biomethane connections – current developments biomaster network meeting norwich 11 th november...

16
Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

Upload: julia-alexander

Post on 27-Mar-2015

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

Biomethane connections – current developments

Biomaster Network MeetingNorwich

11th November 2011

David Pickering

Page 2: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

2

Typical biomethane entry facility

Page 3: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

3

Getting connected – key issues

Location of gas grid compared to Anaerobic Digestion plant?

Does the gas grid have capacity?

The GDN will provide an indication free of charge but to confirm this, a chargeable Feasibility Study will be required

What grid pressure?

Will the gas meet the grid specification?

Key issue is Oxygen concentration – requirement is <0.2%

Design and Build Agreement

Network Entry Agreement

Page 4: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

4

Initial Enquiries

Email : [email protected]

Telephone : 01926 655798 or 01455 231 615

All we need is a postcode and a flow rate of biomethane

Page 5: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

5

What will you receive from an Initial enquiry?

Details of the nearest connecting pipe to your site.

Pressure tier of connecting pipe. Often multiple options available

Volume of gas that can be accepted onto the network and duration of time

Scale map of your site and nearest connection

Page 6: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

6

Face to face discussion

Review of site

Review of nearest connecting pipe work

Advice on costs

Advice on injection equipment

Gas specification requirements for grid entry

Page 7: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

7

Feasibility Study

 Network connection options

 Detailed network modelling and demand forecasting

 Cost of providing these connections

 Plant and equipment required to be provided by the customer

 Major environmental issues and risks

 Foreseen major engineering difficulties

 Programme of work required to deliver a connection

 Other issues relevant to providing a connection

Page 8: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

8

Connection issues

Responsibility for providing grid connection equipment

Provision of capacity

Oxygen concentration <0.2%

Requirement for propane

Gas quality monitoring and energy measurement

A number of barriers to entry have been identified, and these are being addressed by a joint industry group convened by Ofgem. See:

http://www.gasgovernance.co.uk/emib

Page 9: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

9

Responsibility for grid connection equipment

The problem

Uncertainty around responsibility for and level of costs of connection

The solution

GDNs to offer choice over who builds and operates (GDN or biomethane producer)

GDNs to develop standard “plug and play” facilities

Next steps

GDNs to develop specifications for BM connection equipment and interfaces

Page 10: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

10

Provision of capacity

The problem

Low summer demand may mean that the gas grid cannot accept the biomethane on a 365 day basis

The solution

Install compressor within the grid, to export gas from one pressure tier to the higher pressure one that feeds it, to access remote demand

Next steps

Field trial to prove concept

0

100

200

300

400

500

600

700

800

900

1000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

scm

/h

Expected Minimum Hourly Injection Rate (Overnight) Expected in the Driffield Area Based on Standard Load Duration Curves

Cold Profile Average Profile Warm Profile Required Input

Anaerobic Digestion Facility

Grid Injection Equipment

Biomethane Producer’s Site

Pressure Reduction

Station

National GridSite

Medium Pressure Network

Local Transmission System

Page 11: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

11

Oxygen

The problem

Current Regulations prescribe less than 0.2% oxygen in grid gas – difficult to achieve for BM

The solution

Short term – individual exemptions for BM plants, combined with blending to achieve 0.2%

Longer term – class exemption for BM if HSE can be convinced that there are no material additional risks

Next steps

GDNs sponsoring work to demonstrate no material risk of pipe corrosion

Page 12: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

12

Requirement for propane

The problem

Biomethane CV is low relative to grid CV, therefore addition of propane is required to avoid triggering CV “cap” (which would affect consumer bills) -but propane is expensive (capex and opex)

The solution

Where local conditions allow, BM can be blended with grid gas and CV measured downstream of the blending point – minimise propane input

Next steps

Needs approval of low-cost CV measuring instruments

Page 13: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

13

Remote CV monitoring at Adnams

Page 14: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

14

Gas quality monitoring and energy measurement

The problem

Currently monitoring and metering is very expensive (around £150k) as approved devices relate to large (North Sea scale) flows of gas

The solution

Revise measuring specs to be more appropriate for small volumes and for less complex gas compositions

Next steps

EMIB expert group to make recommendations for change in these areas by the end of 2011

Page 15: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

15

Conclusions

No material technical issues with biomethane grid entry

DECC targets for gas to grid and RHI levels have incentivised solutions to be found to remaining barriers to entry

Ofgem-convened Energy Market Issues for Biomethane (EMIB) group is currently meeting, with the aim of making recommendations by the end of 2011 for changes to address barriers

Page 16: Biomethane connections – current developments Biomaster Network Meeting Norwich 11 th November 2011 David Pickering

Thank you

David Pickering

Sustainable Gas Development Manager

[email protected]