balance activity - copy
TRANSCRIPT
-
7/28/2019 Balance Activity - Copy
1/5
ENSCO 84 STRUCTURAL WORK COMPLETION STATUS
JOB DESCRIPTION BALANCE ACTIVITIES PERCENTAGE
COMPLETION
SCHEDULED
COMPLETION
REMARKS
NEW 4TH
MAIN ENGINE
INSTALLATION
4th EMD installation Air duct extension Walk way platform
1. Installation of new air duct extension for the 4 thEMD
New air duct installed but
fouling with the 4th
EMD
exhaust bellow.
2. Installation of new walkway platform for the 4thMD
3. Removal of temporary supports provided IWOthe deck access opening for lowering the EMD
4. Provide 06 nos. collar plates on main decktransverse frame # 14, 15,& 16 IWO deck access
cutout.
5. Painting of the coaming plate around 4th EMD andburn marks inside the tank.
6. Final inspections by clientINSTALLATION OF NEWEMERGENCY GENERATOR
Removal of existingemergency generator
and installation of new
caterpillar generator.
Structural modificationto the EGEN room for
installation of new
control panel.
Relocation of fuel tank.
7. Functional test of fire and gas dampers8. Painting of burn marks inside the accommodationspaced below the Egen room
9. Insulation and panel works completion inaccommodation spaces below EGEN room
10.Paint touch ups IWO pipe and electricalpenetrations
11. Installation of battery box12. Installation and commissioning of the CO2 system
for emergency generator room.
13.Installation of pipe supports for fuel and air lines
HILLMAN ROLLER
INSTALLATION
Structural modificationIWO skid rails
Installation of Hillmanroller assembly
14.2 nos. drain relocation and 01 no. drain linepenetration inside tank no. 27 (cut due to
structural modification for Hillman roller)
15.Pain touch up in tank no 27 and applying ofeureka gel inside tank 28 and 29 ( removed for
hot work)
16.Painting of main deck and Hillman roller structure
-
7/28/2019 Balance Activity - Copy
2/5
above main deck
17.Final inspection and tank closingINSTALLATION OF
REVERSE OSMOSIS UNIT
Installation of the uniton foundation
Installation of chemicalinjection skid
18.Welding of the RO unit skid to the foundation19. Installation of the chemical injection unit skid
foundation and installation of the same.
20.Closing of the access opening above the RO unit.21.Final structural inspection by client.22.Paint touchups IWO paint damaged areas.
RELOCATION OF 07 A/C
CONDENSER UNIT
Platform extensionIWO FWD jack house
top.
Relocating the ACcondensers
Relocating theemergency breathing
stations.
23. Relocating the emergency breathing stations andtubing termination.
24. Removal of old A/C tubing penetration & MCTand installation of inserts on the deck in the same
locations.
25. Heavy duty hand rail fabrication and installation26. Paint touchups inside the accommodation spaces
IWO platform support and MCT penetrations.27. Insulation and panel work completion inside
accommodation spaces removed for hot work.
28.Final inspection by client.NEW PLATFORM FOR 4
TH
EMD RADIATOR AND
CONTAINER PLATFORM
ABOVE THE RADIATORS.
Platform extensionsfor the new radiator
Container platforminstallation above
radiators with access
way and handrails
29.Radiator platform, container platform and hullpaint touchups IWO new structure and paint
damaged areas.
30.Container platform access stair ways installation31.Removable and fixed handrails installation for the
container platform
32.Plating of the container platform above the firsttwo radiators
33. Installations of container hold down locks.34.Final inspection by client
ACCESS FOR CRANE CABS
PORT AND STBD
Installation of newplatform
35. Installation of grating for the new platforms36. Installation of new access stair ways37.Cropping of old platform fouling IWO new access
route and modification of the access ladder to the
-
7/28/2019 Balance Activity - Copy
3/5
New stair waysand hand rails
sheave assembly.
38.Cropping off the old access stair for the cranecabs.
39.Access extension connecting the Jack houseplatform stbd side ony.
40.Required NDT and client inspection41.
Pain touchups of the new structure and paintdamaged areas
SHALE SHAKER HOUSE
ROOF TOP MODIFICATION
Platform extension Modification of access
stair ways
Necessary hand railsprovision.
42.Plating of the extended platform43.Reposition and extending the existing heavy duty
hand rails to the far end of the platform
44.Relocating 01 no. light post fouling IWO stair way.45.Necessary NDT and client inspection46.Painting of the structural modification areas and
the paint damaged areasINSTALLATION OF KING
POST AND BURNER BOOM
PORT AND STBD
Installation of ownersupplied prefabricated
items of the king post
foundation.
Installation of the kingpost base and support
eye pads
47.Completion of fitup and welding of under deckstiffening for port and stbd king post foundation
Class inspection completed
48.Welding completion of king post foundation49. Installation of king post base and holding eye
pads
Canceled
50.Modification of the heavy duty hand rails cut forinstallation of the foundation
51. Installation of the fire line cut IWO king postfoundation
52.Necessary NDT and client/class inspection53.Painting of the structure and paint damaged
areas
PROVISION FOR AIR
STARTING OF THE
EMERGENCY GENERATOR
Fabrication andinstallation of air
54.Fabrication and installation of air receiverfoundation and under deck stiffening
55.Fabrication and installation of booster pumpfoundation
56.Fabrication completion and testing of Air receiver57. Installation of air receiver and booster pump
-
7/28/2019 Balance Activity - Copy
4/5
receiver 660 gals
Installation of boosterpump
58.Required NDT and client inspection59.Paint job completion on the foundations and
paint damaged areas
RELOCATION OF 04 NOS.
TOWING SMIT BKTS
Strengthening of deckstructure @ new
location of towing
arrangement
Relocation of smit bkts Load test
60.Structural modification IWO aft smit bkts Class inspection completed61.Fit up and welding of aft towing bkts62.
Required NDT and client/class inspection Canceled - NDT reports andstrength calculations to be
submitted63.Load test of all smit bkts witnessed by class and
client
64.Painting of structure above deck and reapplyingof eureka gel inside the tanks under the smit bkts.
MODIFICATION OF
ACCOMMODATION
EXTERNAL STAIRS AND
PLATFORM PORT ANDSTBD
Cropping the existingplatform
Installation of newplatform and stair
ways
Extension of old stairways
65.Cropping of the existing platform and stair ways66.Fabrication of new platform and stair ways67. Installation of new platform, stair way and
supports port side
68. Installation of new platform, stair way andsupports stbd side
69. Installation of lights port and stbd70.Necessary NDT and client inspection.71.Final painting of new structure and damaged
areas.
72.Reinsulating the insulating and paneling ofaccommodation spaces IWO hot work.
RELOCATION OF AIRCOMPRESSOR ON THE
EXTENDED JACK HOUSE
PLATFORM
Platform extension Relocation of air
compressors
73.Relocating the the air compressor an the newextended platform and welding the skid to the
deck
74.New hand rail installation75.Necessary NDT and client Inspection76.Paint touchups of the damaged areas.
-
7/28/2019 Balance Activity - Copy
5/5
BULK AIR DRYER ON WELD
ROOF
Installation of thefoundation for the
dryer
Installation of the bulkair dryer unit
77. Installation and welding of the bulk air dryer unitfoundation and under deck stiffening.
78. Installation of the unit and welding.79.NDT of the foundation and under deck stiffening
to be done.
80. Inspection of the structure.81.Painting of the new structure and damaged
surfaces.
NEW HELIDECK
EMERGENCY ACCESS
PLATFORM PORT/STBD
Fabrication andinstallation of new
access platform
extensions
Installation of newstair ways
Installation of newhand rails
NDT
82.Fabrication and installation of the new accessplatform extension
83.Fabrication and installation of the new stair ways84.Fabrication and installation of new handrails85.Structural inspections86.NDT of the new structure87.Painting of the new structure and damaged
surfaces
88.89.90.91.92.93.