Bespoke decommissioning tools save time and operational costs in the Middle East The challenge Innovo was commissioned by multinational oilfield services company Saipem to provide demolition tools for operations in the Middle East. The team was given a tight delivery schedule to design, manufacture and supply equipment capable of dismantling oil and gas platforms operating in the Safaniya field, the largest offshore oilfield in the world.  The solution Innovo’s engineering team designed bespoke equipment capable of reducing operating times and ensuring the cost effectiveness of the project. This included an Internal Cutting Tool (ICT) for internal platform leg cuts, customised to cut internal diameters of up to 42-in and a steel thickness of up to 8-in. For external cuts, two Diamond Wire Cutting Tools (DWCTs) were manufactured with cutting ranges of 16-in. to 30-in. and 26-in. to 60-in. Bespoke internal and external dredging tools were also included to clear consolidated sediment from inside platform legs. The team’s fast and efficient turnaround helped Saipem to meet the operator’s deadline Case study Client Saipem Project Platform decommissioning Location Safaniya field, Middle East Continued overleaf… Innovo’s offshore personnel installed, supervised and operated the bespoke decommissioning tools throughout the duration of the campaign. SAUDI ARABIA IRAN Safaniya Tool design, manufacture and supply 4 months Platforms decommissioned 9 Decommission time saved 4 weeks UAE QATAR

Upload: others

Post on 23-Mar-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Bespoke decommissioning tools save time and operational costs in the Middle East

The challenge

Innovo was commissioned by multinational oilfield services company Saipem to provide demolition tools for operations in the Middle East. The team was given a tight delivery schedule to design, manufacture and supply equipment capable of dismantling oil and gas platforms operating in the Safaniya field, the largest offshore oilfield in the world. 

The solution

Innovo’s engineering team designed bespoke equipment capable of reducing operating times and ensuring the cost effectiveness of the project. This included an Internal Cutting Tool (ICT) for internal platform leg cuts, customised to cut internal diameters of up to 42-in and a steel thickness of up to 8-in.

For external cuts, two Diamond Wire Cutting Tools (DWCTs) were manufactured with cutting ranges of 16-in. to 30-in. and 26-in. to 60-in. Bespoke internal and external dredging tools were also included to clear consolidated sediment from inside platform legs.

The team’s fast and efficient turnaround helped Saipem to meet the operator’s deadline

Case study

Client SaipemProject Platform decommissioningLocation Safaniya field, Middle East

Continued overleaf…

Innovo’s offshore personnel installed, supervised and operated the bespoke decommissioning tools throughout the duration of the campaign.

SAUDI ARABIA

IRAN

Safaniya

Tool design, manufacture and supply 4 months

Platforms decommissioned 9

Decommission time saved 4 weeks

UAE

QATAR

© Innovo Engineering & Construction Ltd. All rights reserved. 11952 January 2022

Certified Management SystemISO 37001:2016

Certified Management SystemISO 9001:2015

Certified Management SystemISO 14001:2015

Certified Management SystemISO 45001:2018

Certified Management SystemISO 50001:2018

Innovo is an engineering, construction and equipment rental company.

We support the renewables, communications, offshore energy, marine, and industrial & civil works industries worldwide with custom-designed and rental products including jack-up systems, modular pontoons, cable laying equipment, and engineering solutions onshore, offshore and subsea.

For more information pleasevisit innovoteam.com oremail [email protected]

Do you have an engineering challenge?

for kick-off operations. Innovo’s skilled personnel installed, supervised and operated the tools offshore, helping to complete the decommissioning campaign safely and ahead of schedule. 

The result

Design, manufacture and delivery of all equipment was successfully achieved in under four months. The reliability of Innovo’s equipment reduced the length of operations. Nine platforms were decommissioned in five months, four weeks ahead of schedule.

ICT performance

Legs removed 31

Leg dimensions 36.5-in. OD (1.5-in. thick), 42-in. OD (8-in. thick)

Average cutting time 1 hour per leg

Average abrasive consumption

75 kg per cut

Number of fillings 1 per leg

DWCT (16-in. to 30-in.) performance

No. of cuts Pipe OD Cut time

4 16-in. riser pipe 30 min

6 14-in. pipeline 15 min

16 32-in. bumper bar 1.5 hours

2 20-in. boat landing 1 hour

43 16-in. bracing 25 min

DWCT (26-in. to 60-in.) performance

Cuts performed 13

Jacket leg dimensions 42-in. OD (1-in. thick)

Platform piledimensions

46.5-in. OD(1.5-in. thick)

Average cutting time 3-4 hours per leg