b&w company presentation 2016 · construction seta. b&w has implemented training programmes...

55
Leading Electrical and Instrumentation Construction Company COMPANY PRESENTATION Leading Electrical and Instrumentation Construction Company

Upload: others

Post on 29-Jul-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

COMPANYPRESENTATION

Leading Electrical and Instrumentation Construction Company

Page 2: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Agenda

1. Company Overview

2. Typical Installations

3. Contract Profiles

4. Typical Projects

5. Experience Schedule

Leading Electrical and Instrumentation Construction Company

Page 3: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company

COMPANY OVERVIEW

Page 4: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

OverviewB&W have been established in the electrical and instrumentation (E&I) construction industryfor 42 years. B&W are one of the largest specialist E&I contractors in South Africa.

B&W has worked and gained valuable experience in mining, oil & gas, chemical, utilities,renewable energy, power generation, industrial process plants and infrastructure. Thestandard of electrical and instrumentation construction varies from industry to industry andB&W have developed highly qualified teams to cater for the needs of our clients.

B&W hosts numerous complementary services ranging from field engineering, equipmentprocurement, material supply, testing and commissioning and maintenance services.

B&W acquired Pontins in 2009, one of the largest specialist suppliers of earthing andlightning protection services and have been in business for 43 years.

B&W’s commitment to providing a professional service, economically, timeously and withconsistency is the key to our enviable growth record.

B&W are a wholly owned subsidiary of the ELB Group.

Page 5: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Company StructureB&W Group

Mozambique

Swaziland

Kenya

Registered Offices

Namibia

South Africa

Company Services

Health, safety and environment

Marketing and proposals

Financial Procurement

Quality assurance Planning

HR skills development and training

Company Operations

E&I installations process plants

Regions

Maintenance and shutdowns Special services

Pontins

Earthing and Lightning Protection Specialists

Conductor Systems

Electrification Systems for Mobile Equipment

B&W Instrumentation and Electrical SA (Pty) Ltd

41.94%Equity

Level 4 B-BBEE Status

Tanzania

Page 6: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Group Structure

ELB Engineering Solutions (Pty) Ltd

ELB Equipment Holdings (Pty) Ltd

B&W Instrumentation and Electrical (Pty) Ltd

ELB Group Ltd

ELB Educational Trust

ELB International (Pty) Ltd

ELB Intelligent Solutions (Pty) Ltd

ELB Engineering (Pty) Ltd

B&W Instrumentation and Electrical Tanzania Ltd B-Quip (Pty) LtdPontins (Pty) Ltd

BWIE Properties (Pty) Ltd

H&S Training Academy (Pty) Ltd

B&W Instrumentation and Electrical SA (Pty) Ltd

B&W Instrumentation and Electrical Kenya Ltd

BWIE Instrumentation and Electrical Swaziland

B&W ElectricidadeLda (Mozambique)

B&W Instrumentation and Electrical Namibia (Pty) Ltd

Conductor Systems

Page 7: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Manpower ResourcesAdministration & Accounting 29

Construction Management 15

Quality Control 7

Planners 4

Junior Planners 3

HSE Personnel 15

Engineers & Technicians 22

Site Managers & Supervisors 38

Professional Project Managers 10

Foremen 21

Artisans 95

Learners 30

Semi-Skilled 250 – 400

Field Labour 600 - 1800

Page 8: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Target Industries

Mining

Renewable Energy

Power Generation

Transmission & Distribution

Industrial & Utilities

Chemical, Oil & Gas

Page 9: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project Footprint

Page 10: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

End User / Clients

Page 11: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Health and Safety

5 Star NOSA graded NOSCAR Award for 5 consecutive years

“Best performance E&I contractor in SA”

Page 12: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

HSE Statistics

Criteria 2012 2013 2014 2015 Total

Man-hours 1,537,436.00 1,832,534.00 1,812,100.00 2,088,867.00 7,270,937.00

Fatalities 0 0 0 0 0

MTC’s and First Aid Cases Combined 14 18 10 6 48

LTI’s 1 0 0 0 1

LTIFR per 200,000 hours Year to Date 0.13 0.00 0.00 0.000.01

LTIFR per 200,000 hours 12 Month Period 0.13 0.00 0.00 0.00

12 Months to Date – 2014 / 2015

Lost Time Injury Rate (“LTIFR”) – 0.00 per 200,000 hours worked

Recordable Case Rate (“RCR”) – 0.33 per 200,000 hours worked

Page 13: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Quality Statement

It is a prime management objective of B&W Instrumentation andElectrical to supply products and services with a high level of qualityand reliability for the realisation of our clients requirements.

It is the objective to effectively complete contracts with the followingcriteria as our primary requirements:

• To minimise all Quality complaints• To maximise client confidence in our competence• The improvement of the profit objectives of the company by

adherence to the above

Page 14: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

ISO 9001:2008

B&W operates in accordance with proceduresestablished to comply with the strenuous ISO9001:2008 quality requirements.

B&W are currently one of the only ISO9001:2008 accredited electrical andinstrumentation contractors in Sub-SaharanAfrica.

This accreditation not only provides newclients with the comfort that our existingclients have come to expect from us, butaffords us the opportunity of outside auditsby the SABS to ensure that the standards setare not only maintained, but continuallyimproved where possible.

Page 15: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

BBBEE Status

B&W aims to bring about true broadbased empowerment. An Employee Trustestablished in September 2006 owns a7% stake in the company benefitingemployees with more than four yearsuninterrupted service, with an emphasison black staff (75% of benefits).

B&W is a comfortable ‘Level 4’contributor in terms of the draftDepartment of Trade & Industry’s BBBEECodes of Good Practice. Accordingly100% of client spend can be counted asspend with a BEE company.

Page 16: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

CIDB Certification

B&W has an 8EP and 8EB grading. This would include major public sector projects such as those for Eskom.

Due to new regulations by the CIDB, certificates are no longer issued.

B&W CIDB number: 149138

Page 17: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Corporate Social Responsibility

In B&W Southern Africa Corporate Social Responsibility is an important business priority and integral to our overall business strategy.

Corporate Social Responsibility (CSR) projects are selected on social need and the extent to which they are aligned with our business and can add value to our clients and our communities.

Our policy is to identify worthy Social Economic Development (SED) projects in the areas in which we work. Our projects have proved highly successful, making a meaningful difference.

CSR to us is about building relationships with our customers, attracting and retaining talented staff, managing risk and building reputation.

Page 18: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Training

In response to the skills shortage in SouthAfrica B&W has invested substantially in thetraining of field labour to increase its skillspool. B&W has its own fully equipped in-housetraining centre based in Alberton and is anaccredited service provider throughConstruction SETA.

B&W has implemented training programmesin line with accredited SAQA unit standards toadvance employee skills and ensure traineesreceive an accredited qualification. Todetermine the appropriate skills developmentrequired B&W provides ongoing on-the-jobassessments. In addition long-term incentivesensure retention of core staff.

Page 19: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Typical Training CoursesApproved Unit Standards

• 229998 Explain and perform fall arrest techniques when working at heights

• 9964 Apply health and safety to a work area

• 12484 Perform basic fire fighting

• 120344 Demonstrate knowledge and understanding of relevant current occupational health and safety legislation

• 12878 Use and maintain power hand tools on a construction site

• 116999 Apply accurate information about HIV & AIDS to everyday life

Unit Standards Awaiting Approval

• Hazard identification and risk assessment

• First aid (Level 1–3)

• Fire fighting

• Occupational health and safety rep

Page 20: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company

TYPICAL INSTALLATIONS

Page 21: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Electrical

Page 22: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Electrical

Page 23: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Instrumentation

Page 24: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company

CONTRACT PROFILES

Page 25: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Contract ProfileTemane Pande Development Project

Client: Sasol 

Project Manager: Foster Wheeler

Engineer: Foster Wheeler

Location: Temane, Mozambique

Value: R49,6 million

Start Date: January 2003

Completion Date: March 2004

Site Man‐hours Used: 256,000

Peak Manpower: 380

Number of Drives: 324

I/O Count: 2800

Field Instruments: 1120

Quantity of Cable: 314,000m

Quantity of Cable Rack: 11,600m

Page 26: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Contract ProfileWaste Water Recycle Facility Project

Client: Sasol / Foster Wheeler

Project Manager: B. Scorpion

Engineer: J. de Lange / J. van Heerden

Location: Secunda

Value: R35,0 million

Start Date: June 2004

Completion Date: November 2005

Site Man‐hours Used: 196,000

Peak Manpower: 200

Number of Drives: 158

I/O Count: 1630

Field Instruments: 879

Quantity of Cable: 182,000m

Quantity of Cable Rack: 7,282m

Page 27: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Contract ProfileVeolia Water Treatment Plant Project

Client: Sasol Veolia

Project Manager: John Henry Pelser

Engineer: C. Marcotta

Location: Secunda

Value: R38,2 million

Start Date: March 2005

Completion Date: April 2006

Site Man‐hours Used: 218,000

Peak Manpower: 288

Number of Drives: 330

I/O Count: 2960

Field Instruments: 1230

Quantity of Cable: 233,000m

Quantity of Cable Rack: 9,214m

Page 28: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Contract ProfilePprust 600KTPM Concentrator Project

Client: Anglo Platinum

Project Manager: C. Coetzee

Engineer: Vhumbanani

Location: Potgietersrust

Value: R179,0 million

Start Date: March 2007

Completion Date: April 2009

Site Man‐hours Used: 802,000 (Accident free)

Peak Manpower: 928

Number of Drives: 483

Field Instruments: 3700

Quantity of Cable: 450,000m

Quantity of Cable Rack: 27,000m

Page 29: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Contract ProfileShondoni Mining Project

Client: Sasol Mining

Project Manager: Peter Wooldridge

Engineer: Bradley Duncan

Location: Secunda

Value: R86,0 million

Start Date: May 2013

Completion Date: June 2015

Site Man‐hours Used: 230,000

Peak Manpower: 94

Number of Substations: 8

Number of Mini Substations: 10

Number of 11kV Panels: 72

Number of 132kV Circuit Breakers: 4

Number of 20MVA 22kV / 11kV TRF: 2

Number of Street Lights: 54

Quantity of Cable: 32,000m

Page 30: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company

TYPICAL PROJECTS

Page 31: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project ReferenceAmbatovy Project Overview

Project Name: Ambatovy (Process Plant)

Location: Tamatave, Madagascar

Project duration: 26 months (July 2009 – September 2011)

B&W contract value: US$ 60 million

• After the successful completion of the Early Works contract on the same project, B&W was appointed as the main Electrical & 

Instrumentation installation contractor on one of the largest projects in the world at the time.

• The plant is designed to produce 50t of nickel, 5t of cobalt and 130t of ammonium phosphate. Although the plant is constructed in 

Tamatave, near the harbour, the mine is situated near the town of Muramanga, some 450km away.

• The scope of work included the entire electrical and instrumentation installation, including calibration and cold commissioning, on the 

plant site, with the exception of the Refinery, Power Generation Plant, Acid Plant and Lime handling sections, which were separate 

packages. The enormous scope of work, and limited time for completion, make the project one of, if not the biggest E&I project 

undertaken by a South African contractor.

• The scope for included everything from the 11kV and 6.6kV distribution, plant wide, to the lighting and small power, calibration of 

instruments, LV and instrumentation installations and cold commissioning, while the Early Works contract included the design, supply 

and installation of 11kV overhead lines, distribution and street lighting on the plant site and 6.6kV overhead lines, distribution and 

street lighting at the mine site.

Page 32: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project Reference

• 900,000m of electrical cabling

• 490,000m of instrument cabling

• 49,000m of straight cable racking plus 4,950 fittings

• 25,000m of stainless steel instrument tubing

• 395t of sundry steelwork & angle droppers

• 30,000m of single unistrut supports

• 1,100 drives

• 3,455 instruments

• 1,950 luminaries 

• 4,880,785 man‐hours – all without lost time injury (5,232,096 including the Early Works)

• A peak of 1,656 personnel on site

• The final value of the contract was roughly R430 million and being that the bulk of the materials, including the equipment, cable, 

racking, luminaries, instruments and even the cable glands were free‐issue by the client; this understates the magnitude of the work 

completed.

• On site, B&W had a peak of 628 expatriates (mainly South African) and employed a peak of 1,028 local Malagasy workers. Due to local 

content requirements, B&W established the subsidiary, B&W Madagascar SaRl, in Madagascar for the execution of the contract.

Ambatovy Project Statistics

Page 33: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project ReferenceAmbatovy Project Overview & Statistics

Project Name: Ambatovy (Early Works)

Location: Tamatave, Madagascar

Project duration: 8 months (November 2008 – June 2009)

Contract value: US$ 16 million

Project statistics (Early Works, Plant and Mine Site)

• 25km 11kV overhead lines

• 22,5km 6.6kV overhead lines

• 28km fibre optic

• 388 luminaries

• 351,311 man‐hours, all without lost time injury

Page 34: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project ReferenceAmbatovy Plant Site

Page 35: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project ReferenceAmbatovy Mine Site

Page 36: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project ReferenceAmbatovy Harbour

Page 37: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Project ReferenceAmbatovy Pipeline

Page 38: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Coal ProjectSouth Africa

Contracts awarded for two Coal Projects in South Africa, combined value of R152.0 million

Page 39: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

InstrumentationMadagascar

Completed Early Works Project and commenced E&I Installation on Main Process Plant

Main Process Plant was initially delayed for ten months

Page 40: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Coal Project

66kV Overhead Line

Remote Northern Mozambique

1.2km span with Lattice Structures

Mozambique

Page 41: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Coal Project

Commenced construction on Moatize Coal Project in Northern Mozambique

Further opportunities in the region with other clients now starting with project implementation

Mozambique

Page 42: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Oil & Gas

Awarded E&I Installation Extension to Panda Gas Project

B&W awarded Phase 1 in 2002

Mozambique

Page 43: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Sands Project

22kV Supporting Infrastructure

‐ Substations & H.T cabling

‐ Back up generators

Process Cabling & Instrumentation for:‐

‐Wet Concentrator Plant

‐ Ponds, Pontoons & Dredges

‐Mineral Separation Plant

‐ Starter Ponds

‐ Product Storage

‐ Conveyors

Mozambique

Page 44: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Solar Photovoltaic

Contract for the 64MWp Solar Photovoltaic ("PV") Project at Postmasburg in the Northern Cape area of South Africa

The project is a key component of Phase 2 of the South African Department of Energy's Renewable Energy IPP Procurement Program

Assistance with commissioning of the total plant

South Africa

Page 45: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company

EXPERIENCE SCHEDULE

Page 46: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Current ProjectsOWNER EPCM

CONTRACTOR PROCESS LOCATION CURRENT VALUE

MONTH OF COMPLETION

Aquarius Aquarius E&I Installation RustenburgRSA R20 million / year On Going

Sasol Sasol E&I Installation SecundaRSA R8 million / year On Going

Sasol Sasol Coal TweedraaiElectrical Infrastructure

SecundaRSA R11,2 million Mar 2016

Sasol BET TweedraaiE&I Installation & Material Handling

SecundaRSA R17 million Mar 2016

Ilitha Mining Enviroplus Chrome Tailings RustenburgRSA R3 million Apr 2016

Sasol ELB ImpumeleloE&I Installation & Material Handling

SecundaRSA R5,8 million Apr 2016

Sasol Coal Worley Parsons Shondoni Phase I & II

Sub-stations & cablingSecunda

RSA R117 million Apr 2016

Vale ABB Moatize Coal mineE&I Installation Mozambique R202 million Apr 2016

Anglo American Venn & Milford Zebulo ColliaryUnderground Mining

OgiesRSA R7 million May 2016

Swakop Uranium Amec / Bateman Husab Uranium MineE&I Installation Namibia R212 million Aug 2016

Eskom ELB MedupiE&I Installation & Material Handling

EllisrasRSA R9 million Jan 2017

Eskom Tenova KusileE&I Installation

OgiesRSA R27 million Jan 2017

Page 47: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Oil & Gas

OWNER EPCM CONTRACTOR PROCESS LOCATION VALUE DURATION

Fina Fluor Daniel Crude Unit Revamp Angola R8 million 6 months

Mosgas / Petrosa Foster Wheeler Low Aromatic Distillation Unit Mossel BayRSA R12,7 million 6 months

Sasol Foster Wheeler Temane Pande Central Processing Facility Mozambique R48 million 17 months

Sasol Foster Wheeler Waste Recycle E&I Installation

Secunda RSA R35 million 11 months

Sasol Veolia / Proconics Veolia Water Treatment Plant Secunda RSA R38,2 million 14 months

Sasol Foster Wheeler Gas Engine Power Plant E&I Installation

SasolburgRSA R22,4 million 7 months

Sasol VGI Consulting Inc.Contractor for Alrode

Depot Wholesale Logistics ProjectE&I Installation

AlbertonRSA R60 million 13 months

Sasol Foster Wheeler Sasol Utilities Expansion ProjectE&I Installation

SasolburgRSA R29 million 8 months

Sasol Sastech New Pre-Coat Tank Unit 219E&I Installation

SecundaRSA R6,4 million 6 months

Page 48: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

ChemicalOWNER EPCM

CONTRACTOR PROCESS LOCATION VALUE DURATION

Bayer Chemicals Foster Wheeler Chrome Chemical Plant NewcastleRSA R23,4 million 9 months

Indian Ocean Fertilizers

Sulphos (EMS / SNC Lavalin)

IOF Sulphuric & Phosphoric Acid Plant

Richards Bay RSA R22 million 8 months

Lafarge ICER Electrical Upgrade(Labour only)

LichtenbergRSA R10,1 million 5 months

Amplats (ACP) Stein Muller Acid Plant RustenburgRSA R15,5 million 8 months

PPC Krupp UHDE Slagment Plant SaldanhaRSA R14 million 14 months

PPC Kentz / TWP PPC Hercules Expansion ProjectE&I Installation

PretoriaRSA R27 million 8 months

Page 49: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Industrial PlantsOWNER EPCM

CONTRACTOR PROCESS LOCATION VALUE DURATION

PFG Glass PFG PFG GlassE&I Installation

SpringsRSA R21,4 million 4 months

Transnet Hatch CoegaInfrastructure

Port ElizabethRSA R68 million 14 months

Transnet Transnet Port Link Line & Salkor Yard Electrical Services

SaldanhaRSA R11 million 6 months

Ubombo Sugar BoschUbombo Sugar Mill Factory

ExpansionE&I Installation

Swaziland R44 million 5 months

Sappi AMEC E&I Installation NelspruitRSA R58 million 14 months

Air Products Air Products G-Plant E&I Installation

VanderbijlparkRSA R14,5 Million 6 months

Nestle ELB Nestle Process PlantE&I Installation

EstcourtRSA R32 million 10 months

Page 50: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Renewable EnergyOWNER EPCM

CONTRACTOR PROCESS LOCATION VALUE DURATION

Lesedi Energy Comycento LesediPhotovoltaic Solar

KathuRSA R40 million 10 months

Page 51: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

MiningOWNER EPCM

CONTRACTOR PROCESS LOCATION VALUE DURATION

Aquarius DRA E&I Construction Concentrator Everest South Platinum

LydenburgRSA R13,4 million 3 months

Amplats WatervalSmelter Hatch ACP Stage B

E&IRustenburg

RSA R16,5 million 7 months

Xstrata J.V DRAMototolo Concentrator & Spiral

PlantE&I Installation

LydenburgRSA R23,1 million 7 months

Nkomati DRA ConcentratorE&I Installation

MachadadorpRSA R16,4 million 6 months

De Beers BatemanFinsch Mine Treatment Plant

Upgrade E&I Installation

Lime AcresRSA R46.3 million 20 months

Aflease Bateman Uranium PlantE&I Installation

KlerksdorpRSA R68 million 11 months

Amplats DRA / Vhumbanani ConcentratorE&I Installation

PotgietersrusRSA R149 million 13 months

Amplats Vhumbanani Amandelbult ConcentratorE&I Installation

NorthemRSA R48 million 6 months

ARM / Assmang DRA Iron OreE&I Plant & Infrastructure

SishenRSA R105 million 14 months

Amplats Vhumbanani Pilanesberg ConcentratorE&I Installation

RustenburgRSA R34 million 4 months

Anglo Coal / BHP Billiton DRA Phola Coal

E&I InstallationOgiesRSA R32 million 6 months

Page 52: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Mining

OWNER EPCM CONTRACTOR PROCESS LOCATION VALUE DURATION

BHP Billiton DRA DMO Washing PlantE&I Installation

MiddelburgRSA R88 million 14 months

Amplats Hatch PMR Effluent Treatment PlantE&I Installation

RustenburgRSA R26 million 7 months

BHP Billiton Bateman ET DMO Materials HandlingE&I Installation

MiddelburgRSA R156 million 16 months

Nkomati DRA Nkomati Phase IIBE&I Installation

MachadadorpRSA R26 million 6 months

Sasol RSV Installation of 11kV Power Lines SecundaRSA R13 million 7 months

Douglas Colliery Bateman Water Reticulation ProjectE&I Installation

WitbankRSA R17 million 5 months

Kumba Iron Ore Hatch Sishen South E&I Installation

PostmasburgRSA R84 million 16 months

Assmang DRA KEP ProjectE&I Installation

KathuRSA R148 million 22 months

Assmang Chrome NAC E&I Installation Machadodorp

RSA R11,5 million 7 months

Sasol RSVThubelisha Mine Project

Electrical Installation, Termination for Plant Wide & OHL

SecundaRSA R34 million 15 months

Whims BKM DRA Iron OreE&I Installation

SishenRSA R64 million 8 months

Page 53: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

MiningOWNER EPCM

CONTRACTOR PROCESS LOCATION VALUE DURATION

Kasese Bateman Kasese Cobalt ProjectE&I Installation Uganda R14,6 million 5 months

Namdeb Bateman DMS Plant – Elizabeth Bay E&I Installation Namibia R28 million 7 months

Kenmare Resources Bateman Moma Mineral SandsOHL and E&I Installation Mozambique R34 million 20 months

LetsengDiamonds Bateman E&I Installation Lesotho R16 million 6 months

African Mining Sennet / Logichem Process PlantE&I Installation Botswana R22,4 million 6 months

Albidon Zambia Limited GRC Minproc Munali Process PlantE&I Installation Zambia R16 million 4 months

Equinox Ausenco / Bateman Lumwana Copper MineE&I Installation Zambia R14,9 million 9 months

Dynatec SNC Lavalin AmbatovyOHL & Early Works Madagascar R96 million 18 months

Hulletts PGBIXinavane 380 TCH Factory

ExpansionElectrical Installation

Mozambique R33 million 6 months

Amplats VhumbananiUnki Mine Platinum

Concentrator E&I Installation

Zimbabwe R67 million 10 months

Sasol Thyssenkrupp Uhde Temane ExpansionE&I Installation Mozambique R58 million 25 months

Page 54: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

MiningOWNER EPCM

CONTRACTOR PROCESS LOCATION VALUE DURATION

Vale ABB

Moatize CoalInfrastructure OHL &

SubstationsE&CI Installation

Mozambique R233 million 30 months

Dynatec SNC Lavalin Ambatovy Process PlantE&I Installation Madagascar R414 million 30 months

Rio Tinto Rio Tinto LV & MV Reticulation Mozambique R6,8 million 7 months

Riversdale SedgemanCoal Handling & Preparation

Plant E&I Installation

Mozambique R53 million 12 months

Vale Vale 66kV OHL Repairs Mozambique R5,6 million 2 months

Assmang DRA KOP E&I Installation

KathuRSA R44 million 16 months

Base Minerals Ausenco Kwale Mineral Sands ProjectE&I Installation Kenya R94 million 9 months

Rio Tinto Rio Tinto Various E&I Installation Mozambique R12 million 24 months

Kumba ELBKolomela & Sishen Iron Ore

Mine - DMS PlantsE&I Installation

Kolomela / SishenRSA R24 million 9 months

Xtrata DRATweefontein Collieries Coal

MineE&I Installation

TweefonteinRSA R144 million 16 months

Jindal S&P B&W Plant 33kV Reticulation Mozambique R13,5 million 11 months

Page 55: B&W Company Presentation 2016 · Construction SETA. B&W has implemented training programmes in line with accredited SAQA unit standards to advance employee skills and ensure trainees

Leading Electrical and Instrumentation Construction Company

Dean NevayProject Director

Tel: +27 11 907 1663

Fax: +27 11 907 1957

E-mail: [email protected]

Contact Details

Ken NelBusiness Development Manager

Tel: +27 11 907 1663

Fax: +27 11 907 1957

E-mail: [email protected]

Leading Electrical and Instrumentation Construction Company

THANK YOU