bridge (revised)
DESCRIPTION
Bridge (Revised)TRANSCRIPT
Maintenance, Inspection and Rehabilitation of Bridges
BySri A.NagendraJoint Secretary (Rtd)Karnataka PWDBangalore
IR-RASTA
WELCOME TO ALL TRAINEES
IR-RASTA
BRIDGES ARE NATIONAL ASSETS
THEY MUST BE MAINTAINED AND PRESERVED IN GOOD CONDITION
IR-RASTA
THREE TYPES OF BRIDGES DEPENDING ON LINEAR WATERWAY1. CULVERTS < 6.0 m
2. MINOR BRIDGES 6.0 to 60.0 m
3. MAJOR BRIDGES > 60.0 m
IR-RASTA
PORTIONS OF A BRIDGE1. FOUNDATION
2. SUBSTRUCTURE
3. BEARINGS
4. SUPERSTRUCTURE
5. PROTECTIVE WORKS FOUNDATION
SUB STRUCTURE
SUPER STRUCTURE
IR-RASTA
BEARINGS
Bed Level
COMPONENTS OF A BRIDGEParapetKerbFoot pathDrainage spoutExpansion Joint Wearing coatDecking structureBearingsBearing seatPierAbutment ReturnsWell cap/Pile capFoundationsProtective Works
IR-RASTA
COMPONENTS OF A BRIDGE (contd)Foundation Open Well Pile
Protective Works Bank Protection Embankment Floor Protection Guide Bunds
IR-RASTA
*****
MAINTANANCEIS DEFINED AS THE WORK NEEDED TO PRESERVE THE INTENDED LOAD CARRYING CAPACITY OF THE BRIDGE AND ENSURE THE CONTINUED SAFETY OF THE ROAD USERS.
REHABILITATIONREHABILITATION OPERATIONS AIM AT RESTORING THE BRIDGE TO THE SERVICE LEVEL IT ONCE HAD AND HAS NOW LOST OR WHICH WAS NOT ACHIEVED DUE TO DEFICIENCES IN ORIGINAL DESIGN OR CONSTRUCTION.
RETROFITTING STRENGTHENING, WIDENING, RAISING ETC., AIMING AT
IMPROVING THE LEVEL OF SERVIE BYa. LOAD CARRYING CAPAICTYb. WIDTH OF CARRIAGE WAY
IR-RASTA
MAINTENANCE BRIDGES FORM VITAL LINK IN ANY
ROAD NETWORK. BRIDGES HAVE TO BE MAINTAINED TO KEEP IT IN TRAFFIC WORTHY CONDITION TO ENABLE UNINTERRUPTED FLOW OF TRAFFIC
SYSTEMATIC MAINTENANCE IS ESSENTIAL TO ENSURE LONG TERM DURABILITY OF BRIDGES
IR-RASTA
OBJECTIVE OF MAINTENANCE
TO KEEP BRIDGES IN SOUND STRUCTURAL CONDITION AND SAFE
FOR TRAFFIC
WATER MUST FLOW FREELY AT ALL FLOOD LEVELS WITHOUT DAMAGING
THE BRIDGE OR WATER WAY
IR-RASTA
MAINTENANCE CONSISTS OF
1. ROUTINE MAINTENANCE ACTIVITIES
2. PERIODIC MAINTENANCE ACTIVITIES
IR-RASTA
ROUTINE ACTIVITIESCLEANING / CLEARINGMINOR REPAIRS LIKEPOINTING OF MASONRYPAINTINGREPAIR TO PARAPETREPLACE DAMAGED FOOTPATH SLABSCLEARING DRAINAGE SPOUTSCLEARING EXPANSION JOINTS
IR-RASTA
PERIODIC ACTIVITIES
RETAINING WALLBED PROTECTIONRESETTING OF APRONS/PITCHINGREPLACING BEARINGSREPLACING EXPANSION JOINTS
IR-RASTA
DEFECTS DEFECTS SHOULD BE DETECTED EARLY.
NEGLECTING CAUSES DAMAGE AND IF UNATTENDED MAY LEAD TO COLLAPSE OF STRUCTURE OR VERY EXPENSIVE REPAIRS
DEFECTS ARE AGAIN CLASSIFIED
1. MINOR DEFECTS
2. MAJOR DEFECTS
IR-RASTA
MINOR DEFECTS1. NON-STRUCTURAL ACCUMULATION OF DIRT AND SOIL ON DECK BLOCKING OF DRAINAGE SPOUT STONE,SOIL,DIRT IN EXPANSION JOINTS DIRT AROUND BEARINGS VEGETATION CRACKING OR MOVEMENT OF APPROACH SLAB SOIL IN WEEPHOLES FLOOD DEBRIS UNDER BRIDGE DEFECTS IN CONCRETE POST AND HANDRAIL SCOUR AT FOOTING, SLOPE FAILURE
MAIN CAUSE POOR ROUTINE MAINTENANCE
IR-RASTA
DEVELOPMENT IF NEGLECTED SLIPPERY ROAD SURFACE WHEN WET – ACCIDENTS
PONDING OF WATER ATTACKING THE STRUCTURE BY PENETRATION
DECK PREVENTED FROM DESIRED EXPANSION CONTRACTION
BUILDING OF PORE PRESSURE BEHIND ABUTMENTS -SETTLEMENT OF FILL
FIRE HAZARD IN DRY SEASON
EROSION OF RIVER BED
REMEDIESCLEANING / CLEARING
IR-RASTA
MINOR DEFECT (contd)2. STRUCTURAL DAMAGED PARAPET MISSING FOOT PATH SLAB MISSING OR LOOSE NUT / CONNECTOR RUSTY STEEL, FADED PAINT DAMAGED WARNING SIGNS DEFECTIVE, MASONRY JOINTS MAIN CAUSES AGE ACTION OF TRAFFIC ACTION OF WATER WEATHERING SETTLEMENT POOR CONSTRUCTION
IR-RASTA
DEVELOPMENT IF NEGLECTED
LOSS OF SENSE OF SAFETYACCIDENT FURTHER DAMAGE BY CORROSIONUNCOMFORTABLE RIDEDAMAGE TO TYRESLOCAL SETTLEMENT OF MASONRYSETTLEMENT OF APPROACHES
REMEDIES
REPLACE MISSING FOOT PATH SLAB AND PARAPETPAINTINGPOINTING MASONRYREPAIR LOOSE OR MISSING CONNECTORS
IR-RASTA
MAJOR DEFECTS WASHING AWAY OF PROTECTIVE WORKS WASHING AWAY OF EMBANKMENT BULGING MASONRY CRACKED CONCRETE / MASONRY SPALLING OF CONCRETE SERIOUS RUST OR CHEMICAL STAINS DAMAGED EXPANSION JOINTS RUSTING OF REINFORCING STEEL OR PRESTESSING CABLE DISTORTED STRUCTURAL STEEL MEMBERS SETTLEMENT OF DECK / PIER / ABUTMENT STREAM EROSION ALL MAJOR DEFECTS SHOULD BE BROUGHT TO THE NOTICEOF THE HIGHER OFFICER IMMEDIATELY
IR-RASTA
MAJOR DEFECTS (contd)
MAIN CAUSES
CAUSE OF MAJOR DEFECTS REQUIRE DETAILED EXAMINATION ON CASE TO CASE BASIS
REMEDIES
REHABILITATION / RECONSTRUCTION
P.S :- NATURAL CALAMITIES LIKE EARTH QUAKE, FLOOD, CYCLONE ALSO CAUSES MAJOR DEFECTS
IR-RASTA
COMMON TOOLS USED FOR MAINTENANCE
IR-RASTA
NOW WE WILL BE SEEING PHOTOGRAPHS OF SOME OF
THE DAMAGED BRIDGES
IR-RASTA
COVER TO DECK SLAB SPALLED
IR-RASTA
SETTLEMENT OF FOUNDATION
IR-RASTA
SETTLEMENT OF FOUNDATION
IR-RASTA
SETTLEMENT OF FOUNDATION
IR-RASTA
SETTLEMENT OF FOUNDATION
IR-RASTA
SETTLEMENT OF FOUNDATION(AFTER RESTORATION)
IR-RASTA
IR-RASTA
IR-RASTA
IR-RASTA
DAMAGE TO SUPER STRUCTURE
IR-RASTA
IR-RASTA
COLLAPSE OF SUPER STRUCTURE
IR-RASTA
CONSEQUENT COLLAPSE OF PIER
DAMAGE TO FOOT PATH SLAB
IR-RASTA
VEGETATION GROWTH
IR-RASTA
VEGETATION GROWTH
IR-RASTA
VEGETATION GROWTH
IR-RASTA
VEGETATION GROWTHIR-RASTA
DISPLACEMENT OF GIRDER
IR-RASTA
CRUSHING OF WEARING COAT
IR-RASTA
CORROSION OF REINFORCEMENT
IR-RASTA
DAMAGED PARAPET
IR-RASTA
DAMAGED PARAPET
IR-RASTA
DAMAGED PARAPETIR-RASTA
TRANSVERSE MOVEMENT OF DECK
IR-RASTA
IR-RASTA
IR-RASTA
DAMAGE TO DECK SLAB
IR-RASTA
DAMAGE TO MAIN GIRDER
IR-RASTA
SPALLING OF CROSS GIRDERS
IR-RASTA
LAPPING OF REINFORCEMENT IN MID SPAN
IR-RASTA
POOR QUALITY CONCRETE
IR-RASTA
LARGE CAVITIES IN CONCRETE
IR-RASTA
CRUSHING OF CROSS GIRDER
IR-RASTA
IR-RASTA
IR-RASTA
SETTLEMENT OF APPROACHES
IR-RASTA
IR-RASTA
IR-RASTA
IR-RASTA
IR-RASTA
SOCIETY HAS RIGHT TO DEMAND ON THE ENGINEER’S SERVICES FOR THE UPKEEP OF THE STRUCTURE SO THAT IT REMAINS THERE FOR THE PURPOSE FOR WHICH IT WAS BUILT IN THE FIRST PLACE
******
IR-RASTA
INSPECTION INDIA HAS THE SECOND LARGEST NETWORK OF ROADS
IN THE WORLD NEXT ONLY TO THE UNITED STATES OF AMERICA
BRIDGES FORM THE VITAL LINKS OF THE NETWORK SIGNIFICANT PROPORTION OF NATIONAL RESOURCES
IS SPENT ON ROADS AND BRIDGES DURABILITY OF INVESTMENT OF SUCH MAGNITUDE AND
IMPORTANCE IS OF PRIME CONCERN TO ALL ENGINEERS AND PLANNERS
THEREFORE IT IS NECESSARY THAT PERIODIC INSPECTIONS ARE CARRIED OUT BY RESPONSIBLE OFFICERS SO THAT TIMELY STEPS ARE TAKEN
IR-RASTA
GUIDELINES FOR INSPECTION IRC – SPECIAL PUBLICATION – NO. 35 “GUIDELINES FOR INSPECTION AND MAINTENANCE OF
BRIDGES” IRC – SPECIAL PUBLICATION - NO. 18 “MANUAL FOR HIGHWAY BRIDGE MAINTENANCE
INSPECTION” IRC – 52 – 1998 – “BRIDGE INSPECTION REFERENCE
MANUAL” THESE MANULS PROVIDE GUIDANCE ON THE TYPE OF INSPECTION TIME AND FREQUENCY OF INSPECTION STATUS OF INSPECTING OFFICER FEATURES TO BE INSPECTED FOLLOW UP ACTION ON THE INSPECTION REPORT
IR-RASTA
INSPECTION (contd) ORIGINAL BRIDGE REPORT TO BE MAINTAINED FOR ALL
BRIDGES ON THE BASIS OF COMPLETED DRAWINGS
FOR OLD BRIDGES BASED ON THE INSPECTION OF RESPONSIBLE OFFICER REPORT TO BE COMPILED
FOR MAJOR BRIDGES ENGINEERS ASSOCIATED WITH CONSTRUCTION OF PROJECT SHOULD ALSO PREPARE MAINTENANCE MANUAL INDICATING CRITICAL POINTS NEEDING SPECIAL ATTENTION FOR GUIDANCE OF SUBSEQUENT ENGINEERS WHO WILL BE INCHARGE OF MAINTENANCE
IR-RASTA
TYPES OF INSPECTION
THE TYPES OF INSPECTION ARE
1. ROUTINE INSPECTION
2. PRINCIPAL INSPECTION
3. SPECIAL INSPECTION
IR-RASTA
ROUTINE INSPECTION – THE PURPOSE IS TO DETERMINE OBVIOUS DEFICIENCIES WHICH MIGHT LEAD TO ACCIDENTS OR MAY INVOLVE HIGH MAINTENANCE COSTS IN FUTUREFREQUENCY OF ROUTINE INSPECTION SHALL BE TWICE A YEAR BEFORE MONSOON AND AFTER MONSOON
IR-RASTA
PRINCIPAL INSPECTION THIS IS MORE INTENSIVE AND DETAILED CLOSE VISUAL INSPECTION OF ALL COMPONENTS OF
BRIDGE SUPPLEMENTED BY STANDARD INSTRUMENTATION AID INCLUDES UNDER WATER INSPECTION
FREQUENCY
FIRST PRINCIPAL INSPECTION TO BE CONDUCTED BEFORE THE EXPIRY OF DEFECT LIABILITY PERIOD BUT NOT LATER THAN 6 MONTHS AFTER COMPLETION
THEREAFTER NOT MORE THAN 3 YEARS
SHALL BE CARRIED OUT BY SENIOR LEVEL ENGINEER
IR-RASTA
SPECIAL INSPECTION UNDERTAKEN IN THE EVENT OF UNUSUAL
OCCURANCES SUCH AS
STRONG EARTHQUAKE ACCIDENTS PASSAGE OF UNUSUAL FLOODS OR UNUSUAL LOADS HEAVY IMPACT OF FLOATING BARGES OR FLOOD
DEBRIS MAJOR WEAKNESS NOTICED DURING ROUTINE OR
PRINCIPAL INSPECTION SUCH INSPECTIONS REQUIRE GOOD DEAL OF
SUPPLEMENTARY TESTING AND STRUCTURAL ANALYSIS
GENERALLY CARRIED OUT BY EXPERTS IN THE FIELD AND SENIOR LEVEL ENGINEERS
IR-RASTA
LENGTH OF BRIDGE STATUS OF OFFICER
UPTO 30 m30 m to 60 m
60 m to 200 m
JUNIOR ENGINEERASST. ENGINEER/ASST. EX ENGINEEREXECUTIVE ENGINEER
ABOVE 200 m AND ALL PRESTRESSED CONCRETE, CONTINUOUS BRIDGES, SUSPENSION BRIDGES, CABLE STAYED BRIDGES AND SPECIAL STRUCTURES
SUPERINTENDING ENGINEER IN ALL CASES AND IN ADDITION CHIEF ENGINEER FOR BRIDGES ABOVE 500 m IN LENGTH
INSPECTING OFFICERS
INSPECTION PROCEDURE ACTIVITIES SCHEDULED SHOUD BE PROPERLY PLANNED IN DETAIL
INCLUDING SEQUENCE OF INSPECTION SHOULD CAUSE MINIMUM INCONVENIENCE TO TRAFFIC
NO COMPONENT SHOULD BE OVERLOOKED
TYPICAL PATTERN MAY BE FOUNDATION ABUTMENTS WINGWALLS / RETURNS PIER-PIERCAP BEARINGS SOFFIT OF DECK AND BEAM DETAILS UNDER THE DECK CONDITION OF ROADSURFACE CONDITION OF FOOTPATH SLAB, PARAPET, DRAINAGE SPOUTS EXPANSION JOINTS CONDITION OF APPROACHES CONDITION OF PROTECTIVE WORKS
THE M.O.R.T.H HAS EVOLVED STANDARD PROFORMA FOR INSPECTION OF BRIDGES WHICH COVERS ALL COMPONENTS
IR-RASTA
ACCESS FOR INSPECTIONALL THE THREE FORMS OF INSPECTION REQUIRE
APPROPRIATE MEANS OF ACCESS BUILT IN ACCESS MANHOLE BUILT IN LADDER PERMANENT CATWALK
SEMI MOBILE ACCESS SUSPENDED LADDER CATWALK SCAFFOLDING PLANKING PLATFORM
MOBILE ACCESS SKY LADDER INSPECTION GANTRY BARGES MOBILE INSPECTION UNIT
IR-RASTA
SKY LADDER
IR-RASTA
INSPECTION PLATFORM SUSPENDED
IR-RASTA
INSPECTION BARGE
IR-RASTA
MOBILE INSPECTION UNIT
IR-RASTA
BRIDGE INSPECTION VEHICLE
IR-RASTA
IR-RASTA
BRIDGE INSPECTION VEHICLE
BRIDGE INSPECTION VEHICLE
IR-RASTA
MOBILE INSPECTION UNITIR-RASTA
MOBILE INSPECTION UNIT
IR-RASTA
INSPECTION GANTRYIR-RASTA
INSPECTION OF BRIDGES SHOULD BE CARRIED DILIGENTLY AND EARNESTLY
THIS HELPS IN FORMING PROPER REHABILITATION SCHEMES FOR WEAK BRIDGES
*****
IR-RASTA
REHABILITATION BRIDGE STRUCTURES DURING THEIR SERVICE LIFE MUST
HAVE A SPECIFIED LEVEL OF SAFETY AND SERVICE ABILITY UNDER DESIGN LOADS AND ANTICIPATED CONDITIONS OF USE
BRIDGES, HOWEVER, GENERALLY DETERIORATE WITH PASSAGE OF TIME DUE TO
AGING AND WEATHERING INADEQUATE MAINTENANCE INADEQUACIES IN DESIGN AND DETAILING MISHAPS AND ACCIDENTS CHANGE OF HYDRAULIC AND LIVE LOAD PARAMETERS
DURING SERVICE DAMAGES DUE TO EXTERNAL CAUSES LIKE FLOOD, FIRE,
EARTHQUAKE AND FOUNDATION SETTLEMENT
REHABILITATION AIMS AT RESTORING THEBRIDGE TO THE SERVICE LEVEL IT ONCE HAD AND HAS NOW LOST
IR-RASTA
TYPES OF BRIDGES VARIOUS TYPES OF BRIDGES MASONRY BRIDGES – STONE/BRICK R.C.C BRIDGES STEEL BRIDGES COMPOSITE CONSTRUCTION PRESTRESSED CONCRETE BRIDGES TIMBER BRIDGES FORMS OF BRIDGES ARCH – MASONRY CONCRETE STEEL GIRDERS WITH CONCRETE DECK SLAB R.C.GIRDERS WITH DECK SLAB BOX GIRDERS R.C.C.RIGID FRAME P.S.C.GIRDERS AND DECK SLAB P.S.C. BOX GIRDERS
IR-RASTA
NORMALLY OBSERVED DISTRESS ARCH BRIDGES CHANGE IN PROFILE OF ARCH LOOSENESS OF MORTAR MOVEMENT OF ABUTMENT/PIER LONGITUDINAL CRACKS LATERAL AND DIAGONAL CRACKS CRACKS BETWEEN ARCH RING SPANDREL OR PARAPET WALL VERTICAL CRACK IN THE RETRUN WALL BULGING OF WALL R.C.C BRIDGES CRACKING SCALING DELAMINATION SPALLING LEACHING STAINS HOLLOW OR DEAD SOUND DEFORMATIONS HOLE IN DECK SLAB PRESTRESSED CONCRETE BRIDGES CRACKING LEACHING STAINS SPALLING DEFORMATION ABNORMAL VIBRATION
IR-RASTA
STEPS INVOLVED IN WORKING OUT A REHABILITATION PROJECT
EVALUATION OF STRUCTURE FROM AVAILABLE DOCUMENTS AND INSPECTION
LOCATING DAMAGES/DEFECTS/DESTRESS ANALYSIS OF CAUSES OF
DAMAGES/DEFECTS/DISTRESS EVALUATION OF RESULTS OF STRUCTURAL
ASSESSMENT DESIGN OF REPAIRS FOR
REHABILITATION/STRENGTHENING FRAMING PROPOSALS AND ESTIMATION OF COSTS FIXING OF AGENCY CARRYING OUT REHABILITATION WORK
IR-RASTA
TECHNICAL APPROACH FOR REHABILITATION
STRATEGY FOR DETERMINATION IS IN THE LIGHT OF
THROUGH INVESTIGATION DIAGNOSIS OF THE CAUSES OF DETERIORATION,
FAULT, WEAKNESS ASSEESSMENT OF CURRENT CONDITION OF
BRIDGE REPAIR AND STRENGTHENING SHOULD BE
STRUCTURALLY AND CHEMICALLY COMPATIBLE WITH THE ORIGINAL STRUCTURE
IR-RASTA
EVOLUTION OF REHABILITATION TECHNIQUES
WITH THE GROWTH OF STRUCTURES INVOLVING COMBINATION OF CONCRETE AND STEEL, PROBLEM OF FUNCTIONALLY SATISFACTORY AND STRUCTURALLY DEFICIENT STRUCTURES AROSE
THIS LED TO THE SCIENCE OF REHABILITATION, WHICH IS RELATIVELY NEW COMPARED TO DESIGN AND CONSTRUCION
REHABILITATION DEMANDS KNOWLEDGE OF DESIGN,DETAILING, CONSTRUCION CHEMISTRY OF MATERIALS, DIAGNOSTIC TECHINQUES, HIGHLEVEL OF ENGINEERING AND SUPERVISION
SUCCESSFUL IMPLEMENTATION OF A REHABILITATION PROGRAM INVOLVES WORK OF MULTIDISCIPLINARY TEAM OF SPECIALISTS FOR INVESTIGATION, DIAGNOSIS, ENGINEERING AND SUPERVISION
CONTINUOUS MONITORING DURING REHABILITATION AND SUBSEQUENT SERVICELIFE IS MANDATORY
IR-RASTA
TESTING AND DIAGNOSIS INVESTIGATION PRIOR TO INVESTIGATION AVAILABLE DRAWINGS MUST
BE STUDIED TO IDENTIFY VULNERABLE DETAILS INVESTIGATION IS CARRIED OUT IN THREE LEVELS• VISUAL METHODS – USEFUL IN DETECTING CRACKING, SCALING
RUSTING, WEARING, ABRASION DAMAGES• GENERAL SURVEY – WITH LIMITED PHYSICAL TESTS TO PLAN FOR
MORE DETAILED INVESTIGATION AND POSSIBLE REHABILITATION• DETAILED TESTING CONSISTING OF ELECTRICAL AND CHEMICAL METHODS – FOR DETECTING CORROSSION ULTRASONIC METHODS – FOR CRACK DETECTION THERMOGRAPHY AND RADAR TECHNIQUE – FOR DETECTING
DELAMINATION AND SCALING BELOW WEARING COAT RADIOGRAPHY – FOR DETECTING VOIDS IN THE GROUT
IRC – SP – 40 – GUIDELINES FOR REHABILITATION OF STRUCTUES GIVES ELABORATE LIST OF TESTS
IR-RASTA
TO ASSESS THE EXTENT OF DISTRESS AND PRESENT CONDITION OF BRIDGES FOLLOWING STUDIES ARE CONDUCTED
STUDY PURPOSE
1. DIMENSIONAL MEASUREMENT OF ALL ELEMENTS OF BRIDGE STRUCTURE
2. CORE EXTRACTION (CST)
TO OBTAIN ACCURATE MEASUREMENTS OF ALL COMPONENTS AND TO PREPARE DRAWING REQUIRED FOR ARRIVING AT METHODS OF RESTORATION
TO ASSESS THE STRENGTH OF INSITU CONCRETE AND FOR VERIFICATION OF RESULTS OF OTHER METHODS OF NON DESTRUCTIONVE TESTING
IR-RASTA
STUDY PURPOSE
3. ULTRASONIC PULSE VELOCITY TEST (UPVT)
4. REBOUND HAMMER TEST(RHT)
TO ASSESS THE QUALITY OF CONCRETE IN GENERAL. DETERMINATION OF UNIFORMITY OF CONCRETE, INTERNAL CRACKING, HONEY COMBING.THE EQUIPMENT IS KNOWN AS “PUNDIT” (PORTABLE ULTRASONIC NONDESTRUCTIVE DIGITAL INDICATING TESTER)
ASSESSING THE QUALITY OF COVER CONCRETEBASED ON SURFACE HARDNESS. HIGHER THE REBOUND NUMBER HIGHER THE STRENGTH.
IR-RASTA
STUDY PURPOSE
5. COVER METER TEST (CMT)
6. HALF CELL POTENTIAL MEASUREMENT TEST
(HCPT)
7. ENDOSCOPIC STUDY
BASED ON ELECTRO MAGNETIC PRINCIPLES TO ASSESS THE COVER PROVIDED. LOCATING AND MAPPING OF REINFORCEMENTS
MEASURED IN TERMS OF MILLIVOLTS WITH REFERENCE TOA REFERENCE ELECTRODE. TO DETERMING THE RATE OF CORROSION OF REINFORCEMENT
WORKS ON THE PRICIPLE OF LIGHT SOURCE THROUGH OPTIC FIBRES. TO STUDY CAVITY, PITTING OF EMBEDDED REINFORCEMENT GROUTING QUALITY OF H.T.CABLES
IR-RASTA
STUDY PURPOSE8. CARBONATION TEST
9. CHLORIDE DETERMINATION TEST
10. SULPHATE DETERMINATION TEST
TO DETERMINE THE DEPTH OF CARBONATION IN R.C.ELEMENTS
TO ESTIMATE THE LEVEL OF CHLORIDES IN CONCRETE.PRESENCE OF HIGHER AMOUNT OF CHLORIDES SURROUNDING THE REINFORCEMENT CAUSES CORROSION
TO ESTIMATE THE LEVEL OF SULPHATE IN CONCRETE.PRESENCE OF HIGHER AMOUNT OF SULPHATES WILL RESULT IN REACTION WITH CALCIUM CAUSING DETERIORATION OF CONCRETE.
IR-RASTA
STUDY PURPOSE11. LEVEL OF pH IN CONCRETE LEVEL OF pH IN FRESH
CONCRETE IS GENERALLY 12 TO 14. IF THE pH VALUE OF HARDENED CONCRETE REDUCES IT INDICATES THAT CONCRETE IS CARBONATED WHEN pH VALUE FALLS BELOW 10 ALKALANITY WILL NOT BE ADEQUATE TO PROTECT AGAINST CORROSION
IR-RASTA
RESULTS CAN BE SUMMARISED AS
• MECHNICAL PROPERTIES
• CHEMICAL PROPERTIES
• PHYSICAL CONDITION
• EXTERNAL MANIFESTATION
*****
IR-RASTA
NON DESTRUCTIVE TESTS NECESSARY FOR CONDUCTING NON DESTRUCTIVE
TESTING FOR CONDITION ASSESSMENT OF BRIDGES HAS GROWN CONSIDERABLY IN RECENT TIMES DUE TO INCREASING NUMBER OF BRIDGES SHOWING SIGNS OF DISTRESS
A LARGE VARIETY OF TECHINQUES AND METHODS ARE BEING DEVELOPED ALL OVER THE WORLD TO ASSESS MATERIAL PROPERTIES AND STRUCTURAL RESPONSE
SCOPE, APPLICABILITY, AND ACCURACY VARY CONSIDERABLY FROM INSTRUMENT TO INSTRUMENT
NON DESTRUCTIVE TESTING IS SUPPLEMENTARY TO VISUAL INSPECTION
IT IS A GROWING FIELD OF SCIENCE AND HAS GREAT SCOPE FOR RESEARCH AND DEVELOPMENT
IR-RASTA
SCHMIDT HAMMER TEST
IR-RASTA
SCHMIDT HAMMER TEST
IR-RASTA
CONCRETE CORE EXTRACTION
IR-RASTA
CONCRETE CORE EXTRACTION
IR-RASTA
PROFOMETER TEST
IR-RASTA
PROFOMETER TEST
IR-RASTA
ULTRASONIC TESTS
IR-RASTA
HALF CELL POTENTIAL TEST
IR-RASTA
CHLORIDE PENETRATION TEST
IR-RASTA
ENDOSCOPE TESTIR-RASTA
*****
REPAIRS AND STRENGTHENING TECHNIQUES
CRITERIA FOR SELECTION OF MATERIALS AND TECHNIQUES FOR REPAIRS AND STRENGTHENING COULD BE
CAUSES OF DISTRESS EFFICIENCY OF THE MATERIALS AND TECHNIQUES IN THE
PRESERVATION AND/OR ENHANCING LOAD CARRYING CAPACITY OF THE STRUCTURE
AVAILABILITY OF MATERIALS AND EQUIPMENT IMPORTANCE OF THE BRIDGE TIME AVAILABILITY LIFE EXPECTANCY FEASIBILITY OF TRAFFIC DIVERSION
IR-RASTA
REPAIRS TO FOUNDATIONS FOUNDATION REPAIRS HAVE TO BE TREATED ON CASE TO CASE
BASIS. EACH CASE HAS TO BE ANALYSED INDIVIDUALLY AND MAY REQUIRE SPECIAL INVESTIGATIONS
SOME EXAMPLES SCOUR AND EROSION PROTECTION REPAIR OF PROTECTIVE WORKS REPAIR OF FOUNDATION BUILT ON SOFT GROUND SUBJECT TO
EROSION STRENGTHENING OF FOUNDATIONS EXTENDING EXISTING FOUNDATIONS REPAIR OF UNDER WATER STRUCTURES REPAIR OF SERRATIONS ON THE SURFACE CAUSED BY HIGH VELOCITY
OF PARTICLES IN THE WATER UNDER WATER WORK PROPERLY TRAINED AND EQUIPPED PERSONNEL TO BE DEPLOYED SOPHISTICATED TECHNIQUES LIKE ULTRASONIC THICKNESS GUAGE,
COMPUTER TOMOGRAPHY, ACOUSTIC MICROGRAPY ARE BEING INCREASINGLY ADOPTED
IR-RASTA
REPAIRS TO MASONRY STRUCTURES LOSS OF BOND FOR CROWN STONEFLAT JACKS ARE USED FOR PUSHING THE STONE TO ORIGINAL
POSITION LOW PRESSURE CEMENT GROUTING IS DONE TO STRENGTHEN OLD MORTAR
LONGITUDINAL CRACKS ALONG THE DIRECTION OF TRAFFICFOR SMALLER DEPTH OF CRACKS RAKE THE MORTAR JOINTS AND REFILL WITH CEMENT MORTARIF DEPTH OF PENETRATION IS MORE IT IS BETTER TO ADOPT FINE
CEMENT INJECTION(GROUTING) FOR REMEDIAL MEASURESGENERALLY IT IS CHEAPER AND BETTER TO GROUT THE CRACKS WITH
CEMENT THAN WITH EPOXY TRANSVERSE CRACKSINJECTION OF CEMENT WILL PROVIDE A GOOD BOND BETWEEN STONE
OR BRICK MASONRY STRENGTHENING OF ARCH RINGSBY ADDING MATERIALS TO INTRADOS AND EXTRADOS
IR-RASTA
REPAIRS AND STRENGTHENING TECHNIQUES FOR CONCRETE BRIDES
REPAIR WORKS NOT REQUIRING STRENGTHENINGTHIS MAY BE CATEGORISED AS REPAIR OF CONCRETE SURFACE REPAIR OF CONCRETE CRACKS REPAIR OF CORRODED REINFORCEMENT REPAIR OF HIGH TENSILE STEEL REPAIR OF POROUS CONCRETE AND HOLES PREREQUISITE FOR REPAIR OF CONCRETE SURFACE IS REMOVAL
OF LOOSE DAMAGED AND FRACTURED CONCRETE BY MECHANICAL METHODS HYDRAULIC METHODS NORMALLY USED MECHANICAL METHODS ARE MILLING, CHIPPING,
SANDBLASTING AND COMPRESSED AIR CLEANING HYDRAULIC METHODS SUCH AS WATER JETTING ARE PREFERABLE TO
JACK HAMMERS FOR PREVENTING DAMAGE 10 – 40 MPa – REMOVAL OF LOOSE PARTICLES, VEGETATION, STAINS 40 – 120 MPa – REMOVAL OF LOOSE CONCRETE 120 – 240 MPa – DEMOLITION, CUTTING
IR-RASTA
RESTORATION MATERIALS
Several restoration materials have been developed in the recent past,which ensure safe and durable restorations. A few of them are -
Modified Mortars. Epoxy Mortars. Cementitious/Epoxy Grouts. Membrane/Protective Coatings. Glass Fiber / Carbon Fiber wrappings Free Flow Micro Concrete. (Super Fluid Micro Concrete)
Free Flow Micro Concrete is an ideal material for encasement / Substitution systems
*****
IR-RASTA
Repair materialsApplication / purpose Speciality chemicals
Corrosion protection Anticorrosive zinc rich coatings, corrosion inhibiting admixtures, permeability reducers like plasticisers and superplasticisers etc.
Bonding aids Acrylic, Styrene Butadiene rubber, epoxies
Additives for grouting / gunniting, shotcreting
Cement based
Prepacked mortars Polymer modified cement based, epoxy based etc.
Shrinkage compensating microconcrete
Cement based
Injection grouts for sealing cracks, pores
Low viscous epoxies, polyurethane’s, cement based
Underwater repairs Epoxy, cement based
Sealing compounds Epoxies, polyurethanes, polysulphides, silicones
Instant plugging mortar Cement based
IR-RASTA
Putties Cement, epoxy based
Anchoring grouts Polyester resin based
Underwater putty Epoxy based
Chemical resistant screed Epoxy based
Mortars / concretes Epxoy, cement based
Anticarbonation coatings Aliphatic, acrylate based
Chemical resistant coatings Epoxy, polyurethane based
Electrochemical range of products like sacrificial zinc anodes, Life jackets, Electrochemical chloride extraction and Realkalisation etc.
Strengthening of structures Composite fibre wrapping
Waterproof slurries / coatings Polymer and cement based epoxy based.
Special concretes Microconcretes, epoxy concretes, latex concretes, polymer modified cements, sulpher concrete, fibre reinforced concrete, shrinkage compensating concretes etc.
Repair materialsApplication / purpose Speciality chemicals
IR-RASTA
Popular Restoration Techniques
1. Substitution techniques
2. Encasement techniques
3. Wrapping-Round techniques
4. Shortcreting techniques
5. Pressure grouting
6. Prestressing techniques
7. Material Strengthening techniques
IR-RASTA
Sl.No. Repair Technique Distress addressed Materials used
1 Injection grouting Seal cracks and pores in concrete.Arrest leakages
Epoxies / Polyurethane Cement also used
2 Guniting / shotcreting Replace cover concreteReinstate locally damaged areasBuild up thickness in overhead situations
Gunites / shotcretes and admixtures
3 Jacketing Reinstatement of extensively damaged concrete members, strengthening for load enhancement
Concrete with water reducing / Shrinkage compensating admixtures
4 Stitching Repair of cracked concrete Holes grouted with epoxy / polyester / cement with nonshrink additives
5 External prestressing For cracked concrete members HTS bars + anchors
6 Microconcrete encasement
Extensively damaged concrete beams and columns. Enhance load carrying capacity. Increase flexural rigidity
Shrinkage compensating, free flow microconcretes
7 Epoxy steel plate bonding
Strengthening weakened members. Reduce deflection
Anchor grout / epoxy for bonding
Repair TechniquesIR-RASTA
8 Underwater repairs Cracks under water strengthening of structures, reinstatement of worn out areas, localised damages etc.
Under water admixtures, anti washout microconcretes, moisture insensitive epoxy resins and putties
9. Patch repairs Localised reinstatement of worn out concrete
Polymer modified / latex modified mortars, epoxy mortars
10. Composite fibre wrapping Strengthening of distress / weakened concrete members, seismic retrofitting
E-glass / carbon / armid fibres with epoxy primer and saturant
11. E-chem repairs Long-term corrosion protection. Prevention of formation of incipient anodes
Sacrificial anodes / Life jackets
12. General grouting To densify porous concrete slabs, retaining walls etc.
Non shrink, plasticising, additives
Repair Techniques
IR-RASTA
STRENGTHENING OF CONCRETE STRUCTURES
STRENGTHENING OF STRUCTURAL MEMBERS CAN BE ACHIEVED BY
REPLACING POOR QUALITY OR DEFECTIVE MATERIAL BY BETTER MATERIAL PROVIDING ADDITIONAL LOAD BEARING MATERIAL REDISTRIBUTION OF THE LOADING ACTIONS THROUGH IMPOSED
DEFORMATION OF THE STRUCTURAL SYSTEM NEW LOAD BEARING MATERIAL WILL USUALLY BE HIGH QUALITY CONCRETE REINFORCING STEEL BARS THIN STEEL PLATES AND STRAPS POST TENSIONING TENDONS VARIOUS COMBINATIONSDESIGN ASPECTSSHOULD BE DESIGNED AND CONSTRUCTED AS PER APPROPRIATE
CODESTYPICAL PROBLEMS WILL BE TRANSFER OF SHEAR FORCES BETWEEN OLD AND NEW CONCRETE POST TENSIONING OF EXISTING STRUCTURE WHICH IS SLIGHTLY
DIFFERENT FROM POST TENSIONING OF NEW STRUCTURE
IR-RASTA
STRENGTHENING OF REINFORCEMENTSTRENGTHENING OF REINFORCEMENT SUBJECT
TO TENSILE FORCE CAN BE ACHIEVED BYREPLACING REINFORCEMENT SEVERELY
DAMAGED BY CORROSIONADDITIONAL REINFORCEMENT PLACED IN THE OLD CROSS SECTION PLACED IN AN ADDITIONAL CONCRETE LAYEREPOXY BONDED STEEL PLATES
THE STRENGTHENING WITH STEEL PLATE AND EPOXY IS WORKMANSHIP SENSITIVE AND SHOULD BE DONE UNDER EXPERT GUIDANCE ONLY
IR-RASTA
STRENGTHENING TO INCREASE LOAD CARRYING CAPACITY
IR-RASTA
STRENGTHENING THE SHEAR ZONE
IR-RASTA
STRENGHTENING THE STEEL GIRDERS
IR-RASTA
IR-RASTA
IR-RASTA
IR-RASTA
STRENGTHENING WITH SUPPLEMENTARY PRESTRESSING
STRENGTHENING BY MEANS OF SUPPLEMENTARY PRESTRESSING IS AN EFFECTIVE METHOD. BOTH R.C.C AND P.S.C STRUCTURES CAN BE STRENGTHENED
ONLY POST TENSIONED SYSTEMS ARE BEING ADOPTED USE OF LOWER STRENGTH, HIGHER DUCTILITY THREADED
BARS WOULD BE SIMPLE. ROBUST AND DURABLE AVOIDS HIGH COST OF ANCHORAGES
DESIGNED AS NORMAL POST TENSIONED GIRDER EXCEPT THAT EFFECT OF CREEP AND SHRINKAGE FOR OLD CONCRETE IS FAR LESS
POST TENSIONING TENDONS SHOULD BE PROTECTED AGAINST COROSION AND FIRE TO THE SAME EXTENT AS IN A NEWLY BUILT STRUCTURE
IR-RASTA
ANCHORAGE WITH AUXILIARY STEEL FRAME
IR-RASTA
ANCHORAGE OF SUPPLEMENTARY PRESTRESSING ELEMENTS WITH
ADDITIONAL SUPPORTS
IR-RASTA
ANCHORAGE OF SUPPLEMENTARY PRESTRESSING ELEMENTS AT THE END
OF THE GIRDER
IR-RASTA
IR-RASTA
PROFILE OF EXTERNAL PRESTRESSED CABLE
IR-RASTA
EXTERNAL PRESTRESSED CABLE
IR-RASTA
DEFLECTOR FOR CABLE SUPPORT
IR-RASTA
MONITORING IT IS ESSENTIAL TO KEEP THE REHABILITATED STRUCTURE UNDER
OBSERVATION AND ITS CONDITION MONITORED REGULARLY ON A SPECIFIED FORM AND INSPECTIONS ARE CARRIED OUT ACCORDING TO A CALENDER
MONITORING ALSO INVOLVES CARRYING OUT CERTAIN LABORATORY AND FIELD TESTS AS WELL AS CONDITION SURVEYS AND MEASUREMENTS TO DETECT EVEN SMALL STRAINS, MOVEMENTS, CHANGES IN REACTION AND DEFORMATIONS
FREQUENT PRINCIPAL INSPECTIONS SHOULD BE CARRIED OUT SPECIAL ATTENTION SHOULD BE GIVEN TO CORROSION
MONITORING AFTER COMPLETION OF EACH JOB OF REHABILITATION, ENGINEER
MUST PREPARE A DOCUMENT TO ENABLE DRAWING LESSONS FOR THE FUTURE AND TO IMPROVE BRIDGE TECNOLOGY
IR-RASTA
BRIDGE MAINTENANCE AND MANAGEMENT IN FUTURE
EVERY STATE IN THE COUNTRY IS BURDENED WITH A NUMBER OF OLD BRIDGES ON ITS ROAD NETWORK MAINTENANCE NEEDS FOR OLDER BRIDGES HAS OUTSTRIPPED AVAILABLE RESOURCES
THE SITUATION DEMANDS NEED FOR IMPROVED REPAIR AND REHABILITATION TECHNIQUES AND ALSO COMPREHENSIVE APPROACH TO BRIDGE MANAGEMENT
THE INDIAN ROADS CONGRESS, MINISTRY OF ROAD TRANSPORT AND HIGHWAYS, THE STATE PUBLIC WORKS DEPARTMENT ARE WORKING TO DEVELOP BRIDGE MANAGEMENT SYSTEMS INTEGRATING THE DISCIPLINES OF STRUCTURAL ENGINEERING, CHEMICAL TECHNOLOGY, INSTRUMENTATION TEHCNOLOGY, OPERATIONS RESEARCH, ECONOMICS PLANNING AND INFORMATION TECHNOLOGY
IR-RASTA
BRIDGE MAINTENANCE(CONTD.) A CENTRAL AUTHORITY IN EACH STATE SHOULD
INSPECT AND INVENTORISE ALL THE BRIDGES ON THE NETWORK. THIS WILL HELP THE DECISION MAKERS FOR OBTAINING TIMELY AND QUALITY DATA ABOUT BRIDGE CONDITIONS. PROJECT COSTS AND FEASIBILITY INSPECTION AND INVENTORISING IS A MAMMOTH PROGRAM AND SHOULD BE DONE IN A PLANNED AND METICULOUS MANNER
IN FUTURE BRIDGE INSPECTION WILL FOCUS ON THE QUANTITATIVE ASSESSMENTS OF BRIDGE PERFORMANCE AND CONDITIONS RATHER THAN VISUAL INSPECTIONS AND CONDITION RATINGS
A VARIETY OF PERMANENT SENSORS ON BRIDGES WILL COLLECT DATA AT MANY POINTS. THESE SENSORS WILL BE POWERED BY – AND REPORT TO WIRELESS NETWORKS. DATA WILL BE ANALYSED AND DETERIORATION WILL BE DETECTED AUTOMATICALLY
IR-RASTA
WHEN PROBLEMS ARISE, ENGINEERS WITH KNOWLEDGE AND EXPERIENCE WILL BE ABLE TO ACCURATELY ANALYSE THE STRUCTURAL CONDITION AND FORMULATE CORRECTIVE STRATEGIES
TECHNOLOGY WILL GREATLY ENHANCE THEIR ABILITY TO MAKE THESE ASSESSMENTS
IR-RASTA
BRIDGE MAINTENANCE(CONTD.)
BRIDGE MAINTENANCE AND REPAIR
HITHER TO REPAIR OF BRIDGES HAS BEEN A REACTIVE ACTIVITY INITIATED ONLY WHEN DETERIORATION THREATENS SAFETY
THE BRIDGE MANAGEMENT SYSTEM WANTS TO EMPHASIZE COST-EFFECTIVE & PROACTIVE ACTION FROM THE TIME WHEN BRIDGE IS NEW.
FUTURE FOCUS WILL BE PREVENTIVE MAINTENANCE. INCREASE IN SERVICE LIFE WILL BE THROUGH ROUTINE ACTIVITIES LIKE CLEANING OF BRIDGE COMPONENTS, OVERLAY RENEWAL, MAINTAINING INTEGRITY OF JOINT SEALS, IMMEDIATE PAINTING OF STEEL
IR-RASTA
• FUTURE APPROACH
APPROACH TO BRIDGE MAINTENANCE IS INCREASINGLY INFLUENCED BY BRIDGE MANAGEMENT SYSTEMS. FUTURE STRATEGY INCLUDES LIFE-CYCLE COST ANALYSIS AND INCORPORATION OF USER COST INTO MAINTENANCE DECISIONS
BRIDGE MAINTENANCE ENGINEERS WILL USE AN ARRAY OF INCRESINGLY SOPHISTICATED INSTRUMENTS PROCEDURES AND
SYSTEMS TO EVALUATE, REPAIR AND REHABILITATE STURCTURES
RESEARCH IN MATERIALS WILL CONTINUE WITH EMPHASIS ON PRODUCTS SUCH AS NON CORRODING REINFORCEMENTS, IMPERMEABLE CONCRETE SUPERIOR COATINGS THAT WILL DRASTICALLY BRING DOWN MAINTENANCE REQUIREMENTS WHEN USED IN NEW CONSTRUCTION
IR-RASTA
BEST BRIDGE IN THE WORLD?
FRIENDSHIP
MAINTAIN IT
THANK YOU