calorimeter status
DESCRIPTION
Calorimeter Status. Outline : X-mas break activities Preparation for 2012 Ageing & Calibration. 27 March 2012. Pascal Perret LPC Clermont. X-mas break activities. A lot of detector movements. Every thing went well and on schedule! - PowerPoint PPT PresentationTRANSCRIPT
Calorimeter Status
Pascal Perret
LPC Clermont
27 March 2012
Outline: X-mas break activities
Preparation for 2012
Ageing & Calibration
2
X-mas break activities
A lot of detector movements
Pascal Perret - LPC Clermont27/03/2012
Every thing went well and on schedule!But SPD had to be reopened to fix 1 VFE & 1 regulator board
problems …
Mo Tu We Th Fr Mo Tu We Th Fr Mo Tu We Th Fr Mo Tu We Th Fr Mo Tu We Th Fr Mo Tu We Th Fr Mo Tu We Th Fr Mo Tu We Th Fr Mo Tu We Th Fr
Detector Side Activities 5 6 7 8 9 12 13 14 15 16 19 20 21 22 23 26 27 28 29 30 2 3 4 5 6 9 10 11 12 13 16 17 18 19 20 23 24 25 26 27 30 31 1 2 3
CERN Closure
AUG Cooling towers maintenance
HCAL side A M1 front, M2-M5
ECAL side A M1 front, M2-M5
PS side A M1 front, M2-M5
Lead side A M1 front, M2-M5
SPD side A M1 front, M2-M5
HCAL side C M1 back, M2-M5
ECAL side C M1 back, M2-M5
PS side C M1 back, M2-M5
Lead side C M1 back, M2-M5
SPD side C M1 back, M2-M5
HCAL side A Maintenance
ECAL side A Maintenance
PS side A
Lead side A
SPD side A
HCAL side C Maintenance
ECAL side C Maintenance
PS side C
Lead side C
SPD side C
CALO System Alignment
XCAL FEB Platform, side A,C FEEB repairs
L0 CABLES Platform, side A cable chain
PS FEB Platform, side A,C FEEB repairs
M1 side A Open
M1 side C Closed, Nacelle
M2-M5 side A Muon nacelle M2-M5 OPEN
M2-M5 side C Muon nacelle M2-M5 OPEN
Muon System Alignment
Yellow nacelle XCAL XCAL
Green nacelle M1 M1
Red nacelle
PS passerelle
XCAL Access
OPEN
A-sideC-side
Week 4 Week 5Week 3
DECEMBER JANUARY
Week 49 Week 50 Week 51 Week 52 Week 1 Week 2
# movements Distance
XCAL 30 99 m
PSPD 25 65 m
3
X-mas break activities
Beam pipe protection Installation of marks on
beam pipe protection
Pascal Perret - LPC Clermont27/03/2012
Installation of mechanical end stoppers when beam pipe protection is in place
ECAL
HCAL
4
X-mas break activities
Dismounting of passive dosimeter detectors for reading PS:
Mystery of a 2nd VFE resetNot yet understood …
L0 hadron trigger: cable tests (XCAL platform) Low rate errors seen in the hadron trigger, from time to time,
usually after powering on/off a crate, and solved by re-plugging the cable (in a different connector or even in the same one)
Reason not understood, very small effect on data but … Several tests done (attenuation of signal, etc.)
No evidence of problem because of weak signal levels in trigger cables
Problem with connectors ?Additional tests to do …
Pascal Perret - LPC Clermont27/03/2012
5
X-mas break activities
Relative crate phase measurements FEB modifications to fix the 2 regimes
observed (collisions/no collisions)The reference calibration signal given by the Sequencer of the FEB
is affected during collisions by many bit flips • ACTEL flash FPGA known problem
The solution adopted consists in taking the calibration signal before the sequencer
+ Fully equip each one of the 2 FEB with 32 channels to reduce X-talks
Cables installation between HCAL and ECAL FEB: HCAL now connected!
Survey measurements Measurements of ECAL irradiated modules
Pascal Perret - LPC Clermont27/03/2012
collisions (L0) - no collisions (no L0)
6
X-mas break activities
SPD Regulator boards
a slight increase in current was observed in some boards (warnings generated during operation!)• Measurements are based on a dedicated fuse• Fuse impedance increase • Exchange the fuse by a higher value avoid any future problem
Pascal Perret - LPC Clermont27/03/2012
6 boards affected (of a total of 16) in SM 1,2, 7, and 8 top• Boards have been dismounted and
the fuses replacedTests ok!
1 VFE showed subtractor problems for 16 channelsImpact only if consecutive eventsNew VFE board installed (same PMT)
7
X-mas break activities
SPD Maraton Backplane problems
Patch-panel measurements: 3.5V instead of 5.5V in 2 channels causing offset problems to all VFEs powered by the same RB.
Problem: loosen nuts at the Maraton backplane providing bad LV cabling contact.
Solution: access from cable platform above the gantry and use an articulated socket wrench and tighten the nuts of the connections.
Pascal Perret - LPC Clermont27/03/2012
8
X-mas break activities
SPD VFE
A new problem appeared once the detector were closed!• One of the voltages was wrong• Connector problems but …• This connector was stuck with
glue as emergency solution (2008) on RB side!
The damaged cable AND the regulator board had to be changed!
Pascal Perret - LPC Clermont27/03/2012
9
> 200 nA (13)100-200 nA (14)50-100 nA (20)
rate effect > 0.2 (11)dead CW (1)
X-mas break activities
HCAL 59 PM replaced: 2x more than in 2010/2011!
Dead: 1Dark current > 50 nA: 47Unstable (rate effect>0.2)
• mainly for studies.
Pascal Perret - LPC Clermont27/03/2012
10
X-mas break activities
ECAL 24 PM replaced
Pascal Perret - LPC Clermont27/03/2012
Green: dismounted for C-W lab. studies (1)Red: the rest of replaced PMs (23)Blue: replaced connectors, PM side (9)Brown: problematic connectors, FEB side (11)Red frame: replaced LEDs (2)
11
Preparations for the 2012 run
HCAL: HV tuning Reduction of PMT gain by a factor 2 to reduce radiation damage
ETmax 15 GeV 30 GeV , but higher noiseHV recipe produced are based on 137Cs run 26/01/2012
Pascal Perret - LPC Clermont27/03/2012
• The ratio is not exactly 0.5: it appears that PMTs’ regulation curves deviate by few % from the exact power law, G=G0∙UB.
• The final adjustment of the 30GeV recipe was done using LEDs.
12
Preparations for the 2012 run
HCAL: HV tuning Another 137Cs run done 12-Mar-2012 for check:
Cs readout system working fine at ETmax=30 GeV Quite significant gain drift since 26-Jan-2012 observed
Pascal Perret - LPC Clermont27/03/2012
The source speed on side C has increased by 12% (34.5 cm/s instead of stable 30.8 in 2009-2012)!• No effect, but to be understood why …
13
Preparations for the 2012 run
Pascal Perret - LPC Clermont27/03/2012
BEFORE AFTER
HCAL: Running at ETmax=30 GeV HCAL PHYSICS HV recipe in use since March 3rd
The LED amplitudes were increased accordingly Change of trigger calibration constants needed in HCAL Front-End
boards:L0 recipe for ETmax = 30 GeV have been produced and in used Problem is that now the transition
• 01 L0ADC, is for ADC=3 (it was for ADC=6 before)• For the trigger, we compute 2x2 sums and take the highest: the board
electronics noise gives always hadron L0 candidates with non 0 ET.
ET hadron ET hadron
14
Preparations for the 2012 run
HCAL: Running at ETmax=30 GeV Input and output L0 hadron candidates are sent from the Selection Boards
to the TELL1: 90 candidates.TELL1 algorithm is to suppress candidates with 0 ET, but now none of the
candidates have 0 ET, and the TELL1 must process the 90 candidates, for which it is not designed throttling when running at 1 MHz (these are the worse conditions the system can achieve)
TELL1 firmware was designed to allow suppression of candidates with ET below a given threshold: this feature is back• TELL1 configured with a Zero-Suppression threshold of 160 MeV.
In parallel, add the possibility to do this suppression directly in the Selection Board: the candidates would then be suppressed both in the DAQ and trigger paths.
The energy scale in the reconstruction (Conddb) is going to be recovered
Pascal Perret - LPC Clermont27/03/2012
15
Preparations for the 2012 run
ECAL: HV tuning LED change during X-mas break:
Pascal Perret - LPC Clermont27/03/2012
PmPin(12 Mar)/PmPin(30 Oct) PmPin(21 June)/PmPin(21 May)
AgeingRecovery Average recovery is on the level of 8÷13%, strongly depends on the detector area (up to 25% in the “horns”)
17
Preparations for the 2012 run
Pascal Perret - LPC Clermont27/03/2012
Change of HV has an impact on timing!update FEB recipeLED system time alignment to be tunedDetector timing to be checked with TAE
Required gain changeRequired gain change
/ Real gain change
ECAL: HV tuning to make uniform the gain after ageing HV have been changed for ageing over 800pb-1 to take care of
refreshing effect : π calibration used (September 25⁰ th)
18
ECAL ageing & calibration
An ageing model is being built by Marie-Noelle 2 components
Neutral (neutral calorimeter clusters) • Distribution of flux weighted by cluster energy
• Corrected by cell surface
Pascal Perret - LPC Clermont27/03/2012
• Fit Aexp(-br) Shape of neutral flux (Tails are not described)
Charged (charged cluster flux)
19
ECAL ageing & calibration
An ageing model is being built by Marie-Noelle 2 components
Charged (charged cluster flux)• Take charged cluster weighted by cluster energy• Adjust on the central zone weighted (1/ cell size)
Pascal Perret - LPC Clermont27/03/2012
• Parametrization A exp(-bx)exp(-cy) Radiation flux:
42% Neutral and 58% charged
20
ECAL ageing & calibration
An ageing model is being built by Marie-Noelle 2 effects:
Scintillator/fiber ageing proportional to the fluxDecrease of the PMT gain due to current
• Depend of the integrated flux / cell Contribution of the 2 effects adjusted from fine calibration
• 52% PMT and 48% radiation
Pascal Perret - LPC Clermont27/03/2012
New coefficients are being produced for 2011 data
Deviation Sept/June Modelisation
21
Calibration
Isolated electrons could also be used Selection
Only RICH was used to identify electrons;Track momentum pe > 3. GeV or pe > 10. GeV;No charged tracks within circle with R = 30 cm at ECAL entrance;Total Preshower energy deposition associated with track
• EPS > 20 MeV;
Total HCAL energy deposition associated with track• EHCAL < 1 GeV.
SampleIt was processed ~3.14x108 physical events collected by LHCb in
2011 (MagDown + MagUp BHADRON streams are used), and ~1.15x108 e-candidates were selected
Pascal Perret - LPC Clermont27/03/2012
O. Stenyakin, O. Yushchenko
22
Calibration
Isolated electrons could also be used
Pascal Perret - LPC Clermont27/03/2012
The method is promising!• It can be used to
perform ECAL and PS calibration (in progress)
• More tests needed
23
2012 Running
HCAL Over a ~200 pb-1 period (or at a change of the magnet polarity):
We expect a change of the gain by ~1.5%; corresponding to a ~2.5% hadron loss
Adjustment of the PMT HV according to LED system During TS
Calibration with Cs source scan ECAL
With the first collisions give new fine calibration time estimate ~ 2 weeks implemented during 1st TS
Update database + ageing Update calibration monthly
Pascal Perret - LPC Clermont27/03/2012
24
Summary & Conclusion
After TS 100% channels are functional ECAL & HCAL PMT HV settings have been tuned to make
uniform detector and reduce possible radiation damage effects Time alignment of the detectors have to be adjusted/checked
with TAE events an first data Piquets:
Almost the same team than last year:-3 + 1Funding could become an issue to have persons at CERN …
Calibration and ageing survey to perform all over the year Production of FmDST is a key tool for ECAL calibration Not in a routine mode! Volunteers are welcome!
Pascal Perret - LPC Clermont27/03/2012