SITE AUDIT REPORT Doc. No. TOS-FAB-157-15-RPT-01 Rev. 0 Date 11 JUNE 2015 Page 4 of 8 1.1 SITE PHOTO FINDING: The initial proposal was to replace new Electrostatic coalesce Transformer Tank at Module 5. However from the Survey, TOS found out that there was space constraint due to existing Fire water Piping. RESULT: 1. Insulate existing Fire water piping. 2. Not Obstruct the existing Walkway. 3. Ample space to do rigging work. RECOMMENDATION: To erect heavy duty scaffolding for rigging work

Upload: wan-syahmi

Post on 13-Feb-2016

6 views

Category:

Documents


0 download

DESCRIPTION

files

TRANSCRIPT

Page 1: BUK - Site Audit Report 0

SITE AUDIT REPORT

Doc. No. TOS-FAB-157-15-RPT-01

Rev. 0

Date 11 JUNE 2015

Page 4 of 8

1.1 SITE PHOTO

FINDING:

The initial proposal was to replace new Electrostatic

coalesce Transformer Tank at Module 5. However

from the Survey, TOS found out that there was space

constraint due to existing Fire water Piping.

RESULT:

1. Insulate existing Fire water piping.

2. Not Obstruct the existing Walkway.

3. Ample space to do rigging work.

RECOMMENDATION:

To erect heavy duty scaffolding for rigging work

Page 2: BUK - Site Audit Report 0

SITE AUDIT REPORT

Doc. No. TOS-FAB-157-15-RPT-01

Rev. 0

Date 11 JUNE 2015

Page 5 of 8

1.2 SITE PHOTO

FINDING:

This is internal view for transformer tank.

TOS found out that transformer oil still in the

tank. No measurement for internal stud.

RESULT:

1. E&I parts will be remove on lay down area.

2. Transformer oil will be stored in barrel at safe

location area

3. Hot work required after dismantle E&I part, to

weld internal stud for support transformer & etc.

RECOMMENDATION:

To drain oil before dismantle E&I parts.

Page 3: BUK - Site Audit Report 0

SITE AUDIT REPORT

Doc. No. TOS-FAB-157-15-RPT-01

Rev. 0

Date 11 JUNE 2015

Page 6 of 8

1.3 SITE PHOTO

FINDING:

There was space available to locate new Transformer

tank at this location before install.

TOS need to proposed and discuss with FVSB

whether we can locate / use available space for

Habitat.

RESULT:

1. Ample space for Installation Work

2. Open Area (No Shelter). FVSB to advise whether

still require Shelter.

3. No access FPSO crane. FVSB to confirm that the

crane barge to be utilized for lifting of new

Transformer Tank

RECOMMENDATION:

To install habitat.