bar chart
TRANSCRIPT
![Page 1: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/1.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
1
What is Activity• An activity or task is a given kind and
amount of work which:– Consumes time– Consumes Resources– has a definable beginning and ending
Fixing False Sealing
3 men x 30 days Start time 3000 board type End time
![Page 2: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/2.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
2
What is Project
• A project is a set of activities with– A well-defined objective(s)– A target completion date– An estimated budget
Plans &
Specifications
Limited Resources
Project Management
Required Product
Project Objectives Given Desired
![Page 3: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/3.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
3
Type of Schedule
• Written Schedule• Gantt Chart (Bar Chart)• CPM Schedules (Critical Path Method)
– Activity on Arrow– Activity on Node AB
• PERT
• LSM (Linear Schedule Method)
A B
A 5
X =36 40 30
![Page 4: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/4.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
4
Bar Chart • STEPS
– Analyze the project and specify the basic approach to be used.
– Break the project down into a reasonable number of activities to be scheduled.
– Estimate the time required to perform each activity.– Place the activities in sequence of time, taking into
account the requirements that certain activities must be performed sequentially.
• Logical constrain• Resources constrain
– If a completion date is specified, the diagram is adjusted until this constraint is satisfied.
![Page 5: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/5.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
5
Bar Chart• Example:
Activity ID
Activity Description Dependency Duration
A Excavation 3
C Foundation A 3
D Column B, C 2
B Moving the soil out A 2
E Wall C, D 5
F Roof E, D 5
![Page 6: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/6.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
6
Solution
A
C
D
B
E
F 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
![Page 7: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/7.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
7
Alternative Solution
A
B
C
D
E
F 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
![Page 8: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/8.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
8
Bar Chart• Advantages of Bar Chart
– Very Graphical– Easy to understand– Most widely used
• Disadvantages of Bar Chart– Difficult to Update– Difficult to find the Critical Path– Difficult to setup and maintain a large project because
it is essentially a manual graphical procedure.
![Page 9: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/9.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
9
How to identify the Critical path in a Bar Chart
• Types of a Project Activity– Critical Activity: if it is delayed, it will delay the
project.– Noncritical Activity: it may not delay the
project if it’s well managed.
![Page 10: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/10.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
10
STEPS to identify the Critical Path
• Start with the last Activity; Draw a vertical line from the i Node of late Activity.
• The activities whose j nodes touch the vertical line, are Potential Critical Activity.
• Draw a vertical line from the i node of the new critical activity.
• Proceed in this manner until you reach Day 0.
i j
![Page 11: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/11.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
11
A
B
C
D
E
F 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Identify the Critical Path
![Page 12: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/12.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
12
Class WorkActivity Depends upon Duration (Weeks)
A C, J 3 B F 2 C F 3 D C, I 4 E G 5 F H 4 G H 2 H - 3 I E, F 4 J B 2
![Page 13: Bar chart](https://reader038.vdocument.in/reader038/viewer/2022102320/5451c23eaf795911068b7b52/html5/thumbnails/13.jpg)
Spring 2008, King Saud University
Bar ChartDr. Khalid Al-Gahtani
13
CW SolutionAct. W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18
H F G E I B C J A D