bill white drive laser [email protected] april 16, 2007 1 drive laser...

17
Bill White Drive Laser Operations [email protected] .edu April 16, 2007 1 Drive Laser Commissioning Experience Reminder of requirements on Drive Laser Thales laser Transport system Commissioning in three areas Thales laser and it’s specs Beam conditioning and transport Virtual cathode alignment Lessons learned – remaining issues Future

Post on 21-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Bill White

Drive Laser Operations [email protected]

April 16, 20071

Drive Laser Commissioning Experience

Reminder of requirements on Drive LaserThales laser Transport system

Commissioning in three areasThales laser and it’s specsBeam conditioning and transportVirtual cathode alignment

Lessons learned – remaining issuesFuture

Bill White

Drive Laser Operations [email protected]

April 16, 20072

UV pulse goals

90-10 rise and fall times < 1 psflat-top, < 8% peak-to peak

• IR to UV conversion efficiency > 10 %, 2.5 mJ output @ 255 nm• 252-258 nm, < 2% energy stability• 120 Hz, MTBF > 5000 hours Spatial Profile

FWHM = 1.2 – 3.0 mm

Temporal ProfileFWHM = 10 ps(5-20 ps)

Bill White

Drive Laser Operations [email protected]

April 16, 20073

Thales Laser system

Oscillator

Stretcher

Dazzler

Regen

Preamplifier

Final Amplifier

Compressor

UV Conversion

Bill White

Drive Laser Operations [email protected]

April 16, 20074

Transport Laser Bay

Launch System

Beam shaper

Vacuum cell Zoom

Transport tube

Table in the

tunnel

Photocathode

Virtual Cathode

Steering system

Active Steering

Stabilization

L1

L2

L3

L4

L5

L6

Waveplate

Polarizer

Powermeter

Camera

Shutter

Bill White

Drive Laser Operations [email protected]

April 16, 20075

Active Steering StabilizationIn order to meet centroid position stability requirement (min 60μm) M6 should be stabilized with 35μrad accuracySensitivity of the mirror mount 7arcsec – 34 μrad

Camera

CameraFrom Virtual Cathode

To Photocathode

Laser Bay

Transport Tube

Table in the tunnel

Steering Stabilization system test is underway

M6

M5

M4

M3

M2

C2

C1

Bill White

Drive Laser Operations [email protected]

April 16, 20076

Transport System in the Laser Bay

Laser Output

Shaper Input Adjustment

ShaperLensBeam Size Adjustment

Remotely Controlled Mirror

To Transport tube

Bill White

Drive Laser Operations [email protected]

April 16, 20077

Optical System next to the PhotocathodeFrom Transport tube

Lens

Lens

Remotely Controlled Mirror

Remotely Controlled Mirrors

Steering Stabilization Camera

Steering Stabilization Camera

Lead Blocks

Lead BlockVirtual Cathode camera

In vacuum mirrorPhotocathode

Powermeter

Bill White

Drive Laser Operations [email protected]

April 16, 20078

Transport Commissioning

TransportShaper

Diagnostics

Characterization

Calibration of diagnostics

GTL Installation

Virtual Cathode

Bill White

Drive Laser Operations [email protected]

April 16, 20079

Timeline - Laser Commissioning• Laser table and LSS in Vault

• Feb 13th – Began taking UV into vault

• Feb 23 – GTL installation began

• VC March 1 to March 12.

• Gun Installation began March 12.

• ARR April 4• Beam April 5

Bill White

Drive Laser Operations [email protected]

April 16, 200710

Commissioning IssuesBetter Schedule coordination

Too many people all working in small space

Minor problems have widespread impact

Because of shortened laser commissioning, some laser commissioning will continue with injector commissioning

Bill White

Drive Laser Operations [email protected]

April 16, 200711

Commissioning Issues

Cross correlatorStreak Camera

Bill White

Drive Laser Operations [email protected]

April 16, 200712

Temporal Pulse Shaping

The achieved temporal pulse shape meets physics requirements for the injector commissioningPlan to improve the temporal shape

Replace the Lyot filter in the regen amplifier by the edge mirrors – this will reduce oscillationsContinue working on the Dazzler settings and the optimum UV conversion crystals lengthsThales engineers are coming back in September to continue working on shaping

Plan B – to use stacking of Gaussian pulsesDesign and parts for pulse stacking are in place

Bill White

Drive Laser Operations [email protected]

April 16, 200713

Commissioning IssuesTransport Tubes

10m long

Hydro-carbons coating and damaging inside of windows when exposed to UV

Dust inside tube settling on inside of windows – Damage and diffraction

Will go to less expensive windows and on site pump so the windows can be replaced more quickly.

Bill White

Drive Laser Operations [email protected]

April 16, 200714

GBS-UV H

Commissioning IssuesNewport aspheric telescope

Converts Gaussian to flat-top

Requires good Gaussian input

Very sensitive to alignment

Aperture is just as good and much simpler to align

Allows flexibilitySimplifies overall transport

Bill White

Drive Laser Operations [email protected]

April 16, 200715

Commissioning Issues

Oscillator ProblemsPicomotor translation stage instability

Femtolase will replace

Coarse control currently disabled/manual

Phase ambiguity due to locking at 476MHz

Impacts phasing of RF

Can make double pulse

Could be solved with newly available upgrade

Replacing this oscillator will solve both problems and provide greater seed energy

Bill White

Drive Laser Operations [email protected]

April 16, 200716

Future - Hand Over to Ops

NowDevelop procedures for laserAutomate things that can and need to be automated

August 07 DownTrain Operations Group on typical Operation ProceduresHand off laser by Jan 08

Laser Group will support Ops Scheduled MaintenanceIssues that arise outside of the typical operation envelope

Bill White

Drive Laser Operations [email protected]

April 16, 200717

End