Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary School 27 Hazel Wolf K-8 at Pinehurst 39 Meany Middle School 52 Olympic Hills Elementary School 60 Seattle New World School at TT Minor 70 New Thornton Creek Building 81 June 3, 2016 Building Excellence IV Capital Levy Projects Under Construction

Upload: vankhue

Post on 17-Apr-2018

220 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Project Slide Number

Arbor Heights Elementary School 2

Cascadia Elementary School & Robert Eagle Staff Middle School 14

Genesee Hill Elementary School 27

Hazel Wolf K-8 at Pinehurst 39

Meany Middle School 52

Olympic Hills Elementary School 60

Seattle New World School at TT Minor 70

New Thornton Creek Building 81

June 3, 2016

Building Excellence IV Capital Levy

Projects Under Construction

Page 2: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy

Arbor Heights Elementary School

Site: Landscape irrigation and drainage installation ongoing, parking lot curbs and paving in-progress, site fence installation ongoing.

South Building: Exterior – painting ongoing. Interior – Light fixture installation ongoing on second and third floors. Casework ongoing at second and third floors. Finish carpentry in-progress. Rubber floor tile and carpet installation ongoing. Mechanical, electrical and plumbing (MEP) fixture installation ongoing. Mechanical, electrical and plumbing installation ongoing at first, second and third floor mechanical rooms and first floor boiler room.

North Building: Exterior – Window installation ongoing. Fiber cement board siding installation ongoing. Interior – Concrete floor polishing complete at Lobby and Arbor. Painting at library, gymnasium, and admin ongoing. MEP fixture installation in-progress. Mechanical, electrical and plumbing installation ongoing Room 306.

Page 3: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

Site Plan

July 1, 2015 July 10, 2015

Page 4: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

Aerial View from the North

May 01, 2016

Page 5: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

Site – Northeast Perspective

May 31, 2016

Page 6: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

South Building – Southeast Perspective

May 31, 2016

Page 7: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

South Building – Boiler Room 110

May 31, 2016

Page 8: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

South Building – Kindergarten Room 124

May 31, 2016

Page 9: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

North Building – Northeast Perspective

May 31, 2016

Page 10: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

North Building – Commons

May 31, 2016

Page 11: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

North Building – Gymnasium

May 31, 2016

Page 12: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

North Building – Library

May 31, 2016

Page 13: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Arbor Heights Elementary School

North Building – Mechanical Room 306

May 31, 2016

Page 14: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy Cascadia Elementary School and Robert Eagle Staff Middle School

Site: Maintaining TESC. Southwest parking lots paved and temporarily

striped.

ES: Roofing ongoing, started installing cap sheet. Exterior sheathing

complete, air barrier ongoing. Interior framing and MEP wall and ceiling

rough-in ongoing.

MS: Exterior sheathing started and metal stud framing ongoing at Zones

1, 2, 3. MEP rough-in ongoing. Metal decking at Gymnasium (Zone 9)

ongoing. Framing at mechanical penthouses.

Page 15: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Site Plan

Page 16: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Zone Map

Middle School Elementary School

Page 17: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Aerial View from the South

May 27, 2016

Page 18: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School, Zones 5, 6 & 7 – Sheathing and Air Barrier

May 27, 2016

Page 19: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School, Zone 7 – Exterior Sheathing and Air Barrier, Looking East

May 27, 2016

Page 20: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School, Zone 2 – Lower Roof Cap Sheet Installation

May 27, 2016

Page 21: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School, Zone 6 – Lower Roof Interply Sheet Installation

May 27, 2016

Page 22: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School, Zone 1 – Ductwork Insulation at Classroom

May 27, 2016

Page 23: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School, Zone 9 - Gym Murals Installed, Looking North

May 27, 2016

Page 24: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School, Zones 2 & 3 – Exterior Framing and Sheathing

May 27, 2016

Page 25: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School, Zone 2 – Mechanical Penthouse Framing, Looking South West

May 27, 2016

Page 26: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School, Zone 9 – Vapor Barrier and Slab-on-Grade Prep

May 27, 2016

Page 27: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy

Genesee Hill Elementary School

Site: Landscaping is ongoing at the upper and lower tiers of site; continued

installation of chain link fencing at south end of lower and upper tiers.

Area 1: Miscellaneous balancing “pick-up” items occurring; HVAC equipment

functional testing completed; revising minor controls sequencing; pretesting

for elevator inspection ongoing.

Area 2: Miscellaneous balancing “pick-up” items occurring; HVAC equipment

functional testing is ongoing; completed resilient flooring and rubber base

installation; continued area final cleaning; pretesting for elevator inspection

ongoing.

Area 3: Completed final cleaning; functional testing ongoing.

Area 4: Completed final cleaning; functional testing ongoing.

Page 28: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Site Plan

Page 29: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Aerial View from the South

Page 30: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Site – Specialized Landscaping Installing Plant Materials at Lower Parking Lot

Page 31: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Site – General Contractor Installing Traffic Gates at Dakota Street Entry

Page 32: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Area 1, Level 3 – Typical Corridor

Page 33: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Area 2, Level 2 – Interior Caulking Ongoing

Page 34: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Area 2, Level 2 – Graphic Wall

Page 35: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Area 2, Level 2 – Library

Page 36: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Area 2, Level 2 – Computer Lab Classroom

Page 37: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Area 3 – Adjusting Audio Equipment at Commons and Gymnasium

Page 38: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Genesee Hill Elementary School

Area 3 – South View of Commons and Gymnasium

Page 39: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy

Hazel Wolf K-8 at Pinehurst

Site: General site clean up and monitoring temporary erosion control measures.

Electrical transformer installed and energized. Grading of loading dock area

access continues. Off-site preparation for placement of concrete sidewalks along

117th Avenue.

Building A: A1 - Top deck water proofing continues. Kitchen cooler installation

complete. Ceiling grid/tile install ongoing. Painting ongoing. Area A2 - Final

coats of paint ongoing at all floors. Ceiling grid complete, ceiling tiles installation

ongoing. Elevator installation work continues. Casework installation complete and

plumbing fixtures being installed. Concrete floors receiving final grinding. Area

A3 - Water proof membrane installation ongoing, exterior concrete stairs form

work ongoing. GWB taping nearing completion. Store front window installation

complete.

Building B: Exterior sheeting and air barrier complete. Exterior masonry

complete. Interior band/choir room GWB taping ongoing.

Building C: Exterior metal siding nearing completion. Windows completed. GWB

finishing in the gym and commons areas completed. Ceiling in the gym and

commons painted. Clouds receiving GWB and starting to be finished.

Page 40: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Site Plan

Page 41: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Aerial View from the East

May 16, 2016

Page 42: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Areas A1 and A2 – Looking Northwest

May 25, 2016

Page 43: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area A2 – Final Exterior Siding Install, Looking Northwest

May 27, 2016

Page 44: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area A2 – Exterior Siding, Looking Southeast

May 25, 2016

Page 45: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area A2 – Final Siding Colors

May 25, 2016

Page 46: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area A2 – Tile Installed

May 27, 2016

Page 47: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area A2 – Lockers Installed

May 27, 2016

Page 48: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area A2 – Learning Commons

May 27, 2016

Page 49: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area A2 – Water Fountains Installed

May 27, 2016

Page 50: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area C – Commons Finishes

May 27, 2016

Page 51: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Hazel Wolf K-8 at Pinehurst

Area C – Gym Sound Board Installation

May 27, 2016

Page 52: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy

Meany Middle School

Site: Partial Site mobilization and protection in place at loading dock and

surrounding the 1954 Classroom Wing. Access to loading dock is

coordinated with Seattle World School administrators and staff.

1954 Classroom Wing: Interior – Demolition of casework, wall finishes,

interior window trim ongoing in Sector 4 and 5N. Wood flooring salvage

complete. Demolition of lower windows ongoing and concrete shear wall infill

at window openings in Sector 4 are scheduled to begin next week. HVAC

demolition complete in Sector 5 at the Band/Chorus rooms. Plumbing

trenching has started and will continue for one week. Electrical demolition in

Sector 4 and 5 is complete.

Remainder of Building: No work occurring until after Seattle World School

leaves site. Contractor has full access to site no later than July 12, 2016

Page 53: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Meany Middle School

1964 Aerial Photo

July 1, 2015 July 10, 2015

1954 Classroom Wing

Page 54: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Meany Middle School

Electrical Rough-In Started in Sector 4

May 26, 2016

Page 55: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Meany Middle School

Floor Slab Cutting and Systems Demolition Complete in Sector 4

May 26, 2016

Page 56: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Meany Middle School

PBS Testing Exterior Walls

May 26, 2016

Page 57: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Meany Middle School

Sector 4 Restroom Floor Removal and Trenching

May 26, 2016

Page 58: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Meany Middle School

Restroom Floor Removal and Trenching

May 26, 2016

Page 59: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Meany Middle School

Band Room Demolition

May 26, 2016

Page 60: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy

Olympic Hills Elementary School

Site: Geothermal underground piping ongoing. TESC measures ongoing.

Building: Framing walls, installing roof joists, installing 2nd floor decking

in Zone A and B, ongoing. Poured slab-on-wood-deck in Zone A.

Started weather-resistant barrier and flashing in Zone A. MEP rough-in

ongoing in Zone A. Steel column erection and wall layout in Zone C,

ongoing.

Page 61: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Site Plan

Page 62: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Zone Map

Page 63: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Aerial View from the West

May 1, 2016

Page 64: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Zone A – Structural Wall Framing, Looking Northwest

May 25, 2016

Page 65: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Zone A – HVAC Ductwork Through Joists in Classroom

May 25, 2016

Page 66: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Zone A – Weather-Resistant Barrier and Flashing, Looking West

May 25, 2016

Page 67: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Zone A – Parapet Walls Insulated and Protected, Looking East

May 25, 2016

Page 68: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Zone B – Wood Decking 2nd Floor, Looking South

May 25, 2016

Page 69: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Olympic Hills Elementary School

Zone C – Steel Column Erection and Wall Layout, Looking North

May 25, 2016

Page 70: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy

Seattle World School at T.T. Minor

Area A – Administration Office, Student Services, Health Clinic and Library: Gypsum wallboard finishing nearing completion. Finish painting ongoing. Ceiling grid installation ongoing. Casework installation ongoing. ADA stage ramp in progress. Overhead MEP rough-in work complete. Light fixture installation ongoing. Low voltage data installation ongoing.

Area B – Multipurpose, Kitchen, Boiler Room: Air Handling Units set in place complete. Kitchen flooring ongoing, walk in cooler and freezer in place. Gypsum wallboard finishing nearing completion. Finish painting ongoing. Ceiling grid installation ongoing. Casework installation ongoing. Overhead MEP rough-in work on-going. Light fixture installation ongoing. Low voltage data installation ongoing.

Area C – Classrooms: Gypsum wallboard finishing complete. Finish painting ongoing. Ceiling grid installation ongoing. Casework installation ongoing. Overhead MEP rough-in work complete. Light fixture installation ongoing. Low voltage data installation ongoing.

Page 71: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Site Plan

Area C

Area B

Area A

Area C

Area B

Area A

Page 72: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Site – Asphalt Installation at New Curb Cut On Pike Street

May 31, 2016

Page 73: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Site – New Entrance Off Of Pike Street For Deliveries and Dumpster Enclosure

May 31, 2016

Page 74: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Site – Sidewalk Ramps Completed on 18th Street and Pike

May 31, 2016

Page 75: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Area A – Entry Vestibule Steel Erection

May 31, 2016

Page 76: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Area A – Entry Vestibule Steel Erection

May 31, 2016

Page 77: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Area B – Exterior Siding Installation Ongoing

May 31, 2016

Page 78: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Area B – Kitchen Flooring Installation Ongoing

May 31, 2016

Page 79: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Area C – New Locker Installation Ongoing

May 31, 2016

Page 80: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Seattle World School at T.T. Minor

Area C – Cabinetry and Casework Installation ongoing

May 31, 2016

Page 81: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

Building Excellence IV Capital Levy

New Thornton Creek Building Site: Ongoing installation of backstop fencing in the playfield. Seattle city

Light installed transformer and connected new primary electrical service to Main Electrical Room. Ongoing grading of athletic field.

Off-site Improvements: Completed pouring of concrete curbs and ADA ramps at intersection of NE 80th St. and 40th Ave NE. Ongoing grading and site prep for sidewalks and street trees on NE 80th St.

Building A: Ongoing roofing over Gym and Childcare. Completed installation of interior framing, hollow metal frame doors and relites. Ongoing hanging of ductwork and installing louvers. Ongoing plumbing, fire suppression and electrical rough-in. Ongoing gypsum wall board (GWB) install in Commons, Main Stage and Music Rooms. Preparation for application of resilient flooring.

Building B: Ongoing Hardie panel installation. Ongoing painting on first and second floors classrooms. Ongoing painting in Library, adjacent Computer Lab, Art and Special Education Resource Rooms. Ongoing HVAC rough-in in mechanical penthouse.

Building C: Ongoing trim of electrical devices. Ongoing ceramic tile installation in bathrooms. Ongoing installing casework in classrooms. Began installing resilient flooring in classrooms.

Page 82: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Key Plan

Building C

Building B

Building A

D

Page 83: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Aerial View from the North

May 15, 2016

Page 84: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Preparing for Concrete Pavement at Main Entry

Page 85: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Storefront Installation at South Commons

Page 86: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Framing Soffit in Commons

Page 87: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Gypsum Wallboard Installation

Page 88: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Kitchen Fiber-Reinforced Plastic (FRP) Wall Panel Installation

Page 89: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Installing Cap Sheet on Commons Roof

Page 90: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Childcare GWB Installation

Page 91: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Operable Partition Track Installation

Page 92: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building A – Music Room/Stage Acoustical Wall Installation

Page 93: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building B – Locker Installation

Page 94: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building B – Second Floor, Preparing Hallway for Resilient Flooring

Page 95: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building B – West Stairwell Painting and Acoustical Ceiling Grid Installation

Page 96: Building Excellence IV Capital Levy Projects Under ... · Project Slide Number ... electrical and plumbing installation ongoing ... Started weather-resistant barrier and flashing

New Thornton Creek Building

Building B – First Floor Polishing Concrete