    COMPLETION

    REMARKS

    NEW 4TH

    MAIN ENGINE

    INSTALLATION

    4th EMD installation Air duct extension Walk way platform

    1. Installation of new air duct extension for the 4 thEMD

    New air duct installed but

    fouling with the 4th

    EMD

    exhaust bellow.

    2. Installation of new walkway platform for the 4thMD

    3. Removal of temporary supports provided IWOthe deck access opening for lowering the EMD

    4. Provide 06 nos. collar plates on main decktransverse frame # 14, 15,& 16 IWO deck access

    cutout.

    5. Painting of the coaming plate around 4th EMD andburn marks inside the tank.

    6. Final inspections by clientINSTALLATION OF NEWEMERGENCY GENERATOR

    Removal of existingemergency generator

    and installation of new

    caterpillar generator.

    Structural modificationto the EGEN room for

    installation of new

    control panel.

    Relocation of fuel tank.

    7. Functional test of fire and gas dampers8. Painting of burn marks inside the accommodationspaced below the Egen room

    9. Insulation and panel works completion inaccommodation spaces below EGEN room

    10.Paint touch ups IWO pipe and electricalpenetrations

    11. Installation of battery box12. Installation and commissioning of the CO2 system

    for emergency generator room.

    13.Installation of pipe supports for fuel and air lines

    HILLMAN ROLLER

    INSTALLATION

    Structural modificationIWO skid rails

    Installation of Hillmanroller assembly

    14.2 nos. drain relocation and 01 no. drain linepenetration inside tank no. 27 (cut due to

    structural modification for Hillman roller)

    15.Pain touch up in tank no 27 and applying ofeureka gel inside tank 28 and 29 ( removed for

    hot work)

    16.Painting of main deck and Hillman roller structure

  • 7/28/2019 Balance Activity - Copy

    2/5

    above main deck

    17.Final inspection and tank closingINSTALLATION OF

    REVERSE OSMOSIS UNIT

    Installation of the uniton foundation

    Installation of chemicalinjection skid

    18.Welding of the RO unit skid to the foundation19. Installation of the chemical injection unit skid

    foundation and installation of the same.

    20.Closing of the access opening above the RO unit.21.Final structural inspection by client.22.Paint touchups IWO paint damaged areas.

    RELOCATION OF 07 A/C

    CONDENSER UNIT

    Platform extensionIWO FWD jack house

    top.

    Relocating the ACcondensers

    Relocating theemergency breathing

    stations.

    23. Relocating the emergency breathing stations andtubing termination.

    24. Removal of old A/C tubing penetration & MCTand installation of inserts on the deck in the same

    locations.

    25. Heavy duty hand rail fabrication and installation26. Paint touchups inside the accommodation spaces

    IWO platform support and MCT penetrations.27. Insulation and panel work completion inside

    accommodation spaces removed for hot work.

    28.Final inspection by client.NEW PLATFORM FOR 4

    TH

    EMD RADIATOR AND

    CONTAINER PLATFORM

    ABOVE THE RADIATORS.

    Platform extensionsfor the new radiator

    Container platforminstallation above

    radiators with access

    way and handrails

    29.Radiator platform, container platform and hullpaint touchups IWO new structure and paint

    damaged areas.

    30.Container platform access stair ways installation31.Removable and fixed handrails installation for the

    container platform

    32.Plating of the container platform above the firsttwo radiators

    33. Installations of container hold down locks.34.Final inspection by client

    ACCESS FOR CRANE CABS

    PORT AND STBD

    Installation of newplatform

    35. Installation of grating for the new platforms36. Installation of new access stair ways37.Cropping of old platform fouling IWO new access

    route and modification of the access ladder to the

  • 7/28/2019 Balance Activity - Copy

    3/5

    New stair waysand hand rails

    sheave assembly.

    38.Cropping off the old access stair for the cranecabs.

    39.Access extension connecting the Jack houseplatform stbd side ony.

    40.Required NDT and client inspection41.

    Pain touchups of the new structure and paintdamaged areas

    SHALE SHAKER HOUSE

    ROOF TOP MODIFICATION

    Platform extension Modification of access

    stair ways

    Necessary hand railsprovision.

    42.Plating of the extended platform43.Reposition and extending the existing heavy duty

    hand rails to the far end of the platform

    44.Relocating 01 no. light post fouling IWO stair way.45.Necessary NDT and client inspection46.Painting of the structural modification areas and

    the paint damaged areasINSTALLATION OF KING

    POST AND BURNER BOOM

    PORT AND STBD

    Installation of ownersupplied prefabricated

    items of the king post

    foundation.

    Installation of the kingpost base and support

    eye pads

    47.Completion of fitup and welding of under deckstiffening for port and stbd king post foundation

    Class inspection completed

    48.Welding completion of king post foundation49. Installation of king post base and holding eye

    pads

    Canceled

    50.Modification of the heavy duty hand rails cut forinstallation of the foundation

    51. Installation of the fire line cut IWO king postfoundation

    52.Necessary NDT and client/class inspection53.Painting of the structure and paint damaged

    areas

    PROVISION FOR AIR

    STARTING OF THE

    EMERGENCY GENERATOR

    Fabrication andinstallation of air

    54.Fabrication and installation of air receiverfoundation and under deck stiffening

    55.Fabrication and installation of booster pumpfoundation

    56.Fabrication completion and testing of Air receiver57. Installation of air receiver and booster pump

  • 7/28/2019 Balance Activity - Copy

    4/5

    receiver 660 gals

    Installation of boosterpump

    58.Required NDT and client inspection59.Paint job completion on the foundations and

    paint damaged areas

    RELOCATION OF 04 NOS.

    TOWING SMIT BKTS

    Strengthening of deckstructure @ new

    location of towing

    arrangement

    Relocation of smit bkts Load test

    60.Structural modification IWO aft smit bkts Class inspection completed61.Fit up and welding of aft towing bkts62.

    Required NDT and client/class inspection Canceled - NDT reports andstrength calculations to be

    submitted63.Load test of all smit bkts witnessed by class and

    client

    64.Painting of structure above deck and reapplyingof eureka gel inside the tanks under the smit bkts.

    MODIFICATION OF

    ACCOMMODATION

    EXTERNAL STAIRS AND

    PLATFORM PORT ANDSTBD

    Cropping the existingplatform

    Installation of newplatform and stair

    ways

    Extension of old stairways

    65.Cropping of the existing platform and stair ways66.Fabrication of new platform and stair ways67. Installation of new platform, stair way and

    supports port side

    68. Installation of new platform, stair way andsupports stbd side

    69. Installation of lights port and stbd70.Necessary NDT and client inspection.71.Final painting of new structure and damaged

    areas.

    72.Reinsulating the insulating and paneling ofaccommodation spaces IWO hot work.

    RELOCATION OF AIRCOMPRESSOR ON THE

    EXTENDED JACK HOUSE

    PLATFORM

    Platform extension Relocation of air

    compressors

    73.Relocating the the air compressor an the newextended platform and welding the skid to the

    deck

    74.New hand rail installation75.Necessary NDT and client Inspection76.Paint touchups of the damaged areas.

  • 7/28/2019 Balance Activity - Copy

    5/5

    BULK AIR DRYER ON WELD

    ROOF

    Installation of thefoundation for the

    dryer

    Installation of the bulkair dryer unit

    77. Installation and welding of the bulk air dryer unitfoundation and under deck stiffening.

    78. Installation of the unit and welding.79.NDT of the foundation and under deck stiffening

    to be done.

    80. Inspection of the structure.81.Painting of the new structure and damaged

    surfaces.

    NEW HELIDECK

    EMERGENCY ACCESS

    PLATFORM PORT/STBD

    Fabrication andinstallation of new

    access platform

    extensions

    Installation of newstair ways

    Installation of newhand rails

    NDT

    82.Fabrication and installation of the new accessplatform extension

    83.Fabrication and installation of the new stair ways84.Fabrication and installation of new handrails85.Structural inspections86.NDT of the new structure87.Painting of the new structure and damaged

    surfaces

    88.89.90.91.92.93.