boiler operation and maintenance experiences

33

Upload: national-productivity-council-hyderabad-india

Post on 20-Jan-2017

571 views

Category:

Engineering


6 download

TRANSCRIPT

Page 1: Boiler Operation and Maintenance Experiences
Page 2: Boiler Operation and Maintenance Experiences

By:

M.SIVARAMA KRISHNA, GM(O&M)

S.K.PRASAD,Sr.Mgr (O)

CH.PRADEEPKUMAR,Dy.Mgr(O)

EFFICIENT OPERATION & MAINTENANCE OF BOILERS

NATIONAL BOILER WORKSHOP-2015

NTPC SIMHADRI –WELCOME’s

Page 3: Boiler Operation and Maintenance Experiences

FLOW OF PRESENTATION :

Journey of NTPC

O & M Best Practices

Zero Boiler Tube leakage

LATEST Technology adopted

Conclusion

Page 4: Boiler Operation and Maintenance Experiences

NTPC VISION

NTPC HAS TO BECOME A 1,28,000 MW COMPANY BY 2032

Page 5: Boiler Operation and Maintenance Experiences

45,548 MW (Including JV’s)

COAL :38,654MW

HYDRO:5984 MW

GAS:1000MW RENEWABLE:100MW

INSTALLED CAPACITY

Page 6: Boiler Operation and Maintenance Experiences

NTPC GROUP ACCOUNTS FOR 16% OF INDIA’S TOTAL INSTALLED CAPACITY AND 25% OF ALL INDIA

GENERATION AS ON 31.03.2015

SUSTAINABLE DEVELOPMENT:A LONG JOURNEY

Page 7: Boiler Operation and Maintenance Experiences

TYPES OF BOILER‘s IN NTPC

CC, RIFLED TUBE, RADIENT RH TOP SUPPORTED 500MW SUB CRITICAL BOILER ONCE-THRU SUPER-CRITICAL, TWO-PASS, BALANCED DRAFT,

RADIANT RH, TOP SUPPORT 660MW

TOWER TYPE(SINGLE PASS),ONCE-THROUGH

SINGLE RH BOILER 500MW

ONCE THROUGH SUPER CRITICAL,

DOUBLRE PASS 800MW

Page 8: Boiler Operation and Maintenance Experiences

FORCED OUTAGE : A MAJOR CHALLENGE

BTL

START UP DEVIATIONS

OVERHEATING/CORROSION

WELD FAILURES

FLUE GAS EROSION

CHEMICAL PARAMETER DEVIATIONS

Page 9: Boiler Operation and Maintenance Experiences

O & M BEST PRACTICES

TO AVOID STARTUP DEVIATIONS

Standardized all Operation procedures & reviewed

periodically for improvement.

No SH/RH Spray till Synchronization. Proper choice of Mill/Oil gun elevations during start-up

Maintaining proper Rate of rise of Pressure/Temperature - Avoid over firing.

Safety valve floating with oil guns only

Passing of SH/RH spray valves attended regularly

Page 10: Boiler Operation and Maintenance Experiences

TO AVOID STARTUP DEVIATIONS

SH/RH Spray limiting interlock to limit temp at De-superheater outlet falling below saturation temp – implemented in all units

Monitoring of Economizer outlet temp w.r.t Saturation

temperature at eco I/l pressure during start-up

Drum Level Control Low range FRS control kept in auto during unit start-up DP across FRS maintained around 5-10 KSC CBD is kept open continuously till chemical parameters are achieved Continuous flow of feed water through economizer during startup is ensured

O & M BEST PRACTICES

Page 11: Boiler Operation and Maintenance Experiences

CHEMISTRY IN STARTUPS

Maintaining the chemical regime of boilers

Ensure CPU availability and putting both in service

during start-ups

Frequent sampling of Steam / water at local and SWAS availability

PH maintained through Ammonia Dozing.

Condensate Dumping

Hot draining as per requirements

O & M BEST PRACTICES

Page 12: Boiler Operation and Maintenance Experiences

WELD JOINT FAILURES 100% Radiography of joints being done during overhauls Radiography of bends during OH for observing any blockages

or deposits

EROSION Tube leakage in BTT - Erosion of Burner transition bends

was observed due to Secondary air from wind box - Application of plastic refractory over Burner transition tube bends

Visual Inspection of tubes in Burner zone for signs of

overheating like bulging etc. during OH

O & M BEST PRACTICES

Page 13: Boiler Operation and Maintenance Experiences

Cutting of Tubes by Grinding machine

HP Jet cleaning boiler surfaces

Use of Beveling machine for chamfering

Plastic refractory over Burner transition tube bends

Inspection of attemperation spray nozzles

Economizer repair on maintenance beds outside

INITIATIVES TAKEN @ SIMHADRI

Page 14: Boiler Operation and Maintenance Experiences

Monitoring metal temperatures – deviations are discussed in DPM

Monitoring Rate of rise of temp / pressure during startup & shutdowns thru PI applications

Pressure setting of wall blowers / LRSBs – Once in three months

Operation of LRSBs in the presence of maintenance Personnel. Incase of any mal-operation, blower can be retracted immediately without any damage.

Optimization of Wall blower / LRSB Operation

Regular checking of SADC/BT at local and remote positions. Defects are attended regularly

OPERATION BEST PRACTICES

Page 15: Boiler Operation and Maintenance Experiences

BOILER TUBE LEAKAGES AT SIMHADRI

Year Tube Leakage (No) Tube Leakage (%)

2011-12 3 0.64

2012-13 9 1.64

2013-14 10 1.37

2014-15 8 1.03

2015-16 0 0.00

Previous Financial year same period

3 1.10

*No tube leakage in the first three months of the last overhauls

Page 16: Boiler Operation and Maintenance Experiences

Area Cause / Mechanism

Remedial actions based on past failures

1.

S -Panel

EROSION Thickness survey & visual inspection of all Z-Panel, intersection and all manhole door tubes.

WELD DEFECT DPI of Peep hole door plates welds.

100% radiography of repair joints.

ATTACHMENT WELD FAILURE

100% DPI in fin welding at repair joints.

ACTION PLANS FOR ZERO BTL

Page 17: Boiler Operation and Maintenance Experiences

Area Cause / Mechanism Remedial actions based on past failures

2

WATER WALL & HANGER TUBES

EROSION

(SB Steam)

Thickness survey and visual inspection of Tube & Burner bends.

Soot blower alignment checking.

Checking of hanger tube shielding and replacement.

SHORT TERM OVER HEATING

(Starvation)

Ensuring plugs during tube repair.

Flushing of bottom ring header by draining at 10 Kg/Cm2.

ATTACH MENT WELD

100% DPI in fin welding at repair joints.

Weld failure To take care while cutting the tube

ACTION PLANS FOR ZERO BTL

Page 18: Boiler Operation and Maintenance Experiences

Area Cause / Mechanism Remedial actions based on past failures

3 ROOF TUBES

EROSION Penthouse cleaning and seal plate

checking.

Inspection of roof tubes from furnace side.

4 PLATEN SH / DIVISIONAL PANEL / SPACER TUBES

WELD

FAILURE

100% radiography of repair joints, Alignment of coils

Random DP and radiography of other joints.

RUBBING

(coil)

Inspection of spacer tubes, girdling loops and binding loops.

Inspection of tubes near cleats during every O/H

Healthiness of Clamp & stopper.

ACTION PLANS FOR ZERO BTL

Page 19: Boiler Operation and Maintenance Experiences

Area Cause /Mechanism

Remedial actions based on past failures

5

RE-HEATER

OVER

HEATING

(Starvation due to

blockage.)

Vertical tubes to be cut by

grinding and capping.

Steam cleaning of new tubes

before welding.

Oxide scale measurement.

Sponge ball checking of RH tubes for identifying blockages

Use of Metal caps

WELD

FAILURE

Radiography of shop & erection joints including DMW

100% DPT & RT in areas of degradation.

ATTACH MENT WELD FAILURE

Cleat welding being done..

Random DP near cleat area.

ACTION PLANS FOR ZERO BTL

Page 20: Boiler Operation and Maintenance Experiences

Area Cause/Mechanism Remedial actions based on past failures

6 RH VENT / DRAIN

STUB

WELD

FAILURE

DP of startup vent / drain stubs of Re heater is being done.

7

ECONOMISER

FLUEGAS

EROSION

Thickness survey and visual inspection.

Cassette baffles and shielding inspection.

WELDFAILURE 100% radiography of repair joints.

Similar erection welds to be inspected by DP & RT.

ACTION PLANS FOR ZERO BTL

Page 21: Boiler Operation and Maintenance Experiences

Area Cause / Mechanism

Remedial actions based on past failures

8

LTSH

Flue Gas

Erosion

Visual inspection and thickness survey.

Shielding of manhole door bends & bifurcation tubes.

Proper Refractory application.

Checking of cassette baffles.

weld

joint Failure

Random and RT of other welds.

100% radiography of repair welds.

Manhole door attachment weld

failure

DP at manhole door bends.

Proper clamping of shield.

Visual inspection of fins in LRSB area.

ACTION PLANS FOR ZERO BTL

Page 22: Boiler Operation and Maintenance Experiences

OTHER BEST PRACTICES

ENERGY & EFFICIENCY MAPPING OF

a) Draught systems

b) Compressed air systems

c) Milling system

d) CW system

e) Ash handling

f) Coal handling plant.

Page 23: Boiler Operation and Maintenance Experiences

LATEST TECHNOLOGIES ADOPTED

ASLD(ACOUSTIC STEAM LEAK DETECTORS)

PADO

PI SYSTEM

SCADA

FLAME CAMERAS

ACOUSTIC PYROMETERS

Page 24: Boiler Operation and Maintenance Experiences
Page 29: Boiler Operation and Maintenance Experiences

BEVELING MACHINE

Page 30: Boiler Operation and Maintenance Experiences
Page 32: Boiler Operation and Maintenance Experiences