berrima colliery - closure working group meeting #3 · environmental protection licence/ mine...
TRANSCRIPT
Berrima Colliery -
Closure Working
Group
Meeting #3
Berrima Colliery, Medway, 11 February 2019
>Welcome
Titlefefefefeffff4g45g4545
Agenda
1. Welcome and Apologies
2. Pit top inspection
3. Review of minutes & actions
4. Estimates of Iron removed since commencement of trials
5. Water Quality Trends and Macroinvertebrate Update
6. Bulkhead Seals Update
7. EPL/MOP Updates
8. Loch Catherine Update
9. Communications Plan
10.General business
11.Next meeting
Titlefefefefeffff4g45g4545
Welcome - CWG Representatives, Apologies & Guests
● Boral - Fabio Colusso, Greg Johnson, David Spears, Chris Maher
● Resource Regulator - Greg Kininmonth,
● Environment Protection Authority - William Dove, Andrew Couldridge
● WaterNSW - Ravi Sundaram
● Wingecarribee Shire Council - Barry Arthur
● Western Sydney University - Dr Ian Wright, Dr Jason Reynolds (Guest)
● Community - Clive West, Alan Lindsay, Graham Kelly, Ray Nolan, Julian Brophy (phone)
● Independent chair - Brad Mullard
● Minute taker – Rob Byrnes
Titlefefefefeffff4g45g4545
Pit Top Inspection
Safety requirements - David/Chris
Titlefefefefeffff4g45g4545
Pit Top Inspection
Titlefefefefeffff4g45g4545
Review of Minutes – suggested amendments & review of actions
Titlefefefefeffff4g45g4545
Terms of Reference
Titlefefefefeffff4g45g4545
Estimated Metals retained within mine 15 Feb 2018 - 26 Nov 2018
Iron - 8956 kg
Manganese - 1834 kg
Nickel - 32.5 kg
Zinc - 72 kg
Titlefefefefeffff4g45g4545
Surface Water Performance Monitoring Update - Report dated 31 October 2018
Titlefefefefeffff4g45g4545
Surface Water Performance Monitoring Update - report dated 31 Oct 2018
Wingecarribee River Flow - Very low flow (before recent rain and releases), mixing becomes non-existent in very low flows, mine
discharge accounted an average of 30% of stream flow during 2018
2018 Annual report due end of February
2019 Study note: Optimistic that with the improved water quality of discharge waters, recent flushes of the river from storm events and
WaterNSW releases coupled with reduced discharges during the bulkhead seal recharging we should see some improvement in stream
health over the coming 6-12 months.
Titlefefefefeffff4g45g4545
Surface Water Monitoring Update
● pH - of mine water averaging 0.5 below long term
average. Not appearing to impact water
downstream.
● Conductivity - higher conductivity causes an
increase within and beyond mixing zone,
increase of 200us/cm, it is generally below
500us/cm which is considered fresh and non-
saline
● Sulphate - Remains relatively constant
downstream, little fluctuation, generally below
100mg/L, which is considered environmental
range
Titlefefefefeffff4g45g4545
Surface Water Monitoring Update
● Iron - Drops rapidly, generally follows upstream
sites.
● Mg - Decreases rapidly through mixing zone.
Similar to historical situation, all below ANZECC
95% default of 1.9mg/l
Titlefefefefeffff4g45g4545
Surface Water Monitoring Update
● Nickel & Zinc - Decreases rapidly within the
mixing zone meeting ANZECC 95% ecosystem
protection values of 0.011 Nickel and 0.008 Zinc
at Biloela
Titlefefefefeffff4g45g4545
Discharge Quality Update - Volumes
● Additional pumping ceased in
October to allow bulkhead works to
commence
● Recharging rate appears to be
slowing with pumping now
intermittent
Titlefefefefeffff4g45g4545
Treatment Trial Water Quality Trends - pH & EC
● pH is relatively constant and
within licence range of 6.5 -
8.5
● Conductivity trending down
towards 2015 levels
Titlefefefefeffff4g45g4545
Treatment Trial Water Quality Trends - Iron and Manganese
● Iron and Manganese - returning
to 2015 levels
● Close to 9t or Iron and 2t of
Manganese prevented from
entering river
● Precipitates remain within the
limestone trench and goaf
● See samples of limestone from
treatment bed
Titlefefefefeffff4g45g4545
Treatment Trial Water Quality Trends - Nickel and Zinc
● Nickel and Zinc has returned to
2015 levels
Titlefefefefeffff4g45g4545
Water Quality Trends along the treatment path - Iron and Sulphate examples
● 400 D12 Sump - Pump pick up
location
● 400 C8 - After aeration, treatment
through lime bed and filtered through
goaf
● Adit Discharge - V - Notch sample
Iron - Level remains elevated from sump.
Treatment significantly reduces level.
Sulphate - Levels are decreasing. Treatment
system assisting binding with limestone to
form gypsum but only minimal.
Titlefefefefeffff4g45g4545
Macroinvertebrate study update - January 2019 Report
● In general, impacts from discharge were observed
downstream at Site 3 (300m downstream) and Site 4
(1000m downstream) in all three survey periods (March,
June and September 2018) with no obvious impacts at
sites further downstream.
● Impacts included: reduction in abundance, taxonomic
richness and EPT, and change in macroinvertebrate
assemblage structure.
● There were some small improvements in EPT, taxonomic
richness at Site 3 and 4 in September 2018 and became
more similar to reference sites.
● However this is difficult to relate to any improvements due
to water quality treatment. Improvements in water quality
were offset by extensive low flows of the Wingecarribee
River and associated water quality.
● Iron precipitate is the likely mechanism affecting
macroinvertebrates, and was the most improved
parameter observed within the mine after improvements in
water treatment practices.
● With the longer term implementation of these measures it
is likely that further improvements will be measurable in
future monitoring.
Titlefefefefeffff4g45g4545
Interim Sealing Plan Update - Location in respect of workings
Titlefefefefeffff4g45g4545
Bulkhead Seal installation update
Titlefefefefeffff4g45g4545
Environmental Protection Licence/ Mine Operations Plan Updates
EPL 608 - Varied in November to amend report submission dates
MOP - Update to MOP to be submitted in April 2019 to reflect Loch Catherine sealing options.
The Loch Catherine Mine was closed in 1959 and although most of the original infrastructure has been removed, the four
entries were never sealed. The permanent sealing of mine entries is a requirement of CCL 748 and the Mining Act 1992.
The type of seal proposed has been the subject of discussions with relevant government agencies for over 10 years. The
location of the entries at the base of an unstable cliff face presents significant safety risks.
Titlefefefefeffff4g45g4545
Loch Catherine Update
Titlefefefefeffff4g45g4545
Loch Catherine Update
Access to the adits via the former drift was reinstated as per the approved Stage 1 MOP in
December.
Titlefefefefeffff4g45g4545
Communication Plan - Update
Master Animation is proposed as a next stage in community engagement, one 2-
3-minute master video animation [shareable format] will be produced to visualise
and explain the current treatment trial and proposed closure approach.
The video will outline:
1. The history of the Berrima Colliery and the surrounding environment
2. The process behind closing the Colliery
3. An overview of the testing approach and results
4. The current approach to water treatment
5. Expectations for the future management of the Colliery and surrounding
environment
6. Boral’s commitment to a best practice approach
Master Animation is proposed as a next stage in community
engagement, one 2-3-minute master video animation [shareable
format] will be produced to visualise and explain the current
treatment trial and proposed closure approach.
The video will outline:
1. The history of the Berrima Colliery and the surrounding
environment
2. The process behind closing the Colliery
3. An overview of the testing approach and results
4. The current approach to water treatment
5. Expectations for the future management of the Colliery and
surrounding environment
6. Boral’s commitment to a best practice approach
Titlefefefefeffff4g45g4545
General business
Titlefefefefeffff4g45g4545
Next meeting date
Due to bulkhead seals, recharging of mine and minimal discharge
Proposing 6 months time - August 2019, will provide an update to members of CWG on site
activities in May 2019.
Location – TBA