boq parrsa
DESCRIPTION
BOQ ParrsaTRANSCRIPT
BILL OF QUANTITY.NAME OF WORK:- REPAIR OF GOVT: BUILDINGS IN DISTRICT UPPER DIR
SUB HEAD:-(1)T.M.A. Office Wari (2)Tehsildar Office Barawal
(3)Tehsildar Office Kalkot (4) Tehsildar Office Barawal
(5)EDO Education Office Upper Dir.
S#Description Qty:Unit Rate Amount
AT.M.A. OFFICE WARI
01P:C:C (1:3:6) plain 3.16M33477/-Rs.10989/-
02B:B Masonry (1:6) 10.19M33721/-Rs.37926/-
03Wooden Joinery 2.32M24036/-Rs.15335/-
04White Washing 280M220Rs.5600/-
05Painting 3-Coats 179M260Rs.10740/-
Total:- Rs.80590/-
Add: Cost Factor Rs.88649/-
Add: 2-0 % Above RS.15730/-
Total:-RS.106379/-
Add: 0.50 % Contingency Rs.532/-
SUB TOTAL:- (A)RS.106911/-
BTEHSILDAR OFFICE BARAWAL
01P/L P:C:C: (1:2:4) Plain 66.79M34156/-Rs.277575/-
02W/O light point , Call bell, Celling Fan 27Nos867/-Rs.23409/-
TOTAL:-RS.300984/-
Add: Cost Factor RS.331082/-
Add: 20 % PremiumRs.66216/-
SUB TOTAL (B)RS.397298/-
CTEHSILDAR OFFICE KALKOT
01P:C:C: (1:3:6) Plain 54.06M34156/-Rs.224675/-
02Water Supply ---Rs.20000/-
03Total:-Rs.244675/-
04Add: Cost Factor RS.269142/-
ADD: 20 % Premium RS.53828/-
TOTAL:-RS.322970/-
Add: 0.50 % Contingency RS.1615/-
SUB TOTAL:- ( C)RS.324585/-
DEDO EDUCATION OFFICE DIR
01Excavation as in foundation 107.36M3105/-RS.11273/-
02P:C:C: (1:4:8) as in foundation 26.86M32578/-RS 69245/-
03R:R Stone Masonry (1:6) CSM 155.04M33185/-RS 493810/-
04P:C:C: (1:3:6) as coping 8.94M33477/-RS 29520/-
05B:B Masonry (1:6) as specified 29.53M33721/-RS 109881/-
Total:-Rs.713739/-
Add: Cost Factor 1.1Rs.785113/-
Add: 20 % PremiumRs.157023/-
Total:-Rs.942136/-
Add: 0.50 % Contingency Rs.4711/-
SUB TOTAL:- (D)RS.946847/-
ETEHSILDAR OFFICE BARAWAL
01
02
03
04
05
06
07
08
TOTAL:-RS.
Add: Cost Factor 1.1RS.
Add: 20 % Premium RS.
TOTAL:-RS.
Add: 0.50 % Contingency RS.
G: TOTAL (A+B+C+D)RS.
SUB DIVISIONAL OFFICER
C&W SUB DIVISION PF - 91
UPPER DIR
Add:___________% Above/Below/AT PAR
On CSR 2009.
CONTRACTOR
BILL OF QUANTITY.NAME OF WORK:- REPAIR OF GOVT: BUILDINGS IN DISTRICT UPPER DIR
SUB HEAD:-(1)T.M.A. Office Dir (2)EDO Agriculture
(3)District Officer Live Stock
S#Description Qty:Unit Rate Amount
ADISTRICT OFFICE LIVE STOCK
01Excavation As in foundation 31.71M3105/-Rs.3380/-
02P:C:C: (1:4:8) as in foundation 5.23M32578/-Rs.13483/-
03R:R Stone Masonry (1:6) 83.67M33185/-Rs.266511/-
04P:C:C: (1:3:6) as in coping 1.98M33477/-Rs.6891/-
TOTAL:-RS.290215/-
Add: Cost Factor RS.63847/-
Add: 20 % PremiumRs.383085/-
Add: 0.50 % Contingency Rs.1915/-
SUB TOTAL (B)RS.385000/-
BEDO AGRICULTURE UPPER DIR
01Excavation as in foundation 4.58M3105/-Rs.480/-
02P:C:C: (1:4:8) as in foundation 1.45M32578/-Rs.3738/-
03R:R Stone Masonry (1:6) CSM 8.01M33185/-Rs.25511/-
04Feb: of Mild Steel 0.077Ton82234/-Rs.6332/-
05R:C:C: (1:2:4) as beam 1.07M35261/-Rs.5629/-
06Wooden Trusses 0.25M2112020/-Rs.28005/-
07B:B Work Masonry (1:6) CSM 4.27M33721/-Rs.15889/-
08Wooden Celling6.41M341667/-Rs.10600/-
09E/Board " thick2.41M22229/-Rs.5386/-
10P:C: Plaster (1:4) CSM 22.11M21231/-Rs.2721/-
11P:C Pointing (1:3) CSM 21.65M2128/-Rs.2771/-
12Steel Door 2M22890/-Rs.5780/-
13P:C:C: (1:2:4) 2" thick 3.25M2338/-Rs.1098/-
14CGI Sheet 6.59M2825/-Rs.5436/-
15Oil Painting 3-Coats all Building 328.32M2184/-Rs.60502/-
16W:C 1M22731/-Rs.2731/-
17Floor Trip 1M2273/-Rs.273/-
18White Washing ,distempering 400M242/-Rs.16800/-
19P:C:C: (1:3:6) plaster 30.62M23477/-Rs.106465/-
Total:-Rs.182159/-
VIP Bath Room Rs.161129/-
Civil Work Rs.182159/-
Total:-Rs.343288/-
Add: Cost Factor Rs.377617/-
Add: 20 % Premium Rs.75523/
Total:-Rs.453141/-
Add: 0.50 % Contingency Rs.2266/-
SUB TOTAL:- (C )RS.455407/-
G: TOTAL:- (A+B))RS.2783678/-
SUB DIVISIONAL OFFICER
C&W SUB DIVISION PF - 91
UPPER DIR
Add:___________% Above/Below/AT PAR
On CSR 2009.