Page 1: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

A Project Management Toolkit for Space Flight Projects

Vincent J. Bilardo, Jr.Chief of Program Planning and Control Office, NASA GRC

Gary L. Crawford, Sr.PPME Toolkit Project Manager, NASA GRC

Page 2: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

Integrated Vision for Program/Project Management & Execution (PPME) Excellence at NASA Glenn Research Center

Focus of this presentation

Space Flight Systems Portfolio

GRC Center Governance Structure

Rigorous Processes (GLPR, GLWI, HBK, etc)

Standardized Tools (PPME Toolkit)

Trained Proficient Staff

(PMs, Resource Analysts, Schedulers)

Execution Metrics (EVM, Budget Execution, Procurement Execution,

etc)

Established Operating Cadence

(Monthly Reviews, PPBE, Milestone Calendar)

Page 3: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

The PPME Toolkit is a web-based one-stop working environment developed to facilitate rigorous, compliant, life cycle-based:- Proposal Development- Project Planning- Project Execution- Project Control & Reporting

Page 4: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

The Toolkit aims to bring GRC-level Process Requirements (GLPRs) “to life” by pulling the content out of the document and serving up the process flows and templates via a mouse click.

Page 5: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

Current Version 1 Capability

Page 6: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

Top Level Products / Milestones

Cost Accounts / Control Points(assignment of Cost Account

Managers - CAMs)

Work / Planning Packages

Task / Activities

WBS: X

WBS: X.Y.Z

WBS: X.Y.Z.A

WBS: X.Y

Standardized Project Planning Approach

Level 0

Level 1

Level 2

Level 3

Staffing AssignmentsLevel 4

WBS: X.Y.Z.A.B

Project Team Builds

ResourceLoaded

Schedule(CAMs from M, D, F, R, Q, etc.)

Performing Organizations

Define Detailed Staffing Plan

Page 7: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

Screen 1.2 B

September

September

October

September

PMT Load per Agency Call

Review / Revise Case Tool Earned Value Plan

Run Case Tool

Macro

EVM Plan Metric

.xlw

Prepare Internal Customer Agreement (ICA)

3.5.4

Review / Revise Phasing Plan Worksheet

Loaded PRD

Review / Approve at PRB

Run Phasing

Plan Macro

OCFO Load Agency Program Management Tool (PMT)

3.3.7

Loaded PMT Phasing Plans

Online Database

From 1.2 A

Run PRD Macro

Review / Revise online Project Requirements Document (PRD)

3.5.4

Online Database

3.3.6, 3.3.9

Begin Project Execution

Future Version 2 Capability

Page 8: Bilardo.vince

Glenn Research Center at Lewis Field

http://pmtoolkit.grc.nasa.gov

Summary• PPME Toolkit v1 successfully developed via rapid

prototyping design approach in 2010.• Early Adopters Pilot Study conducted with five active

GRC Space Flight Projects.• Key findings being incorporated into requirements

and design of v2 for implementation in 2011.

• Forward Plan:• Deploy v1 across GRC Space Flight portfolio in 2011

with goal of 90% of projects captured by 30-Sep-2011.

• Develop and pilot v2 including Microsoft Server Enterprise solution to enable true portfolio management.