Page 1: C-3 -Jamerson - Rockfall Mitigation

Engineering Geology Bridge Engineering & Infrastructure MANAGEMENT

Page 2: C-3 -Jamerson - Rockfall Mitigation

Rockfall Mitigation:Analysis, Design & Implementation

on NJ Highways

Page 3: C-3 -Jamerson - Rockfall Mitigation

New Jersey + Rock

Page 4: C-3 -Jamerson - Rockfall Mitigation
Page 5: C-3 -Jamerson - Rockfall Mitigation

NEW JERSEY

GEOLOGY

101

Page 6: C-3 -Jamerson - Rockfall Mitigation
Page 7: C-3 -Jamerson - Rockfall Mitigation
Page 8: C-3 -Jamerson - Rockfall Mitigation
Page 9: C-3 -Jamerson - Rockfall Mitigation
Page 10: C-3 -Jamerson - Rockfall Mitigation
Page 11: C-3 -Jamerson - Rockfall Mitigation
Page 12: C-3 -Jamerson - Rockfall Mitigation
Page 13: C-3 -Jamerson - Rockfall Mitigation
Page 14: C-3 -Jamerson - Rockfall Mitigation
Page 15: C-3 -Jamerson - Rockfall Mitigation
Page 16: C-3 -Jamerson - Rockfall Mitigation
Page 17: C-3 -Jamerson - Rockfall Mitigation
Page 18: C-3 -Jamerson - Rockfall Mitigation
Page 19: C-3 -Jamerson - Rockfall Mitigation
Page 20: C-3 -Jamerson - Rockfall Mitigation
Page 21: C-3 -Jamerson - Rockfall Mitigation
Page 22: C-3 -Jamerson - Rockfall Mitigation
Page 23: C-3 -Jamerson - Rockfall Mitigation
Page 24: C-3 -Jamerson - Rockfall Mitigation
Page 25: C-3 -Jamerson - Rockfall Mitigation
Page 26: C-3 -Jamerson - Rockfall Mitigation
Page 27: C-3 -Jamerson - Rockfall Mitigation
Page 28: C-3 -Jamerson - Rockfall Mitigation
Page 29: C-3 -Jamerson - Rockfall Mitigation
Page 30: C-3 -Jamerson - Rockfall Mitigation

May 21, 2010 May 22, 2010

Page 31: C-3 -Jamerson - Rockfall Mitigation

Contributing Factors to Highway Rockfall

Hazards• Geology & Geometry

• rock type & characteristics• rock cut slope geometry• discontinuities

(joints,fractures)• roadway geometry

• Groundwater• hydrostatic pressure• icejacking

• Erosional• climatic• chemical• root jacking

• Construction techniques

Page 32: C-3 -Jamerson - Rockfall Mitigation
Page 33: C-3 -Jamerson - Rockfall Mitigation
Page 34: C-3 -Jamerson - Rockfall Mitigation
Page 35: C-3 -Jamerson - Rockfall Mitigation

Rockfall Hazard Management System

Page 36: C-3 -Jamerson - Rockfall Mitigation

• 440+ State & Interstate highway rock cut slopes

• Identify & monitor rockfall hazards to traveling public

• Rockfall mitigation project prioritization & development

Rockfall Hazard

Management System (RHMS)

Page 37: C-3 -Jamerson - Rockfall Mitigation

Rockfall Hazard Rating System (RHRS)

• Developed late 1980’s by FHWA & implemented 1993

• Proactive vs Reactive

• Characterize, evaluate & numerically rank hazards

• ~ 60% of State DOT’s

Page 38: C-3 -Jamerson - Rockfall Mitigation

RHRS• Geology parameters

• Rock type & structure

• Erosional features• Discontinuities• Rock friction• Water• Slope height• Block size• Catch area• Rockfall history

• Roadway parameters

• Roadway width• Sight distance• Traffic data• Speed limit

• Exponential scoring

Page 39: C-3 -Jamerson - Rockfall Mitigation
Page 40: C-3 -Jamerson - Rockfall Mitigation

Rockfall Mitigation Program

Page 41: C-3 -Jamerson - Rockfall Mitigation

RockfallMitigation Program

• Concept Development– Geological field mapping– Kinematic analysis– Rockfall modelling– Selection of mitigation

measures• Preliminary/Final Design

– Mitigation design– Construction considerations

• Construction

Page 42: C-3 -Jamerson - Rockfall Mitigation
Page 43: C-3 -Jamerson - Rockfall Mitigation

Area B: Field Investigation

Page 44: C-3 -Jamerson - Rockfall Mitigation

Area A: Kinematics

Page 45: C-3 -Jamerson - Rockfall Mitigation

Rockfall Modelling

Page 46: C-3 -Jamerson - Rockfall Mitigation

Rockfall Modelling

Page 47: C-3 -Jamerson - Rockfall Mitigation

RockfallMitigation

Approaches

• Removal• Stabilization• Protection

Page 48: C-3 -Jamerson - Rockfall Mitigation

•Removal/Excavation

• Scaling

Page 49: C-3 -Jamerson - Rockfall Mitigation
Page 50: C-3 -Jamerson - Rockfall Mitigation
Page 51: C-3 -Jamerson - Rockfall Mitigation

• Blasting

•Removal/Excavation

• Scaling

Page 52: C-3 -Jamerson - Rockfall Mitigation

Route I-80 Roxbury Twp

Page 53: C-3 -Jamerson - Rockfall Mitigation

Route I-80 Roxbury Twp

Page 54: C-3 -Jamerson - Rockfall Mitigation
Page 55: C-3 -Jamerson - Rockfall Mitigation
Page 56: C-3 -Jamerson - Rockfall Mitigation

•Stabilization

• Shotcrete• Buttresses• Rock bolts/dowels• Pinned mesh• Drainage

Page 57: C-3 -Jamerson - Rockfall Mitigation
Page 58: C-3 -Jamerson - Rockfall Mitigation
Page 59: C-3 -Jamerson - Rockfall Mitigation
Page 60: C-3 -Jamerson - Rockfall Mitigation
Page 61: C-3 -Jamerson - Rockfall Mitigation

•Protection

• Catchment• Barriers/fences• Rock mesh drapes

Page 62: C-3 -Jamerson - Rockfall Mitigation
Page 63: C-3 -Jamerson - Rockfall Mitigation
Page 64: C-3 -Jamerson - Rockfall Mitigation
Page 65: C-3 -Jamerson - Rockfall Mitigation
Page 66: C-3 -Jamerson - Rockfall Mitigation
Page 67: C-3 -Jamerson - Rockfall Mitigation

Recently Completed Projects

Rt. 46 MP 1.4-2.4 KnowltonRt. 5 Edgewater/Fort LeeRt. 80 MP 21.9 Allamuchy

Rt. 80 MP 15 Frelinghuysen/AllamuchyRt. 80 Rockfall Mitigation

Roxbury Rt. 10 MP 22.2 W. Orange

Rt. 46 & 80 Warren/Morris Co.Rt. 78 MP 44.75 Berkeley Heights

Page 68: C-3 -Jamerson - Rockfall Mitigation
Page 69: C-3 -Jamerson - Rockfall Mitigation
Page 70: C-3 -Jamerson - Rockfall Mitigation

Route 46 MP 1.4-2.4WB Knowlton Twp

Page 71: C-3 -Jamerson - Rockfall Mitigation

Route 5 Edgewater/Fort Lee

Page 72: C-3 -Jamerson - Rockfall Mitigation

Route 5 Edgewater/Fort Lee

Page 73: C-3 -Jamerson - Rockfall Mitigation

Current Projects

Rt. 80 Hardwick/KnowltonRt. 78 BethlehemRt. 29 Kingwood

Rt. 29 LambertvilleRt. 22 Phillipsburg

Rt. 80 DenvilleRt. 206 Andover

Rt. 280 W. OrangeRt. 23&94 Hardyston

Rt. 15 JeffersonRt. 23 West Milford

Page 74: C-3 -Jamerson - Rockfall Mitigation

Route I-80Delaware Water Gap

Page 75: C-3 -Jamerson - Rockfall Mitigation

Route I-80Delaware Water Gap

Page 76: C-3 -Jamerson - Rockfall Mitigation

Route I-80Delaware Water Gap

Page 77: C-3 -Jamerson - Rockfall Mitigation

Rt. I-78 Bethlehem

Page 78: C-3 -Jamerson - Rockfall Mitigation

Rt. I-78 Bethlehem

Page 79: C-3 -Jamerson - Rockfall Mitigation

Rt. I-78 Bethlehem

Page 80: C-3 -Jamerson - Rockfall Mitigation

Route 29 Kingwood Twp

Page 81: C-3 -Jamerson - Rockfall Mitigation
Page 82: C-3 -Jamerson - Rockfall Mitigation
Page 83: C-3 -Jamerson - Rockfall Mitigation

Route 29 Kingwood Twp

Page 84: C-3 -Jamerson - Rockfall Mitigation
Page 85: C-3 -Jamerson - Rockfall Mitigation
Page 86: C-3 -Jamerson - Rockfall Mitigation

In Conclusion…

Page 87: C-3 -Jamerson - Rockfall Mitigation
Page 88: C-3 -Jamerson - Rockfall Mitigation
Page 89: C-3 -Jamerson - Rockfall Mitigation
Page 90: C-3 -Jamerson - Rockfall Mitigation

Engineering Geology Bridge Engineering & Infrastructure MANAGEMENT