berrima colliery - closure working group meeting #2 · environmental protection licence/ mine...

25
Berrima Colliery - Closure Working Group Meeting #2 Mittagong RSL 8 October 2018 >Welcome

Upload: others

Post on 16-Oct-2019

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Berrima Colliery -

Closure Working

Group

Meeting #2

Mittagong RSL 8 October 2018 >Welcome

Page 2: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Agenda

1. Welcome and Apologies

2. Review of minutes & actions

3. Terms of Reference

4. Groundwater storage volume

5. Water Quality Trends and Preliminary Macroinvertebrate Comments

6. EPA Presentation – Ecotoxicology Study

7. Bulkhead Seals Explanation

8. EPL/MOP Updates

9. Communications Plan

10.Loch Catherine Update

11.General business

12.Next meeting

Page 3: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Welcome - CWG Representatives, Apologies & Guests

● Boral - Fabio Colusso, Greg Johnson, David Spears,

● Resource Regulator - Greg Kininmonth, Will Mitry

● Environment Protection Authority - William Dove, Andrew Couldridge

● WaterNSW - Ravi Sundaram

● Wingecarribee Shire Council - Barry Arthur (apologies), Proxy?

● Western Sydney University - Dr Ian Wright

● Community - Clive West, Alan Lindsay, Graham Kelly, Ray Nolan, Julian Brophy

● Independent chair - Brad Mullard

● Minute taker – Rob Byrnes ● Guest - Pamela Klioufis

Page 4: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Review of Minutes – suggested amendments

Page 5: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Review of Actions

● CWG Terms of Reference and that it is not the only way Boral will engage with the Community

Page 6: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Terms of Reference

Minor change to clarify that the CWG will not be the only way Boral engages with the Community.

Page 7: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Estimated volume of water contained in the workings

548ML

(Based on: Mine ceasing discharge on

1/09/2015 and free draining on 21/03/2016.

203 days X 2.7ML = 548ML)

There was also a question in relation to the size of the

mine void in total:

5.5 million m2 x 2.2 m (seam height) x 0.4 (% recovery) =

4.8 Million cubic metres

This equates to around 7 Million tonnes (using SG of

1.45).

Or 4,800 ML if all the void could be filled with water, which

wouldn’t happen

Page 8: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

The underground treatment was installed in 3 stages from early December

2017 until mid January 2018

Page 9: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Site and surrounding environment

Page 10: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Discharge Volumes

● Additional pumping commenced

early August 2018

● Water level has now dropped 800-

900mm

● Sufficient level to install bulkheads

● Additional pumping has ceased and

will revert to likely levels of 2.7ML

average

Page 11: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Water Quality Trends - pH & EC

Page 12: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Water Quality Trends - Iron and Manganese

Page 13: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Water Quality Trends - Nickel and Zinc

Page 14: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Water Quality Trends along the treatment path - Iron example

● 400 D12 Sump - Pump

pick up location

● 400 C8 - After

aeration, treatment

through lime bed and

filtered through goaf

● Adit Discharge - V -

Notch sample

Page 15: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Macroinvertebrate study update - Preliminary findings

Based on (two sampling occasions in Autumn 2018) similar story to what was observed previously (2017), although

thorough analysis not been completed at this stage.

● There was a loss of sensitive order mayflies (families Baetidae, Caenidae and Leptophlebiidae) and riffle beetle Elmidae upto

1km d/s of the adit.

● Stonefly Gripopterygidae was observed to be impacted 100m downstream (in 2017), however at 300-500m d/s this was not as

evident and appears to have recovered 500m d/s.

● There was some caddis missing (Philopotamidae) 500m d/s however they were present in good numbers 1km d/s.

● In general there appears to be an impact up to 1km downstream, however the macroinvertebrate fauna appear to be recovering

at this distance downstream.

● At 2km downstream the aquatic fauna appears to have fauna that were missing at sites 500m d/s and 1km d/s and I suspect

closer to upstream reference condition.

Page 16: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

EPA Presentation – Ecotoxicology Assessment

Page 17: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Interim Sealing Plan - Location in respect of workings

Page 18: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Bulkhead Seal design - Explained

Page 19: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Environmental Protection Licence/ Mine Operations Plan Updates

EPL 608

● Background - Special Condition R3 was added to the EPL late last year as a means to monitor the

performance of the underground treatment trial. The condition requires water quality summary reports

to discuss effectiveness of the trial every 2 - 6 months and annual scientific reports including

sediment and macroinvertebrates due annually on 31 Jan 2019 and 31 January 2020.

● Boral difficulties

○ The Special Conditions were agreed prior to the installation of the complete system.

○ The full treatment system was not operational until mid January 2018.

○ Weather and other conditions (bushfire) can vary time of month sampling

○ Laboratory results can take 7+ days from sampling to be received

○ Macroinvertebrate numbers even longer

○ Time required to analyse and assess trends

● Administrative request submitted to the EPA to vary submission dates by 6 weeks

“to allow more time for the licensee's consultants to complete and synchronise the in-situ water quality, sediment and macro-

invertebrate sampling and report preparation as required in the Performance Monitoring Program”.

Page 20: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Environmental Protection Licence/ Mine Operations Plan Updates

MOP - Stage 1 Mine Closure Plan

Background - The current approved closure plan dated January 2018 excludes detail on the proposed

bulkheads. Post the last CWG Boral provided the Resources Regulator a letter update on the bulkheads as

an attachment to the Stage 1 Plan.

● The RR requested feedback from Water NSW and the NSW EPA.

● The RR also requested evidence from Mine Safety they were satisfied with proposed designs

● WaterNSW and the EPA requested how waters will be monitored during and post installation of

bulkheads.

Boral Actions

● Boral has agreed to an updated sampling plan that will be included in a letter amendment to the

MOP.

● Once the final bulkhead designs are finalised, Boral will further consult with Mine Safety and provide

correspondence with the RR

Page 21: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Communication Plan - Workshop

Pamela Klioufis

Page 22: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Loch Catherine Update

Page 23: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

General business

Page 24: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved

Titlefefefefeffff4g45g4545

Next meeting date

Proposing: Monday 11 February 2019

9am – 1pm

Location – Berrima Colliery (including a pit top site inspection)

Page 25: Berrima Colliery - Closure Working Group Meeting #2 · Environmental Protection Licence/ Mine Operations Plan Updates MOP - Stage 1 Mine Closure Plan Background - The current approved