before the maharashtra electricity regulatory commissionmercindia.org.in/pdf/order 58 42/order-186...
TRANSCRIPT
Order Case No. 186 of 2014 Page 1 of 19
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th
Floor, Cuffe Parade, Mumbai 400005.
Tel. 022 22163964/65/69 Fax 22163976
Email: [email protected]
Website: www.merc.gov.in/www.mercindia.org.in
CASE No. 186 of 2014
In the matter of
Petition of Global Energy Pvt. Ltd. regarding grant of Open Access/ NOC, banking
facility and adjustment of GenerationCredit Notes,wrongful levy of Cross-Subsidy
Surcharge and related matters
Coram
Shri Azeez M. Khan, Member
Shri Deepak Lad, Member
M/s Global Energy Pvt. Ltd. ....Petitioner
V/s
Tata Power Company Ltd. (Distribution) …Respondent
Appearance
For Petitioner: Shri Matru Gupta, Advocate
For the Respondent: Smt. Deepa Chawan, Counsel
Consumer Representative: ShriAshok Pendse (TBIA)
ORDER
Date:16 November, 2016
1. M/s. Global Energy Pvt.Ltd. (GEPL), 104, 10th
Floor, Maker Chambers VI,Nariman
Point, Mumbai has filed a Petition on 20 October, 2014 under Sections 42, 57, 60,
86(1) (f), 86(1) (e), 86(k), 142, 146 & 149 of the Electricity Act (EA), 2003 seeking
directions to Tata Power Co. Ltd. (Distribution) (TPC-D) forgrant of Open Access/
No-Objection Certificate (NOC) for adjustment of Wind Energy Generation Credit
Notes (GCNs) in the monthly bills of the end–consumers and related matters.
2. GEPL‟s prayers are as follows: -
Order Case No. 186 of 2014 Page 2 of 19
(a) “To declare and hold that the Respondent had to grant banking facility to the
wind generated power from 1st April to 31
st March for the financial years as
impugned herein;
(b) direct the Respondent that it had to grant NOC/ Open Access to Petitioner/
Wind Energy Generator from 1st April to 31st March of a financial year;
(c) direct that 25% cross subsidy surcharge is applicable to consumers availing
wind power from the Petitioner, in line with the order dated 09.09.2011
passed in Case No. 43 of 2010;
(d) direct the Respondent to compensate GEPLfor an amount of Rs. 6, 68, 97,
751/-, along with interest at the rate of 18% per annum, on account of losses
suffered due to sale of power on power exchange by the Petitioner;
(e) direct the Respondent to refund an amount of Rs. 12,42,563/- on account of
wrongful imposition of cross subsidy surcharge, along with interest at the
rate of 18% per annum;
(f) direct the Respondent to either grant Credit Notes for the unadjusted 7.59
lakh units of wind power towards adjustment in the monthly bills of the
consumers, or compensate GEPLfor an amount of Rs. 40,95, 685/-, along
with interest, in the event of lapsing of the said units;.
(g) declare and hold that the Respondent has abused its dominant position on
account of the following:
(i) by causing a delay/ denial of NOC/ Open Access to the Petitioner/
Wind Energy Generators, as mentioned in the present petition, in the light of
the reliance placed by the Respondent for regulating wind energy upon a
draft MERC (Distribution Open Access) Regulations 2011, as mentioned in
the letter dated 25.07.2012 (Annexure - P/5); and
(ii) by causing a delay/ denial of NOC/ Open Access to the Petitioner/
Wind Energy Generators, as mentioned in the present petition, contrary to
the various orders as detailed in the present petition.
(h) direct the Respondent to pay a compensation to the Petitioner, as may be
determined by this Hon’ble Commission, in terms of Sections 57 read with 60
of the Electricity Act, 2003;
(i) issue appropriate order or directions under Sections 142/ 146/ 149 against
the Respondents, and its officials, by imposing penalties for non-compliance
of various orders mentioned in the present petition;
(j) Pass any other order which this Hon’ble Commission deems fit and proper in
the interest of justice and good conscience.”
3. The facts as stated in the Petition and the subsequent submission of GEPL dated 29
January, 2015are summarized below:
Order Case No. 186 of 2014 Page 3 of 19
(a) GEPL is a Trader of electricity. It has contracted with 5 consumers, situated in the
Distribution Licence area of TPC-D, for selling 23.05 MW power from Wind
Energy Generatorsthrough Open Access (OA) in FY 2012-13, as follows:
Sr.
No.
Consumer Date of
Open
Access
Application
Period of
Open
Access
applied for
Period for
which Open
Access was
granted
Period for which
Open Access
was not granted
Total
Unadjusted
Units
(kWh)
duringthe
period for
which Open
Access was
not granted
1 Asian
Hotels
26 June,
2012
April 2012
to March
2013
July 2012 to
March 2013
April to June
2012
40,92,659
2 TCL
(Andheri)
9 October,
2012
April2012
to March
2013
November
2012 to March
2013
April to Oct
2012
63,42,933
3 TCL
(BKC)
9 October,
2012
April 2012
to March
2013
November
2012 to March
2013
April to Oct
2012
90,45,166
4 Indian
Hotels Ltd
22
November,
2012
April 2012
to March
2013
December
2012 to March
2013
April to Nov
2012
41,97,664
5 Mandke
Foundation
19 October,
2012
October
2012 to
March 2013
November
2012 to March
2013
October 2012 3,24,112
Total 2,40,02,534
(24 MU’s)
The Wind Energy Generators supplying power to these OA consumers are situated
in the area of the Maharashtra State Electricity Distribution Co. Ltd (MSEDCL) and
connected on 132/33kV Sub-stations.
(b) On behalf of these 5 consumers, GEPL made applications to TPC-D for grant of OA
permission along with NOC from MSEDCL for the period from 1 April, 2012 to 31
March, 2013.
(c) In response to the application of GEPL, TPC-D on 25 July, 2012 replied that:
i) There is a need for a separate tripartite agreement.
ii) Where Renewable Energy (RE) Generators are claiming Renewable Energy
Certificate (REC) even though a RE source involved, the power is to be
treated as conventional energy and, as a result, there would be no banking
of energy.
iii) The Contract Demand of the consumer would be reduced as per norms for
conventional electricity.
Order Case No. 186 of 2014 Page 4 of 19
iv) The energy injected would be subjected to daily scheduling on 15-minute
time block on a day-ahead basis.
v) Any deviation from the schedule would invite treatment as per the draft
MERC (Distribution Open Access) Regulations (DOA Regulations‟), 2011.
(d) These conditions laid by TPC-D are against the statutory/ regulatory framework. The
stand of TPC-D for treating the wind energy as equivalent to conventional energy is
completely against the provisions of the EA, 2003, especially Sections 62(3) read
with 86(1)(e).
(e) Banking of electricity is a benefit extended to the power generated from a Wind
Energy Generator since the wind power cannot be scheduled on a real-time basis.
Also, the stand of TPC-D that, once a Wind Energy Generator claims RECs, the
energy becomes equivalent to conventional energy, is wrong, and also contrary to
the Commission‟s Order dated 9 September, 2011 specifying 25% Cross-Subsidy
Surcharge (CSS) on consumers availing power from RE sources under OA.
(f) GEPL wrote to TPC-D on 14 August, 2012 stating as below:
i) The tripartite agreement nowhere makes it mandatory that a Power
Purchase Agreement (PPA) has to be provided by the consumer seeking
OA.The consumer had already furnished a letter of intent (LoI) which was
sufficient to outline the agreement of the parties to schedule power;
ii) Power generated from Wind Energy Generators who avail RECs cannot be
treated and scheduled as conventional energy; and
iii) The Commission in its Order dated 1 December, 2011 in Case No. 57 of
2011 had stated that, once RECs are availed, the energy of a Wind Energy
Generator loses its green attributes only with respect to the fact that
procurement of such power by the Distribution Licensees shall not be
considered for fulfillment of the Renewable Purchase Obligation (RPO)
norms.
(g) On 23 October, 2012, TPC-D issued the first GCNs in favor of Asian Hotels for the
month of July, 2012.
(h) On 26 November, 2012,GEPL wrote to TPC-D asking it to declare the expected RE
generation to the Maharashtra State Load Despatch Centre (MSLDC) in Megawatt
(MW) terms for adjustment of the respective consumer bills to ensure that all wind
generation could be credited to the consumers.
(i) On 29 November 2012,GEPL wrote to TPC-D with respect to the GCNs issued by
TPC-D dated 27 October, 2012, highlighting the problems faced in the energy
adjustment/ credit process of Asian Hotels.
Order Case No. 186 of 2014 Page 5 of 19
(j) As is evident from the above letter, the stand of TPC-D in the GCNs dated 27
October, 2012 was wrong, illegal and arbitrary, since the generation of power was
from RE sources which were eligible for a levy of only 25% of the applicable CSS,
as per the Commission‟s Order dated 9 September, 2011.TPC-Dhad levied 100%
CSS. Thus, instead of levying Rs. 0.065 per unit, TPC-D levied 26 paise per unit.
(k) On 19 January, 2013, GEPL wrote to TPC-D seeking revision in the dates of grant of
OAto 1 April, 2012 instead of the dates cited by TPC-D. Vide letter dated 18
February, 2013, GEPL sought confirmation that energy generation from 1 April,
2012 would be credited to the consumers in the TPC-D area.
(l) On 19 February, 2013, TPC-Dreplied to GEPL‟s letter of 19 January, 2013, and
stated as follows:
“As discussed earlier, we have granted distribution Open Access
from followingdates in case of transactions routed through you:
Consumer Name Date of
Application
Date of grant
of Open
Access
Asian Hotels
Ltd.
26June, 2012 1 July, 2012
TCS, Andheri 9 October,
2012
1November,
2012
Tata
Communication
s, Bandra
9October,
2012
1November,
2012
Mandke
Foundation
19October,
2012
1 November,
2012
Taj Lands End 22 November,
2012
1December,
2012
Global Energy during the conference call on 28th
January 2013 had
suggested the utilization of the energy generated from the wind
projects prior to grant of Open Access. We wish to reiterate (as done
in the conference call dated 28th
January, 2013) that we are not in a
position to give retrospective credit of the energy generated before
the date of grant of Open Access else the significance of Open Access
permission would be defeated.
The energy generated prior to the grant of Open Access has not been
utilized/ claimed by Tata Power-D in the energy settlement by SLDC.
Also, the energy generated from the sources mentioned in the above
application cannot be considered to be banked with Tata Power as
the same is not claimed by Tata Power in its energy settlement. Hence
you may like to utilizesuch energy generated elsewhere.”
(m) Thus, TPC-D refused to adjust the energy under banking principles, though banking
of wind-generated electricity is permitted. With these actions, TPC-D circumvented
Order Case No. 186 of 2014 Page 6 of 19
the whole concept of banking of electricity and also created roadblocks so as to
destroy the OA market in the RE sector.
(n) On 25 February, 2013, MSLDC responded stating that it would credit the energy
generated for the periodApril-December, 2012 in favour of TPC-D on receipt of 15
minute data based on the GCN from MSEDCL and subsequent finalization of the
Final Balancing and Settlement Mechanism (FBSM) bill for the respective months.
(o) On 27 February, 2013, GEPL wrote to TPC-D stating that the energy generated for
the period April-December 2012 will be credited in favour of TPC-D.
(p) After the above certification from MSLDC, there was no impediment left for TPC-D
to not credit energy to the consumers in its distribution area.
(q) On 28 February, 2013, TPC-D wrote to GEPL refusing to acknowledge that any
energy is lying with it as banked energy even after the certification of banked
energy.
(r) On March 22, 2013, GEPL wrote to MSEDCL seeking cancellation of GCNs issued
in favour of TPC-D, and further sought fresh GCNs for sale of banked energy
outside the area of MSEDCL. This was required since GEPL had an obligation to
make payments to the Generators by selling/ adjusting the GCNs.
(s) On 10 April, 2013, MSEDCL wrote to GEPL advising that it had issued OA
permission to the Generators to sell the wind energy to consumers in TPC-D‟s area
and that the GCNs are issued by MSEDCL with Time of Day (ToD)data, and only
ToD-wise data is required to be given for the credit of energy to consumers.
MSEDCL advised that 15 minute data is not required for adjustment/ credit of
energy, and that GEPL will have to follow up with TPC-D to adjust the energy
accordingly.
(t) On 20 May, 2013, GEPL wrote to MSEDCL and submitted the details of the GCNs
which remained unadjusted with TPC-D, seeking their cancellation and permission
to sell the energy on the Power Exchanges.
(u) On 14 October, 2013, MSEDCL wrote to GEPL advising its reconciliation of
1,81,42,672 units of energy permitted for trading, and to prepare and submit a zone-
wise plan. The authorization for sale on Exchanges was not received from
twoGenerators, and hence their energy data was not included.
(v) On 15 October, 2013, GEPL wrote to MSEDCL asking for scheduling 1,81,42,672
units. On 30 October, 2013, MSEDCL replied to GEPL permitting the sale of that
quantum of units from 1 November to 17 November 17, 2013.
(w) On 19 December, 2013, GEPL sought extension of the permission to sell the units as
these had not been sold due to various reasons, including lower prices on the
Order Case No. 186 of 2014 Page 7 of 19
Exchanges.Accordingly, MSEDCL permitted the sale of these units from 23
December, 2013 to 8 January, 2014.
(x) In view of the above, GEPL has suffered a loss of Rs. 7,22,35,999 as a result of the
arbitrary and illegal action of TPC-D in not adhering to the principles of banking in
Maharashtra.
4. In its Reply and submissionsdated2 December, 2014 and 29 December, 2015,TPC-D
has stated asbelow:-
a) GEPL is seeking relief which is in favour of or beneficial to either Generating
Companies who have injected electricity in the MSEDCL distribution system,
or to the OA consumers who are situated in the TPC-D area of supply.
b) Merely based on a presumption of loss due to its arrangements with the
Generating Companies and/or the OA consumers, GEPL cannot be a person
aggrieved, who has suffered legal injury, on account of the action of TPC-D.
Therefore, no claim as sought to be raised by GEPL against TPC-D in the
Petition is sustainable.
c) The present Petition has been filed by GEPL under Sections 42, 86(1) (f), 86(1)
(e), 86(1) (k), 57, and 60 read with Sections 142 and 146 of the EA, 2003.
Section 86(1) (f) vests powers on the State Commission to adjudicate disputes
between Generators and Licensees,It provides for the adjudicatory function of
the State Commission, which can be invoked when there is an inter-se dispute
between (a) Licensees (b) between a Generating Company and a Licensee or
(c) betweenGenerating Companies.
d) GEPL has no contractual relationship with TPC-D and has no basis of seeking
damages for the alleged losses suffered by it. The loss claimed to be suffered
by GEPL is due to its own business decisions. There is no justification for
seeking losses from TPC-D as there is no direct dispute between GEPL and
TPC-D.
e) GEPL has also not put any document on record to demonstrate that there is any
dispute between the Generating Companies and TPC-D.
f) A dispute, if any, with respect to delay in granting OA or wrongly imposing
100% CSS is a dispute between the Distribution Licensee and the consumer
which ought to be adjudicated before the Consumer Grievance Redressal
Forum (CGRF) in terms of Section 42 (5) to 42 (8) of EA, 2003 read with
Regulation 18 of the DOA Regulations, 2005, and not under Section 86(1) (f)
of EA, 2003. Hence, the Petition filed by GEPL is not maintainable and should
be dismissed on this ground alone.
Order Case No. 186 of 2014 Page 8 of 19
g) The factual details with respect to the applications made by each of the
consumers are as under:-
S.No. Consumer Date of
receipt of
application
Period for which
Open Access granted
No. of days
within which
Open Access
became
effective
1 Asian Hotels
(West) Limited
26.06.2012 01.07.2012to
31.03.2013
4 days
2 TCL (Andheri 09.10.2012 01.11.2012 to
31.03.2013
22 Days
3 TCL (BKC) 09.10.2012 01.11.2012 to
31.03.2013
22 Days
4 Mandke
Foundation
(Andheri West)
19.10.2012 01.11.2012 to
31.03.2013
12 Days
5 Indian Hotels Ltd. 22.11.2012 01.12.2012 to
31.03.2013
8 Days
h) As is evident from the above, TPC-D had granted OA, which became effective
within 30 days, i.e. the time prescribed under the DOA Regulations, 2005,
from the receipt of applications seeking OA from the consumers. Thus, there is
no delay in allowing OA by TPC-D.
i) The EA, 2003 and the Rules and Regulations do not contemplate allowing OA
even before an application seeking OA is made by a consumer. The submission
of GEPL is untenable, and accepting it would make the entire process of
seeking OA otiose. On the basis of the above, it is submitted that TPC-D, in
accordance with the provisions of Section 42 of EA, 2003 and the DOA
Regulations, granted OA to the consumers post the applications filed by them
and within the time frame prescribed in the Regulations.
j) As regards GEPL‟s submission that TPC-D has rendered the concept of
banking infructuous by not allowing OA from the beginning of the financial
year, GEPL has misconstrued the concept of banking of electricity. It has
wrongly assumed that banking is to be provided by TPC-D even before an
OAconsumer is identified. Banking of electricity is to be provided by a
Distribution Licensee in whose area of supply the OA consumer is situated.
k) The Commission in itsOrder dated 13 March, 2006 in Case No. 40 of 2005 has
established the fact that (i) for banking of energy, the consumer ought to be
identified, and (ii) the energy can only be banked with the Distribution
Licensee within whose area the consumer is situated. In other words, energy
cannot be banked with an unidentified consumer. The Commission in its Wind
Order Case No. 186 of 2014 Page 9 of 19
Energy Order dated 24 November, 2003 in Case Nos. 17(30, (4) and (5) of
2002has set out the framework governing banking of electricity.
l) It is evident from the Wind Energy Orderdated 24 November, 2003 that:-
i) Banking facility can be granted by a Distribution Licensee to its
existing OA consumers or when the OA consumers are identified. It
is the submission of GEPL that TPC-D should have provided the
banking of electricity from the beginning of the financial year,
irrespective of the date on which the applications seeking OAwere
made by its consumers That submission is contrary to the scope and
intent of the framework of banking of electricity provided by the
Commission in its Wind Energy Order dated 24 November, 2003 in
Case Nos. 17 (3), (4) and (5) of 2002. TPC-Dcould not have provided
the banking facility at the beginning of the financial year, i.e. from a
date before the application seeking OA is made by the consumers.
Consequently, energy credit, if any is to be provided only for the
period after the consumers were identified, and cannot be provided
from the beginning of the financial year. The Generating Company is
also required to inject electricity only after the consumer is identified.
ii) With regard to the submission of GEPL seeking counting of the
electricity injected by the Generating Company in the system of
MSEDCL, TPC-D is not required to provide any credit for the units
generated prior to the grant of OA.
m) TPC-D has to plan its power procurement based on its consumer mix.
However, if it is forced to give credit for energy without it being banked with
TPC-D and without its prior knowledge as sought by GEPL,it would have an
adverse impact on power procurement.Such retrospective banking of energy
would result in excess power procurement by TPC-D than is actually required
for that particular period and may lead to higher power purchase cost, which in
turn will have an impact on the tariff of the consumers. Further, this practice of
retrospective banking may lead to grid indiscipline, with Generators generating
power without identifying consumers relying on retrospective banking.
n) Once aREGenerator avails the benefits and registers for RECs, the REC
component thereafter has to be separated from the environmental attributes.
The energy component has to be treated as conventional energy. Therefore, all
attributes and all benefits qua this energy have to be in line with those provided
for conventional energy. From a conjoint reading of the Commission‟s Order in
Case Nos. 43 of 2010 and57 of 2012, it is evident that no concessional CSS is
to be provided to OA consumers availing power from RE sources, when the
supplier has availed REC. In view of the above, TPC-D has rightly imposed
100 % of the applicable CSS to the consumers of the GEPL.
Order Case No. 186 of 2014 Page 10 of 19
o) TPC-D also rejects the following allegations made by GEPL:-
i) TPC-D has abused its dominant position.
ii) It has violated the directions of the Commission.
iii) It has not adjusted over 7.59 lakh units.
p) MSLDC carries out settlementbased on the GCNs submitted by TPC-D to it,
which are submitted by OA consumers to TPC-D. Therefore, these GCNs have
not been settled in full and are pending for finalization of FBSM solely because
the OA consumer and, in turn, GEPL have not submitted the 15 minute data.
As and when (at the time of finalization of FBSM) the energy corresponding to
these consumers is credited to the TPC-D account, it would be passed on to the
consumers.
q) No dispute has been raised by either the Generating Companies injecting
electricity in MSEDCL‟s distribution system, or by the OA consumers.
r) Vide Order dated 19 August, 2014 in Case No. 148 of 2014, the Commission
had dismissed GEPL‟sPetition raising a dispute with regard to the alleged
illegal conduct of TPC-D of charging a mutually agreed tariff for partial OA on
the ground of locus standi.
5. In its Rejoinder dated29 January, 2015and additional submission dated 30
November, 2015, GEPL stated as below:
a) TPC-D has raised the issue of locus-standi of GEPL to initiate the present
proceedings. The locus of GEPLis on account of the following:
(i) The nature of prayers as a result of the grievance of GEPL
(ii) The jurisdiction to file the Petition.
b) Prayers (a) to (d) and (f) to (h) directly affect GEPL. The prayer (e) is
necessary since refunding of the CSS, which was wrongfully imposed by TPC-
D, will act as a boost for consumers in the TPC-D area to seek avenues for
cheap sources of power throughOA.
c) At present, the market is being manipulated by the TPC-Dso as make the
option of availing OA financially unviable, which is directly affecting the
competition in the market as well as the business of GEPL. This is the “legal
injury” which is being suffered by GEPL. The legal right of GEPL to carry on
the activity of trading in electricity through the use of the provisions of non-
discriminatory OA (Section 42) has been affected. This negative influence on
the said rights provides the cause of action to GEPL for preferring the present
Petition.
Order Case No. 186 of 2014 Page 11 of 19
d) GEPL has produced documents and data evidencing the actions ofTPC-D in
not fully implementing the principle of banking of electricity for RE, as well as
charging CSS in complete violation of the Commission‟s Order dated 9
September, 2011 of specifying 25% of CSS on consumers availing power from
wind energy sources under OA. All this is being done by TPC-D with the sole
aim of preventing consumers in its area from availing power from third-party
sources. This is abuse of its dominant position, which attracts Section 60 of the
EA, 2003. Hence, on the count of abuse of dominant position, GEPL has a
locus-standi.
e) Due to the arbitrary act of TPC-D of non-granting of banking facility from 1
April to 31 March of the financial year, GEPLwas forced to sell its power on
the Power Exchange at a much lower price than the contracted price, thereby
suffering a loss of Rs. 6,68,97,751/-.
f) Moreover, charging of wrong CSS of 100% instead of 25% has led to a loss to
the tune of Rs 12,42,563/- which is entirely on account ofTPC-D. Moreover,
around 7.59 lakhunits of energy are still pending to be adjusted by TPC-D,
which amounts to a sum of Rs. 40,95,685/-.
g) TPC-D has contended that it has granted OA which became effective within 30
days from the date of receipt of applications. However, the DOA Regulations,
2005, which were prevalent during the transactions intended by GEPL, only
require processing of applications within a period of 30 days, but that does not
mean that OAcan only be prospective. TPC-D is trying to mis-interpret the
Regulations so as to make it appear that the time period for “processing” of an
OA application is akin to grant of “prospective” permission for OA.
h) For providing banking of electricity, it is imperative that OA be
“retrospective”. TPC-D is seeking to rely upon Regulations 4.2.1 and 4.2.3 of
the DOA Regulations, 2005 so as to interpret that OA can be granted only
when TPC-D and the intended consumer take necessary steps for termination
of the supply agreement, which means “prospective” grant of OA (Regulation
4.2.1); and OA can be granted only after the date of termination of the
agreement, which means “prospective” grant of OA (Regulation 4.2.3).
i) TPC-D has given a flawed interpretation stating that, for banking of electricity,
a consumer need to be identified first. That interpretation attempts to
completely nullify the benefit of banking extended to Wind Energy Generators.
Banking of electricity does not require a pre-identified consumer, as per the
Commission‟s Wind Energy Order dated 24 November, 2003.
j) TPC-D cannot treat wind energy at par with conventional energy and levying
100% CSS, which is illegal and an example of abuse of dominant position.
Order Case No. 186 of 2014 Page 12 of 19
k) In its Order dated 9 September,2011 in Case No. 43 of 2010, the Commission
determined 25% CSS on consumers availing power from wind energy sources,
as compared to the CSS applicable to conventional energy sources. However,
TPC-D has sought to impose 100% CSS based on the flawed argument that,
once RE/ Wind Energy Generators avail REC, the power becomes brown, and
hence has to be treated as conventional power. That is an erroneous
interpretation since 25% CSS was imposed so as to give benefit/ promotion to
the wind energy developers.
l) TPC-D has failed to appreciate that availing of REC is only a benefit extended
to a Wind Energy Generator. Such availing of REC cannot change the nature of
the wind energy generated. The energy will continue to be infirm/ intermittent
in nature. The distinction between brown and green power, after a Generator
avails REC, was made solely to prevent a Wind/ REGenerator from availing a
double benefit in terms of RECs and preferential tariff.
m) However, TPC-D has chosen to treat wind power as conventional on account
of the availing of REC, which has been solely done as to make OA transactions
financially unviable and to force the consumers in TPC-D‟s area not to take
power from a RE source.
n) The stand of TPC-D in imposing 100% CSS instead of 25% as envisaged for
RE is contrary to the Commission‟s Order in Case No. 92 of 2012 dated 7
April, 2014.
o) TPC-D has not adjusted over 7.59 lakh units pending for adjustment. TPC-D is
required to submit 15-minute data to MSLDC for finalization of FBSM, but
has not complied. In its letter dated 25 February, 2013, MSLDC had stated that
it would credit the energy generated in FY 2012-13 to GEPL, but TPC-D chose
not to carry out the procedure under FBSM. TPC-D‟s submission regarding
such adjustment is based on a wrong premise, as will be seen from its letter 20
March, 2014 to GEPL.
p) As such, any actions of TPC-D of imposing such arbitrary conditions for
granting NOC/ OApermission or charging 100% CSS from RE consumers is a
strictly regulatory issue wherein the rights of not only consumers are affected,
but also of Trading Licensees such as GEPL who play a major in enabling
consumers to take OA.
q) TPC-D cannot be allowed to get away from being (i) penalized for violating its
Licence conditions by violating the Orders of the Commission and the
provisions of the EA, 2003, in terms of Section 57 (2) of the EA, 2003; and (ii)
being directed to grant compensation to GEPLfor abusing its dominant
position.
Order Case No. 186 of 2014 Page 13 of 19
r) GEPL has been created to undertake trading in electricity under Section 42(2)
of the EA, 2003. Hence, it has been granted a legal right to undertake business
through OA, which legal right has been hampered by the actions of TPC-D.
GEPL is completely entitled in the present case to seek relief as prayed for.
6. At the hearings held on 4 December, 2014, and13 October, 2015, the Commission
allowed adjournments at the request of GEPL.
7. At the hearing on 3 November, 2015, the parties were informed that, consequent to
the Chairperson of the Commission having demitted office, this Case would be heard
and decided by a Bench consisting of the remaining two Members. The Advocates
of the parties consented to further hearing of the matter being in continuance of the
earlier proceedings.GEPL reiterated its written submissions, including with regard to
the delay in granting OA, banking, wrongful levy of CSS, breach of the
Commission‟s Orders and abuse of its dominant position by TPC-D. TPC-D also
reiterated its submissions, including with regard to banking of energy, the locus
standi of GEPL, the timely grant of OA, andthat it had not breached the
Commission‟s Order. The Commission directed GEPL to submit the following
within 4 weeks:
i) The authority under which it is making claims on behalf of the
Generators and the consumers.
ii) The actual damages/losses sustained by it.
TPC-D was given two weeks to make further submissions after receipt of GEPL‟s
submission.
8. In its submission dated 5 January, 2016, GEPL stated as follows:
a. The non-grant of NOC/ OA from 1st April, i.e. the start of the financial year,
directly affects the functioning of GEPL, which is a Trading Licensee under
Section 14 of the EA, 2003, as such non-grant is qua the transaction of GEPL
with the consumers. The action of TPC-DL in not granting such NOC is a
violation of the Wind Energy Order dated 24.11.2003 in Case Nos. 17, 3, 4 and 5
of 2002. That Order laid down the protocol for banking of wind energy, and how
the Distribution Licensees have to implement it.
b. Levying of 100% CSS by TPC-D on the consumers of wind energy has resulted
in a direct loss to GEPL as no consumer was willing to take power from Wind
Energy Generators under OAas it had become more expensive because of levy of
100% CSS by TPC-D. The Petitioner, as a Trader, is in the business of
contracting with willing consumers for cheaper wind power. However, the levy of
100% CSS increasesthe transaction cost, which is against the Commission‟s
Order dated 9 September, 2011 in Case No. 43 of 2010. Under that Order, CSS
wasleviableat 25% in case of consumers who purchased power from Wind
Energy Generators under OA.
Order Case No. 186 of 2014 Page 14 of 19
c. TPC-D has relied on Judgments of the ATE and Supreme Court.In Judgment
cited, the issue related to an individual grievance of a “consumer”, while in the
present case the issue relates to GEPL who is a Licensee as per Section 14. GEPL
has a „separate and individual‟ grievance and cause of action for filing the present
Petition.
d. TPC-D is mis-interpreting the Banking protocol envisaged in theWind Energy
Order dated 24 November, 2003 in Case Nos. 17, 3, 4 and 5 of 2002 by
construing that retrospective NOC is not possible for wind energy. In thatOrder,
the Commission has created a protocol and legal framework for retrospective
grant of NOC pertaining to banked wind energy. Banking facility is applicable
qua wind energy, which can be availed directly by a consumer or through a
Trading Licensee. There is no distinction that the Banking facility is not for
Trading Licensees dealing with wind energy, and this is nowhere stated in the
Wind Order.
e. TPC-D cannot levy 100% CSS on consumers who avail wind energy, which
increases the transaction cost of OAand thusdirectly affects the functioning of
GEPLas a Trader. Any availing of RECs cannot change the nature of the wind
energy generated. That energy continues to be infirm/ intermittent in nature. A
Wind Energy Generator opting for RECs does not result in a change of the
“source” of energy as renewable.
f. TPC-D‟s argument of treating wind energy as brown component while REC is the
green component is erroneous as TPC-D, by such argument, is attempting to
distinguish the product of a Generating Station, which is the power generated,
while the benefit of levy of 25% CSS is on the “source” i.e. the Wind Energy
Generator.
Commission’s Analysis and Rulings
Maintainability of Petition
9. As regards the preliminary issue of maintainability of this Petition raised by
TPC-D, the Commission notes the following facts. GEPL is a Trading Licensee
under the EA, 2003. As such, it contracted with 5 consumers of TPC-D to sell a
total of 23.05 MW power from Wind Energy Generators throughOAfor all or
part of FY 2012-13. Accordingly,the consumers applied for OA to TPC-D along
with NOCs from MSEDCL (in whose area the Generators were situated).The
consumers’ applications to TPC-D as well as the NOCs given by MSEDCL to
the Generators cite GEPL as the Trader in respect of this power, and GEPL
has stated that it had submitted those applications to TPC-D. It is also clear (as
will be seen, for instance, from para. 3(l) above) that TPC-D had been engaging
with GEPL on the issues raised by it with regard to the impacts on the
consumers to whom it was supplying power and the Generators from whom it
was sourced. In its submission dated 2 December, 2014, TPC-D has alsostated
that the 5 consumers hadsubmitted Letters of Intent (LoI) to purchase power
from GEPL.
Order Case No. 186 of 2014 Page 15 of 19
10. Section 42 of the EA, 2003 stipulates that
“42....(3)Where any person, whose premises are situated within the area
of supply of a distribution licensee, (not being a local authority engaged
in the business of distribution of electricity before the appointed date)
requires a supply of electricity from a generating company or any licensee
other than such distribution licensee, such person may, by notice, require
the distribution licensee for wheeling such electricity in accordance with
regulations made by the State Commission and the duties of the
distribution licensee with respect to such supply shall be of a common
carrier providing non-discriminatory open access.”
Thus, a consumer can seek OA to source power through a Trading Licensee
(GEPL in this case).Further, as has been brought out by GEPL in these
proceedings, the actions of TPC-D to grant or deny OAand the rate of the
associated charges it levies (CSS in this case) directly affect GEPL as a supplier.
11. In view of the above,the Commission finds no merit in TPC-D’s challenge to the
locus standi of GEPL to file the present Petition, and to its maintainability on
that ground. However, in future it may be appropriate to implead the
concerned consumers and/or Generators as well.
Banking of energy prior to grant of OA
12. The Wind Energy Generators supplying power to the OA consumers through
GEPL are situated in the area of MSEDCL and connected on 132/33kV Sub-
stations. Hence, NOCs for OAwere obtained from MSEDCL in respect of the
Generators for the period from 1 April, 2012 to 31 March, 2013, as relevant.
Thereafter,OA applications were made to TPC-D by the consumers in its area
as shown below:
Sr.
No.
Consumer OA
Applicati
on Date
Period of
OAappliedfor
Period for
which OA was
granted
Date of grant
of Open Access
1 Asian
Hotels
26 June,
2012
April 2012 to
March 2013
July 2012 to
March 2013
1 July, 2012
2 TCL
(Andheri)
9
October,
2012
April2012 to
March 2013
November
2012 to March
2013
1 November,
2012
3 TCL (BKC) 9
October,
2012
April 2012 to
March 2013
November
2012 to March
2013
1 November,
2012
4 Indian
Hotels Ltd.
22
Novembe
r, 2012
April 2012 to
March 2013
December
2012 to March
2013
1 November,
2012
5 Mandke
Foundation
19
October,
2012
October 2012 to
March 2013
November
2012 to March
2013
1 December,
2012
Order Case No. 186 of 2014 Page 16 of 19
It will be seen that the applications for OA were made by the consumers only in
June, October and November, 2012 (i.e. well after 1 April, 2012); that TPC-D
disposed of them within the stipulated time of 30 days; and that OA was
granted with effect from the first day of the month following their
receipt.GEPL is aggrieved that, although OA had been sought from 1 April,
2012 (except for Mandke Foundation, which sought it from 1 October) to the
end of FY 2012-13, TPC-D granted OA only prospectively from the month
following their receipt, and denied banking of the energy from the prior dates.
13. Banking of wind energy was approved by the Commission in its Wind Energy
Order dated November 24, 2003 in Case Nos. 17(3), 3, 4 and 5 of 2002 inter alia
as follows:
“1.6.10.Banking of energy delivered to the grid for self-use and or sale to
third party shall be allowed any time of the day and night subject to the
condition that surplus energy (energy delivered into the grid but not
consumed) at the end of the financial year shall not be carried over to the
next year.
Surplus energy at the end of the year, limited to 10% of the net energy
delivered by the developer to the grid during the year shall be purchased by
the Utility at the lowest TOD slab rate for HT energy tariff applicable on
the 31st March of the financial year in which the power was generated…”
In the event of unforeseen and force majeure conditions, surplus energy at
the end of the year in excess of the 10% limit specified above shall be
purchased by the Utility at a rate equivalent to the weighted average fuel
cost for the year as determined by the Commission in the Tariff Order. The
payment of surplus energy shall be made to the developer/owner and not to
consumer in case of third party sale.”
14. A plain reading of the Wind Energy Order quoted above does not support the
contention that a consumer can approach a Distribution Licensee at any time of
its choosing for OA to be effective from an earlier date, or that the Distribution
Licensee is required to compensate it or the Generator for that prior period. In
its Order in Case No. 40 of 2005, the Commission had stated that
“TPC, as supply licensee, should provide banking facility and should
purchase excess energy…for wind power projects…”
which implies that the consumer has to have been duly identified. The
Commission made this explicitin its Order dated 13 August, 2013 in Case No. 16
of 2013, as follows:
“The Petitioner has also prayed that “ii) The Respondent be directed to
pay, the petitioner, the price of units generated and injected into the
distribution network of the Respondent during the period from 01-04-2012
to 31-03-2013.” In this regard, the Commission opines that any injection,
without valid contract and/or complying with scheduling requirements as
per prevalent procedures for scheduling and dispatch, would not in
Order Case No. 186 of 2014 Page 17 of 19
principle be in the interest of disciplinedoperations of the grid which is of
paramount concern from the perspective of reliable and safe operations of
the Grid. Accordingly, the Section 32(2) [of the EA, 2003] mandates the
SLDC to be responsible for optimal scheduling and dispatch of electricity
within State, in accordance with the Contracts entered into with the
licensees or generating companies operating in that State. Hence, the
prayer for compensating for units generated and injected into the grid is
rejected.”
15. The DOA Regulations, 2005, which were applicable in FY 2012-13, specified as
follows:
“4.2 Application by a consumer -
4.2.1 Where a consumer of the Distribution Licensee, who is eligible
under Regulation 3.1, applies for open access to the distribution system
so as to obtain supply from a Generating Company or a Licensee other
than such Distribution Licensee, the consumer and the Distribution
Licensee shall take necessary steps for termination of agreement for
supply of electricity and discontinuance of supply to such consumer, in
accordance with the procedure and within the time limits specified in the
Electricity Supply Code.
4.2.2 Where a consumer of the Distribution Licensee, who is eligible
under Regulation 3.1, applies for open access to the distribution system
so as to obtain a part of his total requirement for supply from a
Generating Company or Licensee other than such Distribution Licensee,
the Distribution Licensee shall reduce the contract demand/ sanctioned
load of such consumer, to the extent of capacity applied for under open
access, in accordance with the procedure for reduction in contract
demand/ sanctioned load specified in the Electricity Supply Code and
within the time limits specified in the Standards of Performance
Regulations.
4.2.3 Where the grant of open access does not entail extension of
distribution mains or commissioning of new sub-station, the Distribution
Licensee shall permit wheeling of electricity over the distribution system
to such consumer from the date of termination of the agreement in
accordance with Regulation 4.2.1 above or from the date of reduction in
contract demand/ sanctioned load in accordance with Regulation 4.2.2
above, as the case may be.”
16. From the foregoing, it is clear that the OA consumer has to be duly identified;
and that, provided that the grant of OA applied for has not been unduly
delayed or wrongfully denied, it would have prospective and notretrospective
effect. In the present case, the consumer applications were made to TPC-D in
June, October and November, 2012, and OA was granted within the stipulated
time. Hence, the OAand corresponding banking dispensation cannot be
claimedwith retrospective effect from 1 April (or, in the case of Mandke
Foundation which applied on 19 October, from 1 October, 2012).
Order Case No. 186 of 2014 Page 18 of 19
Levy of 100 % instead of 25% CSS
17. TPC-D has levied 100% CSS on the OAconsumers, who are all admittedly
sourcing wind energy. Case No. 43 of 2010 dealt with the re-determination of
CSS and various issues relating to OA. At para. 41(j) of its Order dated 9
September, 2011, the Commission stipulated that OA consumers sourcing RE
would pay CSS to the extent of 25% (instead of the earlier full exemption) of
the CSS applicable to OA consumers obtaining power from other sources. That
stipulation is unqualified and unconditional.
18. Case No. 57 of 2011 dealt with various issues raised on the RPO Regulations,
2010. In its Order dated 1 December, 2011, the Commission held that, to the
extent that RECs have been committed for such power by a RE Generator, the
RE power purchased by Obligated Entities would not count towards fulfilment
of their RPO targets:
“15.4…The Commission is of the view that the RE Generators opting for
the capacity under REC Mechanism, can sell the electricity component and
environment attribute separately. However, the electricity component is
devoid of environmental attribute so it is basically equivalent to
'conventional' electricity. As such, for the capacity committed under 'REC
Mechanism', the Obligated Entities cannot claim for the electricity
component as “Green Energy” purchased from Traders or directly from
RE Generators or from other distribution licensees, for their RPO
compliance.”
19. From a plain reading of the above stipulations and their contexts, it ought to be
clear that these two Orders deal with quite separate issues and that there is no
nexus between them. CSS is payable by OA consumers, and the Commission
had ruled in Case No. 43 of 2010 that OA consumers sourcing RE power would
pay CSS at 25% of the rate otherwise applicable. That is in no way connected to
whether or not the RE Generator from whom the power is being sourced by the
OA consumer has separately availed of the REC mechanism or not. The REC
mechanism devised by the Central Electricity Regulatory Commission is
relevant only to the RPO dispensation of this Commission, inasmuch as the
Obligated Entities can take recourse to procurement of RE power and/or
purchase RECs for fulfilment of their RPO targets. That being the case,
considering procurement of RE power from Generators to the extent of the
capacity committed by them under the REC mechanism would amount to
double-accounting of the same power by an Obligated Entity against its RPO
and normally paid for at the preferential generic tariff determined by the
Commission. Hence, and only for the purpose of accounting against the RPO,
the Commission clarified that RE power committed by a Generator under the
REC mechanism would not count towards meeting the RPO of an Obligated
Entity.
20. In view of the foregoing, the Commission directs TPC-D to refund (with
applicable interest) to the 5 OA consumers in this Case, as well as to any other
Order Case No. 186 of 2014 Page 19 of 19
such OA consumers to the extent that they have sourced RE power, the amount
of the difference between the 100% CSS charged and the 25% applicable,
irrespective of whether or not the concerned RE Generators have availed the
REC mechanism for all or part of their generation. (It may be noted, however,
that in its Multi-Year Tariff Order for TPC-D dated 21 October, 2016 in Case
No. 47 of 2016, the Commission has removed the distinction between the CSS
payable by OA consumers sourcing RE power and the CSS payable by other
OA consumers, with effect from 1 April, 2017.)
The Petition of Global Energy Pvt. Ltd in Case No. 186 of 2014 stands
disposed of accordingly
Sd/- Sd/-
(Deepak Lad) (Azeez M. Khan)
Member Member