This proposed project is intended to improve traffic circulation and access to properties along the Loop 250 frontage road. The extension of Beal Parkway would provide a new connection to Thomason Drive and will reduce traffic in adjacent neighborhoods. A roundabout is also proposed at the intersection of Thomason Drive and Illinois Avenue to provide a safer interchange of traffic between the three roadways.

TRANSCRIPT

Page 1: Beal Parkway Public Meeting (Oct. 14, 2014)

Beal ParkwayCorridor Improvements

City of Midland, Texas – October 14, 2014

Prepared by Maverick Engineering, LLC

Page 2: Beal Parkway Public Meeting (Oct. 14, 2014)

Introductions• Sara Bustilloz

• Public Information Officer—City of Midland

• J.Ross Lacy• City Councilman—District 4

• Jose Ortiz, P.E.• Director of Engineering Services—City of Midland

• Andrew L. Mellen, P.E.• Maverick Engineering

• Matt Carr, P.E.• City Engineer—City of Midland

Page 3: Beal Parkway Public Meeting (Oct. 14, 2014)

Agenda

• Need and Purpose

• Project History

• Community Input

• Engineering Considerations

• Project Schedule

Page 4: Beal Parkway Public Meeting (Oct. 14, 2014)
Page 5: Beal Parkway Public Meeting (Oct. 14, 2014)

Ap

art

me

nts

Tow

nh

om

es

Residential

Residential

Office

Sports Complex

Existing Hike

/ Bike Trail

Beal Parkway The Need

Page 6: Beal Parkway Public Meeting (Oct. 14, 2014)

Project Purpose• Complete Beal Parkway between Illinois Ave and Highway 80.

• Reduce neighborhood traffic.

• Extend existing trail system south to Beal Park, making a continuous 3 miles of trails between Beal Park, Doug Russell Pool, and Lancaster Park.

Page 7: Beal Parkway Public Meeting (Oct. 14, 2014)

Thomason Dr. – Illinois Ave. – Beal Pkwy.Intersection Options

OPTION A: STANDARD

INTERSECTION

OPTION B: ROUNDABOUT

Page 8: Beal Parkway Public Meeting (Oct. 14, 2014)

Option A: Standard Intersection

Pros• Low cost to retrofit intersection• Minimal disruption to existing traffic

Cons• Pedestrian Routes connected by a Pedestrian Crossing

with Advance Warning Lights• Thomason Drive traffic will not stop. • Congestion due to Beal Parkway / Illinois Avenue Traffic

attempting left turns or going straight across Thomason• Traffic through intersection on Thomason moving at 35-

40 mph

Page 9: Beal Parkway Public Meeting (Oct. 14, 2014)

Option B: Roundabout Intersection

Pros• Safer pedestrian crossings due to raised medians• Equal priority to all roads –Traffic on Illinois and Beal

will not back up waiting for Thomason.• Greater traffic capacity• Lower speeds through intersection – 25 mph design

speed• Lowers incidence of severe crashes

Cons• Driver unfamiliarity with using this type of intersection• Will require rebuilding the entire intersection, in

multiple phases.

Page 10: Beal Parkway Public Meeting (Oct. 14, 2014)

Vehicle Conflict Points

US Federal Highway Administration. Roundabouts: An Informational Guide. Exhibit 5-2. Pg 106. Publication number FHWA-RD-00-068. March 2000.

32Conflict Points

8Conflict Points

Page 11: Beal Parkway Public Meeting (Oct. 14, 2014)

Option Comparison Option A: Standard Intersection

Option B: Roundabout Intersection

Meets Purpose & Need

Ope r a t i o n s

Initial Cost

Long Term Cost

Accommodate Pedestrians

Traffic “Queueing”

Operating Speeds

Sa f e t y

Crash Severity

Pedestrian Refuge

Overall

Page 12: Beal Parkway Public Meeting (Oct. 14, 2014)

PEDESTRIAN / BICYCLE TRAFFIC

Advantages Disadvantages

• Pedestrians must only cross one direction of traffic at a time.

• Bicyclists may negotiate roundabout either on sidewalks or on road.

• Pedestrians with vision impairment may have trouble locating crosswalk and determining when/if vehicles have yielded at crosswalk.

Why a Roundabout?

Page 13: Beal Parkway Public Meeting (Oct. 14, 2014)

SAFETY

Advantages Disadvantages

• Reduces Speeds through Intersection

• Reduces crash severity, allows safer merges into circulating traffic, and lower vehicle speeds through intersection.

• Fewer overall conflict point, and no Left-Turn, T-Bone, and Head-On conflicts.

• Potentially increased single-vehicle conflicts due to unfamiliarity with negotiating through roundabouts.

Why a Roundabout?

Page 14: Beal Parkway Public Meeting (Oct. 14, 2014)

OPERATIONS

Advantages Disadvantages

• May have lower delays and queues than other designs.

• Reduces the possibility for interfering with adjacent traffic signals at Loop 250 and Thomason.

• Transition from High-Speed traffic into Residential areas.

• Equal priority for all approaches can reduce the progression for high volume approaches.

Why a Roundabout?

Page 15: Beal Parkway Public Meeting (Oct. 14, 2014)

Project Timeline

Public Meeting Date October 14, 2014

Receive Comments October 21, 2014

Development of Project October 2014 – Spring 2015

Possible Bid Date Summer 2015

Possible Start of Construction Late Summer / Fall 2015

Page 16: Beal Parkway Public Meeting (Oct. 14, 2014)

ContactMatt Carr, P.E. - City EngineerEngineering Services—City of Midland300 N. Loraine, 5th FloorMidland, Texas 79701

Telephone: [email protected]

Page 17: Beal Parkway Public Meeting (Oct. 14, 2014)

QUESTION AND ANSWER

Page 18: Beal Parkway Public Meeting (Oct. 14, 2014)

Using a Roundabout Intersection