brad johnson thesis presentation barriers to certification for leed registered projects

30
Brad Johnson THESIS PRESENTATION BARRIERS TO CERTIFICATION FOR LEED REGISTERED PROJECTS

Post on 20-Dec-2015

221 views

Category:

Documents


0 download

TRANSCRIPT

Brad JohnsonTHESIS PRESENTATION

BARRIERS TO CERTIFICATION FOR LEED REGISTERED PROJECTS

INTRODUCTION

What is Green Building Why is it needed

Resource consumption Energy consumption Economics

Green Building/Sustainability

Optimize Site Potential Minimize Energy Consumption Protect and Conserve Water Use Environmentally Preferable Products Enhance Indoor Environmental Quality Optimize Operational and Maintenance

PracticesWhole Building Design Guide

Why is it needed

Resource Consumption Of the raw materials used, an estimated 40%

are used by buildings In the U.S., in 1996, an estimated 136 million

tons of construction and demolition waste was generated

Why is it needed

Energy Consumption Buildings account for 65.2% of total U.S.

electricity consumption Buildings use greater than 36% of total U.S.

primary energy use

Why is it needed

Economics Reduced energy costs Increased productivity

The United States Green Building Council (USGBC) Formed in 1993 The nation’s foremost coalition of leaders

from across the building industry working to promote buildings that are: environmentally responsible profitable healthy places to live and work

Developed the Leadership in Energy and Environmental Design (LEED) rating system

LEED

A “definitive standard” for what constitutes a green building (Rocky Mountain Institute, 2002).

A point system where points are given in six different categories

Differing levels of certification Projects are registered and certified through a

process of documenting the points earned in each category

THE PROBLEM

Current building practices Green building practices are part of the

solution LEED, a “definitive standard” Several projects are registered but not

certified Why are they not becoming certified? Little research has been done

LIMITATIONS

Projects registered before January 1, 2002 Only early LEED projects are included

LEED was new for these projects Lessons learned

Limited to the accuracy of statements and opinions of respondents

No inference can be made to the population

RESEARCH QUESTIONS

1. What are the motivations for LEED registered projects to become registered and eventually certified?

2. What are some of the encountered barriers for LEED registered projects to become certified?

3. What are some of the observed differences between registered buildings that receive certification and those that do not?

METHODOLOGY

The Population LEED contact persons for projects that were

registered before January 1st 2002

METHODOLOGY

Procedures Identify projects and contact persons Develop the survey Pilot the survey Approval from CSU Human Research

Committee Send survey to the population Analyze the data

Treatment of Data

Multiple choice and Likert scale questions were placed into SPSS

Open ended questions were coded Respondents were divided into two groups to

answer research question three.

RESULTS: Characteristics of Respondents and Projects

Thirty one respondents were LEED accredited professionals and 12 were not

Twenty of the 43 projects were LEED certified Of the 23 non certified projects 14 indicated

that certification was still a goal The owner and architect were the

organizations initiating LEED certification (26 and 15 respectively)

RESULTS: Characteristics of Respondents and Projects

Type of organization that the respondents worked in

11

6

6

9

20

Engineer

GeneralContractor

Other

Green buildingConsultant

Owner

Architect

RESULTS: Characteristics of Respondents and Projects

Respondent Documentation Responsiblility

0

5

10

15

20

25

30

Responsible Participated Not Involved

Involvement

Resp

on

den

ts

RESULTS: Characteristics of Respondents and Projects

Size of Projects

0

5

10

15

20

25

30

Smaller than75,000 sf

75,000 to 300,00sf

Larger than300,000 sf

Project size

Nu

mb

er o

f p

roje

cts

RESULTS: Characteristics of Respondents and Projects

Time in days Frequency Time in days Frequency

0 2 303 1

47 1 317 1

116 1 334 1

120 1 365 1

127 1 397 1

137 1 594 1

183 1 624 1

192 1 795 1

236 1 852 1

259 1 Not Certified 20

Time in days from completion to certificationAverage = 300 days

RESULTS: Characteristics of Respondents and Projects

End use for projects

Government

Medical

Mixed use

Other

Manufacturing

Office space

Retail

Education

12

10

8

6

4

2

0

Count

RESULTS: QUESTION 1- Reasons for certification

Open ended question

Reason FrequencyEnvironmental stewardship / fits the values of the company 19Owner Driven 16To set a standard or example 6Save money through life cycle costs 5Validate achievement through third party review 4To have a good image 3

RESULTS: QUESTION 1- Reasons for certification

Likert scale question (scale from 0 to 5)

Reason MeanStandard deviation

Environmental stewardship 4.33 0.89To keep green building a project priority 3.88 1.19Validate achievement through third party review 3.21 1.26Competitive advantage 2.52 1.47Required by government 1.59 1.94State and local government incentives 1.45 1.49Profit opportunities 1.36 1.17

RESULTS: QUESTION 2- Barriers to Certification

Likert scale question (scale from 0 to 4)

Barrier MeanStandard deviation

Cost of documentation/other indirect cost 2.33 1.183Team members lack of experience w/ LEED cert. 2.17 1.243Cost of green building practices or design 2.05 1.168Direct cost of certification 1.88 1.152Owner unable to recover up front cost 1.53 1.358Communication/misunderstanding with the USGBC 1.49 1.381Poor team communication/education 1.46 1.206Unable to meet LEED prerequisites 1.19 1.087Unable to qualify for enough credits 1 1.148Project team turnover 0.79 1.08

RESULTS: QUESTION 2- Barriers to Certification

Open ended question

Barriers FrequencyDifficulty of LEED documentation 16Cost associated with certification fees, green building practices, and/or design. 13Lack of project team education 7Diffucult communication / misunderstanding with USGBC 6Cost of Documentation 5LEED not part of the planning phase, certification was an afterthought 3Problems applying LEED requirements to unique projects. LEED does not fit all cercimstances 3

RESULTS: QUESTION 3- Differences Between Groups

Likert scale question (scale from 0 to 4)

Barrier CG Mean NCG MeanMean

DifferenceUnable to qualify for enough credits 0.7 1.75 1.05Direct cost of certification 1.15 2.88 1.73Cost of GB practices or design 1.7 2.88 1.18Owner unable to recover up front cost 0.8 2.75 1.95

CG = Certified GroupNCG = Non Certified Group

RESULTS: QUESTION 3- Differences Between Groups

Forty five percent of the certified group stated as a reason for certification “owner driven” none of the non certified group stated this as a reason.

The non certified group mentioned cost more often as a barrier than the certified group

The certified group mentioned a lack of awareness, education or experience as a barrier more often then the non certified group

CONCLUSIONS

Reasons for Certification Environmental stewardship To keep green building a project priority Owner required

Barriers to certification LEED documentation Lack of education Cost Communication Lack of team buy in

CONCLUSIONS continued

Group differences Ranking of barriers

Cost especially Reason for certification

Owner driven

FUTURE RESEARCH

Research the LEED documentation process Cost to benefit study concerning LEED point

categories

QUESTIONS

????????