bsbpmg503a manage project time 6.4 estimate activity duration the process of approximating the...
TRANSCRIPT
BSBPMG503A Manage Project Time
6.4 Estimate Activity Duration
• The process of approximating the number of work periods needed to complete individual activities with the assigned or estimated resources
• Previous experience in the type of project and activities being estimated greatly helps with the accuracy of duration estimates
• Duration is a function of work effort and resources
• Most project management software can perform this function
• Occurs during the Planning Phase
Adapted from PMBOK 4th Edition
Initiation Planning Execution Close
Monitor
Control
BSBPMG503A Manage Project Time
6.4 Estimate Activity Duration
• Inputs to Estimate Activity Duration
Activity list and attributes
Activity Resource requirements and estimates
Resource Calendars
Project Scope Statement
Productivity metrics and estimating data
• Tools and techniques to Estimate Activity Duration
Adapted from PMBOK 4th Edition
Three-PointEstimating
ExpertJudgement
AnalogousEstimating Parametric
Estimating
ReserveAnalysis
BSBPMG503A Manage Project Time
6.4 Estimate Activity Duration
• Analogous EstimatingDevelops duration estimates based on previous projects with
similar size, risk and complexity
Relies heavily of expert judgement and previous experience
Less costly and less time consuming than other methods
Least accurate
Most common form of duration estimating
• Parametric EstimatingDuration is quantified by multiplying the quantity of work by
the labour hours required
Relies on published estimating data
Common in Construction
Initiation Planning Execution Close
Monitor
Control
Adapted from PMBOK 4th Edition
BSBPMG503A Manage Project Time
6.4 Estimate Activity Duration
• Three-Point Estimates - PERT
Calculates the Expected activity duration based on the weighted average of the Most Likely, Optimistic and Pessimistic estimates
Often more accurate than other methods and quantified range of uncertainty
• Reserve Analysis
Inclusion of contingency
Can be calculated for each activity
Can be calculated for entire project
Often a percentage based on risk or complexity
Initiation Planning Execution Close
Monitor
Control
Adapted from PMBOK 4th Edition
BSBPMG503A Manage Project Time
6.4 Estimate Activity Duration
• The major output of this process
Activity Duration Estimates
Draft or High Level Project Duration Estimate
• Often include some form of range of possible results
• Most common form of range is plus or minus - eg
2 weeks +/- 2 days – the activity could take between 8 and 12 days
3 weeks +/- 30% - the activity could take between 2 weeks and 4 weeks
Adapted from PMBOK 4th Edition
Initiation Planning Execution Close
Monitor
Control