bsf borehole status review final - rural water supply thanks to the ministry of water resources and...
TRANSCRIPT
Status Review of BSF’s borehole drilling
component in South Sudan (2006-2012)
Government of South Sudan
Department for International Development (DFID)
Lucie Leclert – BSF WASH monitor
BMB/Euroconsult Mott MacDonald
Acknowledgements
The BSF Secretariat would like to thank in particular all the grant recipients, including the grant
recipients from previous BSF phase, for their time and efforts to execute this status review.
Special thanks to the Ministry of Water Resources and Irrigation, and especially to Eng. Isaac
Liabwel, Under Secretary of the MWRI, Peter Mahal Dhieu, Director General of Rural Water
Supply & Sanitation, Emmanuel Parmenas, Director General of Planning and Manhiem Bol
Malek, Director Water Supply and Development for their availability, regular feedback and advice.
Lucie Leclert
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald ii
Content
Chapter Title Page
List of Abbreviations iv
Executive Summary v
1. Introduction to BSF 1
2. Background 2
3. Purpose 4
4. Concept 4
4.1 Functionality vis-à-vis sustainability ______________________________________________ 4
4.2 Conceptual framework ________________________________________________________ 5
5. Methodology 7
5.1 Materials for data collection ____________________________________________________ 7
5.2 Method for data collection _____________________________________________________ 8
5.3 Limitations of the status review methodology ______________________________________ 9
6. Results of the Boreholes’ Status Assessment 9
6.1 Information received __________________________________________________________ 9
6.2 BSF Borehole functionality rate ________________________________________________ 10
6.3 Analysis of the reasons for non-functionality ______________________________________ 10
6.4 Analysis of the reasons for reduced functionality ___________________________________ 12
6.5 Analysis of the main factors that influence functionality ______________________________ 13
6.6 Other factors that can influence functionality ______________________________________ 15
7. Feedback from NGOs on their drilling activities implementation and impact of the
BSF monitoring approach 17
7.1 Types of contract used and its impact on borehole sustainability ______________________ 17
7.2 Impact of the introduction of independent drilling supervision _________________________ 19
7.3 Feedback from NGOs on their training component _________________________________ 20
8. Conclusion 21
9. Recommendations 24
10. Literature 26
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald iii
Annexes
Annex 1 BSF IA extention. WASH Monitor ToR 28
Annex 2 Institutional and legal context of the WASH Sector 30
Annex 3 Spare parts : Background, Status and views for the future 32
Annex 4 Water quality : Background, current status and indicators 34
Annex 5 Some definitions 35
Annex 6 Borehole Status Review Package: Note sent to the NGOs 37
Annex 7 Borehole Status Review Package : Data Collection Sheet 42
Annex 8 Borehole Status Review Package : Questionnaire to NGOs 44
Annex 9 Key Dates of the Status Review 45
Annex 10 Total boreholes drilled for BSF per NGO and per State 46
Annex 11 Records received per NGO, State and Phase and functionality status 48
Annex 12 Average cost per completed borehole per grant recipient per BSF phase 50
Annex 13 Supporting tables for Unit costs analysis 54
Annex 14 Combined Lessons learned BSF : WASH 56
Annex 15 Examples of types of trainings provided by NGOs 58
Tables
Table 1. BSF Phases, financial envelopes and periods. ................................................................. 1
Table 2. Percentage of population with access to improved water source (various sources) ......... 2
Table 3. Contribution of BSF borehole drilling and repair/rehabilitation activities to MDGs ............ 3
Table 4. Information to collect during the BSF borehole field assessment ..................................... 8
Table 5. Number and percentage of non-functional boreholes reported on per BSF phase......... 11
Table 6. Reasons for actual non-functionality ............................................................................... 11
Table 7. Number of boreholes with reduced functionality and reasons for it................................. 13
Table 8. Breakdown of the functionality status depending on the activeness of the WUC ........... 13
Table 9. Breakdown of the functionality status per type of facilities .............................................. 14
Table 10. Breakdown of the functionality rate per type of underlying geology .............................. 15
Table 11. NGOs’ selection of drilling supervisor ............................................................................ 20
Figures
Figure 1. Conceptual framework : classification of operational status of a borehole ...................... 5
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald iv
List of Abbreviations
BoQ Bill of Quantities
BSF-IA Basic Services Fund – Interim Arrangement
BSF-IAe Basic Service Fund – Interim Arrangement extension
CPA Comprehensive Peace Agreement
CWD County Water Department
DFID Department for International Development
GoS Government of Sudan
GRoSS Government of Republic of South Sudan
JAM Joint Assessment Mission
LS Lump Sum
MDG Millennium Development Goals
MDTF Multi Donor Trust Fund
MWRI Ministry of Water Resources and Irrigation
NBHS National Baseline Household Survey
NGO Non-Governmental Organisation
O&M Operation and Maintenance
PMA Pump Mechanic Association
PWD Payam Water Department
RWSS Rural Water Supply and Sanitation
SDWS State Directorate of Water and Sanitation
SHHS Sudan Household Health Survey
SPLM Sudan People’s Liberation Movement
SSWICH South Sudan Water Information Clearing House
WASH Water Supply, Sanitation and Hygiene
WES Water Environment Sanitation (Database)
WIMS Water Information Management System
WUC Water User Committee
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald v
Executive Summary
In South Sudan, many NGOs are involved in the Water Sanitation and Hygiene (WASH) sector.
Over the four rounds of BSF (2006-2012), 29 NGOs received funding for drilling new boreholes. A
total of 578 hand pump boreholes have been drilled under BSF, providing access to safe water to
144,500 people (based on 250 people per borehole1), assuming all water points are still
functional2.
To guide NGOs towards a more consistent, efficient and sustainable way to implement drilling
activities and to engage in capacity building activities, advice was provided to gradually bring the
NGO sector in line with MWRI sector guidelines and recommendations. Improvements to the
sustainability of borehole drilling, operation and maintenance can be achieved through the
implementation of the following recommendations:
� MWRI and the BSF Secretariat strongly recommended the use of Bill of Quantities (BoQ)
instead of Lump-Sum (LS) contracts;
� MWRI and the BSF Secretariat strongly recommended the need to systematically carry out a
geophysical survey before the start of any drilling activity;
� MWRI and the BSF Secretariat strongly recommended that the services of a full-time drilling
supervisor is used, preferably from the local authorities;
� MWRI and the BSF Secretariat strongly recommended that there is an increased focus on
training and capacity building to ensure the sustainability of the boreholes.
The aim of this status review, requested by DFID, was first, to assess the current operational
status of BSF boreholes drilled between 2006 and 2012, through a borehole functionality
assessment, and, second, to evaluate the impact of the recommendations provided to the
implementing agencies, through requesting information and feedback on how they have been
implementing their drilling activities and the soft component associated to it. The main limitations
of this status review included the risks of biased information (as the data was collected mainly by
the NGOs that constructed the boreholes) and the fact that it took place during the rainy season,
reducing the possibility to access some boreholes.
Regarding the borehole functionality assessment, 69% of the newly drilled boreholes were
assessed, with a good coverage per State and BSF phase. The 31% of the boreholes on which
no information was received are mostly the inaccessible boreholes, or the boreholes made by
NGOs that have withdrawn from the area; implying that these might also be the boreholes with a
higher occurrence of breakdowns or reduced functionality.
The functionality rate as established by the assessment was high, reaching 96.5%. The
boreholes are relatively new, which contributes to the high functionality rate. The assessment of
1 The number of beneficiaries for one borehole is estimated to 250, as, in the Technical Guidelines ‘for the Construction
and the Management of Borehole with Handpump (MWRI, 2009), it is indicated that it is 500 beneficiaries in emergency
situation and 250 beneficiaries for normal situation. As it is impossible to define ‘normal’ situation’ (as it greatly varies
per areas in South Sudan) . Not to over-estimate, it was decided to count on 250 beneficiaries per borehole, keeping in
might that the reality is between 250 and 500. 2 Various other water supply activities were funded under BSF, mostly including the rehabilitation of 535 existing
boreholes, providing renewed access to close to 134,000 people.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald vi
functionality status went one step further by analysing the reasons for reduced functionality or
breakdown. Out of the total reported boreholes, 76.8% were fully functional. Non-functional
boreholes were mainly as a result of a technical break down. Water quality was also a reason for
not using a borehole. The main reasons for reduced functionality were difficulties with pumping
and an objectionable taste or colour.
Factors that can influence functionality are numerous and interrelated. One of the key findings of
this status review is that the existence of a Water User Committee (WUC) appears to have a
positive impact on functionality rate. Therefore, it is important to continue providing training of
WUC, with a special focus on early warning signs and preventive maintenance. Refresher WUC
trainings will also help communities and water pump caretakers to remain active and to continue
collecting fees for potential repair needs. Boreholes located in health facilities had a higher
functionality rate compared with community boreholes or boreholes located in schools.
The feedback from the NGOs on the way they implement drilling activities demonstrated that BoQ
contracts, geophysical surveys and drilling supervision are more and more practiced. Efforts to
systematically implement those recommendations should continue to be advocated, as it is
believed to have a positive impact on borehole functionality and sustainability.
There is a general consensus amongst NGOs that lack of (preventive) maintenance is a result of
lack of ownership, which depends on the extent to which communities value water. NGOs have
been actively engaging in training activities in parallel to their drilling activities, including training
of WUC as well as pump mechanics. From an ownership perspective, repair should be executed
by communities or the local pump mechanics (and not by NGO). Donors should restrict funding to
those activities that will enable communities to execute preventive maintenance and the small
repairs. Examples of such activities are the implementation of refresher WUC trainings,
continuous sensitisation of communities on the need to pay for the delivery of water, provision of
tool kits, refresher training of pump mechanics, supporting the County Water Department (CWD)
in having an updated list of pump mechanics as well as the repair activities that have been
performed, activities related to the development of Pump Mechanics Associations (PMA) and the
private sector for the provision of spare parts. Rehabilitation however requires the services of
contractors.
Rehabilitation of a borehole from a cost perspective is more efficient than drilling a new borehole
(provided that the reasons for the status of the borehole are technical and can be solved). One
key recommendation for future funding programs could thus be to focus on rehabilitation. That
would help increase the low functionality rate county wide (30-50% of the boreholes in South
Sudan are non-functional, according to the Water Policy, 2007) in the most cost effective way.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 1
1. Introduction to BSF
After decades of civil war3, the Comprehensive Peace Agreement (CPA) was signed in January
2005. This was a turning point in South Sudan’s history. Since the CPA, the Government of
Republic of South Sudan (GRoSS), with support of international donors, has been actively
engaging in activities to improve its citizen’s access to basic services. Written in 2005, The Sudan
Joint Assessment4 (JAM) sets the framework for the consolidation of peace, and for attaining
broad-based growth, poverty reduction and sustained human development and presents the
requirements for reconstruction and development for the six year interim period between the CPA
and the referendum for independence of South Sudan. Reaching the targets for improving access
to basic services and developing infrastructure are key priorities.
This is the context in which the Basic Services Fund (BSF) was established, initiated by the
Department for International Development of the UK (DFID). Its overall goal was to expand
access to education, health and water and sanitation to communities recovering from conflict.
While it was originally supposed to end in June 2008, the fund was extended and other donors
started to contribute (Government of Canada, the Netherlands and Norway). Since its start, 4
phases have been consecutively implemented. Up to today (November 2012), a total of
96,093,529 GBP has been spent on education, health and WASH projects (Table 1).
Table 1. BSF Phases, financial envelopes and periods.
Phase Total Contract (GBP) Managed Funds (GBP) NGO grants Grant Periods
BSF1 17,984,643 16,221,447 14 From 1-04-06 to 31-12-08
BSF2 23,568,485 21,554,792 25 From 1-01-09 to 31-06-10
BSFIA 42,676,292 39,970,000 38 From 1-07-10 to 31-12-11
BSFIA e 20,000,000 18,347,290 26 From 1-01-12 to 31-12-12
Total 104,229,420 96,093,529
Since 2006, this integrated approach contributed to the establishment of operational primary
schools, primary health clinics, drinking water points and latrines; in parallel with capacity
building, including training of teachers and health professionals, Water Users Committees (WUC)
and pump mechanics, and management training of local beneficiary groups and County and
State authorities. The strong capacity building and training component has aimed at ensuring the
sustainability of the investment, and that access to basic services is maintained at minimum
levels.
The last phase of BSF (BSF-IAe) focused on providing basic services in the health and education
sector, and ensuring that supported facilities (health facilities and schools) have access to
improved water sources and sanitation.
3 The second civil war started in 1983 and ended in January 2004. 4 Carried out jointly by the World Bank and the United Nation, with the full endorsement, guidance and participation of the
Government of Sudan (GOS) and the Sudan People’s Liberation Movement (SPLM).
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 2
2. Background
General context
Though South Sudan is generally well endowed with water resources, it faces major challenges in
terms of access to water, as a large part of the existing infrastructure was neglected or even
destroyed during the war. Data on trends shows limited progress since 1990 (JAM, 2005). At the
signing of the CPA in January 2005, only 27% of the population of 8 million inhabitants had
access to improved water supply (Water Policy, 2007), The number of water points was
estimated to 6,500, with 65% out of order (JAM, 2005). The total population per water point
ranged from 1,000 to 64,000 and average water collection journeys in un-served areas were up to
8 hours (JAM, 2005).
Different sources indicate that the situation in terms of access to improved water sources is
improving. One of the JAM objectives was that, at the end of 2011, 3,500 boreholes would have
been drilled and equipped with hand pumps (3,000 new boreholes and 500 rehabilitated
boreholes). According to the WIMS5, the number of water points in the country is around 10,000
as of 2010, which shows that the target has been reached. However, the functionality rate in 2011
still seems to be low: The Water Policy (2007) and the WASH Sector Strategic Framework (2011)
indicate that 30-50% of the water points are non-operational at any time in the different States.
A great deal still needs to be done to reach the Millennium Development Goals (MDG). Though
difficult to estimate precisely, the percentage of population having access to improved water
source is an indicator monitored by various sources throughout the year. The Sudan Household
Health Survey (SHHS) 2006 and 2010 shows an increase of the percentage of population having
access to improved water source from 48.3 % in 2006 to 68.7% in 2010 (according to the WHO
definition of access6). Table 2 summarises the different estimates provided by each source.
Table 2. Percentage of population with access to improved water source (various sources)
Source 19902 2004 2005 2006 2009 2010
NBHS1
55% tot pop
53% rural pop
67% urban pop
SHHS 48.3% tot pop 68.8% pop
Water
Policy
27% tot pop
JAM Limited improvement between 1990 - 2004
25-30% rural
pop
1 NBHS: National Baseline Household Survey
2 Baseline MDG
The current monitoring method assesses progress solely on the basis of the types of facilities used. It
does not take into account other important parameters, such as the availability of adequate quantities
5 The MWRI has a Department called Water Information Management System (WIMS) Department, created to manage
an integrated database that provides a systematic way of gathering information about water to assist in decision making at
all levels of the Water Sector. 6 http://www.wssinfo.org/definitions-methods/introduction/
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 3
of water for domestic use, the number of service hours available, the distance to a water source, or the
time household members spend to access sources and facilities (SPHERE project, 2012). Drinking
water quality is also not taken into account as there is still limited capacity to test water quality in the
country7. Though it is becoming a key priority to the Ministry of Water Resources and Irrigation
(MWRI), water quality monitoring is currently conducted in an uncoordinated way by line ministries,
humanitarian agencies and NGOs (see Annex 4 for more details on the current capacity for water
quality monitoring and testing in South Sudan). When taking into account the above mentioned
parameters as well as the estimated low functionality rates of boreholes in South Sudan, the
actual access of population to improved water sources has been estimated to reduce to 34%,
according to the South Sudan Development Plan 2011-2013 (SSDP)8. If one takes 2010 as the
baseline, then the target set in 2005 in the JAM to double rural safe water from the 2004 baseline
of 25-30% by the end of 2011 has not been reached.
Annex 2 provides an overview of the Institutional and legal context of the WASH sector.
Rural water supply achievements through BSF
In South Sudan, many NGOs are involved in the rural water supply sector. Over the four rounds
of BSF, 29 NGOs have received funds for drilling and repair/rehabilitation of new boreholes.
Besides drilling, they have also engaged in activities to ensure the sustainability of the borehole,
following the recommendations of the BSF Secretariat. A total of 578 new hand-pump boreholes
(including the target of 27 boreholes for the on-going BSF-IAe phase) were drilled and 535
boreholes were repaired or rehabilitated9. A definition of maintenance, repair and rehabilitation is
provided in Annex 5. In Annex 10, the breakdown of boreholes drilled per NGO for each BSF
phase is provided10
.
MDG 7, Target 10 is: ’To reduce by half the proportion of people without access to safe drinking
water for 2015’. Considering a total population of South Sudan of 10 million people, BSF has
contributed to increasing the access to improved water sources to 2.7% of the population (see
Table 3).
Table 3. Contribution of BSF borehole drilling and repair/rehabilitation activities to MDGs
No of boreholes
under BSF
People served/borehole Total population served % of population in 2012
Emergency Normal Emergency Normal Emergency Normal
New 578 500 250 289,000 144,500 2.9% 1.4%
Rehab 535 500 250 267,500 133,750 2.7% 1.3%
Total 556,500 278,250 5.6% 2.7%
7 Multi-parameter field test kits exist and are, in some cases, used by NGOs. 8 In the SSDP, the percentage of 34% of people with access to improved water sources is taken as a baseline for 2010. It
does not distinguish rural or urban areas. However, the objectives for urban and rural areas are set both independently
but both based on this 34%, which seems inaccurate. The target set for 2013 for urban and rural areas are respectively:
45% and 40%. 9 The focus on repair and rehabilitation started with BSF-IA. Before that, those boreholes were not clearly reported on. 10 For BSF-IAe, the total number of drilled boreholes indicated is the total target for the phase. The actual number drilled
as per the end of QPR 3 for BSF-IAe is 16.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 4
3. Purpose
Borehole functionality is a major challenge in South Sudan. The National Water Policy (echoed in
the WASH sector Strategic Framework) states that only 30-50 % of the boreholes are functional
in South Sudan at any time.
Throughout the last six years that BSF facilitated drilling and rehabilitation of boreholes in South
Sudan, the BSF Secretariat has gradually optimised its monitoring approach and the related
advice given to the implementing agencies in order to improve the sustainability of the boreholes
drilled. As the management of the BSF by Euroconsult / BMB Mott MacDonald comes to an end
by the end of December 2012, DFID requested the BSF Secretariat to conduct a status review of
the drilling activities since 2006. The ToR of the WASH Monitor for the execution of this status
review is provided in Annex 1.
The purpose of this status review is twofold :
- to assess the current operational Status of BSF boreholes drilled between 2006 and
2012, through a borehole functionality assessment
- to evaluate the impact of the recommendations provided to the implementing agencies,
through NGO’s feedback on how they implement drilling activities
4. Concept
4.1 Functionality vis-à-vis sustainability
Functionality is a simple snapshot view of whether or not water supply systems are working at the
time of inspection. It cannot on its own tell anything about the reasons for the particular state that
the water point is in, or why it may be providing an adequate service, intermittent service or no
service at all. Functionality data are of limited value, but they are often the best indication
available of inadequacies in sustainable service provision.
The sustainability of services is a challenge that professionals in the water sector have been
concerned about for many years. Sustainability is defined here as “continues to work over time
and ‘with the indigenous human and financial resources available’. (If the inputs are external e.g.
donor/NGO, then can it be termed sustainable?). Functionality on the other hand is about whether
a service is operating at a particular point in time. The partial functionality or non-functionality of a
service may provide a trigger for more detailed investigations of sustainability11
.
11 After Richard C Carter et al. ; WaterAid, UK: IRC Symposium 2010, Pumps, Pipes and Promises - User financing of
rural hand pump borehole water services; from www.washcost.info.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 5
4.2 Conceptual framework
Figure 1 summarises the degrees in types of ‘operational status’ of a borehole. It was developed
based on observations and discussions in the field.
Figure 1. Conceptual framework : classification of operational status of a borehole
The approach followed for the borehole functionality assessment goes beyond a standard
functionality assessment. It aims to get substantial information on the current operational status of
BSF’s newly drilled boreholes by:
� Analysing the degree of functionality (fully functional, reduced functionality, or non-functional);
� The problems that led to reduced functionality or non-functionality;
� The reasons why those boreholes have not been repaired;
� The limiting factors that jeopardise their functionality.
As depicted in Figure 1, a borehole can be in use but still having a reduced functionality. The
approach for this survey is to quantify those different degrees of functionality so as to reach a
Serious breakdown
Rehabilitation needed
Functional but hard to pump
Functional but water taste/colour issues
In use
Not in use
Constructed at unfavourable
location
Bad water quality
No pump mechanic came
(transport or availability issue)
Functional but turbid water
Functional but low yield
(throughout the year)
What is the
operational status
of the borehole ?
No spare part available
The community has not
informed anyone (yet)
Functional but no water in the dry
season
Completely functional
The community is not able (yet)
to pay for the repairs
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 6
better understanding of the main factors that have an impact on borehole sustainability (some of
which could potentially lead to a break down). The reasons for reduced functionality can be :
� Low yield throughout the year
Low yield means a lesser yield than the yield of a hand pump (700 litres per hour). A low yield
can be an aquifer characteristic; in that case this would have been found out during analysis of
the test-pumping results. It can also be due to a borehole completion problem, for instance the
borehole has been sited at the wrong location, has not been drilled deep enough, has not been
installed properly, or not properly developed. Other (technical) reasons can include well
diameters (Larger Diameter wells recharge quicker and can sustain higher abstraction rates),
clogging of the filter screen or even a screen with too small a filter size, the grain size of the
packing material around the well which can create locally lower permeability (This can be caused
by the grouting material or sand being forced lower down around the screen).
� Seasonal water supply, i.e. the borehole will have a reduced yield in the dry season, or even
dry up in the course of the dry season
The most probable reason is that the borehole was not drilled deep enough. This may happen
with boreholes in basement rocks that are only tapping water from the overburden which is being
depleted over the dry season and not from the fractured bedrock, or with shallow boreholes in
sedimentary aquifers, that only penetrate the upper water-bearing layer which is of insufficient
extent and also recharged directly from rainwater. The wrong positioning of the screen and the
fact of carrying out the groundwater exploration and subsequent pumping tests during or just after
the wet season can also lead to lower than expected yield.
� Bad taste of the water, coloured water, or turbid water
Problems of water taste and colour, and turbidity, though both water quality issues, are put in two
different categories in Figure 1 as the causes for the water quality issues are different. Taste
issues or coloured water issues are mainly related to the characteristics of the aquifer; mostly it is
related to iron content (reddish colour and metallic taste), and salinity. Although this water is fit for
human consumption, it is excessively hard and salty, and therefore objectionable to the
population. However, turbid water /water with suspended particles is usually the result of a
construction/design issue, for example insufficient well development or placement of the screens
opposite a geological formation that should not have been screened, or inappropriate filter pack.
Turbid water is therefore in most cases in fact the result of a technical failure.
� Difficulty to pump
Difficulty of pumping can have various causes. The causes can be due to borehole completion
issues: for example, the alignment during installation can be improper; either due to poor
installation, or due to non-vertical borehole, or even a default in the manufacture, where bearings
were not properly aligned and designed. When communities complain about ‘hard to pump’, they
might also mean that the water takes long to come, which might be explained by the fact that the
pumps can take long to fill up the column, which can be caused by either a leakage in the pipes,
or the effect of a deep aquifer. This means that the difficulty in pumping may either have a
technical or a geological reason.
Apart from an actual break down, there are other reasons for communities not to use a borehole.
An objectionable water quality or an unfavourable location can lead communities to opt for other
water sources options, even though these might be more unsafe. Examples of unfavourable
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 7
locations include proximity of a river, too far from the community settlement or close to an army
camp. Inaccessibility of the borehole due to insecurity or floods is another possible reason.
In case of a break down, two categories have been distinguished:
� A break down that can be repaired by a pump mechanic;
� A serious breakdown that can only be addressed by rehabilitation;
In the case of repairs that can be handled by a pump mechanic, the survey aims to understand
the reasons why the repair has not happened as yet, which may include the following situations:
� The community has actually informed no one of the breakdown;
� Though the information on the break down was communicated, no pump mechanics came
(which might be due to logistical limitations such as no transport or a accessibility problem);
� The fact that no spare parts are available at local level (which can similarly be due to a
transport and/or accessibility problem). An overview of the background, the status and the
future development of the spare parts’ supply chain is provided in Annex 3.
� The community is not (yet) able to pay for the repairs.
5. Methodology
5.1 Materials for data collection
Since the beginning of BSF in 2006, a total of 29 NGOs received funds for drilling 578 new
boreholes. To execute the status review, each NGO received a so called BSF Borehole Status
Review Package composed of the following:
BSF Borehole Status Review Package
- A general note (Annex 6), explaining the scope and the objectives of the status review
- A data collection sheet (Annex 7) for the borehole functionality assessment to
serve as a support in the field to collect data from the communities about the borehole’s
operational status12
.
- A questionnaire (Annex 8) addressed to the NGOs on construction, independent
supervision, activities to ensure borehole’s sustainability and government involvement, to
be filled by the NGOs
Each NGO was requested to report on all their boreholes and to send their questionnaire back to
the BSF Secretariat. No random sampling method was used for the borehole functionality
assessment. Getting a representative sample would be difficult as too many variables are
involved including, amongst others, type of underlying geology, implementing NGO, age of
borehole, type of contract used for the drilling, drilling company contracted, accessibility,
availability of spare parts, degree of ownership by the community, etc. For the boreholes who
were not (or hardly) accessible during the period of the status review, NGOs could do a quicker
assessment, by simply calling a community member or a local pump mechanic to give the
information on whether the borehole is functional or not. The BSF Monitor also visited some
12 The questions of the data collection sheet were transposed into an excel spreadsheet, in which, per NGOs the list of
boreholes (name, location and geographic coordinate) that was drilled was indicated.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 8
NGOs and has assessed about 70 boreholes with them. In a few cases, NGOs had withdrawn
from the site where they drilled boreholes (case of AMREF, AMA) which made data collection
difficult.
The involvement of the governmental institutions at all levels is an essential component of this
status review. Therefore, the data collection sheet, the questionnaire and the methodology was
developed in close collaboration with the MWRI. Field visits of the BSF WASH monitor would
mostly start by a meeting with a representative of the State Directorate of Water and Sanitation13
(SDWS) and County or Payam Water Department (CWD or PWD). When possible, someone
from the CWD would accompany the WASH Monitor and the NGO WASH expert to the sites and
assist in executing the assessment. Their feedback has also been taken into account in the
interpretations and the conclusion of this report. The timeline of the status review is included in
Annex 9.
5.2 Method for data collection
Data collection for the borehole functionality assessment
During the assessments, the NGOs were recommended to ask the questions to a group rather
than an individual, as this raises discussions among them and the final answer is more likely to
be closest to reality. In case of a borehole located in a school or a health center, the NGOs were
recommended to talk to a member of the parent Teachers Association or to a health worker.
Table 4 summarizes the information to collect when on the site of the borehole.
Table 4. Information to collect during the BSF borehole field assessment
General information
� Name of borehole, Location (Payam, County), Geographic coordinates
� Name of drilling company and drilling date
� Location of the borehole : Health facility, school or community
� Is the borehole functional?
� Information on WUC (including gender aspects)
If the borehole is functional If the borehole is not functional
Questions so as to understand whether the
borehole has some minor issues that could
lead to a complete breakdown in the close
future
Questions on the reasons why the borehole is not being
used. If it is because the borehole has broken down, then
the objective of the assessment will be :
� To understand what was exactly the issue
� Why it has not been repaired yet
Questionnaire for NGO
The questionnaire sent to the NGOs aimed at collecting information and feedback from NGOs on:
� Construction aspects, including type of contract used with the contractors, the approach to dry
boreholes, whether they requested the services of a supervisor during the drilling
� Methods to ensure drilling activities’ sustainability (type of training, follow up activities…)
� Opinion on the sector’s main shortcomings
� Involvement of the government
13 The SDWS is a directorate of the State Ministry of Physical Infrastructure
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 9
5.3 Limitations of the status review methodology
Non-controllable factors
The status review was carried out between May and November 2012, which coincides with the
rainy season. Some boreholes were thus not accessible and could not be reported on.
Some boreholes were drilled by NGOs that are no longer based in that area.
Possible biases
The information provided in this report is based on the assumption that NGOs really executed the
status review. NGOs that have been more committed to execute the status review properly might
have spent more time at each borehole and therefore had more time to discuss with the
communities and to spot functionality issues. Other NGOs who might have executed the
assessment quicker might have not noticed any issues with the borehole at first sight. It therefore
does not seem appropriate to look at the functionality rate per NGO and draw conclusions from it.
The answers given during the borehole assessment highly depend on the person from the
community that is being interviewed, i.e. whether (s)he is part of the WUC, the time (s)he could
dedicate for the questions, and his/her knowledge of the status of the borehole.
Methodological points that could have been improved
Some questions in the data collection sheet could have been formulated in a different way, which
would have led to slightly different reactions from the community. For example, the question ‘is
everything working fine with the borehole?’ was always confirmed. As long as the borehole
provides water, the answer to this question will be ‘yes’ even though there is a functionality
problem
When the borehole is functional, the question: ‘Has it ever broken down?’ could have been
added, as well as the questions ‘For how long did it need repairs’ and ‘who came to repair it’.
6. Results of the Boreholes’ Status Assessment
6.1 Information received
Records on 400 boreholes out of a total of 578 new boreholes drilled through BSF were received,
providing an assessment rate of 69%. The breakdown per NGO, State and BSF phase is
provided in Annex 10, tables A, B and C.
Almost all NGOs have reported on some or all their boreholes, except for those that have
withdrawn from the specific area (AMA, AMREF). Others, and especially when NGOs do not have
a core activity in the water sector, have not at all reported (World Relief, Care, Save the Children,
and Medair).
Reported boreholes are spread over the four phases: 57% of the boreholes drilled during BSF 1,
64% of BSF 2, and 81% of BSF IA. For BSF-IAe, only the boreholes reported up to the QPR3
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 10
(16) have been included. The functionality rate was calculated based on the total reported
boreholes (and not the total number of boreholes drilled).
Except for Lakes State, the results cover the whole country. However, the percentage of reported
boreholes strongly varies per State, with, for example, 91% of reported boreholes in Eastern
Equatoria and 96% in Western Equatoria, as opposed to 13% in Warrap and 29% in Western Bar
El Gazal. This is mainly due to variations in accessibility.
Inaccessibility during the rainy season is the main factor that has restricted NGOs to visit and
report on all their boreholes14
. It is difficult to know whether the 31% of the boreholes not reported
on would follow the same trend as the 400 boreholes reported on. One may expect that the
occurrence of breakdowns or reduced functionality in limited access areas during the rainy
season is higher, as accessibility challenges also reduce the possibility:
� For the communities to inform the authorities about potential functionality issues;
� For the pump mechanics to be able to reach the area where repairs need to be executed; and
� For the spare parts to reach the CWD and, in a second place, the site of the breakdown
The analysis in the following sessions is based on the information received. A unit cost analysis
was executed and is provided in Annex 12 and Annex 13.
6.2 BSF Borehole functionality rate
Out of the 400 boreholes of which reports were received, 386 have been reported functional and
14 non-functional, leading to a functionality rate of 96.5%. This is a very high rate in view of South
Sudan’s reported overall functionality rate of 50-70% to the young age of BSF boreholes is
expected to be one of the reasons for higher functionality rates than a spot-check of all boreholes
ever drilled in the country.
Functional means that the borehole is in use at the time of spot-check, but it does not mean that
the borehole has no functionality problems. 306 boreholes were reported to be without any
noticeable issues, leading to a percentage of 77% of boreholes that are fully functional. In order
to have a meaningful discussion on the status of boreholes drilled under BSF up to now, the
focus was put on the parameters related to reduced functionality. It is also important to note that
the status at spot-checking does not mean that it never broke down before. Some boreholes had
broken down earlier but were rehabilitated or repaired.
6.3 Analysis of the reasons for non-functionality
A non-functional borehole may be the result of a break down, an objectionable water quality or an
unfavourable location of the borehole. Overall, 3.4% (14 boreholes) of the boreholes are not
functional at the time of the spot-check, assuming that the boreholes reported on per BSF phase
provide a representative sample for that phase. The majority of the non-functional boreholes (11)
14 Another option that was given to them was to contact someone living in the vicinity of the borehole and asking about its
functionality without doing the full assessment. This explains why, in some cases, the sum fully functional + reduced
functionality (361) does not always equal total functional borehole; in those cases only ‘non-functional’ or ‘functional’
would be reported, which does not make it possible to determine either full functionality or reduced functionality
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 11
are down because of a break-down, whereas three boreholes are non-functional due to an
objectionable water quality. BSF-2 has the highest percentage of non-functional boreholes, at
10.5%. One of the non-functional boreholes was reported to have a low yield, implying that the
borehole does not yield sufficient water for a hand pump. This borehole should not have been
installed with a hand pump. It may be classified as a dry borehole. Table 5 provides an overview
of the non-functional boreholes for the 4 BSF Phases.
Table 5. Number and percentage of non-functional boreholes reported on per BSF phase
BSF1 BSF2 BSFIA BSF IAe Total
Total Bh reported (number of completed
bh)
89 (156) 95 (149) 201 (247) 16 (27) 401 (579)
Percentage reported on 57% 64% 81% 59% 69%
Total Bh non-functional 2 10 2 0 14
Percentage non-functional: 2.2% 10.5% 1.0% 0%
- Total Bh broken down 2 7 2 0 11
- Total Bh not functional for other
reasons
3 3
The borehole assessment form included questions that aim at identifying the undermining factors
why the broken down boreholes were not repaired as yet (see Table 6).
Table 6. Reasons for actual non-functionality
Issues that jeopardise the possibility of repairs (as per Figure 1)
Repairs cannot be executed by a pump
mechanic
For nine boreholes, the response was that repairs can be
executed by a pump mechanic.
For two boreholes, a pump mechanic would not be able to repair
it, with the following additional comments: ‘a new borehole is
needed’, and ‘the area has a salty aquifer’
The community has not informed anyone
yet
For nine boreholes, the information had been transmitted.
For two boreholes, the community had not informed anyone
(one out of the two said that the WUC is not active so they did
not call a pump mechanic; also, the caretaker is not skilled to
execute the repair)
The community has informed but no
pump mechanic came yet (transport or
availability issue)
Two have informed pump mechanics, six the CWD, four no
detail
Out of the nine that have informed someone, seven said that
they are still waiting for the pump mechanic to come and one
said that a new borehole is needed
No spare parts available Not directly mentioned. The lack of spare parts has been
mentioned in many case by the local authorities as the main
reason why pump mechanics cannot execute repairs
The community is not able to pay for the
repairs
One stated that they are mobilising the community to collect the
funds and the other one has collected the funds already. The
others do not have an active WUC.
Serious breakdown : rehabilitation
needed
Reported in one case.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 12
Six out of the 11 broken down boreholes were reported to be non-functional for over six months,
whereas three boreholes were reported to be down for one week to one month (no info on the
remaining two). Only one borehole was reported to be in need of rehabilitation.
Though the communities seem to submit the information of the breakdown (to the CWD or the
pump mechanic), it appears getting a pump mechanics to execute the repairs is the main limiting
factor. According to local authorities and MWRI, it is mainly due to the fact that no spare parts are
available at local level. Even if the pump mechanic would go to the borehole site, (s)he would not
be able to replace the broken parts. Other reasons may be logistical challenges to reach the
borehole site.
6.4 Analysis of the reasons for reduced functionality
Although almost 97% of BSF’s boreholes were reported in use at the time of the assessment,
some of these are only partially functional. As Table 7 displays, overall, 54 (13%) of BSF’s
boreholes reported on are in use but have issues that need to be addressed in order to make
them fully functional. The highest percentage of reduced functionality boreholes is reported for
those boreholes longest in use, drilled during BSF 1 (19%). The main issues reported are that it is
hard to pump the water (25 boreholes, or 46 % of all cases of reduced functionality), and/or that
the water has an objectionable taste or colour (23 boreholes, or 43% of reported cases of
reduced functionality). Other issues reported on include a low yield (13%), no water during part of
the dry season (11%), and turbid water (6%); these issues are technical issues that have their
origins in challenges during the actual drilling of the boreholes, and one may argue that these
boreholes should not have been installed with a hand pump.
Of the 25 reported boreholes that are hard to pump, the majority is reported to have technical
problems with the hand pump, including a loose handle, worn-out bearing, head assembly in poor
condition, and leakages of the pipes and cylinder (68% of the cases of hard pumping). Other
reasons for difficulty with pumping appear to be related to deep static water levels.
Sometimes, more than one issue is mentioned contributing to the reduced functionality. When the
water gets a milky colour after rain, or smells, and the borehole is dry part of the year, or drying
up after filling a couple of jerricans, this indicates that the water is tapped from a shallow aquifer
that is quickly recharged by rain but that is also of limited extent; moreover, this water is likely to
be contaminated; three boreholes are clearly tapping from a seasonal and shallow aquifer. All in
all, 18 boreholes (33% of reported reduced functionality cases) are reported to have a bad smell
or taste, or colour. For seven boreholes, high iron content is a problem, leading to a rusty smell
and taste, and water with an orange colour.
In 2009, Medair has a salt water issue in Melut County from boreholes founded during BSF-1. As
they had indicated, out of 10 boreholes drilled, nine were installed with a handpump, of which
eight had water with high salinity (water with chloride, sodium and total dissolved solids far
exceeding WHO guidelines15
). Although this water is fit for human consumption, it is excessively
hard and salty, and therefore objectionable to the population. By February 2009, 60% of these
nine boreholes were still being used. As Medair did not report during this BSF status overview
exercise, it was not possible to validate the status of these boreholes and to include it in the
assessment results.
15 See also Euroconsult / BMB MottMacDonald, February 2009.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 13
Table 7. Number of boreholes with reduced functionality and reasons for it
BSF1 BSF2 BSFIA BSF IAe Total
Total Bh reported 89 95 201 16 401
Total Bh functional 87 85 199 16 387
Total Bh with reduced functionality 17 10 26 1 54
% Bh with reduced functionality 19% 11% 13% 6% 13%
- Functional but low yield (throughout the year) 4 1 2 0 7
- Functional but no water in the dry season 1 3 2 6
- Functional but water taste/colour issues 9 2 10 1 23
- Functional but turbid water 1 2 3
- Functional but hard to pump 11 2 12 0 25
In most cases of reduced functionality, no one took the initiative to inform the CWD or a pump
mechanic of the functioning issues.
6.5 Analysis of the main factors that influence functionality
In this section, only the factors that clearly influence the functionality rate according to the results
of the borehole functionality assessment will be presented.
Presence of an active WUC
For this status review, an active WUC is considered to be a WUC that reported having regular
meetings. Some collect water fees on a regular basis, while others collect funds when the
borehole needs to be repaired.
During the WUC training, the importance of collecting fees on a regular basis is also explained.
The information on the patterns of water user fees collection seems inconsistent and not reliable;
therefore comparison between communities not paying fees, and those paying fees on a need
basis or on a regular basis was not possible. Table 8 gives the distribution of the functionality
status according to the activeness of the WUC.
Table 8. Breakdown of the functionality status depending on the activeness of the WUC
WUC status
Bh
Reported
Functional
Not
funct
Funct
rate(%)
%
fully
funct
Funct
(sum)
Reduced
Funct
Fully
funct
WUC active 295 290 33 257 5 98.3 87.1
WUC not active or not existing 71 63 19 44 8 88.7 62.0
Total reported 366 353 52 301 13 96.4 82.2
As Table 8 displays, the percentage of fully functional boreholes is:
� 87% for boreholes that have an active WUC ;
� 62% for boreholes that used to have a WUC (but not active anymore) or stated not having a
WUC16
.
16 The boreholes that do not have a WUC were put in the same category as the borehole with a WUC which is not active
anymore. This is, because the answer to this question from the community is subjective. If the person interviewed is
young or not very aware of the training that occurred in the past, he/she might say that there has never been a WUC.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 14
This demonstrates that active WUCs on average have a greater chance of having a fully
functional borehole. This confirms what the Water Policy (2007) states: ’Sustainability of
community-based water supplies depends on the active participation of user communities in
planning, design, operation and maintenance of schemes. Where water users are not adequately
involved in the process and schemes do not reflect the needs and priorities of end users,
including women and children, there is less incentive for user communities to invest time and
money in maintaining them’.
Ownership of the borehole
In BSF, boreholes have been constructed for communities but also for institutions (health facilities
and schools). Table 9 displays the functionality rate per type of facility for which the borehole was
constructed.
Table 9. Breakdown of the functionality status per type of facilities
Type of
borehole
Bh
Reported
Functional
Not
funct
Funct rate
(%)
% fully
functional
Total
funct
Reduced
funct
Fully
funct
Community 310 299 44 240 11 96% 77%
Health Centre 53 53 6 41 0 100% 77%
School 37 34 4 26 3 92% 70%
Total 400 386 48 307 14 96% 76%
Health facilities seem to have the highest functionality level, with 96% functionality rate and 77%
of fully functional boreholes. This can be explained by the fact that Village Health Committees or
Health workers are dependent on safe water for their activity and do not have time to walk to the
next water source in case of a breakdown. Therefore, their involvement in maintenance and in
bringing the information in case of a breakdown is expected to be higher. They might also have
more transport options to the County capital to inform the CWD in case of a borehole issue. Most
boreholes drilled in health facilities were drilled by NGOs with a health focus. Those NGOs
monitor the activities of those health facilities on a regular basis and are thus able to check the
status of the borehole and support the information flow to the CWD or providing advice on
maintenance.
Community boreholes have a functionality rate of 96% and 77% of the boreholes are fully
functional. School boreholes have a slightly lower functionality rates, with a 92% functionality rate
and 70% fully functional boreholes. This can be explained by the fact that maintenance needs are
higher with children playing around the borehole, walking on the platform and pumping in a
playful way.
Underlying geology
Not all NGOs were able to provide the information on the underlying geology per borehole. This
information was completed using the Hydrogeological Map of Sudan17
. When coordinates of the
borehole were not clearly within a geological unit, the boreholes were put under the category
‘boundary zone’. Table 10 displays the breakdown of the functionality rate per type of underlying
geology.
17 UNMIS GIS production Unit, August 2006, scale : 1:3,500,000
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 15
Table 10. Breakdown of the functionality rate per type of underlying geology
Underlying
geology
Total
bh
Bh
Reported
Functional Not
funct
Funct rate
(%)
%fully
functional Total funct Reduced
Funct
Fully
funct
Unconsolidated
Sediment18
220 160 157 6 151 3 98% 94%
Basement rock 226 181 172 40 116 9 95% 64%
Boundary zone 132 59 57 8 40 2 97% 67%
According to Table 10, the type of underlying geology seems to impact the functionality rates.
Boreholes in sediments have a higher functionality rate, with 98% functional with some issues,
and 94% fully functional boreholes, while boreholes in Basement rock have a functionality rate of
95%, and only 64% are fully functional.
In South Sudan, boreholes in sedimentary formations are in most cases successful and even
high-yielding, whereas boreholes in Basement rocks have much lower yields and lower success-
rates. The lower percentage of fully functional boreholes is therefore partly caused by low
borehole yields. In addition, a high iron content of the water with its impact on colour and taste
also occurs more in Basement rocks than in sedimentary formations. Finally, the intake depth of
the handpump has an effect on the ease of pumping and the force exerted on the handpump to
lift the water. The India MII handpumps used in South Sudan have an optimum intake that
reaches down to 30 meters below ground level (mbgl); with greater depths, the strain on the
handpump becomes more important, which may reduce the lifespan of the handpump, even with
the use of the extra deep handpump. Based on the few records on handpump intake depth, there
seems to be however no difference for borehole drilled in sediments or in basement, with an
average intake depth of 39 m bgl.
Functionality rates per State
As Table F of Annex 11 displays, the functionality rates vary per state. The rate of fully functional
boreholes is the lowest in Western Bar El Gazal, followed by Warrap State. Jonglei and Upper
Nile are the states where all BSF boreholes reported on are fully functional. This difference per
state gives an indication of the influence of the type of underlying geology, but it may also be due
to a difference of cultures (including aspects of leadership and involvement) and the general need
for improved water source in an area (safe water coverage). More in-depth studies are required to
establish which parameter impacts most on success-rates per State.
6.6 Other factors that can influence functionality
Factors that can influence functionality are numerous and interrelated. Factors not yet mentioned
that can influence the functionality of a borehole may be classified into two categories:
� Factors that can be positively influenced; and
� Natural factors that are determined by its location. The latter category includes factors like the
age and frequency of use of the borehole, and the underlying geology19.
18 Basement Rock refers to undifferentiated gneisses and granites of the Basement Complex (Precambrian). Sediments
may be either part of the Alluvial Formation (Recent) or unconsolidated sands, with some gravels, clays and shales of
the Umm Rawaba Formation (Tertiary to Quaternary)
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 16
Factors that can be influenced include the level of ownership of the community and thus their
willingness to maintain the borehole through preventive maintenance. This could be positively
influenced by continuous training of WUC (maybe also refresher training) and sensitising the
community to the need of preventive maintenance. Another influencing factor is the quality of
construction, i.e. drilling depth and design and development of the borehole. This can be
positively influenced by using Bills of Quantities (BoQ) contracts instead of Lump Sum contracts
(LS) as well as professional drilling supervision.
Functionality per NGO
Besides the possibility of biased reporting, it is difficult to compare the functionality rate among
NGOs as the implementing NGO does not have a direct influence on the functionality status.
What would have an influence is more the quality of the construction of the borehole (dependent
on the experience of the contractor, the quality of the construction and materials used, and the
selection of an appropriate design as well as effective well development). The NGOs may
however influence these factors:
� By using BoQ rather than LS contracts (See section 7.1);
� By systematically executing professional geophysical surveys;
� By ensuring that a supervisor is fulltime on site during the drilling and construction process
(see section 7.2).
Comparing NGOs’ functionality rates based on the type of contract used or the type of
supervision deployed is complex as not all NGOs have reported on those aspects. Some NGOs
have also switched from BoQ to LS contracts, or introduced (part-time) supervision at some point
in time during the BSF contract period. Table D of Annex 11 displays the borehole functionality
rates per NGO.
Optimisation of the BSF monitoring approach
Table E of Annex 11 provides the breakdown of the functionality status per BSF phase. The
percentage of full functional boreholes varies per phase, being 68% for BSF-1, 62% for BSF 2
and 86% for BSF IA. BSF-1 and BSF-2 have the lowest percentage of fully functional boreholes.
The age of the borehole and thus the increased likelihood that it breaks down might be an
explanation; however, the difference can also be due to a change of approach used over the
different phases.
19 However, systematically executing a geophysical survey will reduce the occurrence of dry boreholes in Basement
areas.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 17
7. Feedback from NGOs on their drilling activities implementation
and impact of the BSF monitoring approach
Based on lessons learned, the BSF Secretariat has gradually optimized the approach for
monitoring progress of drilling projects implementation (Annex 14). Advice provided to NGOs has
thus been adjusted to reach a more sustainable implementation of the WASH projects. Main
advice has been given on the following aspects:
� The type of contract used between NGOs and contractors and the need to execute
systematically a geophysical survey before the start of any drilling activity (section 7.1);
� Requesting the services of a full-time drilling and construction supervisor (section 7.2);
� Increasing the focus on capacity building and training of WUC.
NGOs have also been asked to report on their training activities and their opinion on the main
shortcomings of the sector. In total, 20 NGOs have responded (fully or partially) to the
questionnaire (Annex 8).
7.1 Types of contract used and its impact on borehole sustainability
In South Sudan, the quality of contractors’ services provided in borehole drilling can vary
significantly. As indicated in the Water policy (2007): ‘the private sector offers a number of
potential advantages in terms of efficiency and flexibility but the difficulties of access in the
Southern Sudan mean that competition is far from perfect. Regulation is mostly through contracts
but there is currently no mechanism for independent monitoring and enforcement, resulting in
significant variation in the quality of services currently provided. Despite growing demand, the
number of private operators equipped and capable of providing quality services in Southern
Sudan remains small.’
The selection of contractors is essential for NGOs to ensure the sustainability (from a
construction point of view) of a borehole. Two different types of contracts may be used: BoQ or
LS. Some NGOs have their own drilling rigs, and invoice for materials, labour and depreciation of
the equipment.
In a LS contract, the contractors, apart from a technical proposal, submit a quotation with a fixed
price per borehole, without providing the details of the costs per unit quantity for each activity and
each material that will be used. Most of the time, a ‘no water no pay’’ clause included, which
means that, in case of a dry borehole, the contractor will not get paid for the work actually
performed. The terms of agreement can give a maximum amount of attempts (2 or 3). Executing
a geophysical survey to increase the borehole success-rate is the decision of the contractor
(though strongly recommended by the MWRI). For a BoQ, the contractor is awarded based on
the contractor’s approach and experience, and value for quoted prices for services and materials.
The contractor will be paid based on the actual works done, as certified by the drilling supervisor.
MWRI strongly recommends the use of BoQ contracts and has developed standard borehole
designs in their technical guidelines. In addition, even in sediment areas where the risk of dry
boreholes is low, MWRI enforces that borehole drilling must be preceded by a geophysical
survey, to increase the knowledge of the hydrogeological condition of the country. The BSF
Secretariat also recommended the use of BoQ contracts in BSF-IA, and a drilling supervision and
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 18
contract management workshop was organised on 2-3 November 2011 for all grant recipients
with a water component in their BSF-IA contract. In this workshop, guidelines on geophysical
siting, drilling supervision, and water quality testing were discussed in detail with the participants.
MWRI and the BSF Secretariat advise that the BoQ includes a budget line for a geophysical
survey to be carried out by an external company so that in case of a dry borehole, the contractors
will be paid for the work done. Despite MWRI’s recommendations and technical guidelines, LS
are still widely used by NGOs implementing drilling projects. Out of 20 NGOs who responded to
the questionnaire, eight are using LS contracts, nine BoQ and four have their own drilling rig
(CRS, World Vision, Oxfam GB, and ADRA). Reasons put forward by NGOs to still use LS
contracts are:
� It is easier to negotiate the total contract price;
� The responsibility for the dry boreholes remains with the contractors so they will also take the
responsibility to do a geophysical survey or not (however, the impact of using poor materials
and development will not have consequences immediately;
� If the NGO does not have technically qualified staff, it is the easiest solution as it does not
require control of the design and specifications (only trust in the drilling company)20
;
� In some cases, the difficult accessibility of sites may result in less drilling contractors quoting,
leading to NGOs having to accept the terms of the one or two contractors that do bid.
Some NGOs have also, over time, changed from one type of contract to another following the
recommendations from MWRI and/or BSF Secretariat. Intersos on the other hand switched from
BoQ to LS for the implementation of their BSF-IA drilling activities (target of 18 boreholes). The
geophysical survey was executed by a specialised company (WE Consult), while Intersos used a
BoQ contract with UHEC to drill on the selected (and approved by BSF) sites. Out of the first four
boreholes, three were dry (which means a success rate of 25 % while executing a geophysical
survey was assumed to reduce the risk to 20-25 %). Intersos therefore decided to drill the
remaining boreholes using a LS contract, leaving the responsibility of the geophysical survey to
UHEC to avoid the risk of paying for other dry boreholes. In total, they completed 17 successful
boreholes, while 11 were dry. The surprising situation is that the drilling company reduced the unit
cost for drilling the remaining 14 boreholes for the lump sum no-water-no-pay contract to USD
13,900 per borehole, from an estimated cost of USD 17,400 per borehole for the BoQ contract,
where he would be paid for all works regardless of the success-rate (A unit costs analysis is
provided in Annex 12). The only explanation for this is that the contractor had misinterpreted the
BoQ or that the unit prices in the BoQ were unrealistic, so that the actual price of a borehole was
much less than anticipated based on the estimated quantities.
Though BoQ contracts are in theory cheaper than LS, it is not always the case in South Sudan. A
comparison of the average price of the boreholes drilled in BSF-IA shows that LS contracts are
slightly cheaper (see Annex 12). This might be explained by the fact that contractors are not able
to provide an accurate estimate for each item of the BoQ, leading to an overestimation per item.
NGOs with their own drilling rig (CRS, World Vision, Oxfam GB, and ADRA) have reported having
a functionality rate of 100% and a rate of fully functional borehole of 100% (except for World
Vision: 42.9%). This could be explained by :
� The quality of the construction is better;
� Quality control can be easier;
20 It should however be noted that strong supervision at key moments is still of paramount importance , to ensure the
contractor is respecting the required standards in terms of depth, materials, water quality and quantity.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 19
� Those boreholes are quickly repaired in case of breakdown (and could be explained by a
better follow up from the NGO).
Interviews with three different drilling companies within the framework of this status review
revealed that contractors tend to prefer LS as it means for them less administrative work and less
supervision; it is therefore much easier to manage. This was also mentioned by ADRA, however,
they do recognise that in Basement rocks the risk of dry boreholes is very high, and therefore the
risks to work at a loss in case of LS contracts.
7.2 Impact of the introduction of independent drilling supervision
All aspects of the drilling process, including amongst others the optimum depth of the borehole,
the accuracy and appropriateness of the borehole design and the use of quality material can be
positively influenced by independent professional supervision on site, from the first day of the
drilling until the validation of the borehole once that the pumping test has indicated a yield high
enough and after the water quality test. The active supervision of adequate constant rate and
step pumping tests during development will help ensuring that robust data is collected to
determine the sustainable yield. “Independent” refers to supervision by someone not serving the
interests of the drilling company. In the ideal situation, the supervisor is therefore involved at the
initial stages including site selection, geophysical survey, as well as during actual drilling, well
development, test pumping, water quality sampling and hand pump installation. During BSF-IA,
the BSF Secretariat strongly recommended NGOs to use the service of an independent
supervisor so as to help assuring that minimum quality standards are adhered to while optimizing
the costs of drilling.
An independent supervisor can be an expert from a hydrogeological consultancy company. Other
options are an expert from the CWD or the SDWS or a WASH expert from the NGO itself.
This will only be beneficial if they are skilled enough to perform the supervision.
20 NGOs have responded to the questions on independent supervision (Annex 8). According to
the information received, 18 NGOs have had a supervisor on site during their drilling activities.
What differs is whether the CWD was involved and whether the supervision was full time or part
time. Eleven NGOs have reported to have involved the CWD in the supervision (seven on a full
time basis and four on a part time basis, with or without an NGO staff member).
One reason reported by some NGOs on why only seven NGOs actually have a full time
supervisor from the CWD is that there is a general lack of qualified engineers at county level who
are able to execute professional supervision and double check the design and the material used
by the contractors21
. Therefore, most NGOs (14) involved one of their WASH experts on a full-
time basis for the supervision. In eight cases, the NGO WASH expert was accompanied by a
supervisor from the CWD (full time or part time). In case the CWD supervisors were not available
to be on site on a full time basis, they were at least asked to be present for the drilling and water
quality test (Concern, MRDA, HARD). Two NGOs did not have any supervisor on site at all
(ADRA, CMSi). The fact that those two NGOs are not specialised in drilling may have led to a
lack of knowledge in the procedures to follow.
21 This can be illustrated by one particular case of a borehole drilled by Malteser (Mambe 1). Despite the supervision of a
CWD representative, the drainage of the borehole was constructed towards the road, creating flooding of the road.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 20
Intersos had an interesting way to ensure good supervision while building the SDWS’s capacity :
when the water projects of Intersos started, they hired a skilled employee from SDWS on a full
time basis for monitoring the water projects, the supervision of the construction and to provide
training to the communities. ZOA used the services of an independent company advised by BSF
as none from their qualified own staff had time to support the supervision by the Payam pump
mechanic. Table 11 provides the overview of how NGOs have taken up independent drilling
supervision in their drilling projects for BSF during BSF-IAe.
Table 11. NGOs’ selection of drilling supervisor
Type of drilling supervisor deployed # of
NGOs who responded to this question 20
NGOs who had an employee from their organization and an employee of the CWD full time 5
NGOs with an employee from their organization and an employee of the CWD part time 3
NGOs who had only an employee from their organization 6
NGOs who only had a full- time supervisor from the CWD 2
NGOs who only had a part-time supervisor from the CWD 1
NGOs who used the services of an independent company 1
NGOs who did not use supervision 2
In BSF IA, 10 NGOs added a budget line for construction supervision. The price varied greatly
depending on whether it was for hiring a WASH supervisor or only facilitating the transport of the
CWD to the site and per diem.
As full time independent drilling supervision is not yet commonly done in South Sudan, it is only
natural that drilling companies do not like to be supervised, especially in those cases where
drilling supervisors are incompetent. The BSF Secretariat therefore organized and funded a 2-day
drilling supervision and contract management course for NGOs working under BSF as well as
State Supervisors in Juba on 2-3 November 2010, to partially address knowledge gaps in drilling
supervision. It has to be borne in mind that drilling supervision is for a large part learnt on-the-job,
and that experience thus comes with time.
In addition, the NGO WASH Cluster (http://groups.google.co.ke/group/southern-sudan-wash-
forum?lnk=srg&hl=en) is currently working on a list of recommended drilling companies based on
the results and experiences of NGOs.
7.3 Feedback from NGOs on their training component
There is a general consensus from the NGOs that lack of (preventive) maintenance is a result of
lack of ownership, which depends on the extent to which communities value safe water.
Therefore, NGOs have been actively engaging in training activities in parallel to their drilling
activities. Examples of training provided by NGOs are provided in Annex 15. These training
activities include training of WUCs (including water point care takers) as well as pump mechanics.
The objective of the WUC training seems to be the same throughout the country, with a special
focus on hygiene, basic O&M of the water point, preventive maintenance and linking the
community to the CWD and the pump mechanics. Communities shall be mobilised and trained to
gradually take over full responsibility for management and financing the operation and
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 21
maintenance of RWSS schemes (Water Policy, 2007). On average, WUC training sessions last
between 2 to 5 days, and are carried out either by an international NGO staff member who
speaks the local language, a local NGO or a member of the County or State Water Department.
Ideally, communities should be involved during the geophysical siting, and community
mobilisation should happen before the actual drilling.
There is no standard way to providing training in South Sudan. Each NGO has its own approach,
involving more or less the local government, and its own training materials. Concerning the
training of pump mechanics and water point caretakers, as mentioned earlier, it is not completely
clear what each NGO actually does and the term ‘pump mechanics’ is sometimes used wrongly,
referring actually to water point caretakers (especially if the NGOs mention that they give a 2
days training to pump mechanics: this small training period suggests the training of water point
caretakers).
Keeping a WUC and the water point caretaker motivated to be continuously involved and
responsible as volunteers turns out to be another challenge, especially after the project period,
when regular interaction with the community stops. According to Winrock International, UNICEF
and SNV (2012), ‘Preventive maintenance is a term that is often used but is probably not
understood, much less, practiced.’ Concerning water fee collection, WUC members most of the
time understand the point of paying water user fees, but after some time, they stop collecting fees
on a monthly basis and decide to pay only when it will be needed. However, when the moment
comes to buy spare parts or hire a pump mechanic, a relatively larger sums (and sometimes
prohibitively so) have to be collected urgently causing the communities to remain without safe
water supply for a while until all required funds are in.
Regarding the pump mechanics, some NGOs (Swiss Red Cross, ZOA) have raised the point that
the amount and distribution of pump mechanics is sufficient. The main issue according to these
NGOs is the insufficient access to spare parts; this is the result of long distances from storage
sites, no means of transport, and lack of financial resources of the communities to pay for the
spare parts and the services. As ADRA indicated, there is a need for clearer mechanisms in the
way CWDs request spare parts. As there is in most cases no local, private sector supply chain
system for spare parts, the communities rely on NGO or RWSS support/intervention. Oxfam GB
and ADRA also added that there is payment for the trained pump mechanics by the community or
beneficiaries.
8. Conclusion
In general, NGOs were receptive to the survey. A total of 69% of the boreholes were assessed
(400 out of 578), with overall a good coverage per State and per Phase. The rainy season was
the main limitation for NGOs visiting and reporting on boreholes: the 31% of the boreholes of
which no information was received are mainly the inaccessible boreholes, or the boreholes
constructed by NGOs that have withdrawn from the area. These may also be the boreholes with a
higher occurrence of breakdowns or reduced functionality. Indeed, the accessibility challenges
and the fact that the implementing agency is not on site to provide follow up support reduce the
possibility for communities to inform authorities of a breakdown and/or get the spare parts, and
the pump mechanics to repair it.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 22
Concerning the 69% boreholes assessed, the functionality rate was found to be high, reaching
96.5%. The boreholes are relatively new (they have been drilled a maximum of six years ago),
which contributes to the high functionality rate. The assessment of borehole functionality status
went one step further by analysing the reasons for breakdown or reduced functionality. Non-
functional boreholes were mainly the result of a technical break down. Water quality was also a
reason for not using a borehole. Out of the total reported boreholes, 76.8% were fully functional.
The main reasons for reduced functionality were difficulties with pumping and an objectionable
taste or colour.
The existence of a WUC responsible for the borehole maintenance who inform a pump mechanic
or the CWD in cases of breakdown proved to have a positive impact on the functionality rate. It
was difficult to collect reliable information on the patterns of water user fees collection, therefore
comparison between communities not paying fees, paying fees on a need basis or on a regular
basis was not possible. Boreholes located in health facilities also had a higher functionality rate
compared with community boreholes or boreholes located in school, most probably due to the
fact that health workers are more committed to maintain the borehole and will be quicker to inform
the CWD in case of functionality problems. Other factors that can influence functionality are
numerous and interrelated, ranging from technical aspects (design, quality of construction,
handpump maintenance, underlying geology, and water quality) to social aspects, such as
involvement of the WUC (if any), cultural behaviour, commitment and value given to the water (if
no other alternative water supply). Though this status review attempted to capture this variety of
factors, it was difficult to conclude on the impact on one individual factor on the final functionality
rate.
Over the years, based on lessons learned and in line with MWRI sector guidelines and
recommendations, the BSF Secretariat gradually adjusted its advice to the implementing partners
in order to optimise drilling activities and the activities to ensure the sustainability of the
boreholes. Amongst others, it was recommended to use BoQ contracts, to systematically execute
geophysical surveys, and to deploy independent supervision during the drilling process,
preferably involving the CWD or the SDWS. It seems that although most NGOs have taken into
account those recommendations, the practices are not yet mainstreamed. The direct impact of
those measures could not be quantified in this status review. What can however be concluded is
that:
� Concerning the use of BoQ: it is still not common practice in South Sudan to use BoQ
contracts though it is becoming more and more frequently used compared to six years ago.
However, it has not yet led to lower price for construction;
� Concerning geophysical surveys: Though in complex Basement rock formation it does not
automatically reduce the rate of dry borehole, it is helping building the information on
underlying geology and aquifer country wide;
� Concerning the deployment of drilling supervision: though capacities from the CWD are
sometimes lacking, it improves the coordination between NGOs and CWD while building the
technical capacity of CWD. It can also help the NGOs to be more aware of MWRI procedures
and guidelines.
Efforts to systematically implement the recommendations from MWRI and the BSF Secretariat
should continue to be advocated, as it is believed to have a positive impact on borehole
functionality and sustainability.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 23
There is a general consensus from the NGOs that the lack of (preventive) maintenance results
from a lack of ownership, which depends on the extent to which communities value water and
consequently their willingness to pay for water services. NGOs have been actively engaging in
training activities in parallel to their drilling activities, including training of WUC (including water
point care taker) as well as pump mechanics. Though the objective of the trainings is the same,
each NGO has its own approach, its own training manual and is involving to some extent the local
government to carry out the training. MWRI is aware of the need to develop a standard manual
and the process is being initiated.
A community’s aversion to preventative maintenance and cost contribution can be partially
explained by the fact that, for a long time, they have survived on other unsafe water sources
(unprotected springs, streams, etc.) and still use them to date. As a result, communities continue
resorting to those sources whenever they are available (particularly during the rainy season),
even when they have been sensitised time and again on the health implications of using unsafe
water.
Less than one decade ago, water points were constructed without initial participation of the
community due to the emergency situation. When hand pumps malfunctioned, NGOs would take
the responsibility, and communities seem to still expect the same today. Community ownership,
behaviour change and capacity building at all levels (from MWRI, State, County and Payam to
local pump mechanics and WUC) are long processes that require time and perseverance, and,
last but not least, education. One may wonder how this process can adequately be monitored and
followed up by implementing agencies in the framework of short-term grants or funding
mechanisms.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 24
9. Recommendations
1. Keep on training Water User Committees
As the existence of an operational WUC appears to have a direct impact on the functionality
status, there is a need to provide refresher trainings focusing on early warning signs and initial
mal-functioning before the borehole breaks down, so that repairs can be smaller and cheaper.
2. Strengthening the capacities of the government
There is a general consensus at the national level, both with NGOs and MWRI, that the use of a
BoQ contract and full time supervision during the drilling process has a positive impact on
borehole functionality and sustainability. Efforts to systematically implement those
recommendations should be pursued, which requires skills at state level. Generally, attention
should be given to capacity building of the government at various levels, from a technical,
managerial and logistical perspective.
3. Supporting the development of the private sector
The development of the private sector as far as supply of spare parts is concerned would
facilitate the options of communities to execute a repair. Pump mechanics should be supported to
form PMA. This would help them to have more negotiation power, to divide the activities, to
request more easily support (transport, spare parts) from the CWD and therefore remain
motivated. However, those initiatives will remain scarce as long as UNICEF and some NGOs
continue to provide the CWD with free of charge spare parts. This practice discourages local
traders from importing spare parts from abroad and therefore blocks the normal trading fluxes.
Promoting a business approach will create awareness within communities on the need to pay for
water services and create resources for spare parts and fees to motivate pump technicians. It is
important to mention that even a mature private sector will not replace the role of the government
water departments at all levels. The CWD still needs to get involved and committed to support
communities in maintaining boreholes especially when highly technical skills are required.
4. Repairs and rehabilitation
As the Water Policy (2007) states, ‘Investment in creating new water sources to reach the desired
service level in rural population and achieve greater equity in access to water are noble
objectives, but such investment cannot be at costs of maintenance.’ Through BSF, repairs and
rehabilitation started to get funded with BSF IA, in 2010. Funding and implementing agencies
(NGOs) should continue giving special attention to funding rehabilitation (such as UNICEF) and
facilitating repairs execution.
Rehabilitation requires the services of contractors and cannot be executed by the communities
and/or pump mechanics. Rehabilitation of a borehole from a cost perspective is more efficient
than drilling a new borehole. One key recommendation for future water supply programmes could
thus be to focus on rehabilitation. However, the reason for non-functionality should be established
first for each borehole, as some boreholes may not have been used at all because of location,
water quality or water quantity issues.
In some cases, a borehole is not functional while only a minor repair is needed. Repairs should
then be executed by communities or the local pump mechanics. NGOs executing these repairs
jeopardise the communities’ sense of ownership, though it increases the number of people
benefiting from access to improved water sources. Communities will tend to rely even more on
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 25
NGO support and will no longer take the initiative to have the repair done. The recommendation
in that regard is that donors only fund activities that will enable communities to execute the
repairs. Examples of such activities are, as mentioned earlier, refresher WUC training, sensitising
communities on the need to pay water fees, provision of tool kits, refresher training of pump
mechanics, supporting the CWD in having an updated list of pump mechanics as well as the
activities performed, activities related to the development of PMAs and private sector for the
provision of spare parts.
5. Need for a more long-term approach from funding mechanisms
The creation of community ownership, behaviour change and building of capacity at all levels
(from MWRI, State, County and Payam to local pump mechanics and WUC) are long term
processes that require time and perseverance, and education. In the case of BSF, grants were
provided for a duration between one year and one and a half year, which made it difficult for
NGOs to engage in long term capacity building activities or to ensure monitoring over a long
period of time. This short term approach from donors is mainly due to the fact that, in emergency
situations such as the one that South Sudan used to face during the war (or is still facing in
particular areas), there is a need for quick actions and basic facilities. However, this can operate
at the expense of sustainability. South Sudan is in a transition phase and needs long-term,
sustained interventions where communities are involved from the identification of the project to
the management and the financing of the operation and maintenance. As the JAM stated (2005),
getting the right balance between humanitarian assistance and long-term recovery is a major
challenge. The recent development in donors’ approach seems to show that donors have
reconsidered the relevance of short-term grants and are willing to engage in longer term funding
mechanisms.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 26
10. Literature
Euroconsult Mott MacDonald, 2009. Capacity building Assessment MWRI, Directorate of Rural
Water and Sanitation. April 2009.
Euroconsult Mott MacDonald, February 2009. Borehole siting, borehole drilling, borehole
rehabilitation and borehole contract management – Evaluation of Best Practices in BSF Project
Area, Southern Sudan. Basic Services Fund for Southern Sudan.
GoSS, 2007. Water Policy. November 2007.
GoSS, 2011. South Sudan Development Plan 2011-2013. Realising freedom, equality, justice,
peace and prosperity for all. Juba, August 2011.
Joint Assessment Mission Sudan,2005. Framework for Sustained Peace, Development and
Poverty Eradication. World Bank, UN, GoSS and SPLM. March 18th, 2005.
Klaassen, W. & Mnyeruke, T. 2010. A Needs Identification Study of the South Sudan Water
Sector. Nuffic. September 2010. Draft.
MIWR- GONU, MWRI-GoSS. 2009. Technical Guidelines for the construction and Management
of Boreholes with Hand Pump. A manual for Field Staff and Practitioners. In partnership with
UNICEF. April 2009.
MoH and SSCCSE, 2010. Sudan Household Health Survey, Southern Sudan Commission for
Census, Statistics and Evaluation and Ministry of Health, Government of Southern Sudan.2010.
MWRI-GoSS, 2011. Water, Sanitation & Hygiene Sector Strategic Framework. August 2011.
MoH and SSCCSE, 2006. Sudan Household Health Survey, Southern Sudan Commission for
Census, Statistics and Evaluation and Ministry of Health, Government of Southern Sudan.2006.
NBS, 2009. National Baseline Household Survey 2009. Report for South Sudan. National Bureau
of Statistics.
Ray Kumar Daw, 2012. Maintenance of handpumps and Supply Chain for Spare Parts in South
Sudan. Winrock International, UNICEF South Sudan, SNV South Sudan. Draft.
SSCCSE, 2006. Poverty in Southern Sudan. Estimates from NBHS 2009. March 2010. SSCCSE, 2011. Statistical Yearbook for South Sudan. Centre for Census, Statistics and Evaluation. 2011.
The Sphere Project, 2012. Humanitarian Charter and Millennium Standards in Disaster
Response. 2011 Edition of the Sphere Handbook 2 September 2012.
WHO-UNICEF, 2012. Progress on Drinking Water and Sanitation. Update 2012.
http://www.wssinfo.org/documents-links/introduction/
Zoa, 2011. Terekeka West Water Source Assessment Report. January 2011.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 27
Interesting links
� WASH legal documents and MWRI technical guidelines. http://www.bsf-south-
sudan.org/content/policies-guidelines
� MWRI : http://www.mwri-goss.org/
� WIMS : http://www.sswich-mwrigoss.org/
� Rural water supply network : http://www.wssinfo.org/documents-links/introduction/
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 28
Annex 1 BSF IA extention. WASH Monitor ToR
Background & Justification
BSF’s purpose is to increase the coverage, access and use of the population of Southern Sudan
of Basic Services in Primary Education, Primary Health, and Water & Sanitation in a sustainable
way. BSF’s main expected results are the establishment of primary schools, primary health
clinics, boreholes and latrines. These results are accompanied by training of professional in
healthcare, teacher training, training for members of the communities and local authorities.
BSF started in January 2006 with GBP 7.9m for grants for 6 NGOs (round 1). Its second phase
(BSF-2 from 1 Jan 2009-31 Dec 2010) issued GBP 20 m (rounded) in grants to 25 NGOs (round
2 and 3). BSF-IA (Interim Arrangement from 1 July 2010-31 December 2011) issues GBP 35m
(rounded) BSF’s to 32 NGOs.
In phase-1 the fund assisted 64 schools, 63 primary health clinics, 219 boreholes and 1203
latrines. In phase-2 the fund assisted 87 schools, 113 clinics, 248 boreholes and 1000 latrines.
The targets for BSF-IA are 37 primary schools, 218 clinics, 378 boreholes, 2673 latrines. The
targets of BSF-IA extension (grants run from 1 January-31 December 2012) are assistance to
250 clinics, 15 schools, 50 classrooms, 68 water points (boreholes and others) and 94 latrine
stances.
The WASH component in BSF-IAe is reduced from GBP 10m (27% in BSF-IA) to GBP 860,000
(5%) in BSF-IAe because WASH is not included in the lead donor’s longer a priority sectors for
investments in South Sudan. But WASH is still included as an integrated part of the BSF-IAe
grants in Primary Health and Primary Education because health facilities are not sustainable and
not effective without access to safe water. And enrolment in primary education, particularly for
girls, will not develop without adequate water and sanitation facilities.
These terms of reference include the monitoring of the implementation in BSF-IA extension and in
addition they include follow-up of the implementation and impact of BSF-IA and BSF-2. This
follow-up is important for reasons of sustainability and value for money, in particular because:
� The analysis of unit prices for the BSF-IA boreholes (repaired and new) can only be
completed when all invoices are in and this is the case by the end of January 2012;
Position Monitor for Water, Sanitation and Hygiene promotion (WASH) projects
Project BSF-IA extension
Duty station Juba, Southern Sudan
Duration 200 days ( at max 26 days per month)
Period 1 January 2012-28 February 2013
Project name Basic Services Fund-Interim Arrangement extension (BSF-IAe)
Launched January 2005/06
Project authority GOSS Steering Committee chaired by Ministry of Finance
Fund GBP 20 m
Donors DFID ( lead donor) and Sweden
Management contract BMB MM 1 January 2012-28 February 2013
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 29
� In BSF-IA the Service provider introduced the “independent “ drilling supervisor to assure that
minimum quality standard are adhered to and the effectiveness of this needs to be analysed;
in other words do boreholes have a longer “maintenance-free” longevity as a result;
� Compare effectiveness and efficiency of new versus repaired boreholes
� Lessons learnt from the Community-lead Total Sanitation in particular for schools and its effect
on attendance
� Hand-over and integrate all BSF water points into MWRI’s SWITCH data base.
Qualifications:
The successful candidate has a master degree in rural development and at least 5 years field
experience in developing countries with fragile states. Previous experience in humanitarian
assistance and non-profit organizations is a pre-requisite. The nature of the assignments (project,
international, deadlines, travel) requires a flexible personality, team player, articulate
communicator, good verbal and written commend of the English language, highly computer
literate.
In close cooperation with the BSF secretariat, in particular with the Team leader, the position
assists the BSF team in providing a service oriented secretariat for Grant recipients where they
can come for help and support and to assure that all interventions are completed in time: in
particular she/he will assist in:
� Field inspection and monitoring visits to project sites to verify progress and adherence to
technical qualifications for boreholes, newly drilled and rehabilitated ones (verify diagnosis);
� Survey boreholes and sanitation of BSF phase 1,2, and IA and follow up on operational and
quality aspects;
� Assist in monitoring of all training efforts in particular those for community members for WASH
and school children;
� Consult with Parent Teacher Associations (primary school WASH), Village Health committees
(for primary health clinics) and water point committees (for boreholes);
� Assure participation on field visits of GoSS staff (central and/or state and/or county);
� Drafting short reports on field trip highlighting main findings, conclusions and
recommendation;
� Verification financial monthly invoices for construction for WASH;
� Documentation prices and unit costs for all construction in WASH;
� Updating indicator values for WASH (MDGs).
� Contribution to project progress reports;
� Perform any other duty as required.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 30
Annex 2 Institutional and legal context of the WASH Sector
With the formation of GRoSS in October 2005 the MWRI was created. Its objective is to develop
policies, standards, guidelines, plans and monitoring for water resources management,
development, and utilization; and for provision of sanitation and hygiene services. The MWRI has
a Water Information Management System (WIMS) Department, created to manage an integrated
database that provides a systematic way of gathering information about water to assist in
decision making at all levels of the Water Sector. It compiles information on water points,
including technical specifications, location and status. One of its mandates is also to manage
drinking water quality information such that it can be centrally accessed by all the relevant
authorities at Government, State and County levels. Initially, the WIMS22
was referred to as the
South Sudan Water Information Clearing House (SSWICH), which was a project started in 2009
following up on the achievement of the Water Environment Sanitation (WES) Database.
The Water Policy of South Sudan was prepared in November 2007. It outlines the country key
issues and priorities in the WASH sector. Access to sufficient water of acceptable quality to
satisfy basic needs is considered a human right and shall be given highest priority in development
of water resources (General Principles of Water Policy, 2.3.3). Water is also defined both as an
economic and social good owned by all riparian people (General Principles of Water Policy, 2.3.1
and 2.3.4) and it is the duty of the GRoSS to ensure effective development and use of water
resources for the benefit of all, including poor and vulnerable groups (General Principles of Water
Policy, 2.3.3).
The Water policy also sets the priorities and the frame for O&M of water points: Regarding rural
water supply, it states that rural communities shall be supported to take an active role in planning,
managing and financing RWSS schemes on a sustainable basis (Guiding Principles for Rural
Water Supply and Sanitation, 4.1.5). More specifically, water users should be supported to make
informed technology choices which take account of local needs and priorities and existing
capacity for management and financing of O&M (Specific Objectives for Rural Water Supply and
Sanitation, 4.2.5) and users should be encouraged to contribute towards O&M costs while
ensuring that poor and vulnerable groups are not disadvantaged (Specific Objectives for Rural
Water Supply and Sanitation, 4.2.6). Those aspects should constitute the frame for any
implementing organisations active in the WASH sector. Involvement of private sector and NGOs
in the delivery of goods and services shall be actively encouraged and supported wherever
appropriate. (Guiding Principles for Rural Water Supply and Sanitation, 4.1.6).
In August 2011, MWRI with support from UNICEF developed the Water, Sanitation and Hygiene
Sector Strategic Framework, with the idea to provide the outline for the operational
implementation of the South Sudan Water Policy. The WASH Strategic Framework, ‘shall pave
the way to move from ad-hoc emergency relief intervention to a holistic, Government-led planning
and implementation of well-targeted interventions in order to move gradually towards achieving
the MDG’. The JAM (2005) had already identified the need to ‘move away from intensive, short-
term initiatives inspired by humanitarian concerns’, to long term and better planned recovery
projects.
22 http://www.sswich-mwrigoss.org/
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 31
The development of the Rural WASH Sub-sector Action and Investment Plan23
(2012-2015)
(Facilitated by UNICEF) and the Water Act Bill (Facilitated by GIZ) are in the pipeline. In addition
to infrastructure development, improving and monitoring water quality aspects is becoming
increasingly a key priority.
The Objective of the SSDP is to increase the access to improved water resources from 34% in
2010 to 45% in 2013 for urban areas and 40% for rural areas. Table 1 provides the breakdown
until 2013 of the objectives of the SSDP in terms of percentage of the population having access
to improved water resources.
Table 1. Objective of the SSDP in terms of percentage of the population having access to
improved water resources.
Source 2010 2011 2012 2013
SSDP Baseline : 34% 35% 38% 45%
23 In process, after a workshop hold the 20th and 21st of October
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 32
Annex 3 Spare parts : Background, Status and views for the future
UNICEF24
started to be active in South Sudan in the late 1980s, with the establishment of
Operation Lifeline Sudan, in April 1989 in response to a devastating famine and the effects of a
long-term civil war. Two major areas of activities were identified: Health and WASH. When areas
would fall out with the Government of Sudan, UNICEF, lead agency for the WASH activities,
would mobilize resources for borehole construction and rehabilitation, provision of spare parts
and support for maintenance of the facilities through campaigns of trainings.
Since that date, UNICEF has remained the major provider of spare parts in South Sudan. The
spare parts have been directly distributed to the 10 States who are then responsible for the
distribution at lower level. NGOs also play a role in the spare parts supply chain. As spare parts
are not often available at local level, some NGOs procure spare parts from neighbouring
countries and use them for the execution for their own repair and rehabilitation programs.
While the Water policy (2007) mentions that communities should contribute to the O&M costs, it
seems that to date, communities have been dependent on external support and supplies. Once
such a situation is in place, reversing it is very difficult, unless, as mentioned in Winrock
International, UNICEF and SNV (2012), some very radical decisions are taken and implemented.
MWRI, UNICEF and other development partners are aware of this new challenge, mainly caused
by the fact that South Sudan is now in a transition phase between humanitarian relief to recovery
stage. UNICEF’s current approach to supplying spare parts is focussing on areas that need
emergency response. On a yearly basis, needs in terms of emergency response per State are
analysed and included in the KAP. This serves as a basis of the year after. But as UNICEF
mentioned (in an interview in November 2012) there is still some work to be done in how to define
emergency and how to better ‘plan the supply’ to respond to it.
UNICEF also focuses on support to rehabilitation of existing facilities. This support goes through
the governmental institutions and the existing capacities. It consists of financial support and
provision of the necessary spare parts. This support does not take place in all States. It is based
on identified needs from the National level and funding opportunities. Special attention is given to
areas with Guinea worms and rehabilitation of boreholes in health or school facilities.
The Technical Working Group of the Water Cluster initiated two surveys to understand the nature
of shortage of spare parts for hand pump maintenance in mid-2011. Under the guidance of the
MWRI, a consortium consisting of Winrock International, UNICEF and SNV took the initiative to
hire a consultant to consolidate the outputs of these surveys and carry out field visits to get
additional observations. This survey is based on the responses of 34 respondents (29 counties)
and 18 NGOs working in seven States and based on field visits in Western Equatoria, Eastern
Equatoria, Northern Bar El Gazal and Warrap.
According to Winrock, UNICEF, and SNV (2012), the spare part supply network is ‘A passive
conduit for transmission of handpump spare parts given free of charge by a number of sources to
24 Result of negotiations between the UN, the Government of Sudan and the Sudan People's Liberation Movement/Army
(SPLM/A) to deliver humanitarian assistance to all civilians in need, regardless of their location or political affiliation
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 33
State and Counties. It is an overstretched system with no planned basis, very difficult logistics
and independent actors sometimes undermining each other’s effort to reach the same objective.
Currently it is not consistent with the stated objective stated in the Strategic Framework of the
government to make communities responsible for their water point’.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 34
Annex 4 Water quality : Background, current status and indicators
Prior to 2006, a limited number of government owned facilities to deliver drinking water, through
conventional treatment, existed. There was also a general lack of technical and organisational
capacities to be able to perform adequate routine water treatment processes. The limited number
of laboratories then also exacerbated the situation, as there was no monitoring system for water
quality.
The MWRI acknowledges the importance of water quality monitoring and is currently giving it a
higher priority. The water policy (2011, General principles 2.3.3) states ‘Access to sufficient water
of acceptable quality to satisfy basic needs is considered a human right and shall be given
highest priority in development of water resources’. In addition to the Water Policy and the WASH
Strategic framework, Water Quality Technical Guidelines for South Sudan have been developed
(2011) as well as an Operations Manual for Water Quality monitoring for South Sudan.
Drinking water quality monitoring is currently conducted in an uncoordinated way by line
ministries, humanitarian agencies and NGOs. There is still no organised system reporting on
drinking water quality from such activities. Although one of the mandates of the WASH
Information Management System (WIMS) is to manage drinking water quality information, this
exercise is still in its juvenile stage.
Each State Directorate for Water and Sanitation (SDWS) has been provided with at least one,
potable water quality testing kit; capable of performing basic water quality test in the field. Some
NGOs have also their own water quality testing kit. There is also a central water quality laboratory
in Juba, which also receives water samples for basic water quality testing. However, for testing
microbiological water quality, the water sample has to reach the laboratory within 6 hours, which
is in many cases a challenge. As part of the Water Supply and Sanitation Project25
(WSSP), a
water quality laboratory has been constructed in each State (but not yet operational). Equipment
and reagents to test for the basic physical, chemical and microbiological parameters are being
brought to the State and training is currently being carried out.
Monitoring the progress toward MDG 7, Target 10: ’to reduce by half the proportion of people
without access to safe drinking water’’ for 2015 is difficult as periodic and standardized water
quality testing is not yet applied is South Sudan (as well as in many other developing countries
(WHO-UNICEF). In their effort to define and measures progress in access to drinking water
sources around the world, WHO and UNICEF have used the terms ‘use of an improved water
source’ as an indicator instead of ‘access to safe water source’ used in the MDG, where
‘improved’ was determined by the type of technology. An improved source is one that increases
the likelihood that it provides safe water. Hand pump borehole is considered to be an improved
technology to deliver safe water (WHO-UNICEF). ‘Use of an improved water sources’ is the
indicator being used for the National Baseline Household Survey (NBHS) of the National Bureau
of Statistics and the Sudan Health and Household Survey (SHHS).
25 The Water Supply and Sanitation Project (WSSP) was designed in 2009 with a total budget of USD30 million fully
financed by MDTF (administered by the World Bank/IDA), and encompasses both rural and urban water and sanitation.
The project became effective on 7th May 2010 and is expected to end on 30th December 2012.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 35
Annex 5 Some definitions
Maintenance, repairs and rehabilitation
Different actors can have different ways of defining and differentiating maintenance, minor
repairs, major repairs and rehabilitation, which can lead to confusion. These terms are thus
defined in Table 1.
Table 1. Classification of typical repairs for hand pump equipped boreholes26
Classification Activities Who can do it? Costs
estimation
Who covers the
costs27?
Routine
maintenance
- Clearing drains and surroundings
- Maintenance of the fence
- Periodical replacement of fast
wearing parts (buckets, values, etc…)
Community with
water point care
taker
50 US$/year
- The communities
through water fees
collection
- or the NGOs
Minor Repair - Repair of damaged parts outside
routine service
- Replacement of damaged slow
wearing parts (handle, chain, few
pipes/rods, cylinder)
- Repair of cracks to platform or drain
Communities
with Water pump
care taker. If too
complex, a
skilled pump
mechanic or
other artisans
100 US$
- The communities
through water fees
collection
- or the NGOs
- The government (Most
spares part will be
provided free of charge
by UNICEF)
Major repairs
(can also be
classified of
rehabilitation
in some case)
- Fishing of dropped pipes and rods
- Cleaning of borehole
-Repairs of borehole casing and
screen
- Replacement of platform and drain
- Replacement of rising mains
Skilled pump
mechanics
2000 US $
- NGOs
- The government (Most
spares parts will be
provided free of charge
by UNICEF) through
donor money
Rehabilitation One or more of the following
activities:
- Flushing and redevelopment of the
borehole
- replacement of worn out parts
- Fishing out of pipes
cylinder, rods, pipes, etc.
- installing new casings/screens
-Test pumping of the well and taking
a water sample for testing
Need for a
drilling company
depends on
location
(mobilisation
fees).
- NGOs
- The government (Most
spare parts will be
provided free of charge
by UNICEF) through
donor money
Remark: According to Winrock International, UNICEF and SNV (2012), the average cost for a
repair is estimated at 1,100 $.
26 Based on the following source document : Government of Uganda, Ministry of water and Environment, 2007. Water
and Sanitation Sector District Implementation Manual Version 1.
27 This column indicates who are currently covering those costs in South Sudan and not who should cover the costs to
make the system sustainable. Who should be responsible for those costs to make the system sustainable has been a key
discussion.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 36
Water point care taker vs. pump mechanic
It is only since a few years that the distinction between water point care taker and a pump
mechanic is being made. According to the survey of Winrock International, UNICEF and SNV
(2012), only 10% of the NGOs that responded to their questionnaire made the distinction between
caretakers training and pump mechanics training. A water point care taker is a nominated person,
part of the WUC, who is given basic training on maintenance and small repairs of the
superstructure. This person should have some knowledge of mechanics, but it is not always the
case28
. A water point care taker, as indicated in Table 1, is expected to do the basic maintenance
and the small repairs. In some cases, they have received, after the WUC committee training, a
tool kit and were taught how to dismantle a borehole and change the fast wearing parts.
A pump mechanic is someone which has undergone a training in basics mechanics or
engineering, and who has gained experience in hand pump repairs. Many of them are working on
a voluntary basis for the County Water Department (CWD). Others are employed at State Level.
Winrock International, UNICEF, SNV (2012) define pump mechanics as ‘someone able to
perform all maintenance needs associated with a handpump i.e. not a caretaker who is likely to
perform only preventive maintenance and very simple repairs.’
28 Discussions are taking place on the fact that not only one person of the WUC should be trained as water point care
takers, otherwise, if this person leaves, the community would be left without responsible person. On the other hand, if
too many communities’ members are being trained, the risk is that none of them will feel responsible.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 37
Annex 6 Borehole Status Review Package: Note sent to the NGOs
Survey on hand-pump boreholes’ operational status in South Sudan
BSF IAe – Lucie Leclert (WASH Monitor)
24/05/12
1. Justification and Value for Money
Sustainable development of South Sudan strongly depends on improving the access of
communities to safe and clean water resources. A lot still needs to be done to meet the
Millennium Development Goal 7 target 10: ‘’To reduce by half the proportion of people without
access to safe drinking water’’.
Considering the hydro-geological conditions of the country and the urgent need for water of most
communities, donors have engaged in funding boreholes drilling all over South Sudan. Since
2006, the Basic Service Fund (BSF) has financed the drilling and repair/rehabilitation of hand-
pump boreholes through NGOs. In total, BSF contributed to the construction of 556 new hand-
pump boreholes and the rehabilitation of 535 existing hand-pump boreholes. Under the
assumption that all hand-pump boreholes (newly drilled and rehabilitated) are still operational, it
would mean that 545,500 people29
got access to improved water supply.
Value for Money is an approach widely used for Aid Programs. The Value for Money of a hand-
pump borehole is not only reflected by its unit price, but also by its efficiency and its
effectiveness. Its purpose being to supply water, the ‘Value for Money’ of a hand- pump borehole
depends on:
� Whether it is actually being used by the community
� Whether it is properly functioning
� How long it remains well-functioning.
In South Sudan, many NGOs are involved in drilling activities. Besides drilling, they also engage
(in principal) in activities to ensure the sustainability of the borehole. Methods and approaches for
construction supervision and contracting as well as for training and capacity building can differ
and have an impact of the well-functioning and the sustainability of the borehole.
29 Calculated on the assumption that a borehole serves 500 beneficiaries.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 38
2. Hypothesis and purpose
This survey is based on the hypothesis that boreholes newly drilled are too often not functional
anymore after a short period of time.
The purpose of this survey is thus to assess the current operational status of BSF hand-pump
boreholes that were drilled in the period 2006-2011 as well as whether the mechanisms and the
enabling conditions for their sustainability are in place.
3. Approach
Definition
Different actors can have different ways of defining and differentiating maintenance, minor
repairs, major repairs and rehabilitation, which can lead to confusion. These terms are thus
defined in the table below30
.
Classification Activities Who is responsible? Costs estimation
Routine
maintenance
- Clearing drains and surroundings
- Maintenance of the fence
- Periodical replacement of fast
wearing parts (buckets, values, etc…)
Community with water
point care taker
50 US$/year
Minor Repair - Repair of Damaged parts outside
routine service
- Replacement of damaged slow
wearing parts (handle, chain, few
pipes/rods, cylinder)
- Repair of cracks to platform or drain
Communities (via the
WUC). They can also
ask the services of
pump Mechanics or
other artisans
100 US$
Major repairs (can
also be classified of
rehabilitation in
some case)
- Fishing of dropped pipes and rods
- Cleaning of borehole
-Repairs of borehole casing and screen
- Replacement of platform and drain
- Replacement of rising mains
Local Government 2000 US $
Rehabilitation
- Flushing and redevelopment of the
borehole
Local government (to
mobilise NGOs and/or
funds)
Depend on location
(mobilisation fees)
30 Base on the following source document : Government of Uganda, Ministry of water and Environment, 2007. Water and
Sanitation Sector District Implementation Manual Version 1.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 39
Conditions for a sustainable borehole
A borehole will be in good-functioning stage and remains so for a long period of time if:
� The design, construction and validation after test pumping and water quality test have been
properly done
� The maintenance and the repairs are well undertaken by the Community and the water point
care taker, or, when more serious repairs, by the (trained) artisans (pump mechanics)
� The Payam (or County) Water Department is strongly involved and able to mobilise spare
parts (or mobilise funds for rehabilitation)
The quality of the design and construction of a borehole can vary depending on:
� The quality and the experience of the contactor
� The quality of the material used
� The type of contract with the contractor (NGOs’ own equipment, lump sum or bill of quantity
contract)
� Whether there has been proper (independent) supervision from the first day of the drilling until
the validation of the borehole once that the pumping test has indicated a yield high enough for
a hand pump and after the water quality test (i.e. good supervision and contract)
� The quality of the supervision (qualification of the supervisor, part time or full time)
Adequate maintenance and repairs depend on various factors:
� The level of ownership for the boreholes of the community
� The effectiveness of the WUC
� The ability of the community to mobilise money to pay for the pump mechanic or the spare
parts
� The availability of skilled pump mechanics and if they have means of transport
� The availability of spare parts for pump repairs
The involvement of the governmental entities at local level (County or Payam) also plays an
important role to ensure regular M&E of the borehole and ensure that spare parts are available.
Ideally, they should be informed by the community when there is an issue on the borehole and
should send a pump mechanic. It also plays a role in mobilising funds to finance the rehabilitation
of boreholes (on request of the communities).
The influence of each factor mentioned above will highly depend on the context and will probably
differ per borehole, per Payam or per NGOs. The results of this survey will provide more
feedback on these influencing factors.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 40
Classification of the boreholes status
The conceptual figure below summarises the different ‘operational status’ of a borehole and the
reasons for it. (The numbers in the boxes are linked to the questionnaire’s questions).
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 41
1. Methodology
a. The population
To get a good assessment of the current operational status of hand-pump boreholes in South
Sudan, the sample of boreholes to assess for this survey should ideally not only include those
drilled under BSF but also those funded by other donors. However, considering the timeframe for
this survey and the fact that we, as Management Consultant for BSF on request of DFID, already
have information on the BSF boreholes, it was decided to focus on the BSF boreholes.
b. Source of information
� From previous reports of other WASH monitors (for the methodology)
� From previous surveys (ZOA31)
� By requesting NGOs to assess the status of previously drilled boreholes and report
� The BSF WASH monitor will also, in some case, join the NGOs to the field and assist them in
the execution of the survey and the collection of the data
c. What is expected from the NGOs
It is part of NGOs’ strategy to ensure the sustainability of the newly drilled boreholes by
monitoring their status. This survey can be seen as an impact review. The survey is developed to
enable us to get a better insight on the reasons why a borehole is functional or not, and provide
feedback on the limiting factors that impact its sustainability. It is expected from the NGOs that
they assess as many boreholes as they can (preferably 100%), before the 20th of August. Though
the aim of this survey is not to compare NGOs’ performance, the percentage of boreholes
assessed per NGOs will be reported on the final report to the government, DFID and other
donors.
The documents to be filled are :
- An excel spread sheet in which the information for each borehole should be
reported. When going to the field to collect the information, the questionnaire (annex
2) can be used to support the data collection
- Some additional/general questions on the construction, the independent
supervision, the borehole’s sustainability and the involvement of the local
government.
31
Zoa, 2011. Terekeka West Water Source Assessment Report, January 2011.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 42
Annex 7 Borehole Status Review Package : Data Collection Sheet
The first page has to be filled no matter is the borehole is functional or not.
In the second page, if the borehole is functional, please fill the green (first) part. If the borehole is not
functional, please fill the red (second) part.
The numbers before certain answers can be ignored. They are referring to the conceptual figure in
the note.
General information Possible answers
Date of assessment
Name of Assessor
Name of borehole
Geographic coordinates
Where is the borehole located School Community Health centre
Date it was drilled
Current status of the borehole 1. Functional 2. Non-functional
What is the alternative source of water?
It is still being used? No Yes Sometimes
Is there a Payam Water Department? No Yes Yes, but not very active
Assessor observation on the borehole’s status
Platform ok? Yes No Fenced ? Yes No
Drainage system ok? Yes No Pump ok ? Yes No
Concrete draining water
collection ponds? Yes No
Water coming out easily and
sufficiently? Yes No
Assessor’s Rating
(1-bad to 5-excellent) 1 2 3 4 5
Additional comments?
WUC Possible answers
Is there a WUC? No Yes Yes but not operational anymore
Does the WUC have regular meetings? No Yes Only when there is a problem
How many members?
How many women?
Are you paying a user fee? Yes No
Additional comments?
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 43
If the borehole is functional Possible answers
Borehole functioning issues
Is everything working fine with the borehole? 1.1.Yes 1.2. No.
If not, what is the problem ?
If not, can you repair it yourself ? Yes No
If not, did you inform a pump mechanic ? Yes, we are waiting Yes, but he could not do anything
No, not yet Other. Specify
Borehole yield and water quality
Is the taste of the water OK ? Yes No
1.2.1. Is the yield of the borehole satisfying? Yes 1.2.1. No 1.2.1.It has been decreasing over the years
Do you have to queue for the water sometimes ? 1.2.2.Often Sometimes Never
Is it hard to pump? Yes 1.2.2. No
Do you have water throughout the year ? Yes 1.2.1. No
Do you always have clear water? Yes 1.2.3. No
Additional comments ?
If the borehole is not functional Possible answers
Why are you not using the borehole ?
2.1. It is broken down 2.2.3. Too far from community
2.2.2.Water quality problem 2.2.1. Too low yield
2.2.4.Too hard to pump 2.2.5.Other water sources close by
2.2.6. Other, specify…..
In case there is a technical breakdown
Is it the first time that it breaks down? Yes No
Since when it is broken down ?
Less than a week A week to a month
A month to 6 months More than 6 months
Why do you think it broke down ? Lack of maintenance Too many users
Construction issue Other (detail)
Do you think it can be repaired ? 2.1.2. Yes 2.1.3. No 2.1.1. I don’t know
Have you informed someone that the borehole is
broken down ?
Yes, The NGO Yes. the water department
Yes, a pump mechanic 2.1.1. No, Noone
If yes, has a pump mechanic come already ? 2.1.2.No, we are waiting Yes, but could not repair
2.1.5.No, we are still mobilising funds Other (detail)
Why could not he repair the borehole ? 2.1.3. No spare parts available 2.1.5. Bh needs complete rehab
Other (fill below)
Other specify :
Additional comments ?
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 44
Annex 8 Borehole Status Review Package : Questionnaire to NGOs
Concerning the construction
- Do you have your own drilling equipment or do you use the services of a drilling contractor?
- What is your relationship with /trust in the drilling company ?
- Do you use Lump-Sum contract or Bills of Quantities contract with the contractor ? Why ?
- What do you do in case of a dry borehole?
Independent Supervision In BSF-IA (2010-2011), the ‘independent’ drilling supervisor was introduced with the idea that it would assure that minimum quality standard are adhered to from the start of the drilling till the water quality test.
- Have you requested the services of an independent supervisor?
- Who was he? (Government, your NGOs, private company?)
- Has he been on site full time or part time? What do you request him to check more in particular? Please provide details.
- If you have used the services of an independent supervisor, what has been the impact of this measure on the sustainability of the drilled borehole to your opinion? Did it improve the quality of the boreholes that were drilled? Please detail.
For ensuring borehole’s sustainability
- How do you keep track of the borehole’s status?
- How often do you visit the site where you drilled the borehole?
- Do you think the lack of maintenance is a major issue? If yes, what do you for it?
- Which type of trainings do you normally carry out to make sure that the borehole will be properly maintained? How many days of trainings do you provide and who do you involve? (please detail the type of trainings you provide and how you select the participants)
- How do you ensure that the WUC are properly trained and remain active?
- What is, according to you, the main reason for the lack of sustainability of the boreholes and what would you suggest solve/improve it?
Concerning the involvement of the local government
- Is there a Payam or County Water Department?
- How involved are they to help communities with the maintenance and the repair of the hand-pump boreholes?
- How much are you involving them in your work? Please provide details.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 45
Annex 9 Key Dates of the Status Review
April - Consultation with key NGOs (meeting in their headquarter in Juba) and getting
feedback and recommendations on the methodology to use and already inform
them on the upcoming status review
- Preparation of a first draft of the BSF Borehole Status Review Package
Consta
nt in
volv
em
ent a
nd c
om
mu
nic
atio
n o
f the M
WR
I
May
- Testing of the data collection sheet in the field with ZOA in Tali and preparing
the final Borehole Status Review Package
June - 7th June :Sending to Each NGO their Borehole Status Review Package (to
send back before the 20th of August)
- Field Visit to start data collection
July - 9th July : First reminder to all NGOs to send back their Borehole Status Review
Package filled
Aug - 14th August : Sending the second reminder to the NGOs
- Combining the received results
Sept - Contacting NGOs who have not sent their Borehole Status Review Package
- Starting the analysis
Oct
- Preparation of the first draft of the Report
Nov - Evaluation mission of DFID
- Collection of the final records (that were not accessible in the rainy season)
Dec
- Submission of the final report
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 46
Annex 10 Total boreholes drilled for BSF per NGO and per State
Table A: Total boreholes with BSF per NGO
NGO BSF-1 BSF-2 BSF-IA BSF-IAe Total
ACF
7
7
ACTED
39
39
ADRA
10 10 20
AMA
49
49
AMREF 20
20
ARC
5
5
AVSI
7 4
11
CARE
1 1 2
CARITAS CH 19
19
CMSI
8
1 9
Concern
7
7
CRS
15
15
HARD
3 4 2 9
Intermon OXFAM
18 17
35
INTERSOS
17
18
IRC 21
21
MALTESER
5 11 16
MEDAIR 10
10
MERLIN 10
10
OXFAM GB 73 29 21
123
OXFAM Novib
6
6
SCiSS
3 2 5
SC-US 3
3
SWISS RED CROSS
19
19
Tearfund b
28
28
UMCOR
10 24
34
WORLD RELIEF
1
1
World Vision
4 5
9
ZOA
29
29
Total 156 148 247 27 578
Remark: For BSF-IAe, the target has been included (27) and not the actual number of boreholes
drilled as per November 2012 (16)
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 47
Table B: Total boreholes drilled with BSF per State
State BSF-1 BSF-2 BSF-IA BSF-IAe Total
CEQ 20 8 44 1 73
EEQ 29 7 19
55
Jonglei
28
28
LAKES
1 3 2 6
NBeG 21 10 36 1 68
UNITY 42 19 1 1 63
Upper Nile 44 29 21 10 104
Warrap
49 20
69
wBeG
21 42 1 64
WEQ
4 33 11 49
Total 156 148 247 27 578
Table C: Total boreholes drilled with BSF per State per type of facility
State Community School Health
Facility
Total
CEQ 58 5 10 73
EEQ 33 10 12 55
Jonglei 28
28
LAKES 2 2 2 6
NBeG 55 6 7 68
UNITY 58 3 2 63
Upper Nile 91 5 8 104
Warrap 64 5
69
wBeG 54 6 4 64
WEQ 19 8 22 49
Total 461 50 67 578
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 48
Annex 11 Records received per NGO, State and Phase and functionality status
Table D: Total boreholes received per NGO and functionality status
NGO
Total
bh Bh
Reported % reported
Average
rating
Functional
Not funct
Funct
rate
(%)
% fully
functional Total funct
Reduced funct
Fully funct
ACF 7 4 57 3.0 2 2 2 50.0 50.0
ACTED 39 5 13 4.2 5 3 2 100.0 40.0
ADRA 20 14 70 4.0 14 14 100.0 100.0
AMA 49 0 0
0.0 0.0
AMREF 20 0 0
0.0 0.0
ARC 5 5 100 4.0 5 1 4 100.0 80.0
AVSI 11 10 91 3.9 10 3 7 100.0 70.0
CARE 2 0 0
0.0 0.0
CARITAS CH (1) 19 17 89 2.6 17 4 4 100.0 23.5
CMSI 9 9 100 3.2 5 2 3 4 55.6 33.3
Concern 7 7 100 4.0 7 7 100.0 100.0
CRS 15 15 100 4.0 15 15 100.0 100.0
HARD 9 7 78 3.4 5 5 2 71,4 71.4
Int. OXFAM (1) 35 29 83 3.7 28 6 6 1 96.6 20.7
INTERSOS 17 17 100 3.8 17 9 8 100.0 47.1
IRC 21 21 100 2.9 19 11 8 2 90.5 38.1
MALTESER 16 16 100 3.0 16 2 14 100.0 87.5
MEDAIR 10 0 0
0.0 0.0
MERLIN 10 8 80 3.4 8 2 6 100.0 75.0
OXFAM GB 123 93 76 3.7 93 93 100.0 100.0
OXFAM Novib 6 6 100 4.2 6 6 100.0 100.0
SCiSS 5 0 0
0.0 0.0
SC-US 3 0 0
0.0 0.0
SRCC 19 19 100 3.8 16 6 10 3 84.2 52.6
Tearfund b 28 28 100 4.0 28 28 100.0 100.0
UMCOR 34 34 100 4.0 34 34 100.0 100.0
Word Relief 1 0 0
0.0 0.0
World Vision 9 7 78 4.6 7 4 3 100.0 42.9
ZOA 29 29 100 4.0 29 1 28 100.0 96.6
Total 578 400 69 3.7 386 306 14 96.5 76.8
(1) Those boreholes were reported on but, due to accessibility challenges, the NGOs could only report on
whether they were functional or non- functional, but not the full assessment. Therefore, the sum fully
functional + reduced functionality (361) does not equal total functional borehole. The difference of 25
corresponds to 16 of Intermon Oxfam and 9 of Caritas that were reported as functional but with no further
details. This could also modify slightly the functionality rate as well as the % fully functional
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 49
Table E: Total borehole received per BSF phase and functionality status
Phase
Total
bh Bh
Reported % reported
Average
rating
Functional
Not funct
Funct
rate
(%)
% fully
functional Total funct
Reduced funct
Fully funct
BSF 1 156 89 57 3.4 87 17 61 2 97.8 68.5
BSF 2 148 94 64 3.7 84 10 58 10 89.5 62.1
BSF IA 247 201 81 3.9 199 26 173 2 99.0 86.1
BSF IAe 27 16 59 3.1 16 1 15 0 100.0 93.8
Total 578 401 69 3.7 386 54 306 14 96.5 76.8
For the BSF-IAe, it was assumed that the ones in progress for the BSF-IAe are fully functional
Table F: Total boreholes received per State and functionality
State
Total
bh Bh
Reported % reported
Average
rating
Functional
Not funct
Funct
rate
(%)
% fully
functional
Total funct
Reduced funct
Fully funct
CEQ 73 53 73 3.8 49 3 46 4 92.5 86.8
EEQ 55 50 91 3.6 50 10 31 100.0 62.0
Jonglei 28 28 100 4.0 28 28 100.0 100.0
LAKES 6 0 0
0
NBeG 68 66 97 3.6 63 11 52 3 95.5 78.8
UNITY 63 31 49 3.8 28 6 22 3 90.3 71.0
Upper Nile 104 85 81 3.7 84 84 100.0 100.0
Warrap 69 13 19 3.5 12 6 6 1 92.3 46.2
wBeG 64 29 45 3.7 26 3 7 3 89.7 24.1
WEQ 48 46 96 3.6 46 15 31 100.0 67.4
Total 578 400 69 6.7 386 54 306 14 96.5 76.8
For the BSF-IAe, it was assumed that the ones in progress for the BSF-IAe are fully functional
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 50
Annex 12 Average cost per completed borehole per grant recipient per BSF phase
The average direct cost per completed borehole32
varies per grant recipient depending on the
concluded contract, after contract negotiations. Part of the boreholes were paid according to LS
no—water-no-pay contracts, where the contract amount equals the amount of completed
(successful) borehole times a lump sum value; in that case the terminology unit cost applies.
Other boreholes were drilled using BoQ contracts, where the final invoiced price per borehole
differs according to actual quantities achieved during the completion of the borehole, and final
costs therefore differ from the contract amount. The cost includes all activities and materials to
arrive at a functional borehole, but exclude costs of personnel administrating the project. Activities
included in the costs are mobilisation to the site, geophysical sitting, drilling, drilling supervision,
well development and test-pumping, water quality tests and construction of platform and hand
pump installation. In most cases the grant recipients subcontracted these works. In case they
used their own drilling rig, the costs depend in what the contract recipient invoice, but typically
this would include the depreciation costs of the rig, costs for materials and fuel, and costs for the
drilling team. The cost however excludes the purchase of spare part kits or the training of water
user committees and/or pump mechanics.
The BSF-IAe phase is currently on-going. Up to present (2012/11/05), a total of 562 boreholes
have been invoiced for the four phases, which forms the basis of the cost calculations. In order to
get an overview of the costs incurred for borehole drilling, and the inherent cost-efficiency of the
borehole drilling component under BSF1 – BSF IAe, average borehole costs have been
determined per grant recipient and per phase, as listed in Annex 8. A subjective classification of
costs per borehole has been made of which the legend has been included as the first table of
Annex 8. The tables in Annex 8 show that there are large cost variations per completed borehole
amongst the grant recipients, from an average cost per borehole as low as GBP 4,853 in Phase 1
(IRC) to as high as GBP 15,433 in Phase 2 (World Vision).
The weighted average cost of completing a borehole over the various phases is provided in Table
F. Table 1 also provides the number of boreholes per phase and in which geological unit they
have been drilled according to the Sudan Hydrogeological Map (UNMIS GIS Unit, August 2006,
scale : 1:3,500,000).
Table 1. Average cost per completed borehole per phase
32 Defined in this context as a borehole installed with a hand pump and invoiced to BSF
Phase Average cost / bh Number of bh bh in
Basement
bh in
sediments
bh in boundary zone
Basement / sediments
BSF-1 £ 5,974 156 36 77 43
BSF-2 £ 8,819 148 40 60 48
BSF-IA £ 7,550 247 133 73 41
BSF-IAe £ 8,362 11 11 0 0
Total number of boreholes invoiced 562
Completed, not invoiced yet 6
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 51
Figure 1 shows the difference in average completed borehole costs per phase. It follows that the
average cost of completing a borehole at GBP 8,819 was highest in BSF-2, and lowest in BSF-1
(GBP 5,974).
Figure 1. The average cost of completing a borehole for the four phases under BSF.
There are many factors influencing the cost of a borehole, including the mobilization costs and
insurance, the type of contract (lump sum or bill of quantities-based), the depth of the borehole,
the design of the borehole and the type of bidding (open bidding, restricted bidding, or only
inviting one driller to bid, or not bidding but using the NGO’s own drilling rig). These factors are
impacted by the distance of the drill sites from the base of the drilling contractor, the accessibility
of the area in terms of seasonal flooding, the type of underlying geology, the internal procedures
of the NGO or the client (donors represented by BSF Secretariat), and the presence of an
external drilling supervisor.
The aspect of mobilisation costs in terms of travelling distance for the drilling contractor is hard
to determine, as it is as this stage not known where the drilling contractors for the various phases
were travelling from. However, IRC employed a Ugandan contractor who drilled for BSF in the
remote part of Western Bahr-el-Ghazal, for the cheapest cost for all BSF Phases. On the other
hand, AMREF drilled with a Southern Sudanese drilling company (based in Juba, Central
Equatoria) in nearby Terekeka County, for the highest average cost per borehole. Though not
conclusive statistically, it does not seem to be a determining factor in establishing the cost for a
borehole.
Accessibility of the drill sites in the wet season is a challenging factor mostly in the sedimentary
formations, but also parts of the Basement areas can be inaccessible. The main issue at hand
seems to be the implementation period (“window”) where rigs can access the sites during the dry
season, and drillers have to plan carefully when to start the drilling and when to complete, as late
completion will have the risk that the rig gets stuck in that area for a couple of months and cannot
drill any other wells; incorporating that risk in the contract cost is impossible as it would render the
contract prohibitively high.
Underlying geology: Boreholes in sedimentary formations in South Sudan are nearly always
producing sufficient water, and therefore one drilling attempt per site is sufficient, unless a
technical failure occurs. Boreholes in Basement rocks in South Sudan require extensive
geophysical surveys and even then, the chances of drilling dry boreholes can be as high as 39%
(Intersos in BSF-IA drilled 28 boreholes to arrive at 17 completed boreholes). Therefore, the
£-
£1,000
£2,000
£3,000
£4,000
£5,000
£6,000
£7,000
£8,000
£9,000
£10,000
BSF-1 BSF-2 BSF-IA BSF-IAe
Cost / Borehole [GBP]
Cost / Borehole [GBP]
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 52
expenses per completed borehole are comparatively higher in Basement formations than in
sedimentary formations.
Figure 2 provides the distribution of boreholes over the different major geological units in South
Sudan for the various BSF phases. BSF-1 has the smallest fraction of boreholes in the low
potential Basement rocks (23%), and also has the least average borehole cost. However, BSF-2,
with the highest average borehole cost has only a marginally bigger percentage of boreholes in
Basement rocks (27). During BSF-IA, more than half of the boreholes (54%) were drilled in
Basement rock, yet the average borehole cost was lower than during the BSF-2 phase.
Figure 2. Percentage-wise distribution of completed boreholes in geological units for the four BSF
phases.
Of the 21 NGOs having worked under BSF that reported in the questionnaire, nine used a BOQ
contract33,
for which contractors are paid according to works done, also for dry boreholes. These
BOQ contracts reported on, signed and invoiced against in Phases IA and IAe, have not resulted
in comparatively reduced contract costs; in fact this has resulted in average costs varying
between GBP 8,163 (UMCOR) and GBP 9,899 (Malteser).
Four NGOs reported that they drilled with their own rig (Oxfam GB, World Vision, CRS and ADRA
partly); the average borehole cost of these grant recipients varies considerably over the BSF
phases. Oxfam GB remains in the average cost ranges per phase, whereas ADRA ’s average
borehole costs are higher than the average rates per BSF phase.
Table 2 Average cost per borehole [GBP] with grant recipients using own drilling equipment.
Grant Recipient BSF-1 BSF-2 BSF-IA
Oxfam GB 6,567 8,500 6,959
World Vision 15,433 9,000
CRS 5.236
ADRA 13,144
External drilling supervision was recommended as one of the lessons learnt to increase the quality of
works and cost-effectiveness of boreholes (the latter in the case of BOQ contracts). This approach was
introduced for all grant recipients in BSF phases IA and IAe. It can be concluded for the few BOQ contracts
reported upon, that the average borehole cost has not significantly reduced as compared to the other
contracts signed for that phase; however. The weighted average borehole cost for phase IA was smaller
33 Acted, Hard, Malteser, Oxfam Novib, Red Cross, Umcor, and Intermon Oxfam
23% 27%
54%
100%
28%
32%
17%
0%
49%41%
30%
0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
BSF-1 BSF-2 BSF-IA BSF-IAe
Number of boreholes in
sediments
% of boreholes in
boundary zone Basement
/ sediments
% of boreholes in
Basement
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 53
than that of the previous phase indicating that the average cost for LS contracts reduced as compared to
BSF-2. It can also be noted that there are other influences that the type of contract cannot affect e.g.
Fluctuations in the inflation rate, price of metal, fuel, labour…
For the NGOs having used LS contracts in BSF-IA, the average unit cost (not weighted) seems to
be slightly cheaper than for boreholes drilled under BoQ, being of GDP 7,885 for boreholes with
LS contract and GDP 8,103 for boreholes with BoQ. This difference is not sufficient to draw
conclusion on the influence of the types of contract when compared to the impact of other factors.
The JAM (2005) applied a unit rate of USD 12,000 (equivalent to about GBP 7,500) for the
construction of boreholes in Southern Sudan. This was achieved in BSF-1 but not in the
subsequent phases.
The higher costs for BSF-IAe boreholes could be explain by the fact that implementing NGOs
were not specialised in water thus maybe not able to compare bids of different drillers and be
critical on price. It could also be explained by the fact that, except for Malteser and ADRA, other
NGO would get funds for one or two boreholes, meaning that the mobilisation costs would have
to be divided for a limited amount of borehole.
All in all, a much more in-depth study is required to analyse the combined effect of all factors
influencing the drilling costs in South Sudan implemented through the BSF Secretariat. The
competitiveness of the bidding exercise, and the availability of drillers (to what extent drillers are
willing to bid for certain inaccessible or otherwise unfavourable areas) may also well have an
impact on the average cost. However, in the absence of conclusive explanations, it seems
reasonable to conclude that using the average rates for the various phases, grant recipients can
be informed that their proposed costs are too high, and need to be further revised downwards, if
average costs exceed GBP 9,000.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 54
Annex 13 Supporting tables for Unit costs analysis
Grant recipients BSF-1
Actual
cost/borehole
[GBP]
Achieved No. of
boreholes
AMREF 10,333£ 20
CARITAS 19
Merlin / AVSI 6,133£ 10
IRC 4,853£ 21
MEDAIR 6,000£ 10
OXFAM GB 6,567£ 73
SC-US 7,524£ 3
Weighted average BSF-1 5,974£ 156
Grant recipients BSF-2
Actual
cost/borehole
[GBP]
Achieved No. of
boreholes
AMA 9,109£ 49
AVSI 9,220£ 7
CMS £ 7,907 8
HARD £ 9,965 3
OXFAM-GB £ 8,500 29
Intermon OXFAM £ 10,137 18
Swiss Red Cross £ 6,300 19
UMCOR £ 8,276 10
World Relief £ 8,000 1
World Vision £ 15,433 4
Weighted average BSF-2 8,819£ 148
Grant recipients BSF-IA
Targeted
cost/borehole
[GBP]
Target No. of
boreholes
Actual
cost/borehole
[GBP]
Achieved No. of
boreholes
ACTED 5,921£ 33 5,955£ 39
ACF-USA 7,061£ 7 6,370£ 7
ADRA 10 13,144£ 10
ARC 7,238£ 4 6,337£ 5
AVSI cat II 6,333£ - 9,639£ 4
Care - 1
CMS Ireland cat II 8,000£ 1 0
CONCERN 9,763£ 7 7,598£ 7
CRS 8,957£ 15 5,236£ 15
HARD 7,500£ 3 7,408£ 4
Intermon OXFAM 9,945£ 17 8,089£ 17
Intersos 9,306£ 18 11,496£ 17
Malteser - 9,850£ 5
OXFAM GB 6,959£ 25 4,791£ 21
TEARFUND 9,143£ 28 7,961£ 28
SCiSS 7,508£ 3 6,362£ 3
UMCOR 8,163£ 12 7,582£ 24
Oxfam Novib 9,002£ - 9,000£ 6
World vision cat II
9,000£ 9 9,879£ 5
ZOA 8,000£ 26 8,502£ 29
Weighted average BSF-IA 7,550£ 247
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 55
Grant recipients BSF-IAe
Actual cost/borehole [GBP]
Achieved No. of boreholes
Achieved but not yet invoiced
CCM £ 7,500 0
Malteser £ 8,362 11
Hard 1
ADRA 4
Care 0
CMSI 1
SCiSS 0
Average BSF-IA £ 7,931 11 6
Weighted average BSF-IAe £ 8,362
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 56
Annex 14 Combined Lessons learned BSF WASH
Throughout the four phases of BSF, the way to implement the WASH component has evolved. By
gaining more knowledge and identifying shortcomings, the BSF Secretariat has gradually
optimized the approach for monitoring progress of WASH projects implementation following the
lessons learnt throughout the years, which helped making remarkable progress towards its
targets in raising safe water coverage. Advices provided from the BSF Secretariat to the grant
recipients have also been adjusted for a more sustainable implementation of the WASH projects.
The main improvements occur on the following aspects:
- Drilling contracts
Almost all drilling contracts for the first two phases were lump sum per successful borehole drilled
(LS). Usually, and especially in the absence of healthy competition, LS contracts turn out to be
more costly, as the drilling contractor wants to ensure that the contract has a decent profit by
covering any risk of drilling a dry borehole through an increased price per borehole. To enable a
good technical assessment of material and design before and during the execution of the drilling
and also to make supervision easier, the BSF Secretariat has strongly advised NGOs to have a
BoQ contract with Contactors, and particularly from BSF-IA. This involved that, in case of a dry
borehole (under the condition that the site was selected after geophysical survey, see paragraph
below), the work executed will be paid for. From BSF- IA, there was an additional budget to pay
for the dry boreholes in addition to the budget agreed with the NGOs.
- Geophysical survey
To avoid the risks of dry boreholes, the BSF Secretariat, from BSF-IA, strongly recommended to
execute a geophysical survey before to start drilling activities. The price for this survey should be
part of the BoQ or, if the contractor does not have the necessary equipment, should be
additionally budgeted for and executed by a specialized company.
- Drilling supervision
Requesting an independent supervisor during the drilling activities did not used to be widespread
in South Sudan. The need for independent supervision was already identified in BSF-1. From
BSF-2 onwards, the BSF Secretariat strongly advised the grant recipients to request the services
of an independent supervisor, either a qualified supervisor from the County or State Water
Department, or an external independent supervisor. Costs for it could be budgeted for. In the last
phase of BSF, the NGOs reported having used the supervision services of County or State Water
Department Staff, some of which attended the training.
- Water quality testing
Water quality testing before to validate a new and rehabilitated water point was a major deficiency
while this is an essential criterion before to install the hand pump and leave the borehole for use
of the communities. The BSF Secretariat has been requesting that water points ‘water quality at
least comply with the standard established by the MWRI’. Boreholes with unacceptable water
quality will be paid for but no hand pump should be installed. Standard water quality forms have
been developed by the MWRI and should be submitted by the NGOs or the Contractor to the
county (or State) water department.
- Reporting
Field reports, geophysical survey reports, borehole drilling logs, and water quality reports need to
be handed in to the County or State Water Department to feed to the SSWICH database. This
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 57
should include both successful and unsuccessful boreholes. As this flow of information has
appeared to be unreliable, and on request of the MWRI, the NGOs were requested to also send a
copy of those forms to the BSF Secretariat. The BSF Secretariat would then hand over those
forms directly to the MWRI to accelerate the feeding of the Water Information Management
System : WIMS (previously called SSWICH). Currently, the MWRI is setting up WIMS offices at
State level and staff are being trained to collect and computerise this information at State level.
Sensitisation campaigns are being carried out to incite NGOs and contractor to hand over
systematically the forms to the State Office.
- Repair and Rehabilitation
Repair/rehabilitation of boreholes is more cost effective (with the benefit measured in terms of
increased access to safe drinking water) than drilling new boreholes. This lesson learned was
taken into account from BSF-2 where borehole rehabilitation and repairs started to be funded
(BSF-1 only funded the drilling of new boreholes). Since BSF-2, 535 boreholes were repaired and
rehabilitated. However, grant recipients do not always distinguish between rehabilitation and
repair and have been reporting minor repairs as rehabilitation. Rehabilitation of boreholes should
include new platform, pump, cylinder, rods, etc. A rehabilitated borehole should, in order to give it
a longer lifespan, also be flushed and disinfected. In BSF-IAe however, the distinction in the
reporting format was made.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 58
Annex 15 Examples of types of trainings provided by NGOs
ACF provides a one day training to WUC while the assessment and repair of the water point is
occurring. Training subjects include administration (roles and responsibilities of WUC members)
and accountancy (user fee collection, accountability, record keeping). Occasionally, a second day
of training can be offered covering general maintenance and water point management (interaction
with users and local authorities). ACF indicated that they are in the process of creating a more
rigorous caretaker training that will take an additional 2 days. It will go into details for the pump
parts, inspection and practical training exercises. The main focus will be for caretakers to
understand their role in planned preventative maintenance (daily, weekly and monthly inspections
and simple repairs or replacements).
Pump mechanics are also trained by ACF for 2 days. ACF has focused on strengthening pump
mechanics skills while also helping them form associations in which they can hone private
business and logistics management skills.
UMCOR conducts several trainings including, water management committee trainings (2 care
takers, chairperson, secretary, treasury and 4 committee members per water point). The
members are taken through 2 days practical and 2 days theory training. The WUC are trained on
their roles and responsibilities on management, active participation, and transparency and being
accountable to the community they serve. In addition to follow up visit from the NGO, the local
chiefs and County Water Departments are also advised to regularly call for meetings with the
group to ensure they remain active. Pump mechanics training lasts 5 days. UMCOR also
provides refresher trainings to pump mechanics that play a pivotal role in the repair of water
points thus ensuring their continued operation.
For each borehole drilled, World Vision provides 5 days training for WUC, focussing on the roles
and responsibilities of water user committee members, management and leadership skills,
community participation and mobilization, user fee management, record keeping, personal
hygiene, common hygiene and sanitation related diseases and role of RWSS department and the
community in managing water points. The person conducting the training in the local CWDE
representative, and a staff member of the World Vision will supervise. They also provide training
of pump mechanics, focusing on Operation and Maintenance of INDIA MK II hand pumps, trouble
shooting and how to channel any mal-functioning issues related to the borehole to the RWSS
office both at the Payam and County level.
Intersos will carry out WUC training of 5 days. The training will be provided by the local
employee of Intersos that used to work for the SDWS.
In the case of ZOA, the WUC training is generally a 7 days training. The objectives of the different
modules and lessons are to make communities understand the importance of safe water supplies
and to enable them to deal with technical, health and social problems in relation to water in an
appropriate way. ZOA is in consortium with a local NGO called Compass, who has local
employee providing the training to the communities.
Intermon Oxfam reported to be providing training for water user committee for 2 days. The hand
pump mechanics training will include 2 people from each WMC (50% of the positions are offered
to women. However, sometimes it is not possible to reach this ratio). They are trained then
trained for 5-7days. RWD participates in the facilitation of these trainings.
Status Review of the BSF drilling activities (2006-2012)
Euroconsult / BMB Mott MacDonald 59
IRC delivers 3 days WUC training for each water point focusing on basic water point
management, hygiene and sanitation and training for care takers.
In the case of Malteser, 3 to 5 days trainings are provided for Water User Committees,
conducted by official trainers from the State Directorate of Water and Sanitation in Yambio.
Malteser also provides trainings for community elected “Care Takers/Pump Mechanics” to ensure
a proper maintenance and usage of the boreholes. For each Borehole there are five of these
“Care Takers/Pump Mechanics” invited to attend the Workshops. The trainings are conducted by
two official trainers requested from the State Directorate of Water and Sanitation in Yambio and
last for 7 days. The syllables for these Workshops are as follows:
- Introductions to a standard tool kit
- Usage of each tool by care takers
- How to remove a cylinder head
- Application of grease to the chain
- Fitting of minor spare parts i.e. nuts
- How to do borehole fencing
(which seems to be more Water point care training subject than real pump mechanics)
ACTED reported to carry out training for 3 days, focusing on practical aspects on O&M of
borehole and supporting communities to link with the CWD
Swiss Red Cross conducted training of pump technician was conducted for 5 days covering
basic maintenance skills.
AVSI reported to carry out trainings of Pump Mechanics, and Water Users Committees; and this
normally takes a period of two to three weeks, depending on the availability of the resources.
Oxfam GB reported that pump mechanics trainings are executed by a qualified water technician
for seven days theory followed by 14 days practical in the field. There after the trainees are
supervised by qualified water technicians throughout, whenever there is a broken pump till they
are competent to handle all types of borehole repairs. They ensure the long term impact of the
borehole drilled by providing refresher retraining of village pump mechanics, and supply of fast
moving kits ( depending on the accessibility and as long as the project does not close down in
that particular site).
CRS facilitates Hand Pump Mechanic and Hygiene Promotion Training targeting the local
community around the water points. Five people are selected (3 for Hand Pump Mechanic
Technicians and 2 for Hygiene Promoters training) from each newly drilled and rehabilitated bore-
hole. The training is categorized in two phases. Phase 1 is two weeks and phase 2 is 1 week. All
the trainees will first undergo hygiene and sanitation awareness training and in the cause of the
training HIV/AIDS awareness and Peace Building is also included in the training as cross-cutting
modules. The Hand Pump Mechanic Technicians after undergoing the said training will then
undergo theories and field practices on dismantling and assembling dysfunctional bore-holes.
CRS send them back to their communities equipped with the tools and repair kits.
ADRA provides WUC training for ten members (5 males and 5 females) per borehole for five
days training in management affairs related to the borehole, while for the pump technicians, the
training is for two weeks and includes the provision of tool boxes for repair of the boreholes.