bar council conference, distillery building · bar council conference, distillery building paper by...

88
CONSTRUCTION LAW BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS AND ARBITRATIONS 1. INTRODUCTION The purpose of this paper is to give an overview of the role that barristers play in mediations and arbitrations of construction disputes, the sort of problems they frequently encounter, the duties that they may have in acting as counsel, and some of the tactical matters which they may have to consider. The idea for this paper sprung from a perception held by many people in our profession and frequently voiced to me that construction law is byzantine in its complexity and yields up its mysteries only gradually and begrudgingly. Barristers unfamiliar with the area are often concerned that, through ignorance or inexperience, they may sell their clients sort. It is to colleagues either wholly or relatively unfamiliar with construction law disputes that this paper is primarily addressed in an attempt to give them some feel for the “landscape” of such disputes. Hopefully at the end of it they will have at least a sense of how such disputes are dealt with. I would also hope that those of you who have greater familiarity may hear something new or at least something to stimulate debate. 2. THE PROBLEM By way of illustration, I set out below a fictional but not untypical scenario which might well land on a barrister’s desk:

Upload: others

Post on 26-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

CONSTRUCTION LAW

BAR COUNCIL CONFERENCE, DISTILLERY BUILDING

Paper by Mark Sanfey SC Saturday 7th February 2009

BARRISTERS IN CONSTRUCTION MEDIATIONS AND ARBITRATIONS

1. INTRODUCTION

The purpose of this paper is to give an overview of the role that barristers play in

mediations and arbitrations of construction disputes, the sort of problems they

frequently encounter, the duties that they may have in acting as counsel, and some of

the tactical matters which they may have to consider.

The idea for this paper sprung from a perception held by many people in our

profession and frequently voiced to me that construction law is byzantine in its

complexity and yields up its mysteries only gradually and begrudgingly. Barristers

unfamiliar with the area are often concerned that, through ignorance or inexperience,

they may sell their clients sort.

It is to colleagues either wholly or relatively unfamiliar with construction law disputes

that this paper is primarily addressed in an attempt to give them some feel for the

“landscape” of such disputes. Hopefully at the end of it they will have at least a sense

of how such disputes are dealt with. I would also hope that those of you who have

greater familiarity may hear something new or at least something to stimulate debate.

2. THE PROBLEM

By way of illustration, I set out below a fictional but not untypical scenario which might

well land on a barrister’s desk:

Page 2: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

2

• Counsel is instructed by a solicitor to advise a client, a building

contractor, who is owed €600,000 in respect of the final account on a

project which involved building a mixed commercial and residential

development;

• No written contract was executed by the parties. The project leader is

an architect, who acts on behalf of the employer. The tender

documentation which was issued by the architect made no reference to

the form of contract which would govern the project. However, a letter

accepting the contractor’s tender stated that the form of the contract

was to be the “blue form” RIAI contract (2002 edition). The contractor

did not reply to this letter, nor dispute or demur from the letter in any

way. During the course of the project, the parties generally observed

the procedures laid down by the RIAI contract.

• Practical completion has been certified by the architect. Practical

completion occurs when …”the works have been carried to such a stage

that they can be taken over and used by the employer for their intended

purpose and that any items of work or supply then outstanding or any

defects then patent or of a trivial nature only and are such that they are

completion or rectification does not interrupts such use…” [Clause 31

RIAI contract]. However, half of the retention fund has not been

released by the architect under clause 35(f)(2)(ii) because the architect

claims that the retention bond furnished by the contractor pursuant to

clause 35(f)(1), the furnishing of which by the contractor is a

prerequisite to the release of the retention monies, is not acceptable to

him;

• An interim certificate issued a month prior to the certificate of practical

completion in the sum €50,000 has not been discharged;

• The contractor achieved completion of the works several months after

the “date for completion” in the appendix to the contract; he says this is

because he was repeatedly asked to carry out variations to the contract

works by the architect. However, the contractor has not confirmed

those variations in writing to the architect as required to do by clause

13.01 of the RIAI contract. Neither has he applied to the architect

under clause 30 for an extension of time in respect of the variations,

Page 3: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

3

with the result that the architect now seeks to impose liquidated and

ascertained damages;

• The defects liability period triggered by the certificate of practical

completion is almost at an end. The architect has given notice to the

contractor and the employer of his intention to issue the final certificate

and has notified the parties that the adjustments to the final account

which he proposes to make will result in a negative balance, i.e.

according to the architect, the contractor owes the employer money,

not the other way around.

3. WHAT DOES YOUR SOLICITOR EXPECT?

The service you will be expected to give will depend on whether your solicitor is a

specialist in the area or a more general practitioner who may have either reasonable

familiarity – or perhaps no familiarity at all – with construction disputes.

A specialist is less likely to require assistance from counsel, and may merely require an

opinion or advocacy in a particular court application relating to the dispute. You are

far less likely to get from such a solicitor an instruction to “please advise generally”.

What would be more typical is that you would be contacted by a more general

practitioner who, I would suggest, would expect two things of you:

1. That you have sufficient legal knowledge and ability to be able to

identify what the legal issues are, and advise on them effectively and

promptly;

2. That you will be able to map out a strategy for the conduct of the

dispute resolution, whatever form it may take, that will advance your

clients interests and keep him “on the front foot”.

4. THE NEED TO BE PROACTIVE

Most barristers are reactive. They get sent a brief and instructions from a solicitor,

and generally tend only to do what they are asked. A barrister may draft proceedings

at the start; the various stages of pleadings and discovery come and go. Very often,

Page 4: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

4

the first detailed look at the strategy of the case by a barrister is when he or she is

asked to advise on proofs.

This is not an approach that can work in construction disputes. There is usually a

large amount of work to be done by solicitor and counsel as soon as they receive

instructions in gathering in evidence, reports, documentation and further instructions

where necessary in order to be able to understand the nature of the dispute and

analyse it. Counsel should be proactive in ensuring that the solicitor understands

exactly what has to be done in terms of gathering information and materials, and

organising consultations between counsel, the client and any other witnesses or

experts in order to ensure that the nature of the problem is fully understood, and that

counsel is in a position to give an analysis of the legal problems and to map out a

strategy.

Counsel should advise the solicitor that the work and costs in relation to the dispute

will be to some degree “front-loaded”, and that this should be explained to the client

so that he can understand the degree of work required, the level of commitment of

counsel and solicitor to the case, and the resultant cost involved.

5. LEGAL ANALYSIS

At the earliest opportunity, counsel needs to assess the strengths and weaknesses of

the client’s position in the dispute. In the case of our problem, the sort of issues that

arise and must be considered are as follows:-

(i) What is the contract?

• Do the dealings between the parties suggest that the conditions of

the RIAI agreement mentioned in the architect’s letter have been

incorporated in the contract at all?

• There is much case law to do with the so-called “battle of the

forms”. Two key Irish cases which dealt with motions to stay court

proceedings under section 5 of the Arbitration Act, 1980, and

whether or not the arbitration clauses should be deemed to govern

the dispute in circumstances where there was no signed contract

are:

Page 5: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

5

a. Lynch Roofing Systems Limited v Bennett & Sons

Limited [1999] 2IR 450 (Morris P), where the key

question was whether the parties habitually traded under

contracts which incorporated arbitration clause so that a

court would be forced to conclude that the parties expected

and knew that this clause would govern their contract;

b. McCrory Scaffolding Limited v McInerney

Construction Limited [2004] 3IR 592 (Peart J)

…”The important consideration is not whether the two

parties had between themselves previous dealings, but

rather whether the plaintiff was somebody who had previous

general experience of trading under contracts which included

an arbitration clause”.

• In our problem, was the letter accepting the tender

imposing a contractual term not already agreed between

the parties?, i.e. is it a counter-offer rather than an

acceptance of the tender?

• If it is a counter-offer, was it accepted by the contractor,

by conduct if not expressly?

(ii) What should be done about the undischarged certificate?

• The question that arises here is whether summary proceedings

should be issued to recover the amount of the certificate;

• The traditional view for decades has been that, while it may be

necessary to arbitrate a “dispute or difference”, monies certified by

the employer’s agent – the architect – must be regarded as being

beyond dispute, and the courts have tended to refuse to allow set-

off against an interim certificate. Three Irish decisions set out the

position in this regard:

• John Sisk and Sons Limited v Lawter Products BV,

unreported, High Court, Finlay P, 15th November 1976. In

this case Finlay P (as he then was) took the view that the

Page 6: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

6

employer was not entitled to deduct anything from the

certificate.

• However, in PJ Hegarty & Sons Limited v Royal Liver

Friendly Society [1985] IR 524, Murphy J, held that an

employer was entitled to deduct monies from an interim

certificate and that “an amount included in a certificate

(whether interim or final) does not constitute a debt of a

particular character and enjoys no special immunity from any

cross-claim or right of set-off to which the debtor may be

entitled”.

• Costello J however declined to follow the Hegarty decision in

Rowan Construction Limited v Antigen Limited [1989]

ILRM 783, holding that a right of set-off was inconsistent

with the terms of the RIAI contract.

• While the Rowan v Antigen decision has tended to be the

decision observed in practice in the courts, two recent

decisions of the High Court may signal a change in this

regard. In Powderly v McDonagh [2006] IEHC 20, Kelly

J considered whether summary judgment could be granted

on foot of an architect’s certificate in circumstances where

the Defendant sought to counterclaim damages for

negligence. There was no written agreement between the

parties, although the Defendants believed that the works to

be undertaken by the Plaintiff would be governed by the

RIAI contract (1996) edition for use when quantities did not

form part of the contract.

• Kelly J stated that …”perhaps the best analysis of the

position is contained in the judgment of Murphy J in [PJ

Hegarty]…”, and also endorsed the test adumbrated by

Finlay P in John Sisk & Son Limited, where he said:

“I believe the true test to be not whether the common

law right of set-off has, by the terms of the building

contract been unequivocally excluded, but rather as to

whether all the relevant terms of the building contract

Page 7: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

7

are in any particular event inconsistent with the exercise

in that event of such a right of set-off;

• In the event, Kelly J stated that he was “not persuaded” that

the contractual arrangements excluded a defence of set-off

which the Defendants might have, and that the Defendants

had demonstrated a tryable issue in respect of them. He

therefore declined to grant summary judgment in respect of

the architect’s certificate.

• In Moohan v S & R Motors (Donegal) Limited, [2007]

IEHC 435 the parties entered into a written agreement –

the RIAI 2002 edition – and Clarke J had to consider whether

the Defendant was entitled to raise a set-off in equity as

against architects certificates under the RIAI contract.

Clarke J analysed the cases set out above, and agreed with

the opinion of Kelly J that the analysis by Murphy J in

Hegarty was “perhaps the best analysis of the position”.

• Clarke J went on to hold that

…”the overall test is as to whether, as a matter of

construction of the contract taken as a whole, it can

properly be said that the parties have agreed that there

can be no set-off…the default position is that a party is

entitled to a set-off in equity in relation to any cross-

claim arising out of the same contract. Thus if a builder

is owed money on foot of a construction contract, the

employer is prima facie entitled to a set-off in equity, in

principle, in respect of any defective works. The question

which arises is as to whether that prime facie has been

displaced by the terms of the contract. There is no doubt

but that the parties are free to agree that there will be no

set-off. The question is whether they have in fact done

so. I am not satisfied that the balance of the authorities

favours the view that the current standard form RIAI

template does give rise to an agreement to exclude a

set-off, at least, and this is the only issue relevant in this

Page 8: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

8

case, in circumstances where the contract is completed

to the stage of a certificate of practical completion having

been issued by the architect and where, therefore, any

entitlement to arbitration on the part of the employer is

immediate. It is, of course, the case that Finlay P, in

John Sisk had significant regard to the fact that, in the

case then under consideration, there was no immediate

right to arbitration as the contract was ongoing”.

• It appears from these decision therefore that, at least in relation

to the RIAI contract which governs our problem, a court is now

more likely than before to accede to a plea by a Defendant in

response to summary proceedings that it is entitled to raise an

equitable set-off and would be entitled to establish, according to

the test laid down by the Supreme Court in Aer Rianta CPT v

Ryanair Limited [2002] 1 ILRM 381, that there is a fair and

reasonable probability that the Defendant has a real and bona

fide Defence.

(iii) Failure to release retention:

Under clause 35(f)(1), the architect is not entitled to unreasonably

withhold approval of the retention bond. Counsel would have to

consider whether there was an objective basis for the architect

withholding his approval. If not, this issue must form part of the

contractor’s claim.

(iv) Other issues:

What is the legal effect of:

• The failure of the contractor to confirm a variation in writing

within five working days of the instruction being given as

required by clause 13 of the contract?

o Courts/arbitrators will usually accept that variations have

been carried out by the contractor because he was

instructed by the architect to do so. However, where

Page 9: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

9

there is a serious dispute about the scope or method of a

variation, a lack of confirmation in writing may seriously

undermine the contractor’s claim.

• Failure of the contractor to give notice of the “event causing

delay” in writing to the architect as required by clause 30:

• Failure in this regard may be fatal to a claim by the

contractor for an extension of time. If the event causing

delay is not promptly notified by the contractor, an

architect can say that he is not able to judge what is a

fair and reasonable extension before the delay becomes

swallowed up in the general programme and other

factors contribute to delay on the project. However, if

the “event causing delay” is an instruction by the

architect himself, the failure on the part of the contractor

to give notice is less likely to be fatal to a claim for

extension of time.

• Failure by the architect to “certify in writing, on simultaneous

notice to the employer and the contractor, that in his opinion the

[works] ought reasonably … to have been completed [by the

date for completion in the appendix or any extended date for

completion]”. [clause 29(a)].

• Certification by the architect may well be an essential

prerequisite to a claim for liquidated and ascertained

damages. A contractor who receives such a notice may

take acceleration matters to limit the extent of the delay

beyond completion date, and may claim to be prejudiced

if he does not receive such a notice.

• Note that “liquidated and ascertained damages” must be

a genuine pre-estimate of loss, and not a “penalty

clause”; See Dunlop Pneumatic Tyre Company

Limited v New Garage and Motor Company

Limited [1915] AC 79.

6. OTHER MATTERS TO ADVISE

Page 10: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

10

Having made an assessment of the legal position, the claim for payment must be

subjected to scrutiny in the light of what is known about the employer’s opposition to

it.

The sort of questions that should be asked are:

• “What do we say they owe us”?

• “What did they say in response”?

• “Are we confident that, even on a pessimistic view of our final account, the net

position is that we are owed money”?

• “Are there technical questions at issue between the parties on which we need a

view before we can assess the strength of our case”? (e.g., a question of

whether foundations are of sufficient load bearing strength or may require

underpinning).

• If so, do we need to engage experts to help us form a view on this;

• Do our records corroborate the claims we are making? Are there other

witnesses who will corroborate our position, e.g. subcontractors, suppliers etc.

The solicitor should be asked to obtain all contractual documentation (a written

contract if there is one, quotations, tenders, specification, drawings, correspondence

between the parties) and all site records (diaries, site meeting minutes, records of

instructions, correspondence etc.).

If the contractor instructs solicitor and counsel to take legal action, the options are:

• Court proceedings

o May be stayed to allow the matter to be arbitrated under section 5 of

the Arbitration Acct, 1980 or the inherent jurisdiction of the Court;

� Conciliation/mediation

� Mandatory in many arbitration contracts, including all RIAI contracts

and GDLA 82

� Arbitration

7. CONCILIATION/MEDIATION

Page 11: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

11

The RIAI contract in our problem contains a mandatory conciliation clause, and it is

only if settlement cannot be reached under the RIAI conciliation procedures that a

party can refer the matter to arbitration.

In essence, the conciliation procedures provide that an agreed conciliator - or in the

absence of agreement, a conciliator imposed by the President of the RIAI – requires

the parties to submit a brief written opening statement appending necessary

documentation not later than ten working days after his appointment. Within 10

working days after receipt of that documentation, the conciliator organises a hearing.

The conciliator …”may consider and discuss such solutions to the dispute as he thinks

appropriate or as may be suggested by either party. All information given to the

conciliator is confidential and shall remain so unless authorised by the party who

supplied the information… A conciliator may, having informed the parties, consult

independent third party experts.”

The conciliator “shall endeavour to commit the parties to reach a mutual settlement

failing which he shall within ten working days of the hearing, issue his

recommendation. He shall not be required to give reasons. It shall remain confidential

if rejected by either party”.

If neither party rejects the recommendation within ten working days after its issue it is

final and binding on the parties. If the recommendation is rejected, either party may

at that stage refer the matter to arbitration. Each party to the conciliation pays his

own costs, and the parties are jointly and severally liable for the conciliator’s costs in

equal shares, unless the conciliator decides otherwise.

Page 12: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

12

The conciliation is in effect a settlement negotiation in which the conciliator attempts

to “midwife” a settlement. All statements, information and material given or

exchanged are inadmissible in any legal proceedings, although evidence which is

otherwise admissible is not rendered inadmissible as a result of its use in the

conciliation.

8. THE ROLE OF THE BARRISTER DURING CONCILATION/MEDIATION

The purpose of mediation is to allow the disputing parties to come to their own

resolution of the dispute. This means that there is a limited role for the lawyer during

the mediation, and in my experience, barristers are not usually involved in construction

mediations. To the extent that counsel may be involved, he or she can contribute by

assisting in the choice of an enthusiastic and proactive conciliator. Both counsel and

solicitor should ensure that the client understands the nature of conciliation/mediation,

and its difference from litigation. It is always advisable to encourage maximum client

communication with the mediator, as “venting” by the client, in the knowledge that

such process is confidential and will not be transmitted to the other side, is often very

valuable in leading towards settlement.

A good conciliator will encourage the parties to state their position honestly and

discard the posturing that often characterises more adversarial proceedings. The

solicitor or counsel can contribute to the process by providing reassurance to the

clients in respect of the possible implications of any settlement. If the client reaches a

settlement with which he or she is satisfied, solicitor and counsel have fulfilled their

professional responsibilities, even in circumstances where the lawyer thinks the value

of the case was greater or less than the client agreed to in conciliation/mediation.

Page 13: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

13

The foregoing presupposes a genuine attempt by both sides to see if a solution can be

achieved. It can happen that one or other party, whether through lack of preparation

or a belief that the other party is so intransigent that no progress can be made, does

not participate effectively in the conciliation/arbitration and makes no meaningful

attempt to progress the negotiations. In such circumstances, counsel may be well

advised to “pull the plug” i.e. inform the conciliator that his client no longer wishes to

participate in the conciliation. This triggers the end of the conciliation process, and the

matter can then be referred to arbitration.

9. ARBITRATION

I do not propose in this paper to enter upon any detailed consideration of how

arbitrations are conducted, or the law relating to arbitrations. However, there are

some points which I would like to make in relation to the role of barristers in the

conduct of arbitrations.

10. THE CODE OF CONDUCT

Rule 5 of the Code of Conduct for the Bar of Ireland (adopted on 13th March 2006)

applies to “relations between barristers and the court, arbitrators, tribunals, statutory

or other bodies, boards and other persons exercising judicial or quasi- judicial

functions”. The rule deals primarily with the way in which barristers must conduct

themselves in their relations with the court, and sub-rule 5.23 reads as follows:-

Page 14: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

14

“The Rules set out in this section governing a barrister’s relationship with the

courts apply also to the barrister’s relations with and conduct before arbitrators

and any other persons exercising judicial or quasi-judicial functions and the sole

member or members of tribunals appointed under statute or by the Oireachtas

or any other investigating body”.

Barristers therefore owe the same duties to an arbitrator that they would owe a court.

While we should all perhaps reread rule 5 from time to time to remind ourselves of its

terms, it is worth noting that, in the context of an arbitration, a barrister is obliged to

maintain due respect and courtesy towards the arbitrator; he/she must in every case

use best endeavours to avoid unnecessary expense and waste of the arbitrator’s time;

he/she must not deceive or knowingly mislead the court, and must correct any

misleading statement as soon as the fact that it is misleading becomes apparent; and a

barrister must inform the arbitrator of any relevant decision on a point of law and, in

particular, “of any binding authority or of any applicable legislation of which they are

aware and which the barrister believes to be in point whether it be for or against their

contention”.

11. ADVOCACY IN LITIGATION AND IN ARBITRATION

In Bernstein’s “Handbook of Arbitration and Dispute Resolution Practice”, 4 ed, [2003],

Thomson Sweet & Maxwell, the authors set out at paragraph 2-822 …”the particular

differences between litigation and arbitration that affect the task of the advocate…”:

“(a) In domestic arbitration at least, the arbitrator will probably have been

chosen by the parties (directly or through their choice of an appointing

institution) for his expertise of some kind;

Page 15: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

15

(b) The arbitrator will personally control the preparations for the hearing, or

the assembly of information and arguments if there is not to be a

hearing;

(c) In many domestic cases the arbitrator will not be a lawyer and he will

prefer, if he can, to avoid having to decide issues of law;

(d) Unless the arbitrator happens to be a barrister, solicitor or retired judge

the arbitrator will have less experience in absorbing oral evidence and

oral argument than the average judge, and accordingly will gain far

more assistance from written evidence and written argument, than

would a judge;

(e) Unless the arbitrator is a lawyer himself the arbitrator will have far more

suspicion of lawyers, and far less understanding of how to get

lawyer/advocates to help him in his task than a judge would have”.

The summary above – which I believe to be broadly fair – gives rise to two particular

points which concern the barrister acting as an advocate in arbitrations. Most

arbitrators, in arbitrations of any appreciable size, adopt the following methodology:

o Witness statements must be provided in advance of the hearing of all

non-expert witnesses;

o Expert reports are to be disclosed in advance of the hearing;

o Experts should be encouraged to agree as much as possible, and where

this is not possible, to identify and list areas of disagreement;

o Quantity surveyors should also list areas of agreement and

disagreement, preferably by way of “Scott Schedule”. In as far as

Page 16: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

16

possible, figures should be agreed “as figures”, without prejudice to any

arguments on liability.

o After discovery, a “core book” of documents should be extracted from

the discovered documentation and agreed between the parties.

All of the above leads to much greater expedition at the hearing and tends to bring

areas of agreement and disagreement to the forefront of the parties mind, thus

promoting the possibility of settlement. The arbitrator also has the advantage of being

able to familiarise himself with the issues and the evidence prior to the hearing.

12. ISSUES OF LAW

As Bernstein points out in the passage quoted above, an arbitrator in a construction

dispute is probably not going to be a lawyer. An arbitrator’s familiarity as an architect,

engineer, or quantity surveyor, with construction projects and practices should greatly

assist in expediting matters at arbitration. However, such a person is unlikely to have

any expertise in the law, and as we can see from the hypothetical problems cited

earlier, many knotty issues of law can arise during an arbitration. A barrister therefore

needs to give some consideration to how the arbitrator should deal with issues of law.

Most arbitration procedures entitle the arbitrator to obtain such professional advice as

he may deem fit in the exercise of his duties. While it may be open for an arbitrator to

consult a lawyer of his choice in relation to legal issues that arise, I would suggest that

it is more appropriate that the parties “take ownership” of the issue of legal advice and

agree with the arbitrator that he can avail of the services of a specified

solicitor/barrister agreed to be suitable by the parties to advise him as a “legal

Page 17: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

17

assessor” on discrete legal issues. The parties are then assured that the arbitrator is

getting expert legal advice from a lawyer that they trust, even if ultimately that advice

is not to their liking.

Under section 35(1) of the Arbitration Act 1954 an arbitrator can state a … “question

of law arising in the course of the reference … in the form of a special case for the

decision of the court”. While having the benefit of producing a definitive finding on the

legal point at issue by the High Court, such a procedure can be time-consuming and

costly and such applications are relatively rare.

Under Section 35(2) of the Arbitration Act 1954, the court may require a case to be

stated on the application of the parties. However, the courts are generally most

reluctant to interfere in the arbitral process unless it is absolutely necessary, and

particularly where the arbitrator is a lawyer; see Ireland v Flattery, unreported,

High Court, Murphy J, 31st May 2006.

13. A RESPONDENT’S TACTICS

While I approached the problem at the beginning of this paper from the point of view

of a barrister instructed for the claimant, a barrister instructed for a prospective

respondent in an arbitration will prepare in the same way, and for the same reasons.

However, there are some considerations which apply to the conduct of the Defence of

an arbitration which bear special mention:

(i) Security for costs; under section 22 of the Arbitration Act, 1954, the High Court

has power to make an Order for security for costs “for the purpose of and in

Page 18: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

18

relation to a reference … “. The arbitrator has no inherent power to make an

Order for security for costs unless it is agreed by the parties that he may do so.

Particularly if the claimant is a limited company, it would be worthwhile for

counsel to see whether it would be possible to establish “by credible testimony

that there is reason to believe that the company will be unable to pay the costs

of the defendant if successful in his defence…” (section 390, Companies Act,

1963). An award of security for costs may impose an intolerable burden on the

claimant company which would prevent it from continuing with the arbitration.

For an example of a successful application for security for costs, and a detailed

examination of the evidential burden which a Plaintiff must surmount to

establish “special circumstances” so as to avoid an Order for security, see the

decision of Clarke J in Connaughton Road Construction Limited v Laing

O’Rourke Ireland Limited, unreported, High Court, 17th January 2009.

(ii) Sealed offer:

A sealed offer or “Calderbank offer” is the arbitral equivalent of a lodgement in

court. It generally takes the form of a letter from the respondent to the

claimant which is “without prejudice save as to costs”. The offer must be

expressed in clear terms and should state whether it relates to the whole of the

claim or to part of it, or whether it takes into account any counterclaim. It

must be a bona fide offer, and the respondent may be required to demonstrate

that he was capable of satisfying an acceptance of the offer made in

accordance with its terms. For a case in which a Calderbank offer was deemed

ineffective, see Murnaghan v Markland Holdings Limited [2004] 4IR

537.

Page 19: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

19

Order 99 Rule 1A(i)(b) of the Rules of the Superior Courts is as follows:

(b) The High Court, in considering the awarding of the costs of any action

(other than an action in respect of a claim or counterclaim concerning

which a lodgement or tender offer in lieu of lodgement may be made in

accordance with Order 22) or any application in such an action, may,

where it considers it just, have regard to the terms of any offer in

writing sent by any party to any other party or parties offering to satisfy

the whole or part of that other party’s (or those other parties’) claim,

counterclaim or application”. [emphasis added]

This sub rule (inserted by SI 12 of 2008) suggests that the High Court can take

a Calderbank offer into account in considering the awarding of the costs of any

action, but may not do so where the lodgement procedure was available to the

Defendant. It seems therefore that, in construction disputes which remain in

Court, the Defendant must avail of the lodgement procedure and cannot rely on

a Calderbank offer.

When a Calderbank offer has been made, the parties should inform the

arbitrator of the fact of the offer – but not, obviously, of the amount – and ask

him to make an interim award in relation to liability and quantum. When that

award has been made, the arbitrator can convene a hearing to discuss the

question of costs.

Page 20: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

20

CONSTRUCTION LAW

BAR COUNCIL CONFERENCE, DISTILLERY BUILDING

Paper by Gerry Meehan BL Saturday 7th February 2009

Global Claims

Introduction

The concept of the global claim in construction law is somewhat complex. In order to

make a successful claim for damages under a construction contract, a claimant must

establish that a breach of contract or other ‘claim event’ has occurred, that the

claimant has suffered a loss, and that there is a causal link between the claim event

and the loss. Obviously, once it is established that loss occurred, the claimant also has

the burden of proving the amount of that loss.

For a claimant to succeed in a claim for damages, he must establish on the balance of

probabilities an effective causal connection between the defendant’s breach of contract

or negligence and the claimant’s loss.1

On the other hand, construction projects tend to be long and complex and it is not

always practical or possible to identify the precise consequences of a particular event.

Many construction projects take a months or years to complete and cover large

geographical areas. There are usually a myriad of different parties, works packages

and programme activities so that it is often practically impossible to identify the effect

(s) of any particular claim event. For example, a late instruction from an engineer on a

large civil engineering project might have a local effect, cause delay to the

commencement of subsequent works packages, disrupt the performance of sub-

contracts and push out the critical path.

1 Stephen Furst and Vivian Ramsey; Keating on Construction Contracts Eighth Edition Thomson Sweet

& Maxwell London 2006

Page 21: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

21

Given the above difficulties, situations arise where the claimant cannot trace each

causal thread from cause to effect and instead offers a collection of breaches / events

and asserts that those breaches / events caused a total sum of loss.

Definitions of Global Claims

The leading textbook on Building and Construction Contracts offers the following

definition:

Global claims may be defined as those where a global or composite sum,

however computed, is put forward as the measure of damage or of

contractual compensation where there are two or more separate matters of

claim or complaint, and where it is said to be impractical or impossible to

provide a breakdown or sub-division of the sum claimed between those

matters. “Total actual cost” or “total cost” are American expressions used in the

Courts of Claims to describe those claims, whether in respect of one only or more than

one matter of complaint, where the alleged total costs of the contractor, usually

derived from alleged internal records and documentation and sometimes supported or

certified by internal or external accountants, is compared with the contract value or

price, and the difference then put forward as representing the measure of damage or

additional cost caused by the one or more matters complained of. Where more than

one separate matter is relied on, as is very often the case, a total cost claim will also,

therefore, constitute a global claim as above defined2

In the leading case of Laing Management (Scotland) Ltd v John Doyle

Construction Ltd, Lord MacLean defines a global claim as: “a claim in which the

individual causal connections between the events giving rise to the claim and the items

of loss and expense making up the claim are not specified, but the totality of the loss

and expense is said to be a consequence of the totality of the events giving rise to the

claim.3

A further definition was given by Byrne J of the Supreme Court of Victoria: “The claim

as pleaded…is a global claim, that is, the claimant does not seek to attribute

2 I.N. Duncan Wallace; Hudson’s Building and Engineering Contracts Eleventh Edition Sweet &

Maxwell London 1995; para. 8.200 3 Per Lord MacLean in Laing Management (Scotland) Ltd v John Doyle Construction Ltd [2004] BLR

295

Page 22: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

22

any specific loss to a specific breach of contract, but is content to allege a

composite loss as a result of all of the breaches alleged, or presumably as a

result of such breaches as are ultimately proved. Such claim has been held to be

permissible in the case where it is impractical to disentangle that part of the loss which

is attributable to each head of claim, and this situation has not been brought about by

delay or other conduct of the claimant…”4

It is relatively common in construction projects for a whole series of events to occur

which individually would form the basis of a claim for loss and expense. These events

may interact with each other in complex ways, so that it becomes very difficult, if not

impossible, to identify the precise loss and expense caused by each event. In those

circumstances, the claimant then points to a global loss which he claims is the result of

the series of breaches. Such claims are known as global claims.

Difficulties with global claims

The obvious difficulty with global claims is that they do not meet the classic

requirements for the party making a claim to particulartise his case. Even where a

claimant can show a number of breaches of contract by the defendant and where he

can show that he suffered a loss (e.g. that the total cost of delivering the project was

in excess of the tender price) that is not in itself evidence of a valid claim because

there is no way of knowing what part of the loss was caused by the breaches. There

are obviously many possible causes for cost overrun and not all of them are necessarily

the responsibility of the defendant. It is generally an essential part of any legal

proceedings that the party seeking damages must show causation.

A further difficulty with global claims is that there is a lack of specificity in their

pleading. The purpose of pleadings was set out by Fitzgerald J in Mahon v Celbridge

Spinning Co Ltd:5

The whole purpose of a pleading, be it a statement of claim, defence or reply, is to

define the issues between the parties, to confine the evidence at the trial to the

matters relevant to those issues, and to ensure that the trial may proceed to judgment

4 John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd (1996) 82 BLR 81

5 [1967] IR 1

Page 23: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

23

without either party being taken at a disadvantage by the introduction of matters not

fairly to be ascertained from the pleadings. In other words a party should know in

advance, in broad outline, the case he will have to meet at the trial.6

The pleadings in a global claim will be unfair and prejudicial against the defendants as

they will not set out the exact case to be met. This will enable the claimants to change

course during the course of their evidence. An Irish court might be quite critical of

such an approach given the general towards requiring greater specificity in pleadings.

Case Law

There are a number of cases that tend to be cited in the treatment of this topic by the

various text books and articles. The earliest of these is J Crosby & Sons Ltd v

Portland Urban District Council7. In that case, Donaldson J said: “I can see no

reason why the arbitrator should not recognize the realities of the situation and make

individual awards in respect of those parts of individual items of the claim which can be

dealt with in isolation and a supplementary award in respect of these claims as a

composite whole.”

The commentary on this case; contained in the Building Law Reports, contains the

following passage:

“[Donaldson J] acceded to the argument that where a claim depends on ‘an extremely

complex interaction in the consequences of various denials, suspensions and

variations, it may well be difficult or even impossible to make an accurate

apportionment of the total extra cost between the several causative events’. In doing

so he gave judicial approval to a widespread and commonsense method of measuring

claims. The principle is, of course, applicable to claims for extensions of time as well as

to claims for additional money.”8

It is only that part of the award that Donaldson J refers to as the “supplementary”

award that is a global claim. In those circumstances, the Judge envisages a cause and

effect analysis for those individual items where such an analysis is possible and a rolled

6 Per Fitzgerald Ibid. at 3

7 [1967] 5 BLR 121

8 Ibid. p. 123

Page 24: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

24

up claim for the remaining items. This however, by definition is the part of the claim

where the sources of the loss cannot be identified.

It is submitted that this makes it almost impossible for a defendant to defend. The

claimant, typically a contractor who is in the best position to keep records of the job

(because he built it) cannot identify the cause of the loss yet the employer, who has

not the same intimate knowledge of the carrying out of the job is expected to defend it

by identifying causal elements for which the employer is responsible.

In London Borough of Merton v. Leach (1985)9, the contractors’ claims were for

damages for breach of contract, and also for direct loss and expense under the clauses

of the contract dealing with variations and late instructions. Vinelott J in that case,

referring to the Crosby decision said that it was: “implicit in the reasoning of

Donaldson J first, that a rolled up award can only be made in the case where the loss

or expense attributable to each head of claim cannot in reality be separated and

secondly that a rolled up award can only be made where apart from that practical

impossibility the conditions which had to be satisfied before an award can be

made have been satisfied in relation to each head of claim.”

It is respectfully submitted that there is an inherent contradiction in the above

passage. One of the conditions that must be satisfied before an award can be made in

relation to an individual head of claim is that there is a causal link between that head

of claim and an item or items of loss. It is impossible therefore to satisfy that condition

where the loss or expense attributable to each head of claim cannot in reality be

separated (Donaldson J’s first condition).

Wharf Properties Ltd v Eric Cumine Associates (1991)10 concerned a

development in Hong Kong. A separate foundations contract for the development was

delayed and this in turn delayed the contractor who was retained to build the super-

structure. The latter contractor sued the employer and the proceedings were settled.

The employer then went after the architect for the cost of the settlement alleging that

the architect had failed properly to manage control, co-ordinate, supervise or

9 32 BLR 68

10 52 BLR 8

Page 25: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

25

administer the foundation contract, or to provide information or instructions for it in

time. In its discussion of this case Hudson11 writes that:

The developers pleaded that, due to the complexity of the project and the cumulative

and “knock on” effect of a large number of delaying and disruptive factors, it was

impossible to identify and isolate individual delays and until the trial it would not be

known which if any variations or other events had caused the delays.”

The Privy Council held that whereas there was a reasonable cause of action pleaded,

the pleadings failed to explain the nexus between the individual breaches and the

sums claimed, and they should be struck out as embarrassing and prejudicial to a fair

trial.

This case is slightly different from the previous ones in that it was not a total cost

claim. The damages claimed were ascertained and precise. Lord Oliver of Aylmerton in

his consideration of the Crosby and Leach cases distinguished them as follows:

“ECA are concerned at this stage not so much with quantification of the financial

consequences – the point with which the two cases referred to were concerned – but

with the specification of the factual consequences of the breaches pleaded in terms of

period of delay. The failure even to attempt to specify any discernable nexus between

the wrong alleged and the consequent delay provides…‘no agenda’ for trial.”12

The sum sought was an exact amount and in principle it was recoverable provided

each causal nexus was fully explored and its effect identified. The separate delay

consequences of the separate breaches were not identified however and therefore the

pleading was hopelessly embarrassing and an unparticularised pleading in such a form

would not be allowed to stand.

Hudson continues:

The Wharf case is, however, an example of how global claims, which can be relatively

rapidly and easily assembled, can be presented in the form of “a document of immense

length and complication” which serves both to conceal the absence of any real

substratum of supporting fact from a weak or inexperienced tribunal, and to impede

the defendant’s preparation of a detailed and convincing case by way of rebuttal.

11

Ibid. para. 8.207 12 Per Lord Oliver, ibid. at p. 9.

Page 26: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

26

…neither the Crosby nor the Leach cases indicate any considered judicial support for

the use of global claims even in the particular construction contracts before the courts

– in the Crosby case, Donaldson J. Was dealing with a finding of fact by an arbitrator,

binding on the Court, to the effect that the particular causes of delay in that case could

not as a fact be separated as to delay or disturbance, while Vinelott J. in Leach was

dealing with an entirely hypothetical case of loss and expense due to combined

variation and late instruction grounds of claim, with no findings of fact as yet made by

the arbitrator at all.13

In McAlpine Humberoak Ltd. V McDermott International Inc (1992)14 the

contractor defendant engaged the claimant as a sub-contractor to construct steel

pallets forming part of a weather platform for an oil rig. The claimant’s case was that it

had been considerably delayed in constructing the pallets by late receipt of materials,

revised drawings and late replies to technical queries and was entitled to extra

payments in respect of the delays it had suffered. The direct costs of these events was

agreed and paid but indirect costs were also sought. The claimants assessed the time

needed for each individual revision , their evidence on quantum being based on the

assumption that during that time no other work could be performed and that the

contract as a whole had been delayed to that extent. The Court of Appeal held that the

claimant had not established a right to be paid any sum in respect of its indirect costs

as a result of the variations and revisions in the absence of any evidence showing that

the individual variations and revisions had caused delay to progress. The Court

essentially disallowed the claim because the claimants had failed to show causation.

Lloyd LJ set out quite clearly the extent to which causation was necessary:

“The judge dismissed the defendants’ approach to the case as being ‘a retrospective

and dissectional reconstruction by expert evidence of events almost day by day,

drawing by drawing, TQ by TQ and weld procedure by weld procedure, designed to

show that the spate of additional drawings which descended on McAlpine virtually from

the start of the work really had little retarding or disruptive effect on its progress’. In

our view the defendants’ approach is just what the case required.”15

13

Ibid. para. 8.208 14

58 BLR 1 15 Per Lloyd L.J., ibid at p.28

Page 27: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

27

Hudson opines that :

The Humberoak case reflects an increasingly common tendency for exaggerated claims

to be advanced, whether for the valuation of variations or damages for breaches of

contract, based on unrealistic theoretical assumptions which conveniently dispense

within any detailed investigation of either causation or quantum, and which are often

the result of so-called expert claims advice obtained at an early stage: “It seems to be

the practice in the construction industry to employ consultants to prepare a claim

almost as soon as the ink on the contract is dry.”16 The Wharf and Humberoak

judgments represent a fully justified and overdue judicial response to these tendencies,

and should provide valuable support where better particularisation of claims is sought

by defendants at the interlocutory stages of either litigation or arbitration.17

It must have appeared therefore at the time of the publication of the eleventh edition

of Hudson’s Building and Engineering Contracts (1995) that the Humberoak and Wharf

decisions pointed to a move away from global claims by the courts. Two recent

decisions however seem to adopt a more permissive approach to global claims.

The first important point to note in relation to Laing Management (Scotland) Ltd v

John Doyle Construction Ltd18 is that the employer conceded that a “global claim”

(in this case a claim for loss and expense calculated using a comparison between pre-

contract estimates and actual costs) was permissible if it were impossible for each

casual link to be traced between each individual event (i.e. each cause of delay and

disruption) and each item of loss, although the burden of showing this was upon the

claiming party. The defendants accepted that the claimants were entitled to make a

global claim. Indeed there does not seem to be any authority for the proposition that a

global claim is never permissible. It is also of relevance that this is a Scottish case and

as such is of only limited persuasive value in Ireland.

The court did not decide whether an averment that it was impossible to draw a causal

link between each causative event and each item of loss and expense was essential in

order to make a global claim. Neither did their Lordships decide what is necessary to

16

Per Lloyd L.J., ibid at p. 24 17

Hudson para 8.211 18 [2004] BLR 295

Page 28: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

28

prove such an averment once it is made and what the consequences are if the

averment is made but not proven.

Notwithstanding the above, the court found that if a claimant puts forward a global

claim, he must eliminate all causes of loss and expense that are either the claimant’s

responsibility or neutral events (a contractor is entitled to claim an extension of time

for some neutral events but not loss and expense). In other words no causative

element can be included in a global claim that is not the responsibility of the

defendant.

Lord MacLean sets forth the following analysis of the nature of a global claim: “For a

loss and expense claim under a construction contract to succeed, the contractor must

aver and prove three matters: first, the existence of one or more events for which the

employer is responsible; secondly, the existence of loss and expense suffered by the

contractor; and thirdly, a causal link between the event or events and the loss and

expense…Normally individual causal links must be demonstrated between each of the

events for which the employer is responsible and particular items of loss and expense.

Frequently, however, the loss and expense results from delay and disruption caused by

a number of different events, in such a way that it is impossible to separate out the

consequences of each of those events. In that event, the events for which the

employer is responsible may interact with one another in such a way as to produce a

cumulative effect. If, however, the contractor is able to demonstrate that all of the

events on which he relies are in law the responsibility of the employer, it is not

necessary for him to demonstrate causal links between individual events and particular

heads of loss. In such a case, because all the causative events are matters for which

the employer is responsible, any loss and expense that is caused by those events and

no other must necessarily be the responsibility of the employer. That is in essence the

nature of a global claim…if the claim is to fail, the matter for which the employer is not

responsible in law must play a significant part in the causation of the loss and expense.

In some cases it may be possible to separate out the matters for which the employer is

not responsible.19

The passage does not provide for the very common scenario; where events for which

the contractor is responsible interact with events for which the employer is responsible

19 Per Lord MacLean, ibid. at pp. 300-301

Page 29: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

29

to produce the cumulative effect. The foregoing analysis of Lord MacLean only requires

the contractor to demonstrate that all the events on which he relies are in law the

responsibility of the employer. There is no provision for a situation where there are

causal factors contributing to the consequences that are difficult to identify (or perhaps

easy for a claiming contractor to conceal) and are not the employer’s responsibility.

There is an inherent contradiction in this approach. If the contractor is not required to

demonstrate causal links between individual events and particular heads of loss it

cannot be said (in the very next sentence) that all the causative events are matters for

which the employer is responsible. At best, all that can be said id that the causative

events identified are matters for which the employer is responsible. Clearly the court is

correct in stating that any loss and expense caused exclusively by events for which the

employer is responsible must necessarily be the responsibility of the employer. The

problem however is that the contractor is not required to show that such events are in

fact the cause of the loss and expense.

This approach shifts the burden of proof from the claimant to the defendant. This is

obviously contrary to a fundamental rule of law. Furthermore it places the burden of

proof on the party who is worst placed to shift it. Typically global claims will be taken

by contractors against employers. Contractors are generally in the best position to

monitor the progress of a construction project and to keep records. If a contractor,

who has first hand knowledge of the carrying out of a job is unable to separate out the

consequences of the various events, the employer is unlikely to be able to do so. This,

it is submitted is prejudicial and highly unfair to an employer.

Lord MacLean’s judgment in Laing goes on to cite the following passage from

judgment of Byrne J in John Holland Construction & Engineering Pty Ltd v

Kvaerner RJ Brown Pty Ltd (1996)20:

“….a contractor, as the maker of such a claim (total cost claim), alleges against a

proprietor a number of breaches of contract and quantifies its global loss as the actual

cost of the work less the expected cost. The logic of such a claim is this:

(a) the contractor might reasonably have expected to perform the work for a

particular sum, usually the contract price;

(b) the proprietor committed breaches of contract;

20 82 BLR 81

Page 30: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

30

(c) the actual reasonable cost of the work was a sum greater than the expected

cost.

The logical consequence implicit in this is that the proprietor’s breaches caused the

extra cost or cost overrun. This implication is valid only so long as, and to the extent

that, the three propositions are proved and a further unstated one accepted: the

proprietor’s breaches represent the only causally significant factor

responsible for the difference between the expected cost and the actual

cost. In such a case the causal nexus is inferred rather than demonstrated…The

under-stated assumption underlying the inference may be further analysed. What is

involved here is two things: first, the breaches of contract caused some extra cost,

secondly, the contractor’s cost overrun is this extra cost. The first aspect will often

cause little difficulty but it should not…be ignored…It is the second aspect…which is

likely to cause the more obvious problem because it involves an allegation that the

breaches of contract were the material cause of all of the contractor’s cost overrun.

This involves an assertion that, given that the breaches of contract caused some extra

cost, they must have caused the whole of the extra cost because no other relevant

cause was responsible for any part of it.21

In considering the John Holland Construction case, Lord Mac Lean continued:

Byrne J went on to consider the claim made by the plaintiffs in the case before him,

and pointed out that, because it was a total cost claim, it was necessary to eliminate

any causes of inadequacy in the tender price other than matters for which the

employer was responsible. It was also necessary to eliminate any causes of overrun in

the construction cost other than matters for which the employer was responsible.

This, it is submitted is clearly impossible unless every single causal link is examined. In

order to eliminate any causes of overrun in the construction cost other than matters

for which the employer was responsible, every cause of overrun must be identified and

analysed to see who is responsible. If it is the case that this is possible, then it should

not be necessary to present a global claim because it would not be impossible or

impractical to separate out the consequences of each claim event.

21 Ibid. pp. 85-87)

Page 31: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

31

After considering the John Holland case and following consideration of Boyajian v

United States22 (1970), Lord MacLean went on to state that: If a global claim is to

succeed, whether it is a total cost claim or not, the contractor must eliminate from the

causes of his loss and expense all matters that are not the responsibility of the

employer…23

As outlined above, it is difficult to see how it is possible for a contractor to demonstrate

that he has eliminated such matters other than by the making of a bald assertion. Lord

MacLean went on to say that this requirement is mitigated however by three

considerations; firstly:

It may be possible to identify a causal link between particular events for which the

employer is responsible and individual items of loss. On occasion that may be possible

where it can be established that a group events for which the employer is responsible

are causally linked with a group of heads of loss, provided that the loss has no other

significant cause. In determining what is a significant cause, the “dominant cause”

approach...is of relevance24

This point raises no difficulty whatsoever however it is submitted that to the extent

that this is possible, the claim is not a global claim but a conventional claim requiring

the claimant to show causation. The second and third mitigating considerations

identified by his Lordship were that:

the question of causation must be treated by “the application of common sense to the

logical principles of causation”…In this connection, it is frequently possible to say that

an item of loss has been caused by a particular event notwithstanding that other

events played a part in its occurrence…if an event…for which the employer is

responsible can be described as the dominant cause of an item of loss, that will be

sufficient to establish liability, notwithstanding the existence of other causes that are to

some degree at least concurrent.25

22 423 F 2d 1231 23

Per Lord MacLean, ibid. at p. 302 24

Per Lord MacLean, ibid. at p. 302 25

Per Lord Mac Lean, ibid at p. 302 In analysing the concept of the dominant cause, Lord MacLean used

cited Leyland Shipping Company Limited v Norwich Union Fire Insurance Society Ltd [1918] AC 350

Page 32: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

32

And that:

Even if it cannot be said that events for which the employer is responsible are the

dominant cause of the loss, it may be possible to apportion the loss between the

causes for which the employee is responsible and other causes…the event for which

the employer is responsible should be a material cause of the loss. (e.g. concurrency)26

Laing has received some measure of approval from the English Courts in London

Underground Ltd v Citylink Telecommunications Ltd27. That case involved the

replacement of the telecommunications network throughout the London underground

network. Certain enabling works needed to be carried out by the employer prior to the

start of the contract works and these works were delayed. The contractor claimed

there were a large number of alleged breaches and claimed an overall extension of

time. The arbitrator found that the claim was a global claim. The case came before

Ramsey J in the High Court in England:

…I consider that the proper approach to global claims is relevant. The approach set

out in the decision in Laing v Doyle is not challenged on this application and I accept

that approach.

Despite this, both the arbitrator and the Judge went on to reject the global claim and

decide only those issues where the evidence showed a connection between the delay

and the event. The Judge went on to find that in circumstances where the arbitrator

considers the global claim to have failed, it is open to him, on the evidence before him,

to establish causation and make appropriate findings.

There does not seem to be a large body of judicial support for the concept of global

claims. Indeed it is possible that if the concept was tested in the Irish courts, it would

be met with an unfavourable response. This is unlikely to happen in the near future

however given that all standard forms of construction contracts contain arbitration

clauses. It seems to be the case that every large construction project in Ireland in

recent years involves a number of significant claims by the contractor against the

employer. As well as the usual claims such as delay and disruption claims, acceleration

26

Per Lord MacLean, ibid. at pp. 302-303. His lordship cited Apportionment cases: Lichter v Mellon-

Stuart Company (1962) 305 F 2d 216 and Phillips Construction Co Inc v United States (1968) 394 F 2d

834 in support of apportionment. 27 [2007] BLR 391 at 414

Page 33: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

33

claims, variations and employer’s breaches, most claimants will include a global claim.

These claims are used as currency in settlement negotiations to put pressure on

employers in the context of alternative dispute resolution. They are so familiar now in

the world of construction claims that they barely raise an eyebrow when they land with

a thud on the employer’s desk. It is doubtful whether one would carry any weight if it

was to be subjected to the scrutiny of the High Court.

Global claims avoid the central requirement of tying the individual breaches or grounds

of claim to the particular sums claimed. A global claim or a total cost computation is

not evidence of a breach of contract or any other entitlement and it is not evidence of

damage or additional costs. The eleventh edition of Hudson was published in 1995

(before the Laing and London Underground decisions) and its author then wrote:

It is submitted that, in the English and related Commonwealth jurisdictions, claims on a

total costs basis, a fortiori if in respect of a number of disparate claims, will prima facie

be embarrassing and an abuse of the process of the court justifying their being struck

out and the action dismissed at the interlocutory stage. It is further submitted that,

even if such a claim is allowed to proceed, it should only be on the basis that, on proof

of any not merely trivial damage or additional cost being established (or indeed any

other cause of the additional cost, such as under-pricing) for which the owner is not

contractually responsible, the entire claim will be dismissed. Any other course places

the practical onus of proving the extent of the plaintiff’s damage on the defendant or

on the court itself.28

Although the courts in the English and Scottish jurisdictions have shown a limited

willingness to allow global claims, it is very possible that an Irish court would not.

28 Hudson para 8.204

Page 34: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

34

CONSTRUCTION LAW

BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Michael Stimpson BL Saturday 7th February 2009

NOTICE PROVISIONS AS CONDITIONS PRECEDENT

EXEMPTION CLAUSES – GENERAL PRINCIPLES This paper deals with the trend in modern construction contracts requiring the Contractor to give notice of claims for extensions of time and/or money within a

particular time frame and whether a notice given outside that timeframe results in the barring of the claim which the Contractor wishes to pursue.

If the Employer alleges that such clauses bar the Contractor’s claims, then the clause in question will be an exemption clause and subject to the numerous cases on that topic. Before dealing with the specific clauses which are the

subject of this paper, we should remind ourselves of the following basic

principles: “The General rule is that where there is any doubt as to the construction of any stipulation in a contract, one ought to construe it strictly against the party in whose favour it has been made.” 29 “I think that any clause or provision that purports to have that effect (i.e. to exclude liability) ought to be clear and unambiguous, so that the Contractor knows exactly where he stands.”30 (i) If the clause contains language which expressly exempts the person in

whose favour it is made (hereafter called the “proferens”) from the consequences of the negligence of his own servants, effect must be given to that provision...

(ii) If there is no express reference to negligence, the court must consider whether the words used are wide enough, in their ordinary meaning, to cover negligence on the part of the servants of the proferens. If a doubt arises at this point, it must be resolved against the proferens.

(iii) If the words used are wide enough for the above purposes, the court must then considered whether the ‘head of damage’ may be based on some ground other than that of negligence ... The ‘other ground’ must not be so fanciful or remote that the proferens cannot be supposed to have desired protection against it; but subject to that qualification ... the existence of a possible head of damage other than that of negligence is fatal to the proferens even if the words used are prima facie wide enough to cover negligence on the part of his servants. 31

“ ... the reason for the principle that an exclusion clause must be clearly and unambiguously expressed in order to exclude liability for negligence

29

Burton v English [1883] – Brett MR 30

Houghton v Trafalgar Insurance Company Ltd [1954] – Romer LJ 31 Canada Steamship Line v R [1952] Lord Morton

Page 35: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

35

is that the defendant is seeking to exclude the application of the common law and his or her common law liability. Certainly, the parties may agree to exonerate a party from such liability in advance, but to do so it is just and reasonable that the courts should be satisfied that the exemption is clearly intended. This is more particularly the case when the exemption is imposed as the term of a contract which in its standard form contact or ‘unilateral’ contract in the sense that its provisions are not subject to significant negotiation or the exclusion from liability is dictated by the party who will enjoy the immunity. The principle is not, therefore, an arbitrary or artificial rule of construction. Rather it is a realistic principle which recognises that the parties are not to have been taken to have intended to exclude the common law, or the common law liability of the defendant, unless they have said so in clear and unambiguous terms”32 “If you examine all the cases, you will ... find that at bottom it is because the clause (relieving a man from his own negligence) is unreasonable, or is being applied unreasonably in the circumstances of the particular case. The judges have, then, time after time, sanctioned a departure from the ordinary meaning. They have done it under the guise of ‘construing’ the clause. They assume that the party cannot have intended anything so unreasonable. So they construe the clause ‘strictly’. They cut down the ordinary meaning of the words and reduce them to ordinary proportions. They use all their skill and art to this end.” 33 “In this type of case two principles are well settled. The first is that if a person desires to exempt himself from liability which the common law imposes upon him, he can only do so by a contract freely and deliberately entered into by the injured party in words that are clear beyond the possibility of misunderstanding. The second is: if there are two possible heads of liability on the part of the defendant, one for negligence, and the other for strict liability, an exemption clause will be construed, so far as possible, as exempting the defendant only from strict liability and not relieving him from liability for negligence.”34 “Are the courts then powerless? Are they to permit the party to enforce his unreasonable clause, even when it is so unreasonable, or applied so unreasonably, as to be unconscionable? When it gets to that point, I would say ... ‘there is the vigilance of the common law which, while allowing freedom of contract, watches to see it is not abused’ ... It will not allow a party to exempt himself from his liability at common law when it would be quite unconscionable for him to do so.”35

Summarising the principles (from the above and generally):

1. The exemption clause must be clear and unambiguous.

32

Livingstone v Roskilly [1992] New Zealand High Court, Thomas J 33

Gillespie Bros v Bowles (Roy) Ltd [1973] Lord Denning MR 34

White v Warwick [1953] Denning LJ 35 Gillespie Bros v Bowles [1973] Lord Denning MR

Page 36: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

36

2. It will not apply to claims in tort or statutory claims unless express reference is made to either or both.

3. If truly unconscionable, it will not be applied at all.

4. If the clause is in conflict with another clause of the contract, it may not be applied.

5. If there is any element of fraud, it will not be applied.

6. The clause has to be brought to the notice of the party against whom it is to be enforced with suitable panoply.

In England whether an exemption clause may be relied upon or not is governed by the Unfair Contract Terms Act 1977. There is no such statute in Ireland and therefore the cases highlighting unreasonable and unconscionable exemption

clauses come to the fore in this jurisdiction.

They are also in point with regard to innocent as opposed to fraudulent misrepresentations. Such claims are dealt with under the Misrepresentation Act

1997 in the UK, which has no statutory counterpart in Ireland.

SPECIFIC EXEMPTION CLAUSES IN USE IN IRELAND

The Standard RIAI Building Form of Main Contract and the standard IEI Form of Contract for Civil Engineering Works do not contain clauses which bar claims

if they are not put in within a certain time.36 However, the Government has long required the County Councils to use Clause

20.1 of the FIDIC contract in respect of contractors’ claims, particularly in respect of National Roads Contracts. The standard FIDIC Clause 20.1 provides:

‘If the Contractor considers himself to be entitled to any extensions of the Time for Completion and/or any additional payment, under any clause of these Conditions or otherwise in connection with the Contract, the Contract shall give notice to the Employer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the contractor became aware, or should have become aware, of the event or circumstance. If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim... The requirements of this Sub-Clause are in addition to those of any other Sub-Clause which may apply to a claim. If the Contractor fails to comply with this or another Sub-Clause in relation to any claim, any extension of time and/or additional payment shall take account of the extent (if any) to which the failure has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the second paragraph of this Sub-Clause.’

The question therefore arises whether a failure to give notice of a claim within the 28 day period bars the claim forever.

36

Save for Clause 66 of the IEI Form which requires a reference to arbitration within one month of an

Engineer’s decision under Clause 66 in respect of interim certificates and three months in respect of

claims arising out of the final certificate/account.

Page 37: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

37

Clause 20.1 goes on to request that supporting records be kept and that a fully

detailed claim including full support particulars of the basis of the claim or an extension of time and/or additional payment, should be provided by the Contractor within 42 days after he became aware, or should have become

aware, of the event or circumstance giving rise to the claim, or within such

other period as may be proposed by the Contractor. However, there would appear to be no sanction against failure to comply with these time limits, save for any prejudice caused to the Engineer in investigating the claim by such a

failure. Traditionally in construction claims, no particular form of notice of a claim has

been required, and as long as the Architect/Engineer/Employer have been put on notice of a claim, minutes of meetings, letters and interim applications for payment have all been treated as proving satisfactory notice where the claim is

referred to in such documents. There is also authority for oral notice being

adequate even where the clause requires a written notice37. Under the new Public Works Contract Forms, both these matters have been addressed. Clause 10.3 states as follows:

10.3 Contractor Claims 10.3.1 If the Contract considers that under the Contract there

should be an extension of time or an adjustment to the Contract Sum, or that it has any other entitlement under or in connection with the Contract, the Contractor shall, as soon as practicable and in any event within 20 working days after it became aware, or should have become aware, of something that could result in such an entitlement, give notice of this to the Employer’s Representative. The notice must be given according to sub-clause 4.14 and prominently state that it is being given under sub-clause 10.3 of the Contract. Within a further 20 working days after giving the notice, the Contractor shall give the Employer’s Representative details of all of the following:

(1) all relevant facts about the claim (2) a detailed calculation and, so far as practicable, a

proposal, based on that calculation, of any adjustment to be made to the Contract Sum and of the amount of any other entitlement claimed by the Contractor

(3) if the Contractor considers that the programme contingency referred to in sub-clause 9.4 should be used or that there should be an extension of time, the information required under sub-clause 9.3, and, so far as practicable, a proposal, based on that information for any use of the programme contingency or any extension to the Date for

37

See Merton London Borough Council v Stanley Hugh Leach Limited [1985] 32BLR51; CCECC (HK)

Ltd v Might Foundate Developments Ltd [2001] HCCT 23/2001; and Hersent v Burmah Oil Ltd 10BLR1

Page 38: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

38

Substantial Completion of the Works and any affected Section.

The Contractor shall give any further information about the event or circumstance requested by the Employer’s Representative.

10.3.2 If the Contractor does not give notice and details in accordance with and within the time provided in this sub-clause 10.3, except where the Contractor has been required to and has given a proposal complying in full with sub-clause 10.4 [notwithstanding anything else in the Contract] the Contractor shall not be entitled to an increase to the Contract Sum or extension of time or use of the programme contingency referred to in sub-clause 9.4 [and the Employer shall be released from all liability to the Contractor in connection with the matter].

10.3.3 If the cause of the claim has a continuing effect, the Contractor shall update the information at monthly intervals (1) stating the extension of time and adjustment to the

Contract Sum claimed for delay and cost already incurred and

(2) so far as practicable, proposing a final adjustment to the Contract Sum and Date for Substantial Completion of the Works and any affected Section and

(3) providing any other information the Employer’s Representative reasonably requires.

10.3.4 The Contractor shall keep detailed contemporary records to substantiate any aspect of an event of circumstance about which it has given, or is entitled to give, notice under this sub-clause 10.3, and its resulting costs. These shall include any records the Employer’s representative directs the Contractor to keep. The Contractor shall give the records to the Employer’s Representative if so directed.

Thus it can be seen that under the new Public Works Contract, both the notice

of the claim and the particulars of the claim must be given within 20 working days and a further 20 working days otherwise the Employer will be released

from all liability, and further, that the notice must comply with the formal notice

provisions of sub-clause 4.14, stating that it has been given under sub-clause 10.3. Accordingly, the days of proffering oral notice or minutes, letters and payment applications as notices appear to be over, as will be the claims

themselves if the time limits are not met.

The question, therefore, for Contractors and those advising them is how, if at all, these stringent provisions can be circumvented. Reverting to the general principles at the beginning of this paper, it may be that, if the Contractor is out

of time for providing his notice/particular, his claim can be framed in negligence (or possibly some other tort) or for breach of statutory duty. The question will

then arise as to whether such claims are caught by the words “under any

Page 39: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

39

clause of these Conditions or otherwise in connection with the Contract” (FIDIC), or “under the Contract ... or ... under or in connection with the Contract” (New Public Works Contract). Naturally, the facts of any particular case are of more than peripheral

importance in answering these questions. In my view, it is certainly important

to persuade the Arbitrator (or the Court where there is no arbitration clause), that the overall merits of the claim are with the Contractor. The tribunal will then be more disposed to finding these provisions unconscionable in any

particular case or, perhaps, construing the clauses so as not to catch claims for negligence, breach of statutory duty, and, even damages.

If an Arbitrator finds in favour of a Contract on these issues, the findings would be difficult to challenge unless they incorporated propositions of law which were “clearly wrong”38. There may be mixed findings of fact and law which would

prevent this conclusion. In any event, the proposition of law in question must

not be one referred by the parties to the Arbitrator for the Arbitrator’s exclusive determination (see McStay and Keenan v Shield Insurance Company Ltd [1988] IR89). The proposition of law must be material to the decision of the Arbitrator:

See Limerick City Council v Uniform Construction Ltd [2007] IR30, where Clarke J stated:

“In order to be a ground for setting aside the award an error in law on the face of the award must be such that there can be found in the award, or in a document actually incorporated with it, some legal proposition which is the basis of the award and which is erroneous.”

In order to be sure of flagging up the point of law as one not left exclusively to

the Arbitrator’s determination, a requirement for the Arbitrator to state a case

on the point for the opinion of the Court must be taken at an early stage in the arbitration proceedings, i.e. in the pleadings or at the latest in the opening of the case before any evidence is heard.

THE “PREVENTION” ARGUMENT

Even in the Employer manages to surmount the earlier arguments in this paper

against exemption clauses, the Employer still has to deal with the issue of “prevention”, i.e. is it equitable for such exemption clauses to be relied upon to defeat claims which arise as a result of the Employer preventing the Contractor

from operating the construction contract in the manner intended?

This is an important matter for Employers, because if the Architect/Engineer has not given an extension of time purely on the ground that the application for

such extension was itself outside of the time stipulated in the contract for giving

notice and/or particulars of such a claim, then, if the notice provision is held to be ineffective, in the absence of any extension of time award, time for completion is “at large” and the Employer will lose its automatic right to

liquidated damages against the Contractor. In this instance, the Employer will

have to prove unliquidated damages based on a new “reasonable time” for completion, which itself will be decided in the light of all relevant circumstances

38

McStay v Assicurazioni Generali SpA [1991] ILRM, Sheahan v FBD Insurance 1998 IEHC,

unreported, High Court, Kelly J, March 25, and Church & General Insurance Co v Connolly.

Page 40: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

40

and not necessarily just those referred to in the extension of time clause

entitling the Contractor to an extension of time. There is no direct authority in either Irish law or English law as to whether clause 20.1 of FIDIC is a condition precedent to a valid claim for more time or

more money, and there are no cases at all as yet under the new Public Works

Contract. Even where a time-bar clause appears to be a condition precedent, a court or arbitral panel may refuse to interpret it this way. A notable example is

Chiemgauer Membran und Zeltbau GmbH (formerly Koch Hightex GmbH) v New Millennium Experience Co Ltd (formerly Millennium Central Ltd) (No1)39 where the English Court of Appeal held the following clause not to be a condition precedent:

“The provision of a guarantee and performance bond is a condition precedent to any liability or obligation of the New Millennium Company [as employers for the supply of the roof for the Millennium Dome] under the contract.”

In Chadwick LJ’s view, if the clause were held to be a condition precedent “such an arrangement could properly be described ... as commercial nonsense”. The Judge was not convinced that the Employer and the Contractor intended that the effect of their agreement was that the Contractor should carry on working

(and could then – as happened – have its employment terminated) without any

entitlement to be paid, until it chose to provide the guarantee and performance bond, which after termination became unrealistic. Outside of Ireland and England there are conflicting decisions as to whether or

not the prevention principle is the undoing of a time-bar clause. In the

Australian case of Turner Corporation Ltd v Austotel Pty Ltd Cole J in the New South Wales Supreme Court stated:

“If the Builder having a right to claim an extension of time fails to do so, it cannot claim that the act of prevention which would have entitled it to an extension of time ... resulted in its inability to complete by that time. A party to a contract cannot rely upon preventing conduct of the other party where it failed to exercise a contractual right which would have negated the effect of that preventing conduct.”

In the case of City Inn Ltd v Shepherd Construction Ltd [2002] SLT781 and [2001] SCLR961, the Scottish Court of Session took a similar view stating that

compliance with the time provision in the relevant contract would not impose an “excessive burden” on the Contractor, thus giving rise to a potential argument that such clauses can be circumvented if they do impose an

“excessive burden” on the Contractor. Indeed, this may often be the case in cases where complex facts give rise to legitimate claims on construction contracts where it might not be possible to comply with the time limits set out

in the new Public Works Contract, for example.

In the case of Gaymark Investments Pty Ltd v Walter Construction Group Ltd [2000] 16BCL449 Supreme Court Northern Territories, an amended version of

39

Chiemgauer Membran und Zeltbau GmbH (formerly Koch Hightex GmbH) v New Millennium

Experience Co Ltd (formerly Millennium Central Ltd) (No1) [1999] CILL1595, CA (3rd

November 1999),

reported by Westlaw as 1999WL1019561.

Page 41: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

41

the Australian Public Works Standard Form NPWC3-1981 included at sub-clause

SC19.2: “The Contractor shall only be entitled to an extension of time ... where the Contractor ... (b)(i) has complied strictly with the provisions of sub-clause SC19.1 and in particular, has given the notices required by sub-clause SC19.1 strictly in the manner and within the time stipulated by the sub-clause; ...”

It was agreed that the Contractor had failed to give a notice in accordance with

the clause, but the Judge, Bailey J, refused to treat it as a condition precedent. He refused to overturn the Arbitrator’s award on this point and in distinguishing

Turner (see above) stated that the prevention principle presented a “formidable barrier” to the Employer’s claim for liquidated damages (the amended contract made no provision for an extension of time unless the Contractor complied with

the time-bar clause).

Again, in Peninsula Balmain Pty Ltd v Abigroup Contractors Corp Pty Ltd [2002] NSWCA211, the New South Wales Court of Appeal considered a time-bar clause in the following terms:

“The Principal shall not be liable upon any claim by the Contractor in respect of or arising out of a breach of the Contract unless within 28 days after the first day upon which the Contractor could reasonably have been aware of the breach, a Contractor has given to the Superintendant the prescribed notice.”

Although the Contractor failed to comply with this clause, the Court held that this did not deprive him of his right to an extension of time and that “the prevention principle” overrode the time-bar clause, and that the Superintendent

should have exercised his unilateral power to grant an extension of time to cover the Employer’s delay. Gaymark and Peninsula Balmain have attracted adverse judicial comment. In

the case of Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No2) [2007] EWHC447(TCC), [2007] BLR195, where Jackson J (now Jackson

LJ) stated:

“Whatever may be the law of the Northern Territory of Australia, I have considerable doubt that Gaymark represents the law of England. Contractual terms requiring a Contractor to give prompt notice of delay serve a valuable purpose; such notice enables matters to be investigated while they are still current. Furthermore, such notice sometimes gives the Employer the opportunity to withdraw instructions when the financial consequences become apparent ... if Gaymark is good law, then a Contractor could disregard with impunity any provision making proper notice a condition precedent. At his option the Contractor could set time at large.”

CONCLUSION

It has been suggested by some commentators that the prevention principle is not a rule of law but a rule of construction and therefore cannot defeat time-

bar clauses, and also that the ‘proximate cause’ of the Contractor’s loss is not to

Page 42: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

42

be found in the Employers acts of prevention, but the Contractor’s own failure

to operate the contractual machinery and judicial lines of thought for both propositions do emerge from some cases. Those commentators therefore suggest that Arbitrators should apply time-bar clauses ‘freely negotiated

between commercial men’.

For what it is worth, I do not subscribe to either view. I would suggest that the “prevention principle” is well rooted in Equity, and that the ‘proximate cause’ theory is mere sophistry.

For good measure, I do not accept that the amended FIDIC Clause 20.1, nor Clause 10.3 in the new Public Works Contract, in the Irish context at least, have

been ‘freely negotiated between commercial men.’ The fact is that they have been imposed upon the contracting fraternity who were/are in no position to resist, after inadequate consultation and in the teeth of a gale of protest from

contractors and (it is rumoured) from consultant engineers and architects, and

even some County Councils who are required to follow Government policy in this matter as required by the Department of the Environment and Local Government and the National Roads Authority.

POST SCRIPT

In addition, I strongly suspect that these time-bar clauses can be attacked on Constitutional grounds, but being a ‘blow-in’ of a mere 18 years call to the Bar

of Ireland, it is, perhaps, not for me to be the first to adduce such arguments

and for the purposes of this seminar, at least, I have regarded them as outside my remit.

Michael Stimpson

7th February 2009

Page 43: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

43

CONSTRUCTION LAW

BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Anthony Hussey Saturday 7th February 2009

THE NEW PUBLIC SECTOR CONTRACTS

INTRODUCTION

The New Public Sector suite of contracts essentially comprises five forms, a Building

Contract based upon Employer’s Design, a Building Contract based on Contractor’s

Design, a Civil Engineering Contract based on Employer’s Design, a Civil Engineering

Contract based on Contractor’s Design and a Minor Works Contract. This paper

addresses issues which are common to the first four of these.

It is important to say at the outset that in so far as I am critical of these contracts, and

in particular the transfer of risk from the employer to the contractor, that criticism for

the most part relates to the standard contract where the employer is responsible for

the design and the contractor is responsible for the execution of the works. It is clearly

appropriate that there be a greater transfer of risk to the contractor where the

contractor is himself responsible for the design of the project.

The stated purpose of the Department of Finance in relation to these new contracts is

to “introduce lump sum fixed price contracts which will bring cost certainty and value

for money to the complex process of procuring and contracting and project managing

public works contracts”. These contracts seek to achieve this purpose through the

following means:-

1. They are fixed price lump sum contracts;

2. Many of the contractual risks which are traditionally borne by the Employer now

pass to the Contractor.

Page 44: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

44

3. The Contractor’s ability to make claims is restricted by the introduction of

stringent procedural requirements compliance with which is a pre-requisite to

any successful claim.

4. More responsibility for contract management and administration will move from

the Employer’s Representative to the Contractor.

The new forms are to be welcomed in certain respects. The standard forms currently in

use (primarily GDLA and IEI Third / Fourth Editions) are substantially out of date with

the result that public and private Employers, except in relation to very minor works,

have been incorporating by way of amendment to the standard forms many and varied

new provisions with a view to taking account of recent legislation and modern

practices. In so far as these contracts address such issues they are to be welcomed. In

so far as they will require Contractors to operate contracts far more efficiently, this too,

certainly in the long term, is to be welcomed.

The wording of all five contracts is almost identical. Only minor changes are made to

distinguish civil engineering contracts from building contracts and design construct

contracts from construct only contracts. This is to be welcomed not only by the

industry but also by lawyers practising in the construction sector. The contracts

represent a one stop shop and the department has made it clear that these

agreements should not be amended. This is a vast improvement on the contracts

previously used. These comprised a variety of different contracts invariably heavily

amended.

BACKGROUND

Traditionally contracts of this nature are negotiated between the relevant government

agencies and representatives of the industry. A liaison committee was set up through

the Construction Industry Federation comprising representatives from the RIAI,

Engineers Ireland, contractors, quantity surveyors etc. This liaison committee

commenced negotiations for a new contract with the Department of Finance several

years ago. The Department took a very hard line in these negotiations. This was

because the Government of the day was being criticised by the media and others for

allowing roads and other contracts to overrun. The public could not understand why

contractors were being allowed to finish contracts long after the anticipated completion

date whilst at the same time being paid hugely increased prices. It was calculated that

in civil engineering contracts the ultimate price was approximately 40% on average

above the anticipated price.

Many civil engineering contracts take several years to complete from the date of

tender. The government agencies did not explain to the media that the main causes

for the increased cost and delay were:-

Page 45: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

45

a) Changes to the contract works instructed after commencement (variations);

b) The cost of inflation (price variation) which is normally allowable in contracts of

this nature;

c) Delays caused by factors for which the employer would be contractually

responsible.

The perception was that contractors were running rings around the contracting

authorities and making a fortune in the process.

The fact is that the Irish construction market, right through the days of the celtic tiger,

and before, has always been extremely competitive. A search in the companies office

on the major contractors will reveal that on average profit is about four or five percent

of turnover. Now that the economic climate has changed and there are so few projects

available, contractors are tendering for these at well below cost. If therefore the

intention was to obtain “value for money”, the reality was that the State was already

receiving value for money and would in the course of events receive even better value

for money irrespective of the introduction of these contracts.

In any event, the unwillingness of the Department of Finance to compromise led to the

Department abandoning the process of negotiation and employing A&L Goodbody

solicitors to draw up new contracts from scratch. The contracts are quite unique in that

regard. They are unashamedly biased in favour of the employer.

RISK TRANSFER

Traditionally the Employer in construction projects has borne the risks which cannot be

foreseen or accurately estimated in terms of cost. This has always been considered fair

given that the Employer has chosen to undertake the project and the site is owned by

the Employer. If therefore it transpires that there is a problem with the site, which the

Contractor could not reasonably have foreseen, it seems appropriate and fair that the

Employer would meet the cost of overcoming the difficulty.

Dr. Nael Bunni, apart from being Ireland’s most eminent international arbitrator, is a

well known expert in the field of construction contracts. He has written extensively on

the FIDIC forms of contract, upon construction contract insurance clauses and other

complex issues. In the January 2009 edition of the International Construction Law

Review he analyses what he regards to be the four criteria of risk allocation in

construction contracts with particular reference to judicial precedent. In this interesting

article he argues that the Courts make assumptions as to where the risk should fall in

Page 46: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

46

construction contracts and that the risk should not be lightly re-allocated. These

assumptions are based on the following criteria:-

1. Which party can best control the risk and / or its associated consequences?

2. Which party can best foresee the risk?

3. Which party can best bear that risk?

4. Which party ultimately most benefits or suffers when the risk eventuates?

I would ask you to bear these questions in mind when considering the risks allocation

set out below. I don’t propose to deal with the analysis in any way because once the

questions are asked with reference to any particular risk, the answer suggests itself. In

essence Dr. Bunni suggests that risks which the contractor cannot control and which

cannot be insured against should be allocated to the employer. Although the article

was not written for the benefit of an Irish audience in particular, the author cannot

resist mention of these new government contracts in respect of which he describes the

allocation of risk in terms of “faulty concepts”.

GROUND CONDITIONS

Much of the work carried out in relation to civil engineering contracts is underground

or underwater. The difficulty encountered with ground conditions varies enormously

from project to project and from one depth to another. The contractor is usually given

some information by way of a site investigation report. The traditional forms of civil

engineering contracts provide that the contractor will be entitled to be paid the

additional cost incurred by him by reason of the ground conditions being materially

different to those he could have reasonably foreseen. All of the other risks I am going

to mention are automatically passed to the contractor under these new forms of

contract. This particular risk is an optional one. If the contracting authority ticks one

box in the tender documents the risk will pass to the contractor, otherwise it will not. I

would confidently expect that in the vast majority of cases the risk will be allocated to

the contractor. This is a risk which the contractor cannot control. Any attempt to put a

price against it is a gamble. Modest profit can translate to a very substantial loss if

unexpected ground conditions are encountered.

FIXED PRICE RISK

The new contracts contemplate a fixed price period of thirty-six months including a six

month lead in time. This in effect eliminates the price variation head of claim.

Page 47: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

47

CONSENT & AUTHORISATION RISK

Under most standard contracts the Employer is obliged to obtain any necessary

planning permission and other authorisation or consent required by law. In the new

forms of contract the position is reversed. The Employer is now to furnish details of

such consents, permissions and authorisation as it has identified in a contract as being

the responsibility of the Employer. The securing of all other consents, permits etc.

becomes the Contractor’s burden. This places the onus on the Contractor to fully

familiarise himself with the site and all permissions and legal impediments relating to

it. This is an added area of risk and expense for the Contractor.

An example of how this might arise is provided by the events which occurred at

Carrickmines Castle some years ago. A national monument was located on the route of

the works. Specific procedures had to be followed to obtain departmental consent to

interfere with the castle or any part of it. The Contracting Authority had not obtained

this consent. The Contractor was delayed for a very long period of time but was

entitled to be compensated under the standard conditions of contract which applied.

Under the new form of contract the risk would be with the Contractor. Again this risk

has to be quantified and priced.

RISK ATTACHING TO LEGAL REQUIREMENTS

Under the new forms of contract, the Contractor is obliged to comply with all “Legal

Requirements”. This expression is defined as including any requirement which applies

to the works as a result of “the legal rights of any person” or as a result of a decision

of a court. Therefore if any person has, for instance, a right of way over the site, the

Contractor must respect that right of way even if he was not advised of it by the

Employer. There is no entitlement to compensation or extension of time arising from

delay resulting from a failure of the contractor to comply with all “Legal

Requirements”. However it is worth noting that if the observance of Legal

Requirements prevents the works being completed in accordance with the Works

Requirements then the Employer’s Representative is required to give an instruction

changing the Works Requirements and the Contractor would be entitled to be

compensated. An injunction restraining a contractor from working during permitted

hours because the work is judged to be excessively noisy would, as a result of this

provision leave the contractor with no remedy even if the excessive noise is

unavoidable by the nature of the works, for instance piling.

Page 48: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

48

DELAY & DISRUPTION RISK

Clause 9.4.2 states:-

“The Contractor has included in the initial Contract Sum and shall include in its

programme a contingency for delays to the Date for Substantial Completion of the

Works caused by Compensation Events”.

This is one of a number of provisions the effect of which will be to hugely discourage

the making of claims while at the same time ensuring that such claims as are made will

only succeed if they are absolutely genuine and are brought to the attention of the

employer as soon as the events giving rise to them occur. This provision is the most

innovative and ingenious of all the provisions contained in the contract.

Through this provision the contractor is deemed to have allowed in his tender price for

the cost of certain delays caused to him by the employer. The number of days involved

will vary from contract to contract but typically it might be fifty working days in a year

long contract. Delays caused by the employer in this context would include delays

caused by variations instructed by the employer and breaches of contract on the part

of the employer.

On the face of it, the clause cannot be considered unfair to the contractor. If anything

it is generous. If the contractor includes in his tender for the number of days he is

deemed to have included, and no such delays occur, he will have been paid for fifty

days of delay which never actually happened. The reality is however that in the

tendering process contractors will never allow for the full number of days they are

deemed to have included. Whether they do or not is to some extent beside the point.

The real benefit is that it discourages claims. A contractor is going to have to prove

that the first fifty days of delay are attributable to the employer before he will receive a

cent in compensation. This along with other disincentives will discourage claims.

One of those disincentives is that in tendering for the job the contractor will have been

obliged to nominate a compensation figure for the daily cost of delay. That cost,

through a mathematical formula is brought into the sum of his tender and may affect

the outcome. Therefore the tenderer who succeeds is likely to have nominated a very

low sum for his daily cost. Even therefore if he can prove delay in excess of the

threshold period, there will be no pot of gold at the end of the rainbow.

It is worth looking at an example as to how this would operate in practice. Suppose a

contractor has undertaken to complete a school building for €50milliion over a one

year period and there are liquidated damages payable to the employer of €10,000 a

week if he fails to do so. The employer decides to build on some extra rooms at a cost

of €300,000 and, because of the work itself and the lateness of the change this delays

Page 49: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

49

the contract by seventy working days. The contractor has set his delay costs in his

tender at €2,000 a day. Finally let us suppose that the threshold period deemed to be

included in the contractors tender price and programme is forty days.

The good news is that the tenderer gets paid for the full price of the variation at

€300,000. However in so far as he has been delayed by seventy days he will get no

compensation for the first forty of these. He will be compensated at the reduced rate

provided for in the contract for the next thirty days but as against that he will have to

pay the employer liquidated damages for forty of the seventy days of delay in

completion. This is because he is deemed to have included that extra period of time in

his programme for completion of the contract and therefore is not entitled to any

extension of time for delays caused by the employer in that period.

Therefore for his seventy days of delay, the contractor is paid €60,000 i.e. €2,000

multiplied by thirty days. On the other hand he has to pay the employer liquidated

damages for approximately six weeks at €10,000 per week. He is therefore not

compensated at all for the delay.

(The above example is simplified and is therefore inaccurate as to the number of days

to be allowed or disallowed by reason of the contract providing for two thresholds

rather than one but that inaccuracy does not impact upon the principle of the point

being demonstrated).

CLAIMS

If the Contractor considers that he is entitled to an extension of time or to any

additional sum, he is obliged to make his claim as soon as practicable and in any event

within twenty working days after he becomes aware of it, or should have become

aware of it. The notice must prominently state that it is being given under clause 10.3

of the contract. There can therefore be no fudging of claims. Either the Contractor

complies with this procedure and puts the Employer clearly on notice or he loses the

entitlement to claim.

Within a further twenty working days the Contractor is obliged to submit all relevant

facts concerning the claim, a detailed calculation of the quantum together with any

further information requested by the Employer’s Representative.

If the circumstances giving rise to the claim have a continuing effect the Contractor is

obliged to update this information on a monthly basis.

In the context of claims, it is to be noted that by virtue of a rather unusual provision

the Contractor is obliged, if requested, to provide the Employer’s Representative with

all information, documents and records in the Contractor’s possession that the

Page 50: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

50

Employer’s Representative requires to perform his functions and powers under the

contract – which would include assessing the claim. In effect this is the equivalent of

the Contractor having to make full discovery, in a legal context, of all his documents if

required to do so by the Employer’s Representative even at this very early stage.

Clause 10.3.2 provides:-

“If the Contractor does not give notice and details in accordance with and within the

time provided in this sub-clause 10.3……..the Contractor shall not be entitled to an

increase to the Contract Sum or extension of time…….and the Employer shall be

released from all liability to the Contractor in connection with the matter”.

Therefore not only is compliance with the requirement to give notice a condition

precedent, so too is the requirement to provide follow up details.

PROGRAMMES & PROGRESS REPORTS

At the outset the contractor has to submit a hugely detailed programme. If the

contractors programme no longer corresponds with actual progress the Employers

Representative may insist upon a new programme being produced and this must be

done within fifteen days.

The contractor is obliged to provide the employers representative with monthly

progress reports throughout the term of the contract. These reports are hugely

detailed and must include “anything relevant to a progress report that the Employers

Representative directs”. The provision of such programmes and progress reports

should have the effect of hugely increasing the administrative burden on both the

contractor and the employers representative. This should lead to greater efficiency on

the part of both because the cause of any claim is likely to be far more transparent,

and this is not a bad thing. In the broader sense however these requirements are likely

to act as disincentives to the making of claims and in particular dubious claims. A

contractor can be reasonably certain that the employers representative will insist upon

the fullest possible information and vouching when a claim is made.

It is to be noted that the employer is entitled under this form of contract to hold back

fifteen percent of any sum due to the contractor if there is any delay on his part in

producing such a programme or report.

TERMINATION

The termination clauses contain some unusual provisions. The contract provides for

voluntary termination by the Employer at any time. This may not be availed of by the

Employer if his intention is to continue the work with another Contractor. In the event

Page 51: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

51

of voluntary termination the Contractor is entitled to no damages such as loss of profit

but is merely entitled to the value of work done up to termination, the cost of

demobilisation and some other direct costs.

The contract also provides for termination by reason of the Contractor’s default. Some

of these grounds for termination are very wide. For instance the contract may be

terminated if the Contractor has committed a breach of the Safety, Health & Welfare at

Work Act 2005 or any regulations made thereunder. The provision does not state that

the breach has to be a serious one and in so far as other breaches are qualified by the

word “serious” it could be argued that any breach, even the most minor, of health and

safety requirements will justify a termination.

These provisions, although unusual, are not unique. What is unique is the use of

conciliation with reference to the employers wish to terminate the contract for the

contractors default. If the Employer wishes to terminate the contract by reason of a

Contractor’s breach, he may refer the issue of whether he is entitled to do so or not to

a Conciliator. If the Conciliator decides that the Employer is so entitled and the

contract is then terminated, the Contractor is entitled to have the issue reopened in

arbitration. However the contract specifically provides that in these circumstances if

the arbitrator ultimately decides that the Employer was not entitled to terminate, the

Contractor will, nevertheless, not be entitled to any damages or compensation by

reason of any breach of contract on the part of the Employer. Instead the Contractor’s

entitlements are to be confined to those which would have applied had there been a

voluntary termination i.e. value of works to termination and demobilisation costs etc.

The outcome of the arbitration between Uniform Construction and Limerick City

Council is in the public domain. The effect of the termination on Uniform was that it

could no longer work in the public sector. This is hardly surprising given that its bond

was in jeopardy and it was facing a huge counterclaim from Limerick City Council if the

termination was justified. Had that contract been regulated by these provisions,

Uniform’s only entitlement in its arbitration proceedings would have been a claim for

its demobilisation costs and other miscellaneous costs, assuming a Conciliator had

confirmed prior to termination that Limerick was entitled to terminate the contract.

Page 52: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

52

CONCLUSION

It is my view that these contracts are likely to achieve their goal of bringing contracts

home on time and more or less on budget subject to the effect of variations. They are

cleverly designed to discourage Contractors from permitting delays (even those caused

by the Employer) and from making claims. Contractors will be at a major loss if they do

not adequately price for the transfer of risk, the loss of claims opportunities and the

extra layer of administrative personnel required. In today’s economic circumstances,

there is no doubt that contractors are not adequately pricing for the additional level of

risk. On the contrary, prices being submitted under these new forms of contract are

actually lower than the prices that were being submitted under the old contracts which

did not contain the same risks. This is partly as a result of the economic climate and

partly as a result of contractors not fully understanding the risks involved.

The contracts contain many provisions relating to such matters as the final account,

novation and collateral warranties. Whilst these may be of interest to certain

audiences, they are not likely to be of much interest to this audience. I have confined

my paper to those areas which I think might be of particular interest to lawyers

engaged in or wishing to become engaged in construction disputes and issues.

Page 53: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

53

CONSTRUCTION LAW

BAR COUNCIL CONFERENCE, DISTILLERY BUILDING

Paper by John Trainor SC Saturday 7th February 2009

ARBITRATION PROCEDURES UNDER THE NEW GOVERNMENT CONTRACTS

Introduction

1 The dispute resolution process in building and civil engineering contracts

usually culminates at arbitration. Until recently, most Public Works Contracts

were carried out pursuant to the IEI Conditions of Contract which specifically

imported the most recent IEI arbitration procedure. However, the new Public

Works Forms of Contract, required for all Public Works Contracts since 13th

February 2008, now import the Public Works and Services Arbitration Rules

2008. As of the date of writing, it is believed that no arbitrations have yet

taken place under these Rules involving the New Forms of Contract, no doubt

because such contracts are still in their early days, and the Dispute Resolution

Process set out in Clause 13 of the New Forms provides for a detailed

conciliation procedure which may be first undergone prior to proceeding to

arbitration under Clause 13.2.

2. However, it can be expected that such arbitrations will inevitably, in due

course, find their way to construction professionals and advisers. It is thus

appropriate to examine the Rules, and to consider them generally in the

context of the management of the Arbitration process. But a few introductory

observations are relevant.

3. The New Government Contracts lay a heavy emphasis on the need for a timely

flow of information between the Employer’s personnel and the Contractor’s

Page 54: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

54

personnel, and create specific obligations in the nature of pre-conditions in

relation to the giving of Notices. For example, under Clause 10.3, a Contractor

seeking an extension of time (or, indeed, any other entitlement) must give

timely notice, and thereafter must give the Employer’s Representative all

relevant facts about the claim, a detailed calculation, and, so far as practicable,

a proposal based on that calculation, of any adjustment to be made for the

contract sum, or of any other entitlement. The Employer’s representative, in

reply, is required to make a determination on the claim, and to notify the

Contractor and Employer accordingly. If the Contractor disagrees with the

decision of the Employer’s

Representative, thus giving rise to a “dispute”, either party may refer the dispute for

conciliation, in the course of which the parties are required to “….promptly make

available to the Conciliator all information, documents, access to the site and

appropriate facilities…”.

4. Accordingly, it is likely that, by the time the dispute has made its way to

Arbitration, all the relevant issues, documents, arguments etc will have become

well identified. It is likely that the scope, if any, for the introduction of new

arguments, (or to argue for a given outcome from a different perspective) will

be limited. It may be that it will be more likely that the issues that will give

rise to Arbitrations will concern fundamental issues as to contract construction

or interpretation, or the extent to which the Contractor may be bound by

information (or the lack of it) provided at tender time by the Employer, or

factual disputes where the parties are simply not in agreement as to what

transpired.

5. In general, members of the legal profession may not currently be up to date on

how the new Government Contracts are working out in practice. In contrast,

most construction professionals have been receiving briefings and “road shows”

on these Contracts for the past 2 years. Some professional organisations

(such as the Chartered Institute of Arbitrators (Irish Branch)) have been

conducting courses with a view to accrediting Conciliators for the purposes of

securing appointments pursuant to Clause 13. But Lawyers, and members of

the Bar, in particular, with proven advocacy and contract construction skills are,

Page 55: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

55

arguably, ideally placed for appointment when construction disputes do reach

the Arbitration stage.

6. The new Government Contracts, as to their wording, have no direct precedent.

There is thus no settled or judicially approved construction of any of the

Clauses. It is likely, accordingly, that all of the main contentious areas of the

Contract will fall for construction at Arbitration in early course.

7. Although activity in the construction sector generally is down (the DKM Review

of the Construction Industry for 2007 and its Outlook for 2008-2010 (dated

September 2008)) reported overall fall of 23% of construction output for 2008),

public sector new construction output rose by 14% in 2008. Overall

investment in productive infrastructure projects is expected to increase in

volume terms by over 8%, led by a substantial increase in airports (71%) and

public transport (16.5%)), while construction-related investment in social

infrastructure projects rose, in 2008, by over 12%. Despite the drastic

collapse in the public finances, the draft Framework Agreement announced on

January 29th last confirmed the Government’s intention to provide a fiscal

stimulus in 2009 and 2010 by maintaining capital investment at a higher level

by both international and historical standards, with re-prioritisation of this

capital expenditure in 2009 and 2010 in order to support labour-intensive

activities where possible. All this points to a Government intention to maintain

expenditure on important capital projects, with regard to which the new

Government Contracts will be of central importance. However, given the

extreme need to control public expenditure on the one hand, coupled with the

inevitable fact that Contractors will be likely to be pressurised into the need to

make claims to recoup additional expenditure, all points to an impending boom

in growth in construction disputes.

8. The New Government Contracts themselves, ironically, encourage the

progression of disputes to Arbitration, since the conciliation provisions under

the Contract provide that, where a Conciliator has recommended the payment

of a sum of money (which will usually be to the Contractor) and a Notice of

Dissatisfaction is given (most usually by the Employer, though possibly by

both), the party recommended to pay by the Conciliator is obliged to make the

Page 56: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

56

payment in question provided only that the other party firstly gives a Notice

referring the dispute to Arbitration, and also provides a bond for the amount of

payment. The Training Manual published by the Department of Finance in

February 2007 (reissued May 2008) commenting on the then draft form of

Public Contracts, (which required a bond only to be provided as a precursor to

payment), drew attention to the fact that, once a Contractor has received a

payment under a Conciliator’s award, he may be content not to pursue a

subsequent Arbitration; alternatively, he might not wish to be seen to be the

Claimant in such an Arbitration. The training course recommended, from the

Employer’s point of view, that it would be essential that the Contractor be the

Claimant in the Arbitration, since, otherwise, it would become evident to the

Arbitrator that a payment had been made on a Conciliator’s recommendation.

The current form of Government Contract presently in circulation now obliges a

party taking payment under a Conciliator’s recommendation, to be the party to

serve the Notice to Refer. Since, as we will see below, the Notice to Refer

under the 2008 Rules is intended, in effect, to comprise a full Statement of

Claim, to which the Respondent is in due course required to file a Defence, it

follows that the Contract provisions for conciliation, far from encouraging a

resolution of the dispute (such as might happen were the Contractor to decide

to accept the payment recommended), actually forces the Contractor to

arbitrate.

9. It is not surprising, in one sense, that, in conjunction with the introduction of

the new Contracts, the Department of Finance, has caused new arbitration

rules to be prepared. The new Government Contracts appear to be sui

generis. They are not merely a development of either the IEI 1980 Conditions,

nor the RIAI Conditions. They do not lean upon, or draw from, Conditions of

Contract proposed by any particular professional body. In this context, it is

not surprising that the Arbitration Procedure 2000 (promulgated by the

Institute of Engineers of Ireland, and thus capable of being perceived as

leaning towards the needs and requirements of that body), should be replaced

by new procedures not capable of being perceived as derived from any

particular source.

Page 57: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

57

10. Although Arbitrations can be carried out satisfactorily without the incorporation

of Procedural Rules (by adopting the statutory formalities, and ensuring natural

justice), there is no doubt that the existence of Procedural Rules greatly

facilitates the smooth running of the arbitral process. Procedural Rules

frequently make provision for matters going beyond the requirements and

entitlements set out in the Arbitration Acts (in this regard Rule 23.4 of the 2008

Procedure expressly provides that the powers of the Arbitrator under those

Rules are “…additional to the powers of the Arbitrator and the Court under the

Arbitration Acts 1954 – 1998”). In the United Kingdom, the JCT Contracts

expressly incorporate the Construction Industry Model Arbitration Rules

(CIMAR), along with the JCT additions to them (see “Emdens Construction

Law”, Binder 3 p.53). International Arbitrations are frequently conducted

under the ICC Rules of Arbitration.

Commencement of Arbitration and the Notice to Refer.

11. An Arbitration is commenced under the 2008 Rules by one of the parties giving

to the other a Notice to Refer the dispute to a sole Arbitrator in accordance

with the Contract and the 2008 Rules.

12. Importantly, under Rule 2.2, no party may disclose to the Arbitrator anything

said or done at any previous conciliation, its outcome, or, (except in

proceedings dealing with interest), any payment made under a Conciliator’s

recommendation. All this is consistent with previous provisions concerning

conciliation.

13. Under Rule 4.1, the Notice to Refer is required to:-

- State the names, addresses and telephone numbers of the parties to

the Contract;

- Expressly state that it is a Notice to Refer a matter to arbitration;

- Contain particulars of the nature of the claim and the facts supporting

the claim, and an indication of the amount in dispute, if any, and

Page 58: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

58

- Contain particulars of the relief or remedies sought.

14. Under the IEI Arbitration Procedure 2000, the Notice to Refer is a far more

general document, and is merely required to “…list the matters which the Party

serving the Notice to Refer wishes to be referred to Arbitration”. Under Rule

2.3 thereof, it is expressly provided that “…nothing stated in the Notice to Refer

shall restrict that party as to the manner in which it subsequently presents it

case”. Subsequent to the Arbitrator’s appointment under the I.E.I. Procedure

2000, either party could refer further disputes or differences to the Arbitrator

by serving additional Notices to Refer.

15. Under the 2008 Arbitration Rules, the Notice to Refer appears now intended to

operate in a much more fundamental manner than under the 2000 Procedure,

and appears intended, in effect, to incorporate the Claimant’s Statement of

Case, as traditionally understood. Thereafter, under Rule 11.4 of the 2008

Procedure, within 30 days after receipt of the Notice to Refer, or 14 days after

appointment of the Arbitrator, whichever is the later, the Respondent is

required to send a written Statement of Defence, responding to the issues

raised in the Notice to Refer, and raising any other relevant issues, including

any Counterclaims that are to form part of the proceedings.

16. The Arbitrator may extend the time for sending the Statement of Defence to

allow the Respondent a reasonable time to prepare it, having regard to the

quantity, quality and timing of information given to the Respondent by the

referring party in, or before, the Arbitration.

17. It should be noted that, under Rule 13, the Arbitrator has the power to decide

all procedural and evidential matters, including:-

- The adequacy of the Notice to Refer and Defence and the extent to

which they can be later amended;

- Whether the Arbitrator requires further written statements from the

parties in addition to the Notice to Refer and Defence, and when those

Page 59: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

59

statements are to be provided, being, if possible, directed to be

provided within 30 days of the date of the direction;

- And a number of other procedural matters which we will come to below.

18. Given that, under the 2008 Procedure, the Notice to Refer is effectively a

Statement of Case, Claimants would be well advised not to serve a Notice to

Refer until full particulars of the claim have been collected and prepared.

Construction professionals intending to prepare a Notice to Refer under the

2008 Procedure should ideally ensure that, before settling the document they

have:-

- Taken full instructions from the Claimant;

- Collected all relevant documents that would support the claim;

- Ideally, prepared a chronology whereby their instructions can be pinned

to dates and documents;

- Ascertained the availability of the relevant witnesses, and ascertained

what those witnesses would be likely to say (including, ideally, obtained

draft witness statements);

- Identified the issues upon which expert evidence will be required, and

confirmed the availability of such expertise and the views which such

experts will opine;

- Carefully quantified the loss and other relief to be claimed. This may

require careful quantification of the amounts to be claimed in respect of

additional remuneration, extensions of time, and, where applicable, any

other relief.

19. While, under the 2008 Procedure, the Notice to Refer would appear to require

to be laid out as though it was a Statement of Case under the IEI 2000

Procedure, it should also be noted that there appears to be no express

requirement under the 2008 Rules for documentation to be appended thereto.

Under the Arbitration Procedure 2000, Statements of Case are required, to the

extent directed by the Arbitrator, to include a summary of the case of each

party, a summary of their evidence, a summary of the issues between the

parties, a list and/or a summary of the documents relied upon, any points of

law (with references to any authorities relied upon), a statement or summary of

Page 60: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

60

any other matters likely to assist the resolution of the disputes, along with any

other documents or statements that the Arbitrator might consider necessary. It

was quite usual for Statements of Case under the 2000 Procedure to therefore

comprise lengthy documents with very voluminous tabbed appendices

comprising extracts of all the key documents to be relied upon by the party

concerned.

20. The new 2008 Procedure appears to envisage a more expedited process

whereby, in effect, matters do not go to the Arbitrator until the referring party

has first prepared a Notice to Refer with the same degree of requisite detail as

a Statement of Claim. Only then may the Arbitration be commenced.

21. One consequence of the detail with regard to which the Notice to Refer is

intended to be prepared would appear to be that it may not be easy for the

referring party to significantly add new issues to the Notice to Refer at a later

stage. The provisions contained in the Arbitration Procedure 2000, allowing

for the reference of further disputes or differences to the Arbitrator, through

the service of an additional Notice to Refer, before the completion of his

appointment, appear to be absent from the 2008 procedure.

22. The requirement for the Notice to Refer to contain the detail stipulated in Rule

4 of the 2008 Procedure is not surprising, and should not provide a difficulty to

referring parties, since nothing will usually be referred to Arbitration until it has

first undergone the conciliation procedure set forth in Clause 13.1 of the new

Contract Conditions. This conciliation procedure envisages very extensive

disclosure to the conciliator of all relevant facts and documents. Under Rule

13.1.3, the parties are each initially required to send to the Conciliator “brief

details of the dispute” setting out the contentions advanced by each party and

identifying the rights and obligations relied upon in support thereof. The

parties are then required to make available to the Conciliator all information

and documents, along with access to the site and appropriate facilities, as the

Conciliator may require. Thereafter the Conciliator is entitled to consult with

the parties. He may meet with the parties, and he may conduct investigations

in the absence of the parties, or make use of specialist knowledge, and obtain

technical and legal advice and establish the procedures to be used in the

Page 61: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

61

conciliation. Thereafter, if the dispute is not resolved by agreement, the

Conciliator gives both parties a written recommendation. Only if a party is

dissatisfied with the Conciliator’s recommendation, does the option of

Arbitration thereafter become possible. Further, as we will see below, the new

forms of Contract actually appear designed to force Contractors, who may be

entitled to compel payment under a Conciliator’s recommendation from the

Employer, to themselves initiate the arbitrations, in which they would have to

be the Claimants, (even where they do not wish to do so), but where they can

be compelled to do so as a condition of receiving the payment recommended

by the Conciliator.

23. Against a background where the issues in dispute will normally have been well

ventilated between the parties at conciliation, it is submitted that there should

be no great injustice caused to the referring party by requiring them to compile

the Notice to Refer, required to commence an arbitration under the 2008

Procedure, with the same sort of detail as might be required by a Statement of

Claim, and the relevant factual information should normally be readily available

to the drafter.

The Key Requirement of Efficiency under the 2008 Procedure

24. Arbitrators have always been required to conduct their proceedings with due

regard to efficiency, and with a view to minimising the costs of the parties.

The Arbitration Procedure 2000 contained an admirable statement in this

regard:-

“The objective of arbitration is to obtain the fair resolution of disputes

and differences by an impartial and independent Arbitrator without

unnecessary delay or expense. The Parties and the Arbitrator shall do

all things necessary to achieve this objective. The Arbitrator shall give

each party a reasonable opportunity of putting its case and dealing with

that of its opponent. This procedure shall be interpreted and the

proceedings shall be conducted in a manner most conducive to

achieving these objectives”.

Page 62: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

62

25. It is to be hoped that Arbitrations carried out under the 2008 Procedure will

adopt a similar approach to the Arbitration Procedure 2000, which appeared to

attach equal priority to the three requirements of (i) “obtaining a fair resolution

of disputes”, (ii) “by an impartial and independent Arbitrator”; and (iii) “without

unnecessary delay or expense”.

26. However, it is at least arguable that the 2008 Rules attach greater importance

to the need for dispute resolution to be expeditious and at minimal cost. It is

hard to imagine that these requirements could be intended by the 2008 Rules

to be achieved at the cost of any impairment to the fairness of the process.

However, there is no doubt that the 2008 Rules do provide ammunition to a

party seeking to have the process expedited in priority to all other requisites.

For example:-

- Under Rule 10.1 it is provided that:-

“The Arbitrator shall at all times seek to move the Arbitration Process

forward as quickly and efficiently as possible”.

- Under Rule 11 point 8 it is provided that, in relation to the directions

which the Arbitrator may issue at the preliminary meeting:-

“Whether or not the short procedure applies, any directions should be

aimed at achieving an early resolution of the matters in dispute and to

keep the costs of the arbitration to a minimum”.

27. The 2008 Rules therefore attach a premium to the saving of cost and efficiency.

This is not surprising. The underlying rationale of the New Public Works

Contracts is to reduce cost and promote certainty in the construction process to

ensure better value for the Exchequer. It is therefore not surprising that the

2008 Rules, prepared in conjunction with the Public Works Contracts, should be

specifically tailored to ensure that the Arbitration stage, when reached, be

conducted as quickly and efficiently as possible. There is no doubt that this is

a beneficial development. Those familiar with construction arbitrations

generally will be aware that they tend to be both very lengthy and very costly,

factors that often result in the parties, having exhausted all resources of money

and patience, eventually resorting to compromise as the only means of

Page 63: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

63

escaping from what can often seem like a form of eternal purgatory. Anything

that encourages Arbitrations to be conducted with greater speed and efficiency

is therefore to be welcomed. As in all other matters connected with litigation,

speed and efficiency favours the party best prepared for the process.

Appointment of, and challenge to, the Arbitrator

28. Under the 2008 Rules, it is provided that, at the same time as serving the

Notice to Refer, the referring party is required to propose the name of one or

more persons to act as Arbitrator. Within 14 days, the Respondent is required

to either agree to the appointment of the Arbitrator proposed by the referring

party, or propose alternatives, in which case the referring party must either

agree one of the alternatives or notify its disagreement with all. If an

Arbitrator has not been agreed within 28 days after the Notice to Refer was

given, any party may apply to the nominating body named in the Contract to

nominate the Arbitrator.

29. As of May 2008, the Department of Finance had approved a number of

professional bodies to be the nominating bodies named in the Contract. The

approved professional bodies are:-

- The Bar Council of Ireland;

- The Chartered Institute of Arbitrators – Irish Branch;

- Engineers Ireland;

- The Law Society of Ireland;

- The Royal Institute of the Architects of Ireland.

- The Society of Chartered Surveyors.

30. By approving a number of additional professional bodies, the Government has

removed what might have been perceived as the monopoly right of the

President of the Institute of Engineers of Ireland to appoint Arbitrators as, for

practical purposes, was the case prior to the introduction of the new

Page 64: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

64

Government Contracts. The approval of a variety of professional bodies also

has distinct advantages because, approaching the matter on a contract-by-

contract basis, the Employer (whichever Local Authority or State Body might be

involved), might wish to consider whether or not, in the context of a Building

Contract, the Conciliator or Arbitrator should definitely be an Architect, in which

case he might feel it appropriate to utilise the RIAI as the appointing body.

This would result in the appointment of an Architect as the Conciliator or

Arbitrator. Alternatively, in the case of a civil engineering project, the

Employer might take the view that the Conciliator and Arbitrator should be an

Engineer, in which case Engineers Ireland should perhaps be the appointing

body. Likewise, the Chartered Institute of Arbitrators – Irish Branch, or one of

the other bodies listed above, might be the preferred option if neither of the

above areas of expertise was required. For instance, if the dispute were purely

a quantity surveying issue, then the Society of Chartered Surveyors might be

more appropriate.

31. In the context of the audience to whom this paper is primarily addressed, it is

clear that there is great potential for the Bar Council of Ireland to lobby for

appointment as the nominating body in the new Government Contracts.

32. However, if the Bar Council is to be successful in this regard, it is submitted

that it will need to demonstrate an ability to provide a shortlist of suitably

qualified Arbitrators, with the required degree of experience and expertise in

construction

law. The Bar Council, in this regard, will have to engage in direct competition

with the lobbying which is undoubtedly already taking place on behalf of the

other nominating bodies. It must be remembered that, in particular,

organisations such as the Chartered Institute of Arbitrators – Irish Branch, and

Engineers Ireland have well-established panels of very experienced and

qualified persons suitable for appointment as Arbitrators. Applicants seeking

inclusion on the panels of such bodies have to demonstrate appropriate

qualifications and detailed experience and expertise. To secure success in this

field, it is submitted that the Bar Council will have to establish its own panel of

suitably qualified Arbitrators from amongst its ranks, comprised of persons with

Page 65: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

65

appropriate arbitration expertise and qualification, with a proven track record of

expertise and involvement in construction disputes.

33. Once an Arbitrator has been agreed or nominated, either party may write to

him seeking confirmation of his willingness to act, enclosing two copies of the

Notice to Refer, along with a copy of the Contract, copying all documents to the

other party.

34. If, within 14 days after such letter has been sent, the nominee notifies the

sender of his acceptance of appointment as Arbitrator, that party must

immediately notify the other party, and the nominee thereupon stands

appointed, and has jurisdiction “…over all issues connected with and necessary

to the determination of the dispute.”

35. If the Nominee does not accept within the stipulated time, either party may

apply to the nominating party to make a further nomination, and the process

will start again.

36. Within 14 days after his accepting his appointment, the Arbitrator is required to

send to the Department of Finance, National Public Procurement Policy Unit,

notice of the appointment, along with one of the copies of the Notice to Refer

sent to him or her.

37. The 2008 Procedure, accordingly, will operate to alert the Department of

Finance, National Public Procurement Policy Unit, of the existence of all

Arbitrations under the new Contracts at a very early date. This provision of

the 2008 Procedure has to be read in conjunction with Rule 17.2 whereby,

within 14 days of having sent an award to the parties, the Arbitrator is required

to also send a copy of the Award, likewise, to the Department of Finance,

National Public Procurement Policy Unit.

38. In the ordinary way, Arbitration is a confidential private process (indeed, under

Rule 17.4, an award may be made public only with the consent of all parties or

as required by law or as permitted by the Contract). Individual Contractors,

contemplating an Arbitration, may not fully appreciate the extent to which the

Page 66: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

66

issue under Arbitration may already have been the subject of earlier Rulings.

No doubt, the Department of Finance will ensure that all Public Body Employers

are rapidly appraised of the effect and import of the findings in earlier

Arbitrations. Arguments deployed in such earlier Arbitrations may then

possibly be deployed against the Contractor involved in the instant Arbitration,

to his disadvantage. It may be that legal advisers involved in procuring earlier

successful Arbitration outcomes will be recommended for deployment against

the Contractor in any new Arbitration involving the same point. In contrast, in

all likelihood, the Contractor in such new Arbitration may find himself without

any convenient means of ascertaining whether or not the point has been

considered before, or if so, to what effect.

39. It is submitted that there may be a potential danger that nominating bodies

responsible for the appointment of Arbitrators, who may have regularly made

findings contrary to the interests or expectations of Employers, may find

themselves “sidelined” in the context of any future appointments as nominating

bodies. Further, it is not clear whether or not the Department of Finance

intends, in the future, to prepare annual or periodic reports on such arbitral

results. Indeed, one possible outcome here may be that arbitral awards, from

time to time, (particularly where findings in favour of the Contractor are made),

may be reflected in future amendments to the new forms of Contract intended

to further protect and better the position of Employers. It is submitted that

better equality of arms, in this regard, might have been provided by requiring

Arbitrators also to furnish their awards to Contractor’s representative bodies,

such as the Construction Industry Federation, possibly subject to suitable

redaction to prevent immediate identification of the contracting parties.

40. Before accepting appointment, the Arbitrator is required under Rule 7 to notify

the parties of any circumstances that might give rise to “…any justifiable doubts

about the Arbitrator’s impartiality or independence”. The Arbitrator is under a

continuing duty to disclose any such circumstances that may arise during the

period of his appointment. The use of the words “…any justifiable doubts…”

would here appear intended to exclude notional or hypothetical concerns which

an Arbitrator might think could remotely be regarded as giving rise to doubts

about his impartiality or independence. This would appear to exclude any

Page 67: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

67

remote issues which only the most paranoid litigant would consider likely to

impede an Arbitrator’s impartiality or independence. However, no doubt,

Arbitrators will, in the future, as in the past, continue to err on the side of

caution here and disclose any matter that might conceivably cast any doubt on

his or her impartiality. Once an Arbitrator proceeds cautiously here, it is

submitted that the higher threshold of disclosure required by Rule 7 would be

likely to amply cover any disclosure actually made, and, more importantly, the

non-disclosure of any more extreme or paranoid matter or issue that might

have been, but was not, disclosed.

41. Under Rule 8, a party may challenge the appointment or continuation of an

Arbitrator if circumstances exist “…that give rise to justifiable doubts about the

Arbitrator’s impartiality or independence”. There is ample jurisprudence in

Ireland as to the circumstances which would be regarded as raising a justifiable

question mark over the impartiality or independence of a judicial figure, and it

is not proposed to discuss these in detail in this paper. The use of the word

“justifiable” in relation to “doubts” again clearly emphasizes the intention of the

2008 Rules to ensure that fanciful or contrived doubts will provide no basis for

the removal of an Arbitrator.

42. If the Arbitrator has been appointed by agreement between the parties, no

subsequent challenge to his appointment can be made save for circumstances

of which the challenging party became aware after the appointment was made.

A challenge can only be made in writing, and must be sent to the Arbitrator and

each other party within 21 days after the party raising the challenge became

aware of the justifiable doubts. Any challenge, in writing, must state the

reasons justifying the challenge. If a challenge is made, then, if either both

parties agree, or if, on the application by a party, the nominating body so

decides, the Arbitrator shall forthwith resign and a replacement Arbitrator is to

be appointed in accordance with the Rules. Importantly, if the parties do not

agree, or the nominating body dismisses the challenge, the Arbitration must

proceed. Under Rule 9.4 any replacement Arbitrator under Rule 9 is

empowered to determine the procedure for taking matters forward, and is

entitled to decide whether it is necessary to repeat any hearings previously

held. Given that, in almost every case, the Arbitrator will be required to make

Page 68: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

68

findings of fact which, will require, to some degree or other, his own personal

assessment of the witnesses in question, it is submitted that, in almost every

case where an Arbitrator is replaced, it will be necessary to repeat the hearings

previously held, and, in particular, for any oral evidence previously given to be

re-taken. Inevitably, this will involve further cost and delay, a delay likely to

be exacerbated by the fact that any new cross-examination will be assisted by

the transcripts of any evidence previously given, which could be put to the

witness whose evidence is being re-taken for the purposes of demonstrating

inconsistency with prior testimony. It is submitted that, in cases where

witnesses may be re-heard, the replacement Arbitrator should give

consideration to directing the parties to endeavour to agree matters in relation

to evidence previously given so as to ensure that the re-taking of such evidence

is confined only to the matters truly in dispute.

Preliminary Matters

43 Under Rule 11, the Arbitrator is empowered to conduct the Arbitration in any

way he considers appropriate subject to the 2008 Rules and the law.

44 Importantly, all documents and information given to the Arbitrator by one party

are required, at the same time, to be given by that party to all other parties.

No party (or person acting on its behalf) is to have any private communication

with the Arbitrator “relating to the substance of the matters in dispute”.

Notices and written communications may be sent by electronic means when

there is provision for this in the Terms of the Appointment of the Arbitrator, or

when agreed between the parties or directed by the Arbitrator.

45. These provisions in relation to communication would appear intended to rule

out the unilateral telephonic communications that have historically happened on

occasions in the past where Arbitrators would often take phone calls from the

solicitors for one or other of the parties on minor procedural matters. This

practice was the subject of adverse comment by Coleman J. in Norbrook

Laboratories v Tank ((2006) EWHC 1055, para 132) when he stated that:-

“The making of direct unilateral telephone contact by the Arbitrator with the

parties is generally to be deprecated for it inevitably gives rise to the risk that

Page 69: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

69

evidence of submissions will be put before the Arbitrator in circumstances

where no record is kept of what has been said and without the opposing party’s

awareness and therefore of an opportunity of challenging it. That is why

Arbitrators invariably communicate with the parties in writing on even the most

trivial matters of administration and do so by copying in the opposite party”.

46. While the facts of the Norbrook Laboratories case were somewhat extreme, the

observations of Coleman J. were more recently the subject of approval by Mr.

Justice McMahon in the case of Galway City Council v Samuel Kingston Limited

(Unreported, The High Court, 17th October 2008) when he stated:-

“I agree wholeheartedly with these sentiments. They are not,

however, absolute rules of law. They must be applied in the

circumstances of the case which comes before the court”

47. Significantly, the embargo against unilateral private conversation with the

Arbitrator in the 2008 Rules is not absolute. It only relates to private

communications relating to the substance of the matters in dispute. Arguably

this would not apply to communications on uncontroversial matters of

procedure or logistical arrangements, e.g. choice of venue, stenographers etc.

However, having regard to the judicial dicta stated above, it is to be

recommended that all communications with an Arbitrator, even the most trivial,

should be in writing and copied to the other side as a counsel of prudence. In

these days of e-mail, this general recommendation should provide no

disadvantage to any party. The key issue here is that any private

communication between one party or the other, or their advisers, with the

Arbitrator can create a suspicion of closeness or over-familiarity between the

Arbitrator and the party in question, with the engendering of suspicion in the

mind of the other party that, during such private communications, remarks

made sotto voce may operate to give the party in question an insight into the

thinking of, or an opportunity to surreptitiously influence, the Arbitrator, either

with regard to the general merits of the case, or to canvas his opinion on the

witnesses, or to gain an insight as to how the case might be better presented

to the disadvantage of the other party.

Jurisdiction

Page 70: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

70

48. Under Rule 12 of the 2008 Rules, the Arbitrator has power to decide a wide

variety of matters going to his jurisdiction including:-

- Whether there is a valid Arbitration Agreement;

- Whether he is properly appointed;

- Whether there is a dispute capable of being referred to Arbitration;

- Whether the dispute has been validly referred to Arbitration;

- Whether the 2008 Rules apply to the conduct of the Arbitration and if

so, to what extent;

- Whether the Arbitrator has himself complied with the 2008 Rules;

- Whether he has jurisdiction under the Contract or the 2008 Rules to

hear a matter, and the extent of that jurisdiction.

49. If any of the above matters, or, indeed, any other issue concerning the

Arbitration, is referred to court, the Arbitrator is empowered to direct whether

or not the Arbitration Proceedings will continue pending the decision of the

court. A similar provision to this effect had been contained in the 2000

Procedure. In practice, Arbitrators invariably prefer to defer continuing with

the reference where the party intent on going to court is demonstrating

expedition with its legal proceedings such as e.g. an early application to have

the issue admitted to the Commercial List (where it will be subject to the

expedited hearing provisions provided there), or where, as appropriate, there is

an undertaking to apply to the Supreme Court for an early date.

50. Neither party may challenge the arbitration process or ask the Arbitrator to

make a ruling on jurisdiction in respect of the matters set out above later than

60 days after such party became aware of circumstances that might affect a

ruling of the Arbitrator on any of such matters. This 60 day period is, in

Page 71: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

71

reality, very generous. It is not unusual for Construction Arbitrations to be all-

absorbing, with those involved (Contractors personnel, legal advisers (including

Counsel), and the relevant experts), committed on virtually a full-time basis to

its prosecution. Most litigation (with the possible exception of matters

admitted to the Commercial List) tends to be prosecuted by lawyers on a stop-

start basis, with their attention in the meantime diverted to other cases. In

the case of Construction Contracts, this tends, in many cases, not to be so.

Construction Arbitration is part of the dispute resolution phase of a

Construction Contract, and Contractors often commit members of their staff to

the full-time attendance on the resolution of such disputes, with a view to

securing an outcome as soon as possible. The primary requirements of speed

and efficiency contained in Rules 10 and 11 of the 2008 Procedure reflect the

imperative to have such disputes resolved as quickly as possibly. Lawyers, and

in particular, Barristers, involved, whether as Counsel or Arbitrators, in

Arbitrations under the 2008 Rules, should be prepared for the fact that such

engagements may well involve a large commitment in time. A jurisdictional

issue is a fundamental matter that should, where it arises, be addressed

immediately. If a Rule 12 issue arises, and is considered to be well-founded, it

is submitted that the matter should be raised with the Arbitrator and the other

side as soon as possible, i.e., within days, not weeks. In this context, the 60

day period provided for in Clause 12 should, it is submitted, be more than

adequate.

Preliminary Meeting

51. As soon as possible after his appointment, the Arbitrator is required to summon

the parties to a preliminary meeting for the purposes of establishing:-

- The likely length of the Arbitration;

- Directions for the conduct of the Arbitration;

- Whether the short procedure in Rule 16 should apply and;

- Whether any party requires an oral hearing.

Page 72: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

72

52. As noted earlier, any such directions should be aimed at achieving an early

resolution of the matters in dispute and the keeping of costs to a minimum.

The parties are required to try to agree directions before the preliminary

meeting, and the Arbitrator may require the parties to submit brief statements

before the preliminary meeting, outlining the directions they consider

appropriate.

53. As many will be aware, it was often usual practice under the Arbitration

Procedure 2000 for parties to try to agree preliminary directions in advance, so

there is little new here. (For those looking for guidance on practical issues

with regard to Arbitrations, and particularly in relation to the preliminary

meeting, see “Arbitration Law”, by Dowling-Hussey & Dunne, at para 4.18-

4.20). Some experienced Arbitrators produce detailed pre-preliminary check

lists, and this is a commendable practice which greatly facilitates progress at

the preliminary meetings.

Procedural and Evidential Matters

54. Under Rule 13.1 of the 2008 Rules the Arbitrator is required to apply the

burden of proof “…according to the law”. Thus, it would appear that either

party will be entitled to call in aid all evidential presumptions and obligations in

relation to the burden of proof as may be available to it, and suit its case. (For

example, the presumption that documents and deeds have been validly

executed; that documents posted may be expected to have been delivered in

the ordinary course of post and any other evidential presumption the existence

of which can be established at law, the most important of which being, of

course, that he who alleges, must prove). Rule 13.1 is mandatory, and it

would appear that an Arbitrator under the 2008 Rules would accordingly not be

entitled to disregard any applicable legal provisions in relation to the burden of

proof. Again, the contract provisions that require a Contractor, satisfied to

accept a Conciliator’s recommendation in relation to payment to him of a sum

of money, and who elects (due, e.g., to financial need), to take up the

payment, is required, under the new Government Contracts, to be the party

responsible for service of the Notice to Refer to Arbitration and, as a result, be

Page 73: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

73

the Claimant in the Arbitration. This can perpetrate an unfairness on the

Contractor who may thus be required to take on the onus of proving, possibly,

some fact he may have admitted, in the conciliation, of being unable to prove.

55. Among the procedural and evidential matters which the Arbitrator has power to

decide under Rule 13, include:-

- The adequacy of the Notice to Refer and Defence, and the extent to

which they can later be amended;

- Whether the Arbitrator requires further written statements from the

parties and, if so, by when;

- The classes of documents and information to be disclosed between the

parties (if any) and the time when disclosure will be made;

- Whether any questions should be answered in writing by a party in

advance of the hearing;

- The extent of oral and written evidence (including the exclusion of

repetitive or irrelevant testimony or other evidence);

- The extent of expert evidence;

- Whether or not evidence will be given under Oath or by affirmation;

- The admissibility, relevance, materiality and weight of the evidence

offered by any party;

- Whether documents are to be translated and;

- Whether evidence is to be given by way of signed witness statement

with oral evidence limited to cross-examination and re-examination.

Page 74: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

74

56. The above procedural powers of the Arbitrator may be capable of tactical

exploitation by a party. In particular, the power of the Arbitrator to require

questions to be answered by a party in advance of the hearing may be a very

useful jurisprudence to invoke. In the event that a party’s claim, or defence,

depends upon whether or not the other party can prove a particular set of

facts, or agrees to, or disagrees with, that particular matter, it would make

obvious tactical good sense for the opposite party to endeavour to formulate a

question which, if answered truthfully by the other party, might allow the

questioning party to thereafter apply to the Arbitrator for Judgement in limine

and/or for the striking out of a pleading of the other party.

57. Another example of an instance where it may be useful to request an Arbitrator

to direct that questions be answered in writing by a party in advance of a

hearing relates to reports from experts. In some cases, experts reports,

exchanged pursuant to direction from the Arbitrator, can be ambiguous. In

other cases, the factual assumptions upon which the expert has based his

opinion may not be clear from his report. In such instances, it may be useful

for the Arbitrator to direct the opposite party to answer questions intended to

elucidate ambiguities or uncertainties in the reports of the opposite expert. In

many cases, however, directions from the Arbitrator requiring the experts to

meet and discuss their reports (or draft reports as appropriate), with each

other, with a view to preparing a Scott Schedule (either in advance of, or

subsequent to, the finalisation of their reports for the hearing) can also be a

useful process to resolve ambiguities.

58. One area where it may be particularly useful for the Arbitrator to be asked to

direct the other party to answer questions relates to reports from time delay

experts, in particular, experts preparing computer-based time impact analyses.

In some cases, experts present their reports via CD. It is not unusual for a

time expert to present his analysis via a CD containing dozens of time

“snapshots”, with each “snapshot” involving a sequential analysis of hundreds

of individual activities, backed, in turn, by thousands of “frag-nets”, each

purporting to analyse the impact of each particular delay event on different

contractual activities. The validity or reliability of the subsequent analysis

depends, in turn, upon the extent to which the time expert’s assessment of

Page 75: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

75

each impact is, itself, valid or fair. Testing such findings requires, in turn,

identification, firstly of those areas where the time expert has applied his own

independent judgement, a matter which may be very difficult to ascertain from

the finished time analysis. It is submitted that, in such circumstances, it is

often useful for the Arbitrator to be asked to direct the other party to provide,

with regard to any such time impact analysis:-

- A full list of each occasion upon which the time expert has applied his

own judgement to the effect of the delay event in question, along with

his conclusion thereon; and

- In the case of each such exercise of judgement, a list of the facts relied

upon, or assumed, by the time expert in coming to such conclusion.

59. Such questions, if answered concisely, will enable ready identification by the

other party of the matters with regard to which it might take issue with the

expert, and thereby ensure that any cross-examination at the hearing is

directed to exploring such issues only. The alternative approach of

endeavouring to ascertain these matters at the hearing can itself take days of

cross-examination. As it is usual practice for Arbitrators to endeavour to limit

the time for cross-examination of witnesses, it occasionally happens that a time

expert may be content to “play for time” trying to avoid answering such

questions in the hope that the “clock will run down” on the cross-examiner

before he manages to stumble upon any key frailties that may undermine his

report.

60. One benefit of the new Government Contracts is the requirement for

Contractors to maintain a detailed programme “…of a quality that will permit

effective monitoring of the works”. Such a programme, if kept, will admit of

ready scrutiny by time experts subsequently retained for the Arbitration

hearing, and will avoid the necessity, as has happened previously, for time

experts to have to firstly recreate a reliable programme, and should also avoid

disputes over, e.g. where the critical path of the works lay at any given time,

and as to what element of the works contained float or other flexibility.

Page 76: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

76

61. The powers of the Arbitrator identified in Clause 13.2 of the 2008 Rules are

broadly reflective of (though not perhaps as expressly wide as), the powers

previously set out in Clause 7.3 of the Arbitration Procedure 2000.

Nevertheless, it would not appear from the 2008 Rules that there has been any

attempt to deliberately cut back or confine an Arbitrator’s power to decide all

procedural and evidential matters. Although Rule 13.2 contains examples of

occasions upon which such powers may fall to be exercised, it does not appear

to derogate from the general power of the Arbitrator “…to decide all procedural

and evidential matters..”

62. The Arbitrator has, additionally, similar powers to ensure compliance with his

directions under the 2008 Procedure as he had under the Arbitration Procedure

2000, namely, he may prevent a party in default for relying on the matter in

respect of which it is in default; he may draw adverse inferences from the act

of non-compliance that the circumstances justify; and he may proceed to an

award on the basis of materials that have been properly provided.

63 Significantly, a number of powers expressly provided for in the Arbitration

Procedure 2000 do not appear to have been expressly carried over to the 2008

procedure. For example, the 2008 Procedure does not appear to provide

expressly for:-

- An express power for the Arbitrator to direct a party to provide

additional information, clarification or elaboration of the Notice to Refer,

or the Statement of Defence (as per Rule 8.3 of the 2000 Procedure);

- An express power to enable the Arbitrator to make a peremptory Order

requiring compliance with any Order made by him within such time as

the Arbitrator might consider appropriate (Arbitration Procedure 2000,

Rule 8.4);

64. On the other hand, the 2008 Rules do contain (Rule 21) provisions which

enable the Arbitrator, if satisfied that a party has inexcusably delayed in

pursuing a claim in the Arbitration, and that that delay gives rise to, or is likely

to give rise to, substantial risk that it is not possible to have a fair resolution of

Page 77: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

77

the issues in that claim, or has caused, or is likely to cause, serious prejudice to

the other party, to dismiss the relevant claim. (Rule 21 of the 2008 Procedure

largely replicates Rule 8.5. of the IEI Arbitration Procedure 2000).

Expert Evidence:

65. The 2008 Procedure provides that expert evidence may only be admitted by

leave of the Arbitrator, to be given on terms that the Arbitrator thinks fit.

Where leave to deliver an Expert’s Report is given, that report must be

provided to the other party in good time, and in any event, at least 30 days,

before any hearing. (Rule 13.6).

66. The Arbitrator is also given power (Rule 13.7) to appoint one or more

independent experts to report to him, in writing, on specific issues designated

by the Arbitrator and communicated to the parties, and further provision is set

out in the Rules in this regard.

Protective and Interim Measures

67. The 2008 Rules also contain extensive provisions whereby the Arbitrator (Rule

13.9), may direct the preservation of evidence, give directions relating to any

property which is a subject of the Arbitration; give directions on the detention,

storage, sale or disposal of the whole or any part of the subject matter of the

dispute; or give any other directions he considers necessary in respect of the

subject matter of the dispute.

Requirement and Preparation for Hearing

68. The 2008 Procedure does not necessarily involve automatic provision for a

hearing. On the contrary, a hearing shall only be held “…if any party requires

it by Notice sent to the Arbitrator and the other parties not later than 30 days

after the Statement of Defence has been sent” (Rule 14.1), or if the Arbitrator

so decides.

Page 78: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

78

69. The 2008 Rules (Rule 14.4) provide for directions on an agreed bundle, which

“…shall stand as entered in evidence without further proof and without being

read out at the hearing”, albeit the inclusion of a document within the agreed

bundle does not establish either its genuineness or admissibility.

70. The Arbitrator, as soon as he considers it appropriate, (Rule 14.5) may require

the parties to provide:-

- A summary of the documents intended to be relied upon by each party;

- A summary of the issues between the parties;

- Any points of law with legal references;

- A statement or summary of any other matters likely to assist the

resolution of the dispute;

- Any other document or statement that the Arbitrator considers

necessary.

71. At least 30 days before the hearing (Rule 14.6), the Arbitrator, will as far as is

possible, require that any witnesses giving evidence have produced a Witness

Statement to be exchanged between the parties.

72. It should be noted that it is usual in Construction Arbitrations for the Arbitrator

to give, in addition to the above, directions as to the following:-

- That, where appropriate, facts be agreed as facts;

- Where appropriate, figures be agreed as figures;

- Where appropriate, a chronology be agreed between the parties;

- That the parties endeavour to agree quantum so far as possible;

Page 79: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

79

- That certain issues e.g. quantum and delay issues, be referred to the

experts for agreement;

- It is also not unusual for Arbitrators to direct the parties to exchange

written openings and to direct that, in general, Witness Statements

stand as the evidence of the Deponent with matters proceeding to

cross-examination almost from the outset.

Procedure at any Hearings

73. Rule 15 of the 2008 Procedure governs the way in which the hearings are

conducted. Under Rule 15.1, the Arbitrator may give directions about the

manner in which the hearings will be conducted, including the order in which

parties present their cases, or the order in which issues will be heard and

determined.

74 Having regard to the Arbitrator’s primary obligation to conduct the hearing as

efficiently as possible, it is not unusual for Arbitrators to request the parties to

identify preliminary issues which, depending on their resolution, might

determine all or the bulk of the matters at issue between the parties, or, which,

if subject to an early determination by the Arbitrator, might assist the parties to

resolve their differences.

75. It also happens, frequently that Arbitrators sub-divide the hearings into

different phases, each phase dealing with a different aspect of the Arbitration

e.g. different phases of the Contract, the liability effects thereof, with quantum

issues often reserved for a separate hearing.

76. The Arbitrator may proceed with the hearing in the absence of a party who has

been given adequate notice of the hearing (Rule 15.3), and, having inquired of

the parties whether they have further proof to offer or witnesses to be heard or

submissions to make, may, if advised they have none, declare the hearings

closed (Rule 15.4). An Arbitrator may, if he considers it necessary due to

exceptional circumstances, either on his own initiative or upon the application

Page 80: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

80

of a party, re-open a hearing at any time before the award is made. However,

by reference to the principle that all litigation must have an end, it is

considered unlikely that an Arbitrator will readily accede to the re-opening of a

hearing and the requirement for the existence of “exceptional circumstances”

will be likely to assist an Arbitrator in refusing to re-open a hearing where he

considers a party is requesting the re-opening on spurious grounds.

77. One issue with regard to which the 2008 Rules appear to be silent concerns the

extent to which the Arbitrator may have regard to matters within his own

knowledge and expertise, particularly the area of expertise by reference to

which he was appointed an Arbitrator (i.e., the extent to which he may give

evidence to himself). In general, where an Arbitrator intends to have regard

to matters within his own expertise, he is required to disclose such matters to

the parties, in advance, so as to enable them to have an opportunity of making

whatever submissions thereon they think appropriate, or, where relevant, to

adduce expert evidence in the event that they believe that the Arbitrator’s

views, based on his expertise, may be mistaken.

78. The IEI Arbitration Procedure 2000 contained a number of express provisions in

relation to the hearing which, though not expressly referred to in the 2008

Procedure, would appear to fall within the wide powers conferred on the

Arbitrator to give directions about the manner in which any hearing should be

conducted, including in particular, the adoption of a “chess clock” procedure,

whereby the time available for the hearing is allocated between the parties.

The parties are then required to adhere strictly to that allocation. Should a

party’s representative fail to complete his presentation within the time allowed,

further time will only be allocated at the sole discretion of the Arbitrator, and

upon such conditions as to costs that the Arbitrator may see fit to impose.

Short Procedure

79. Under Clause 16 of the 2008 Rules, provision is made for a short procedure

whereby, within 30 days after the preliminary meeting held under Rule 11.7, or

within 30 days after the Respondent has sent its Statement of Defence

(whichever is later), the parties are required to agree and provide a file to the

Page 81: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

81

Arbitrator containing all the relevant materials. In default of agreement as to a

joint file, each party prepares their own file, including Witness Statements.

Thereafter, the Arbitrator may view the site or the works, with or without the

parties, and may permit or require the parties to submit additional information,

whereafter, within a further 30 days, the Arbitrator must either make the award

or schedule a meeting for the purposes of receiving any oral submissions the

parties wish to make, or, in the alternative, ask questions of the parties (Rule

16.4). If such a meeting is held, the Arbitrator is required to make his award

within 30 days after the end of the meeting.

80 Under Clause 16.1, the short procedure is the norm. Rule 16.1 provides that

the short procedure shall apply “…unless all the parties agree or the Arbitrator,

on the application of a party, considers that it should not apply because of the

complexity of the issues”.

81. The short procedure contained in Clause 16 of the 2008 Procedure mirrors,

very closely, Clause 15 of the IEI Arbitration Procedure 2000.

Award

82. The 2008 Procedure contains detailed provisions in relation to the making of

awards. Again, these largely reflect the provisions of the IEI Procedure 2000.

In particular, the Arbitrator is entitled to make interim awards. Each award is

to be made in writing and to be sent to the parties promptly. Awards are to be

“…final and binding on the parties”. Under Clause 17.2, the parties undertake

to carry out the Arbitrator’s awards without delay.

83. As noted earlier, under Rule 17.2, the Arbitrator is also required to send a copy

of his award, within 14 days of having sent it to the parties, to the Department

of Finance, National Procurement Policy Unit. This requirement appears intent

on ensuring that the Department of Finance quickly builds up a library of all

arbitral awards under the new Contracts. No doubt this will be beneficial for

the purposes of advising the Department of Finance, and the Government, as

to how the new Contracts are operating in practice. (It is not clear whether

this information is going to be shared with the Construction Industry

Page 82: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

82

Federation, but one presumes that this will be unlikely). This requirement

may be beneficial also in that any significant additional payment required to be

made to a Contractor as a result of an Arbitration award may, dependent on

the circumstances, have to be met out of the general vote of either the

Department of Finance, or the Department of the Environment. Hence, it may

be desirable and appropriate that the relevant payor mandarins have an

opportunity to understand fully why such awards were made.

84. Under Rule 17.5, the Arbitrator is required to state, in his award, the reasons

upon which the award is based, unless all parties have agreed that no reasons

are to be given. The default position whereby reasons are to be given unless

the parties agree otherwise reverses the provision previously set out in Rule 20

of the IEI Arbitration Procedure, whereby the Arbitrator does not provide

reasons unless requested to do so by at least one of the parties.

84. Under Rule 17.6, the Arbitrator may not withhold his award pending payment

of fees, though he may require a deposit from one or more of the parties for

security for costs (presumably his costs on this issue) during the Arbitration

proceedings.

Interest

86. Under Rule 18, the Arbitrator has power to award interest in accordance with

the Contract and the law, but may consider interest only after all other matters

(except costs) have been dealt with by interim award.

87. The Arbitrator’s power to award interest under the 2008 Procedure contrasts

with the power given to Arbitrators under the 2000 Procedure where the

Arbitrator had power to award interest “…either simple or compound at such

rate and between such dates or such events as he thinks fit”. This wide

latitude given to Arbitrators appointed under the IEI Procedure 2000 has now

been removed. In general, this is a beneficial development. Under the 2000

Procedure, Arbitrators were often invited to award interest on a compound

basis. Some Arbitrators, indeed, regarded compound interest as the

appropriate measure for interest, treating interest as, in effect, compensation

Page 83: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

83

for the wrongful retention of monies. Other Arbitrators tended to take a very

restrictive view, only awarding a Contractor interest at its relevant bank

overdraft rate, or where no overdraft rate was applicable, at relevant bank

deposit rates.

88. It should be noted that the new Government Contracts provide that interest

shall be added to any payment not made by the Employer within the time

provided for in the Contract, at the rate provided in the European Communities

(Late Payment in Commercial Transactions) Regulations 2002, with interest to

run from the date the payment was due.

89. Interestingly, however, if the Arbitrator should conclude that the Contractor is

entitled to a payment at a level less than that recommended by the Conciliator,

the Contractor is obliged to repay the excess to the Employer with interest

calculated at 2% per annum more than that provided for in the 2002

Regulations.

Costs

90. Clause 19 of the 2008 Rules allows the Arbitrator to award costs. While costs

will normally follow the event, the Arbitrator may also allocate the costs

between the parties in a manner he thinks appropriate, and make other Orders

in relation to the costs in accordance with Rule 19.

91. Under Rule 19.3, the Arbitrator is also empowered to direct that security for the

costs of one or more of the parties be provided by way of deposit. The

requirement for the security for costs to be provided “…by way of deposit”

would appear to preclude the furnishing of security by way of a bond,

guarantee, or other means short of the making of a deposit.

92. Under Rule 19.4, the Arbitrator may limit the recoverable costs of the

Arbitration to an amount specified by himself, or by the parties, but only where

the parties agree, after the Arbitrator was appointed, to give the Arbitrator this

power.

Page 84: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

84

Correction of an Award

93. Within 30 days after receipt of an award, any party, on notice, “may request

the Arbitrator to interpret the award or correct any clerical, typographical or

computation errors or make an additional award about claims presented but

omitted from the award”. If the Arbitrator considers such a request to be

justified, and after considering the parties’ submissions, he is required to

comply with the request within 30 days.

94. The above provisions are to be contrasted with Rule 21.3 of the 2000

Procedure, under which an Arbitrator, within 28 days of the award, was

empowered to “…correct an award so as to remove any clerical mistake, error

or ambiguity, and may also make an additional award in respect of any matter

which was not dealt with in the award.”

95. There was, for many years, doubt among arbitration practitioners as to the

ambit of the power conferred on Arbitrators under Rule 21.3 and as to what

was meant by the power to remove “…any clerical mistake, error or

ambiguity…”, words which appeared to somewhat extend the power set out in

Section 28 of the Arbitration Act 1954 which provided for a power to correct

“…in an award say clerical mistake or error arising from any accidental slip or

admission”

96 Rule 21.3 of the 2000 Procedure had an interesting genesis insofar as it derived

from the 1997 I.C.E. Rules adopted in England following the enactment of the

Arbitration Act 1996, an Act which expanded the power of Arbitrators to correct

for ambiguity. In adopting the formula provided in the 1997 I.C.E. Rules in the

I.E.I. procedure 2000, the I.E.I. was, in effect, providing for a broader power

for Arbitrators to correct their awards than existed under the 1954 Act, a fact

acknowledged by McMahon J. in Galway City Council v Samuel Kingston Limited

when he stated as follows:-

“following this amendment, the English Institution of Civil Engineers

adopted their “Arbitration Procedure (1997)” and set out for the first

time the new text of Clause 21.3 which the IEI “Arbitration Procedure

(2000)” adopted as the appropriate procedure to govern arbitrations in

Page 85: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

85

Ireland under that procedure. As already mentioned, Clause 21.3 now

gives the Arbitrator power “…to correct an award so as to remove any

clerical mistake error or ambiguity…” as well as also giving the

Arbitrator power to make an additional award in respect of any matter

which was not dealt with in the award…This is the correct interpretation

can be seen from the statement in Russell on Arbitration (23rd Edition)

when it speaks of the ambiguity provision under the English legislation.

At pp336-337, para 6.170 of that treatise it is stated:-

“This would cover a situation where the Tribunal’s reasoning or

decision is not sufficiently clear and clarification or correction is

therefore warranted. The courts have drawn a distinction

between seeking to effect a change in the Tribunal’s decision in

referring a matter to the Tribunal for clarification of what it has

decided. An award which contains inadequate rationale or

incomplete reasons for a decision is likely to be ambiguous and

need clarification. The sub section may therefore provide a

means to request further reasons from the Tribunal or to request

reasons where none have previously been given in relation to a

particular issue, but only where there is genuine ambiguity”.

From this can be seen that the word ambiguity in the English Act is not

restricted by the word “clerical”, and since it is linked in the text of

Clause 21.3 of the Irish Arbitration Procedure (2000) with the word

“error”, both words must enjoy that freedom. Had there been a

different intention, the drafters of this Clause would have reproduced

the Section 28 phraseology which restricts correctional errors “arising

from any accidental slip or omission”.

97. The Judgement of McMahon J. in the above case would, it is submitted,

generally be regarded as beneficial insofar as practitioners have long thought it

desirable that, on occasion, Arbitrators should be given power to expand upon

the reasoning set out in their awards where appropriate. The new Rule 20.1 in

the 2008 Procedure confers an express power on Arbitrators “…to interpret the

award…”. In addition, the Arbitrator has power to correct “…any clerical,

typographical or computation errors”. By making no reference to the

Arbitrator’s power to remove “ambiguity”, under Rule 21.3 of the 2000

Page 86: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

86

Procedure, but substituting a power on the part of the Arbitrator to “…interpret

the award…” it would appear that the 2008 Procedure is intended, in effect, to

ensure that an Arbitrator’s power in this regard under the 2000 Procedure, as

amplified and explained by McMahon J. in the Kingston case, has been

preserved.

98. Problems may still arise in relation to the use of the words “…interpret the

award”. For example, while no doubt, the Rule will allow an Arbitrator to

better explain the words used by him to explain the reasoning by which he has

come to his award, the Rule would not appear intended to allow the Arbitrator

to expand on the reasons already given, or, more importantly, to substitute

better reasons. This question may assume considerable practical importance

in that a party, disappointed with the Arbitrator’s decision, and believing it to be

wrong in law and on the facts, or irrational or improperly reasoned, may

request the Arbitrator to interpret the award under Clause 20.1 of the 2008

Procedure, in the hope that the Arbitrator, in doing so, will in effect “dig himself

into a hole”, and thereby improve the prospects of the requesting party to

subsequently obtain an Order for set aside or remission under the 1954 Act.

An Arbitrator, who has had any alleged irrationality or lack of logic pointed out

to him, may be tempted to expand upon or alter his reasoning so as to better

immunise his award from judicial interference and, in so doing, may be

tempted to go beyond mere interpretation. This would not appear permissible

under the 2008 Rules.

Court Applications

99. If any party applies to the Court for any relief in connection with the arbitration

proceedings or an award issued by the Arbitrator, or for the removal of the

Arbitrator, that party is required, at the same time, to notify the Arbitrator of

the application, whereupon the Arbitrator is empowered to continue to proceed

with the Arbitration proceedings pending a decision by the court. Once an

award or decision has been made or taken up, the Arbitrator is under no

obligation to make any further statement in connection with it, other than in

compliance with an Order of Court.

Page 87: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

87

100. Importantly, the powers of the Arbitrator provided for by the 2008 Procedure

are expressly stated to be additional to the powers conferred on the Arbitrator

and the Court under the Arbitration Acts, 1954 – 1998.

Waiver of Rules

101. The 2008 Procedure contains a very important provision that stipulates that a

party who knows that any provision of, or requirement under the Rules, has not

been complied with, and yet proceeds with the Arbitration without promptly

stating the objection to the non-compliance, shall be deemed to have waived

the right to object. Rule 25, which provides to this effect, is consistent with

the general principles of law that apply in relation to procedural matters, in that

a party who permits an Arbitration to proceed, in the knowledge of some frailty

or impairment to the arbitral process, can be held to be disentitled from

subsequently invoking that impairment to have any subsequent award set

aside. Again, a recent example of this is to be found in the Kingston case

where the Respondent Employer sought to challenge an Arbitrator’s award on

the grounds, inter alia, that, early in the Arbitration, he had been seen to

apparently fall asleep. While the matter was discussed between the lawyers,

nothing was said to the Arbitrator at the time. The arbitration ran into a

second week, whereafter there were very lengthy submissions over a long

period of time followed by an award and requisitions under Rule 21.3. When

the findings ultimately went against the Employer, a High Court challenge was

initiated to have the award set aside on the grounds that the Arbitrator had

fallen asleep not only on the occasions when the matter was drawn to the

attention of both advisers, but also on a number of other occasions, when the

Employer’s representatives claimed they had seen the Arbitrator nodding off.

The Contractor’s advisers hadn’t noticed anything irregular, and nothing had

been said to them by way of further complaint by the Employer’s advisers, and

the Arbitration had thereafter been allowed run its course. Judge McMahon

found that, in all the circumstances of the case, it would not be fair to set aside

the award on this basis.

Concluding Remarks

Page 88: BAR COUNCIL CONFERENCE, DISTILLERY BUILDING · BAR COUNCIL CONFERENCE, DISTILLERY BUILDING Paper by Mark Sanfey SC Saturday 7 th February 2009 BARRISTERS IN CONSTRUCTION MEDIATIONS

88

102. In delivering his address to the Annual Dinner of the Chartered Institute of

Arbitrators (Irish Branch), in December 2007, the then Chairman of CIARB’s

Irish Branch, Joe Behan, stated as follows:-

“We are about to witness an explosion in the amount of conciliation and

arbitration on account of the new Contracts… parties to the Contracts

have no precedents, the Contract Conditions and Clauses will be

interpreted differently by everyone. Every single Clause will have to be

tried and tested, both at the mandatory conciliation process and in the

default arbitration process…Disputes will occur, not because people

want to be engaged in conflict, but because simply there is no history

and no guidance…I really do believe that it will be a battlefield with

many casualties left on it”.

103. Mr. Behan will be well known to anybody experienced in the field of

Construction Arbitration being, himself, an Arbitrator of very considerable

experience indeed. It is submitted that, in due course, his observations may

well be seen to have been truly prophetic. The field of arbitration, and indeed,

conciliation in respect of the new Government Contracts thus represents, it is

submitted, a significant niche opportunity for lawyers, and, in particular, the

Bar. Persons with an interest in this area are to be encouraged to acquire

familiarity

with the new contractual landscape and the procedural rules which will govern

the Arbitrations to be conducted thereunder.

John Trainor S.C.

February 7th 2009.