beamline
DESCRIPTION
Beamline 1. Beamline Target/Misalignment problem 2. Magnet measurements 3. Everything that’ critical and outstanding – eg d/str beamline monitors final use cases - complete commissioning plan - apologies if this section is incomplete. 4. Beamline review – 16 th . - PowerPoint PPT PresentationTRANSCRIPT
1
Beamline
1. Beamline Target/Misalignment problem
2. Magnet measurements
3. Everything that’ critical and outstanding – eg d/str beamline monitors final use cases
- complete commissioning plan - apologies if this section is incomplete.
4. Beamline review – 16th.
Kevin Tilley MICE VC. 1st November
2
1. Beamline / MICE-Target Misalignment
Seeds of a problem:-
At cm19: Observation that MICE target & beamline axis may not “necessarily” coincide. MICE target quoted as intercepting beam at ~+40mm above beam centre.
Subsequent to cm19: Beamline assumes target is & points back at +65mm above beam centre. MICE target at ~+40mm above beam centre.
-> beam starts at y=-25mm, y’=+9.7mrad. -> beam will misteer.
-> beam will pass through ISIS vacuum vessel.
3
1. Beamline / MICE-Target Misalignment
What effect would the misalignment have, if true:-
i) Optical misalignment:-
- Before decay solenoid – central ray has y=0 y’=+20mrad. - pion flux is 20% down due to steering &
scraping- After TOF1:- - change in alignment of muon beam into
MICE (hence effect on max cooling
performance)
ii) Beam passage through vacuum vessel:-Scenario Flux at MICE
(arb units of
muons. Nmll +/-10% momentum cut)
Basic beam optics design:-65mm source, no steel:
5196
Current situation:-40mm source, 10mm sidewall
(at 25deg->23mm in direction of beam) 840
What we should have:-65mm source, 2mm window parallel to ISIS
(at 25deg->4.7mm in direction of beam) 2840
From 65mm point
From 40mm point
4
1. Beamline / MICE-Target Misalignment
Corroborating the numbers:-
1) Axis of beamline:- 65mm from engineering (apologies for the diagram)
5
1. Beamline / MICE-Target Misalignment
Corroborating the numbers:-
2) Target dip: 40mm?? - 3 approaches to corroborate:
Approach 1/3:-
Sheffield are checking their numbers which gave position at which target intercepted beam:
eg. 40mm? = physical offset in unpowered + (internal measure @ clip – internal @ unpowered)…. Underway.
physical offset in unpowered.
Internal measure @ unpowered
Internal measure @ clip
40mm?
- From diagrams.- Else whole thing from Laras computations
6
1. Beamline / MICE-Target Misalignment
Corroborating the numbers:-
2) Target dip: 40mm? 3 Approaches to corroborate Approach 2/3:-
Measurements: target dipped at least 20mm from edge of beam when at 2ms. Beam within beampipe -> Thus dips from somewhere below 67mm -> somewhere below 47mm.
cf MICE 40mm measurement.
7
1. Beamline / MICE-Target Misalignment
Corroborating the numbers:-
2) Target dip: 40mm? 3 Approaches to corroborate
Approach 3/3:- From the Old HEP target:
Target nominal centre position: 63.5mm.
Target size to tip ~ 6.25mm Target oscillation amplitude ~ 5mm ISIS Beam bumps ~ 15mm.
-> 63.5-6.25-5-15 = 40mm to centre of (bumped) beam. = cf 40mm MICE tgt
measurement This doesn’t take account different
positions of HEP target &MICE target (MICE target is ~760mm upstream. Difft
beamsizes – assume (bigger,less dense) -> same overall movement.
8
1. Beamline / MICE-Target Misalignment
Proposal / solution.
Plan to realign beamline axis & vacuum vessel around 38mm datum.- Reason: -MICE target measurement actually 40-37mm. - We may wish to dip further in to increase rates. - Thus choose 38mm.
New vacuum vessel
New upstream frame with largertilt to aim at +38mm.
9
2. Magnet measurements.
Plan to measure Q4-Q9 from next week hopefully onwards. ~ 1 x Q35 per week?
B2 from early December hopefully.
Recheck above polarities when hooked up (Dec/Jan)
Return to B1 when hooked up – late Jan (polarities)
Return to Q1-Q3 when hooked up – late Jan (polarities)
10
3. Everything that’ critical and outstanding
– eg d/str monitors final use cases (TOF0/1 good enough?)
- complete commissioning plan
- apologies if this section is incomplete.
11
4. Beamline Review
16th November.
Finish Agenda/charge & forward – discussion after VC? – OR TOMORROW PREFERABLY?
12
Extra Slides:- Effect of passing through thick vacuum vessel.
Calculation of beam fraction traversing thick steel:-Assuming source at 40mm point above vacuum pipe centre:-centre relative to edge of window:- (40/2)-(65-40)+214 tan (9.7mr)~-3mm.Then beam overlap is: 3.75mm (beam half-height) -3mm -> overlap of ~ 0.75mm. Rest of beam height, 6.75mm tranverses thick steel. Note if beam drops to 38mm puts more in steel (comp a little by angle).Vessel same, quads aligned – removes angle – puts centre to -5mm. Hence all beam in steel.Thus at present, from source at 40mm, most of beam passes through the thick steel.
Impact on beam at MICE:-
Scenario Flux at MICE (arbitrary units of muons. Normal +/-10% momentum cut)
Beam optics design:-65mm source, no steel: 5196
Current situation:-40mm source, 10mm sidewall(at 25deg->23mm in direction of beam) 840
Possible changes:-40mm source, 2mm window prl to to ISIS (at 25deg->4.7mm in direction of beam) 2840 40mm source, 2mm wdw perp to MICE beam(perpendicular->2mm in direction of beam) 3773
13
From 65mm point
From 40mm point
14
Original design optic – no upstream steel.
15
Current situation. Original design optic (red) & rms-profiles with 23mm stainless steel (below beam window & thru 10mm @ 25deg = 23mm).
16
Possible change. 2mm window parallel to ISIS beam (as currently, but lowered).Original design optic (red) & rms-profiles with 4.7mm stainless steel (thru 2mm beam window @ 25deg = 4.7mm).
17
Possible change. (2mm Beam window perpendicular to MICE beam: presenting 2mm only)