bus reqt template oct 2010
TRANSCRIPT
-
7/31/2019 Bus Reqt Template Oct 2010
1/17
Business Requirements Document
Business Analyst: Jonathan DonaisJan 19/2011
-
7/31/2019 Bus Reqt Template Oct 2010
2/17
Table of Contents0 Revision History ................................................................................................................... 3
1 Preface ................................................................................................................................ 42 Stakeholders ........................................................................................................................ 5
Project Sponsor................................................................................................................5
Business Team Lead..........................................................................................................5
Project Manager(s)/ Business Analyst.................................................................................5Business Team Member(s).................................................................................................6Marketing Prime/Training Consultant..................................................................................6
IT Team Member..............................................................................................................72.1 Purpose ......................................................................................................................... 7
2.2 History .......................................................................................................................... 72.3 Project Goals .................................................................................................................. 7
2.4 Project Issues ................................................................................................................ 82.5 Assumptions/Notes ......................................................................................................... 8
2.6 Constraints .................................................................................................................... 82.7 Risks ............................................................................................................................. 9
3 Detailed Business Requirements ........................................................................................... 103.1 In Scope ...................................................................................................................... 10
3.2 Out of Scope ................................................................................................................ 103.3 Functional Requirements ............................................................................................... 11
3.4 Non-Functional Requirements ........................................................................................ 12Appendix A. Requirements Waiting Room.................................................................................15
3.5 Quality Gateway Process ............................................................................................... 151) After completion of all requirements, the list of requirement must go through an approval
process. There will be two individuals, Jonathan Donais (BA) and Catherine Jones (Tester) ...... 152) Jonathan and Catherine will go through each requirement and review the fir criterion to
ensure the requirement is measurable. We will also check for completeness, relevance and
traceability........................................................................................................................ 153) After those checks, Jonathan and Catherine will accept or reject the requirements.............. 15
4) After the Gateway process, Jonathan will setup a meeting with the stakeholder to discuss the
requirements, and the questions they came up with doing the checks..................................... 153.6 Business Requirement Approvals .................................................................................. 16
105307942.doc/Version 0.1.1 February 24, 2011 Page 2Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
3/17
0 Revision History
Date Revision Description Author & contributors
01/20/1
1
1 Final Copy Jonathan Donais
105307942.doc/Version 0.1.1 February 24, 2011 Page 3Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
4/17
1 Preface
This document outlines the business requirements, risks and goals to minimize thecustomer wait time in the retail locations.
105307942.doc/Version 0.1.1 February 24, 2011 Page 4Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
5/17
2 Stakeholders
Project Sponsor
Greg Sangster VP, Communications
Owns the project and the responsibility for the success of the project.
Drives the project by setting strategic guidelines, creating and communicating the visionand empowering others to act on the vision.
Sets expectations at the executive level.
Facilitates buy-in by regular and effective communications with stakeholders.
Establishes business objectives.
Provides the necessary guidance and decisions to the project team when obstacles areencountered or the project progress is impeded.
Negotiates agreement on project expectations.
Commits the required resources to the project
Business Team Lead
Michelle Sparrow Director, Business Planning
Leads role in the collection of requirements, design and implementation of processes.
Define, monitor and audit the quality of processes.
Communicates, cooperates and coordinates with the managers of departments impacted
by process changes.
Gains business approval for new or modified business processes.
Identifies and arranges training of business users.
Assists project manager with the assignment of tasks to the project team, thecoordination of this work and the monitoring of the quality of this work.
Review and approves all deviations as required.
Conducts workshops and presentations to validate process with the client community.
Provides post-go-live support.
Participates in the project lessons learned session
Project Manager(s)/ Business Analyst
Jasmine Singh IT project manager
Jonathan Donais IT Business Analyst
Vanessa Dairy IT Business Analyst
Responsible for delivering agreed upon scope on time and budget (where applicable).
Defines project scope and objectives with the business team lead and the project sponsor.
Formulates project deliverables and critical target dates to be reflected in the project plan.
Develops a detailed project plan with the project team. Follows the IT project methodology to manage the project.
Manages all system configuration and development activities, including required
documentation.
Responsible for the day-to-day management of the project.
Develops user, functional and technical specifications in coordination with the business.
Monitors and reports on the progress of the project against the implementation plan.
Assists project team with the establishment and tracking of measurable success criteria.
105307942.doc/Version 0.1.1 February 24, 2011 Page 5Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
6/17
Resolves business/technical conflicts through consultation, issue control, change request
and if necessary, escalation to appropriate decision-makers.
Aids in the resolution of issues when necessary.
Assigns tasks to and coordinates work of the project team.
Identifies and arranges training of business users.
Creates minutes, status reports and issue log.
Creates Procedures in support of the business processes and application usage Support project and process documentation
Coordinates and hosts meetings.
Creates and follows up on all IT service requests.
Ensures all technical requirements are met.
Business Team Member(s)
Mike Snail Super User Employee 1
Mark Davidson Super User Employee 2
Executes all project tasks in a timely fashion as per the project schedule, and notifiesproject manager of conflicts immediately.
Resolves project issues and change requests in a timely manner. Attends and prepares for all project meetings and work sessions.
Ensures all technical deliverables are coordinated to ensure on time completion.
Identifies functional risk areas.
Receive training from Business Analyst
Train end users
Adheres to established change request processes, relevant Procedures.
Participates in the project lessons learned session.
Marketing Prime/Training Consultant
Steve Tyler Marketing
Mark Braysen (Training Consultant)
Review and approval of requirements, design, UAT testing and implementation of
processes and change requests
Develops and manages scope, assigns and schedules resources, and monitors deliverableprogress with the project manager.
Define, monitor and audit the quality of processes.
Communicates, cooperates and coordinates with the managers of departments impacted
by process changes.
Assists project manager with the assignment of tasks to the project team, thecoordination of this work and the monitoring of the quality of this work.
Provides post-go-live support.
Assist in creating training plan/Assists in training (Training Consultant)
Participates in the project lessons learned session.
105307942.doc/Version 0.1.1 February 24, 2011 Page 6Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
7/17
IT Team Member
Jessica Query Web Specialist
Help Desk IT Help Desk
Install Fax and Printers
Provides technical assistance to the business team.
Attends and prepares for all project meetings and work sessions.
Participates in the project lessons learned session.
System, database, network, operating system administration.
Provides post-go-live support.
Assures system security and access control
Diagnoses development, interface, report, and enhancement problems.
Creates/maintains technical development standards.
2.1 Purpose
SuperCom Inc. provides telecommunication products and services to customers inManitoba through 47 authorized retail locations. Our company has growntremendously in the past five years causing customer wait times to increase due tothe complexity of the order process, inadequate customer literature, insufficientnumber of fax machines to service customers and inadequate employee training.An improved customer order process is required by the third quarter of 2007 due tothe increased risk of lost customers to competition. Our project will focus onimproving the customer order process. The other problems identified in the analysisstage will be addressed by other project teams.
2.2 History
SuperCom Inc. provides telecommunication products and services to customers inManitoba through 47 authorized retail locations. Customer wait times haveincreased in the retail locations due to the complexity of the order process,inadequate customer literature, insufficient number of fax machines to servicecustomers and inadequate employee training.
2.3 Project Goals
To minimize the customer wait time in the retail locations by 5% through simplifying
the customer order process by the third quarter of 2007.
105307942.doc/Version 0.1.1 February 24, 2011 Page 7Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
8/17
2.4 Project Issues
Find a way to bring back the customers we lost.
Our training facility is current being rebuilt and will be completed Q42007, wewill need to find another location or setup a temporary solution for employeetraining
2.5 Assumptions/Notes
The following is an ongoing list of assumptions for this project. As assumptions arecleared up, they shall be crossed out (crossed out), and clarification will be providedin a sub-point.
All resources required to complete this project are available.
New hardware will be functional
Adequate budget allocations are made
Dedicated staff will remain in their current roles. Dedicated staff will cross train one another.
2.6 Constraints
The following is an ongoing list of constraints for this project. As constraints areresolved, they shall be crossed out (crossed out), and resolution will be provided ina sub-point.
Project will be completed within a Budget of $12,000
Project must be completed by Q3 2007
105307942.doc/Version 0.1.1 February 24, 2011 Page 8Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
9/17
2.7 Risks
The following is an ongoing list of risks for this project. As risks are resolved or
mitigated, they shall be crossed out (crossed out), and resolution will be provided ina sub-point.
Risk Mitigation
RiskCurrent project may potentially impact other
approved projectsSeverity: High
Likeliness: Medium
If such a conflict is identified, project
managers for this and other projects willprepare impact assessments. Then All
Project sponsors will prioritize andapprove changes if needed.
RiskDepending on the amount of priority projects
and other issues it may affect resourceavailability
Severity: High
Likeliness: Medium
If resource conflicts are identified during
the project lifecycle, the projectmanager will prepare an impact
assessment, and Project sponsors willprioritize and approve proposed changes
to the plan.Also project schedule duration will be
extended to factor in the time thatresources are not available
RiskDue to the old hardware we currently have,
we cannot procure the same type of faxmachines. New hardware may not work with
our current process, and may have to changeout all the hardware to match.
Severity: Medium
Likeliness: Low
Additional testing may be required. If
all old hardware needs to be replace, atthat time we will determine which
changes to make and their impact inschedule and budget.
RiskThere is a possibility that requests for changes
to the requirements will arise throughout thedesign and implementation stages. Typical
reasons for these change requests includeproviding missing functionality and improved
usability, as well as additional requirements,identified within the scope of other projects
Severity: High
Likeliness: High
As requirements evolve over the
lifecycle, project change requests will becreated. At that time we will determine
which changes to make, and theirimpact on schedule and budget.
105307942.doc/Version 0.1.1 February 24, 2011 Page 9Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
10/17
3 Detailed Business Requirements
3.1 In Scope
At the time this document was last updated, the following is considered in scope:
Wait time in the queues is unacceptable.
Response time to customer when orders are complete is unacceptable.
Insufficient product and service information is available for customers at theretail locations.
Employees in the retail location lack product, service and customer servicetraining.
Employees are not effectively resolving customer issues in a timely manner.
Brochures and tear sheets are not written in plain language. Quantity of fax machines is insufficient to handle customer demand
Customer wait time in the retail locations is unacceptable.
Customers are being lost to competitors due to customer congestion in the storelocations.
Order processing is complex and time consuming.
Customer satisfaction results are below target.
3.2 Out of Scope
At the time this document was last updated, the following is considered out ofscope:
Insufficient floor space is dedicated to handling customers.
Staffing levels in the retail locations are insufficient to handle customerdemand during peak times.
105307942.doc/Version 0.1.1 February 24, 2011 Page 10Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
11/17
3.3 Functional Requirements
The following are high level, functional business requirements that have beenidentified by the project team. All requirements here are considered to be in scope.All other requirements are listed in the Waiting Room Appendix B.
Requirement #: 1
Description: Must simplify the ordering process
Rationale: To prevent frustrated customers, which will lead tocustomers becoming impatient and may go to the competition
due to frustrations. Simple Orders = More Sales
Originator: Mike Snail
Fit Criterion: The order completion process shall be completed
in 2 minutes
Priority 1 Conflicts: none
Dependencies: none Dependants: noneSupporting Materials: none
History: Feb 16/2007
Requirement #: 2
Description: Must decrease response time for notifications tocustomers when orders are complete
Rationale: Part of the customer satisfaction initiative, goodresponse time makes the customer think you care
Originator: Michelle Sparrow
Fit Criterion: Customers shall be notified within 10 mins oforder completion
Priority 3 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: none
History: Feb 16/2007
105307942.doc/Version 0.1.1 February 24, 2011 Page 11Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
12/17
3.4 Non-Functional Requirements
Requirement #: 3
Description: Must Increase Customer Satisfaction
Rationale: Increased customer satisfaction = more sales
Originator: Greg Sangster
Fit Criterion:8 of 10 customers must deem satisfaction of(Excellent 9+ on a 10 point survey scale)
Priority: 1 Conflicts: none
Dependencies: none Dependants: Req 1, 5, 6, 7,8
Supporting Materials: Survey 2006
History: Feb 18, 2007
Requirement #: 4
Description: Must find a solution to bring back old customers
Rationale: To increase revenue by having a healthy amount of
customers
Originator: Greg Sangster
Fit Criterion: Of all lost customers, the Customer satisfactiondept shall bring back 50% of lost customers
Priority3 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: none
History: Feb 17,2007
Requirement #: 5
Description: Must order more fax machines
Rationale:Due to company growth, we are waiting on fax
machines to process the completed orders
Originator: Mike Snail
Fit Criterion: No employee shall wait more than 5 secs for an
availiable fax machine
Priority 4 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: none
History: Feb 17/2007
105307942.doc/Version 0.1.1 February 24, 2011 Page 12Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
13/17
Requirement #: 6
Description: Must provide more product and service manuals atretail locations
Rationale:Manual bins are always empty at retail locations.
Without manuals, customers are not aware of our services.
Originator: Mark DavidsonFit Criterion: Manual bins should always have a minimum of10 manuals per bin
Priority 5 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: none
History: Feb 18,2007
Requirement #: 7
Description: Must revise all brochures and tear sheets in plain
languageRationale: Users are having a hard time understanding thebrochures/sheets, so the customers dont bother reading our
services we have to offer, therefore no sales
Originator: Mark Davidson
Fit Criterion:95% of customers must understand the
brochures without asking questions to the sales staff
Priority3 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: none
History: Feb 20,2007
Requirement #: 8
Description: Must increase knowledge of all business processesto employees
Rationale: To allow employees to wear multiple hats (able toperform any job) and to increase the professionalism of the
company (Customers have a sense that the sales staff areknowledgeable)
Originator: Mark Braysen
Fit Criterion:100% of all employee shall be fully trained in allbusiness processes
Priority 2 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: Training documents/Training Plan
History: Feb 20, 2007
105307942.doc/Version 0.1.1 February 24, 2011 Page 13Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
14/17
Requirement #: 9
Description: Must resolve customer issues in a timely manner
Rationale: Fast response time makes the customer feel that theyare important and that the company cares. Prevents frustrated
customersOriginator: Greg Sangster
Fit Criterion: All issues shall be resolved within 2 businessdays
Priority 2 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: none
History: Feb 21, 2007
Requirement #: 10
Description: Must decrease customer wait timesRationale:No customers like waiting, short wait times will
prevent from a possible customer loss to the competition
Originator: Mike Snail
Fit Criterion: No customer shall wait for no longer that 3 mins
Priority3 Conflicts: none
Dependencies: none Dependants: none
Supporting Materials: none
History: Feb 21, 2007
105307942.doc/Version 0.1.1 February 24, 2011 Page 14Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
15/17
Appendix A. Requirements Waiting Room
(Items are in order of importance)
1) Must increase floor space to handle the growing number of customers.2) Must hire more skilled staff to handle customer demand during peak times.3) Automate the notification process when orders are complete.4) Create an advertising plan to advertise on Radio, TV and Flyers.
3.5 Quality Gateway Process
1) After completion of all requirements, the list of requirement must gothrough an approval process. There will be two individuals, Jonathan Donais(BA) and Catherine Jones (Tester)
2) Jonathan and Catherine will go through each requirement and review the fircriterion to ensure the requirement is measurable. We will also check forcompleteness, relevance and traceability.
3) After those checks, Jonathan and Catherine will accept or reject therequirements.
4) After the Gateway process, Jonathan will setup a meeting with thestakeholder to discuss the requirements, and the questions they came up withdoing the checks.
105307942.doc/Version 0.1.1 February 24, 2011 Page 15Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
16/17
3.6 Business Requirement Approvals
Sign-off on this document must come from all Business Stakeholders identifiedbelow. Sign-off shall indicate absolute agreement that the requirementsdocumented herein accurately and completely represent the needs of each
stakeholder and their respective department within SuperCom Inc. The approval isthe joint responsibility of the listed functional areas of SuperCom Inc.
Document Approved by:
Name/Title Signature Date
Jasmine SinghProject Manager
Name/Title Signature Date
Greg Sangster
Project Sponsor
Name/Title Signature Date
Michelle SparrowDirector, Business Planning
Name/Title Signature Date
Jonathan DonaisBusiness Analyst
Name/Title Signature DateVanessa Dairy
Business Analyst
Name/Title Signature Date
Steve TylerMarketing
Name/Title Signature Date
Mike SnailSuper User 1
Name/Title Signature Date
Mark DavidsonSuper User 2
105307942.doc/Version 0.1.1 February 24, 2011 Page 16Proprietary and Confidential
-
7/31/2019 Bus Reqt Template Oct 2010
17/17
Name/Title Signature Date
Jessica QueryWeb Specialist
105307942.doc/Version 0.1.1 February 24, 2011 Page 17Proprietary and Confidential