© 2009 PETROLIAM NASIONAL BERHAD (PETRONAS)
All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.
MAKING IT HAPPENMAKING IT HAPPEN
MLNG/PLM/2010/0013PROVISION OF CONDITIONAL ASSESSMENT & REMAINING LIFE ANALYSIS FOR MODULE 2 BOILERS IN PETRONAS LNG COMPLEX
INTERNAL USE
Presented toBidder’s Site Visit on 17th May 2010ByZamsyari Bin MadhanMLNG
2MAKING IT HAPPENMAKING IT HAPPEN2
1. Objectives
2. General MLNG Boiler Arrangement
3. Scope of Inspections
Appendix I: PhotosAppendix II: Work Specification
Contents
3MAKING IT HAPPENMAKING IT HAPPEN
General MLNG Boiler Arrangement
3
4MAKING IT HAPPENMAKING IT HAPPEN
General MLNG Boiler Arrangement
4
5MAKING IT HAPPENMAKING IT HAPPEN5
To brief the bidder with on MLNG/PLM/2010/0013 Conditional Assessment & Remaining Life Analysis For Module 2 Boilers In PETRONAS LNG Complex.
Objectives
6MAKING IT HAPPENMAKING IT HAPPEN6
Scope Of Inspections
Test Conducted
1 Visual Inspection (VI) 8 Remote Field Electromagnetic Test (RFET)
2 Dye Penetrant Test (DPT) 9 Remote Visual Inspection (RVI)
3 Magnetic Particle Test (MPT) 10 In Situ Metallography (IM)
4 Ultrasonic Flaw Detection (UFD) 11 Hardness Testing (HT)
5 Ultrasonic Thickness Measurement (UTM) 12 Dimensional Measurement (DM)
6 Non Destructive Oxide Thickness Inspection (NOTI) 13 Metallographic Replication (MR)
7 Non Destructive Hydrogen Damage Inspection (NDHDI) 14 Deposit Collection (DC)
7MAKING IT HAPPENMAKING IT HAPPEN
Scope Of Inspections
7
DC &DM
Drums, Stack
DPT Drums, Headers & All weld joints
MPT Drums, Headers & all weld joints
UFD Headers , Drums
UTM Headers , Drums & Stack, MSL, PSH & SSH, DSH
NOTI PSH & SSH tubes
NDHDI Furnace wall tubes
RFET Boiler bank tubes, Furnace wall tubes
RVI Headers & Drums
IM Furnace wall tubes, PSH&SSH tubes
HT Headers, Drums & MSL
DM Headers, Drums & MSL, All tubes
MR Furnace wall tubes, PSH & SSH tubes
VI All pressured parts, insulation , Structure & Drums Supports
8MAKING IT HAPPENMAKING IT HAPPEN8
Photos
Visual Inspection (VI)
Mud Drum Steam Drum
9MAKING IT HAPPENMAKING IT HAPPEN9
Photos
Dye Penetrant Test (DPT)
Buckstay Steam Drum
10MAKING IT HAPPENMAKING IT HAPPEN10
Photos
Magnetic Particle Test (MPT)
SSH Header Steam Drum
11MAKING IT HAPPENMAKING IT HAPPEN11
Photos
Ultrasonic Flaw Detection (UFD)
Steam Drum Steam Drum
12MAKING IT HAPPENMAKING IT HAPPEN12
Photos
Non Destructive Oxide Thickness Inspection Service (NOTI)
Primary & Secondary Superheater
13MAKING IT HAPPENMAKING IT HAPPEN13
Photos
Non Destructive Hydrogen Damage Inspection (NDHDI)
14MAKING IT HAPPENMAKING IT HAPPEN14
Photos
Remote Field Electromagnetic Test (RFET)
Steam Drum Steam Drum
15MAKING IT HAPPENMAKING IT HAPPEN15
Photos
Remote Visual Inspection (RVI)
Primary Superheater Header
16MAKING IT HAPPENMAKING IT HAPPEN16
Photos
In Situ Metallography (IM)
Primary Superheater Outlet
17MAKING IT HAPPENMAKING IT HAPPEN17
Photos
Metallographic Replication (MR)
18MAKING IT HAPPENMAKING IT HAPPEN18
Thank You