Runway 16R RehabilitationBuilding a Higher Level of World-Class
Project BriefingJanuary 8th, 2013
VNY 16R – Building a Higher Level of World-Class
Agenda• Welcome
• Project Team
• Project Scope• Runway Rehabilitation• Run-Up Area
Improvements
• Phasing
• Stakeholder Outreach
• Questions and Answers
• Break-Out Session
01/08/2013 2
VNY 16R – Building a Higher Level of World-Class
Owner and Operator
Design Engineer
Contractor
Construction Manager
Project Team
01/08/2013 3
VNY 16R – Building a Higher Level of World-Class
Mark Vicelja, PE-Airside Project Manager, LAWA
401/08/2013
VNY 16R – Building a Higher Level of World-Class
Project Scope
North Run-Up Area Improvements
Runway Rehabilitation
Shoulder Improvements
MALSR Adjustments
501/08/2013
VNY 16R – Building a Higher Level of World-Class
Runway RehabilitationIsolated Concrete Repairs
Isolated Concrete Repairs
• Full Reconstruction• ± 650’
• Full Width Overlay• ± 3850’
• Keel Reconstruction w/ Overlay• ± 2300’
601/08/2013
VNY 16R – Building a Higher Level of World-Class
Existing Run-Up Area
701/08/2013
Deficiently Sized
Permits Holding Within the RSA
VNY 16R – Building a Higher Level of World-Class
Run-Up Area Improvements
801/08/2013
Realigned Service Road
Two Sequencing Positions
Engine Maintenance Position
Appropriately Located Hold-Bar
VNY 16R – Building a Higher Level of World-Class
Mark Vicelja, PE-Airside Project Manager, LAWA
James Long, PE-Airfield Engineer, HNTB Corporation
901/08/2013
VNY 16R – Building a Higher Level of World-Class
Construction Schedule
Full Closure
No RWY Impacts
LEGEND
Night Closure
Shortened RWY
1001/08/2013
Note: All schedules presented here are targeted construction schedules and subject to change.
2/24
3/26
4/25
6/9
6/29
7/9
7/19
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Mobilization
90 Days
11/26/12 2/23/13
1101/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
During Run-Up Area construction, Runway 16L may be used for Run-Ups with clearance from tower and VNY Operations
No Restrictions on Runway
Phase 1 – Run-Up
60 DAYS
2/24/13 4/24/13
Salvage Existing Blast Fence
Expand Run-Up Area
Realign Service Road
Construct New Blast Fence
1201/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 1A – Run-Up
Temporary Taxilane A1 Centerline
RWY Access at TWY C is closedAsphalt Paving
60 DAYS20
3/26/13 4/14/13
1301/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 2A – Night Work
Phase 1 Phase 2
4 Nights
Nightly Closures of 16R
Nightly Closures of 16L
Relocate Blast Fence
Temporary Threshold Lights
Temporary PLASI
Marking Removals
New Threshold Markings
1401/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
RSA 34L Arrivals & Departures16R Departures16R ArrivalsRSA
Phase 2 – North End
MALSR System Adjustments
Reconstruction of Runway and Shoulder
Pavements
Isolated Repairs on Existing Concrete
45 Days
4/25/13 6/8/13Arrivals Departures
16R 5417’ 6017’
34L 5017’ 5017’
1501/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 3A – Night Work
Phase 2
4 Nights
3
Relocate Blast Fence
Temporary Threshold LightsTemporary Threshold Lights
Temporary PLASI
Temporary Markings
Marking Removal
Nightly Closures of 16R
Nightly Closures of 16L
Temporary PLASI
1601/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
RSA16R DeparturesRSA 34L DeparturesRSA 34L Arrivals RSA16R Arrivals RSARSA
Phase 3 – South End
20 days
Reconstruction of Runway and Shoulder
Pavements
Isolated Repairs on Existing Concrete
Arrivals Departures16R 5079’ 5563’
34L 5761’ 5161’6/9/13 6/28/13
1701/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 3B – Night Work
Night Closure of 16R
Night Closure of 16L
1 Night
3
Temporary Marking
1801/08/2013
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 4A – Pre-Work
Nightly Mill and Replace
Nightly Closure of 16R & 16L
9 Nights
1901/08/2013
6/30/13 7/8/13
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 4 – Runway Closure
Full Closure of 16R
No Impacts to 16L
Reconstruction of Runway Pavements
10 days
2001/08/2013
7/9/13 7/18/13
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 4B - Shoulders
Nightly Shoulder Work
Nightly Closure of 16R & 16L6 Nights
2101/08/2013
7/19/13 7/24/13
VNY 16R – Building a Higher Level of World-Class
Operational Runway
Construction Area
Already Constructed
December ‘12
January ‘13
February ‘13
March ‘13
April ‘13
May ‘13
June ‘13
July ‘13
August ‘13
Note: All schedules presented here are targeted construction schedules and subject to change.
Phase 4C – Close Out
Final Pavement Markings
Nightly Closure of 16R & 16L2 Nights
2201/08/2013
VNY 16R – Building a Higher Level of World-Class
Phasing Summary
2301/08/2013
2/24 - 4/24
• Run-Up Area Improvements
• Runway Access at TWY C limited for 20 days
4/25 - 6/28
• North and South Runway Improvements
• Shortened Runway for 65 Days
6/30 – 7/8
• Keel Prep-Work• Nightly
Closures
7/9 – 7/18
• Central Runway Improvements
• Full Runway Closure
7/19 – 7/24
• Shoulder Work• Nightly
Closures
8/18 – 8/19
• Final Marking• Nightly
Closures
VNY 16R – Building a Higher Level of World-Class
Jess Romo, AAE-Van Nuys Airport Manager
2401/08/2013
VNY 16R – Building a Higher Level of World-Class
Before You Fly, Check VNY
For Latest Updates, Call or Click:
• Project Website:▫ www.lawa.org/vny16R
• Project Hotline:▫ (818) 442-6556
• Social Media:
2501/08/2013
VNY 16R – Building a Higher Level of World-Class
Than
k Yo
u • Questions
• Comments
• Break-Out Session
2601/08/2013