building excellence iv capital levy projects under ... · project slide number ... electrical and...
TRANSCRIPT
Project Slide Number
Arbor Heights Elementary School 2
Cascadia Elementary School & Robert Eagle Staff Middle School 14
Genesee Hill Elementary School 27
Hazel Wolf K-8 at Pinehurst 39
Meany Middle School 52
Olympic Hills Elementary School 60
Seattle New World School at TT Minor 70
New Thornton Creek Building 81
June 3, 2016
Building Excellence IV Capital Levy
Projects Under Construction
Building Excellence IV Capital Levy
Arbor Heights Elementary School
Site: Landscape irrigation and drainage installation ongoing, parking lot curbs and paving in-progress, site fence installation ongoing.
South Building: Exterior – painting ongoing. Interior – Light fixture installation ongoing on second and third floors. Casework ongoing at second and third floors. Finish carpentry in-progress. Rubber floor tile and carpet installation ongoing. Mechanical, electrical and plumbing (MEP) fixture installation ongoing. Mechanical, electrical and plumbing installation ongoing at first, second and third floor mechanical rooms and first floor boiler room.
North Building: Exterior – Window installation ongoing. Fiber cement board siding installation ongoing. Interior – Concrete floor polishing complete at Lobby and Arbor. Painting at library, gymnasium, and admin ongoing. MEP fixture installation in-progress. Mechanical, electrical and plumbing installation ongoing Room 306.
Arbor Heights Elementary School
Site Plan
July 1, 2015 July 10, 2015
Arbor Heights Elementary School
Aerial View from the North
May 01, 2016
Arbor Heights Elementary School
Site – Northeast Perspective
May 31, 2016
Arbor Heights Elementary School
South Building – Southeast Perspective
May 31, 2016
Arbor Heights Elementary School
South Building – Boiler Room 110
May 31, 2016
Arbor Heights Elementary School
South Building – Kindergarten Room 124
May 31, 2016
Arbor Heights Elementary School
North Building – Northeast Perspective
May 31, 2016
Arbor Heights Elementary School
North Building – Commons
May 31, 2016
Arbor Heights Elementary School
North Building – Gymnasium
May 31, 2016
Arbor Heights Elementary School
North Building – Library
May 31, 2016
Arbor Heights Elementary School
North Building – Mechanical Room 306
May 31, 2016
Building Excellence IV Capital Levy Cascadia Elementary School and Robert Eagle Staff Middle School
Site: Maintaining TESC. Southwest parking lots paved and temporarily
striped.
ES: Roofing ongoing, started installing cap sheet. Exterior sheathing
complete, air barrier ongoing. Interior framing and MEP wall and ceiling
rough-in ongoing.
MS: Exterior sheathing started and metal stud framing ongoing at Zones
1, 2, 3. MEP rough-in ongoing. Metal decking at Gymnasium (Zone 9)
ongoing. Framing at mechanical penthouses.
Cascadia Elementary School & Robert Eagle Staff Middle School
Site Plan
Cascadia Elementary School & Robert Eagle Staff Middle School
Zone Map
Middle School Elementary School
Cascadia Elementary School & Robert Eagle Staff Middle School
Aerial View from the South
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Elementary School, Zones 5, 6 & 7 – Sheathing and Air Barrier
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Elementary School, Zone 7 – Exterior Sheathing and Air Barrier, Looking East
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Elementary School, Zone 2 – Lower Roof Cap Sheet Installation
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Elementary School, Zone 6 – Lower Roof Interply Sheet Installation
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Elementary School, Zone 1 – Ductwork Insulation at Classroom
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Middle School, Zone 9 - Gym Murals Installed, Looking North
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Middle School, Zones 2 & 3 – Exterior Framing and Sheathing
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Middle School, Zone 2 – Mechanical Penthouse Framing, Looking South West
May 27, 2016
Cascadia Elementary School & Robert Eagle Staff Middle School
Middle School, Zone 9 – Vapor Barrier and Slab-on-Grade Prep
May 27, 2016
Building Excellence IV Capital Levy
Genesee Hill Elementary School
Site: Landscaping is ongoing at the upper and lower tiers of site; continued
installation of chain link fencing at south end of lower and upper tiers.
Area 1: Miscellaneous balancing “pick-up” items occurring; HVAC equipment
functional testing completed; revising minor controls sequencing; pretesting
for elevator inspection ongoing.
Area 2: Miscellaneous balancing “pick-up” items occurring; HVAC equipment
functional testing is ongoing; completed resilient flooring and rubber base
installation; continued area final cleaning; pretesting for elevator inspection
ongoing.
Area 3: Completed final cleaning; functional testing ongoing.
Area 4: Completed final cleaning; functional testing ongoing.
Genesee Hill Elementary School
Site Plan
Genesee Hill Elementary School
Aerial View from the South
Genesee Hill Elementary School
Site – Specialized Landscaping Installing Plant Materials at Lower Parking Lot
Genesee Hill Elementary School
Site – General Contractor Installing Traffic Gates at Dakota Street Entry
Genesee Hill Elementary School
Area 1, Level 3 – Typical Corridor
Genesee Hill Elementary School
Area 2, Level 2 – Interior Caulking Ongoing
Genesee Hill Elementary School
Area 2, Level 2 – Graphic Wall
Genesee Hill Elementary School
Area 2, Level 2 – Library
Genesee Hill Elementary School
Area 2, Level 2 – Computer Lab Classroom
Genesee Hill Elementary School
Area 3 – Adjusting Audio Equipment at Commons and Gymnasium
Genesee Hill Elementary School
Area 3 – South View of Commons and Gymnasium
Building Excellence IV Capital Levy
Hazel Wolf K-8 at Pinehurst
Site: General site clean up and monitoring temporary erosion control measures.
Electrical transformer installed and energized. Grading of loading dock area
access continues. Off-site preparation for placement of concrete sidewalks along
117th Avenue.
Building A: A1 - Top deck water proofing continues. Kitchen cooler installation
complete. Ceiling grid/tile install ongoing. Painting ongoing. Area A2 - Final
coats of paint ongoing at all floors. Ceiling grid complete, ceiling tiles installation
ongoing. Elevator installation work continues. Casework installation complete and
plumbing fixtures being installed. Concrete floors receiving final grinding. Area
A3 - Water proof membrane installation ongoing, exterior concrete stairs form
work ongoing. GWB taping nearing completion. Store front window installation
complete.
Building B: Exterior sheeting and air barrier complete. Exterior masonry
complete. Interior band/choir room GWB taping ongoing.
Building C: Exterior metal siding nearing completion. Windows completed. GWB
finishing in the gym and commons areas completed. Ceiling in the gym and
commons painted. Clouds receiving GWB and starting to be finished.
Hazel Wolf K-8 at Pinehurst
Site Plan
Hazel Wolf K-8 at Pinehurst
Aerial View from the East
May 16, 2016
Hazel Wolf K-8 at Pinehurst
Areas A1 and A2 – Looking Northwest
May 25, 2016
Hazel Wolf K-8 at Pinehurst
Area A2 – Final Exterior Siding Install, Looking Northwest
May 27, 2016
Hazel Wolf K-8 at Pinehurst
Area A2 – Exterior Siding, Looking Southeast
May 25, 2016
Hazel Wolf K-8 at Pinehurst
Area A2 – Final Siding Colors
May 25, 2016
Hazel Wolf K-8 at Pinehurst
Area A2 – Tile Installed
May 27, 2016
Hazel Wolf K-8 at Pinehurst
Area A2 – Lockers Installed
May 27, 2016
Hazel Wolf K-8 at Pinehurst
Area A2 – Learning Commons
May 27, 2016
Hazel Wolf K-8 at Pinehurst
Area A2 – Water Fountains Installed
May 27, 2016
Hazel Wolf K-8 at Pinehurst
Area C – Commons Finishes
May 27, 2016
Hazel Wolf K-8 at Pinehurst
Area C – Gym Sound Board Installation
May 27, 2016
Building Excellence IV Capital Levy
Meany Middle School
Site: Partial Site mobilization and protection in place at loading dock and
surrounding the 1954 Classroom Wing. Access to loading dock is
coordinated with Seattle World School administrators and staff.
1954 Classroom Wing: Interior – Demolition of casework, wall finishes,
interior window trim ongoing in Sector 4 and 5N. Wood flooring salvage
complete. Demolition of lower windows ongoing and concrete shear wall infill
at window openings in Sector 4 are scheduled to begin next week. HVAC
demolition complete in Sector 5 at the Band/Chorus rooms. Plumbing
trenching has started and will continue for one week. Electrical demolition in
Sector 4 and 5 is complete.
Remainder of Building: No work occurring until after Seattle World School
leaves site. Contractor has full access to site no later than July 12, 2016
Meany Middle School
1964 Aerial Photo
July 1, 2015 July 10, 2015
1954 Classroom Wing
Meany Middle School
Electrical Rough-In Started in Sector 4
May 26, 2016
Meany Middle School
Floor Slab Cutting and Systems Demolition Complete in Sector 4
May 26, 2016
Meany Middle School
PBS Testing Exterior Walls
May 26, 2016
Meany Middle School
Sector 4 Restroom Floor Removal and Trenching
May 26, 2016
Meany Middle School
Restroom Floor Removal and Trenching
May 26, 2016
Meany Middle School
Band Room Demolition
May 26, 2016
Building Excellence IV Capital Levy
Olympic Hills Elementary School
Site: Geothermal underground piping ongoing. TESC measures ongoing.
Building: Framing walls, installing roof joists, installing 2nd floor decking
in Zone A and B, ongoing. Poured slab-on-wood-deck in Zone A.
Started weather-resistant barrier and flashing in Zone A. MEP rough-in
ongoing in Zone A. Steel column erection and wall layout in Zone C,
ongoing.
Olympic Hills Elementary School
Site Plan
Olympic Hills Elementary School
Zone Map
Olympic Hills Elementary School
Aerial View from the West
May 1, 2016
Olympic Hills Elementary School
Zone A – Structural Wall Framing, Looking Northwest
May 25, 2016
Olympic Hills Elementary School
Zone A – HVAC Ductwork Through Joists in Classroom
May 25, 2016
Olympic Hills Elementary School
Zone A – Weather-Resistant Barrier and Flashing, Looking West
May 25, 2016
Olympic Hills Elementary School
Zone A – Parapet Walls Insulated and Protected, Looking East
May 25, 2016
Olympic Hills Elementary School
Zone B – Wood Decking 2nd Floor, Looking South
May 25, 2016
Olympic Hills Elementary School
Zone C – Steel Column Erection and Wall Layout, Looking North
May 25, 2016
Building Excellence IV Capital Levy
Seattle World School at T.T. Minor
Area A – Administration Office, Student Services, Health Clinic and Library: Gypsum wallboard finishing nearing completion. Finish painting ongoing. Ceiling grid installation ongoing. Casework installation ongoing. ADA stage ramp in progress. Overhead MEP rough-in work complete. Light fixture installation ongoing. Low voltage data installation ongoing.
Area B – Multipurpose, Kitchen, Boiler Room: Air Handling Units set in place complete. Kitchen flooring ongoing, walk in cooler and freezer in place. Gypsum wallboard finishing nearing completion. Finish painting ongoing. Ceiling grid installation ongoing. Casework installation ongoing. Overhead MEP rough-in work on-going. Light fixture installation ongoing. Low voltage data installation ongoing.
Area C – Classrooms: Gypsum wallboard finishing complete. Finish painting ongoing. Ceiling grid installation ongoing. Casework installation ongoing. Overhead MEP rough-in work complete. Light fixture installation ongoing. Low voltage data installation ongoing.
Seattle World School at T.T. Minor
Site Plan
Area C
Area B
Area A
Area C
Area B
Area A
Seattle World School at T.T. Minor
Site – Asphalt Installation at New Curb Cut On Pike Street
May 31, 2016
Seattle World School at T.T. Minor
Site – New Entrance Off Of Pike Street For Deliveries and Dumpster Enclosure
May 31, 2016
Seattle World School at T.T. Minor
Site – Sidewalk Ramps Completed on 18th Street and Pike
May 31, 2016
Seattle World School at T.T. Minor
Area A – Entry Vestibule Steel Erection
May 31, 2016
Seattle World School at T.T. Minor
Area A – Entry Vestibule Steel Erection
May 31, 2016
Seattle World School at T.T. Minor
Area B – Exterior Siding Installation Ongoing
May 31, 2016
Seattle World School at T.T. Minor
Area B – Kitchen Flooring Installation Ongoing
May 31, 2016
Seattle World School at T.T. Minor
Area C – New Locker Installation Ongoing
May 31, 2016
Seattle World School at T.T. Minor
Area C – Cabinetry and Casework Installation ongoing
May 31, 2016
Building Excellence IV Capital Levy
New Thornton Creek Building Site: Ongoing installation of backstop fencing in the playfield. Seattle city
Light installed transformer and connected new primary electrical service to Main Electrical Room. Ongoing grading of athletic field.
Off-site Improvements: Completed pouring of concrete curbs and ADA ramps at intersection of NE 80th St. and 40th Ave NE. Ongoing grading and site prep for sidewalks and street trees on NE 80th St.
Building A: Ongoing roofing over Gym and Childcare. Completed installation of interior framing, hollow metal frame doors and relites. Ongoing hanging of ductwork and installing louvers. Ongoing plumbing, fire suppression and electrical rough-in. Ongoing gypsum wall board (GWB) install in Commons, Main Stage and Music Rooms. Preparation for application of resilient flooring.
Building B: Ongoing Hardie panel installation. Ongoing painting on first and second floors classrooms. Ongoing painting in Library, adjacent Computer Lab, Art and Special Education Resource Rooms. Ongoing HVAC rough-in in mechanical penthouse.
Building C: Ongoing trim of electrical devices. Ongoing ceramic tile installation in bathrooms. Ongoing installing casework in classrooms. Began installing resilient flooring in classrooms.
New Thornton Creek Building
Key Plan
Building C
Building B
Building A
D
New Thornton Creek Building
Aerial View from the North
May 15, 2016
New Thornton Creek Building
Building A – Preparing for Concrete Pavement at Main Entry
New Thornton Creek Building
Building A – Storefront Installation at South Commons
New Thornton Creek Building
Building A – Framing Soffit in Commons
New Thornton Creek Building
Building A – Gypsum Wallboard Installation
New Thornton Creek Building
Building A – Kitchen Fiber-Reinforced Plastic (FRP) Wall Panel Installation
New Thornton Creek Building
Building A – Installing Cap Sheet on Commons Roof
New Thornton Creek Building
Building A – Childcare GWB Installation
New Thornton Creek Building
Building A – Operable Partition Track Installation
New Thornton Creek Building
Building A – Music Room/Stage Acoustical Wall Installation
New Thornton Creek Building
Building B – Locker Installation
New Thornton Creek Building
Building B – Second Floor, Preparing Hallway for Resilient Flooring
New Thornton Creek Building
Building B – West Stairwell Painting and Acoustical Ceiling Grid Installation
New Thornton Creek Building
Building B – First Floor Polishing Concrete