caltrain modernization program update 8 10-2012

19
Caltrain Modernization Program Update Palo Alto City Council Rail Committee August 10, 2012

Upload: adina-levin

Post on 12-Nov-2014

503 views

Category:

Travel


1 download

DESCRIPTION

Caltrain modernization presentation delivered at the Palo Alto Rail Committee meeting on August 10 2012

TRANSCRIPT

Page 1: Caltrain modernization program update 8 10-2012

Caltrain Modernization Program Update

Palo Alto City Council Rail CommitteeAugust 10, 2012

Page 2: Caltrain modernization program update 8 10-2012

Presentation Topics

1. State Legislature Update

2. Next Steps for the Peninsula

3. Blended System Planning Analysis Update

4. Discussion

Page 3: Caltrain modernization program update 8 10-2012

State Legislature Update

Page 4: Caltrain modernization program update 8 10-2012

Green Light for HSR & Blended System• Bay Area State Assembly and Senate support

– Elaine Alquist, D-San Jose– Tom Ammiano, D- San Francisco– Jim Beall, D-San Jose– Nora Campos, D-San Jose– Paul Fong, D-Mountain View– Rich Gordon, D-Menlo Park– Jerry Hill, D-San Mateo– Mark Leno, D-San Francisco– Fiona Ma, D-San Francisco– Leland Yee, D-San Francisco

Page 5: Caltrain modernization program update 8 10-2012

SB 1029• Appropriates $705 million for Caltrain Modernization

– $600 million from Prop 1A (HSR)– $105 million from Prop 1A (Connectivity)

• Funds available for:– “blended system improvements consistent with the MOU” and– “shall not be used to expand the system to a dedicated four-track system”

• Bonds sold and allocated to project by State Controller

Page 6: Caltrain modernization program update 8 10-2012

Next Steps for the Peninsula

Page 7: Caltrain modernization program update 8 10-2012

Project Delivery Focus• Early Investment (2019)

– Define outreach/decision-making structure and process– Advanced Signal System

Advance design from “Critical” to “Final”

– Electrification & Electric Vehicles Update / Recirculate Caltrain EA/EIR Define project delivery approach/team

• Blended System (2029)– Complete current planning studies– Schedule for completing planning process

Page 8: Caltrain modernization program update 8 10-2012

Blended System Planning Update

Page 9: Caltrain modernization program update 8 10-2012

Blended System Planning Process

Decision-Making Matrix

Blended System Alternatives

Design & Environmental Review

Infrastructure Need Revenue / CostFleet Need

Capacity Analysis

Service Plan Options

Grade Crossing & Traffic Analysis

Service Plan / Operations Considerations

Page 10: Caltrain modernization program update 8 10-2012

Blended SystemService Plan/Operations Considerations Analysis

Page 11: Caltrain modernization program update 8 10-2012

Purpose / Goals

• Consider service / operations variables not included in capacity analysis

• Requested by stakeholders

• Inform development of service plan options

Page 12: Caltrain modernization program update 8 10-2012

Scope of Work

Page 13: Caltrain modernization program update 8 10-2012

Passing Track Options

Options Locations

4 Tracks – Northern Milepost 5 to 15.2 (Bayshore to Millbrae stations)

4 Tracks - Full Midline Milepost 18.1 to 27.2 (Hayward Park to Redwood City stations)

4 Tracks - Short Midline Milepost 18.1 to 24.2 (Hayward Park to Whipple Ave.)

4 Tracks - Southern Milepost 33.8 to 41.6 (San Antonio to Lawrence station)

3 Tracks Milepost 18.1 and 33.7(Hayward Park to California Ave. )

Page 14: Caltrain modernization program update 8 10-2012

Simulation Model Results

• 4 Track Options

• 3 Track Option–Model: high performance–Practice: further evaluation

Operational Performance Ranking

High: Full Midline

Medium: Short Midline & Southern

Low : Northern

Page 15: Caltrain modernization program update 8 10-2012

Decision Matrix (work in progress)

Passing Track Options

Considerations

Operations E & C ROW Cost City / County

4 Tracks - Northern

4 Tracks - Full Midline

4 Tracks - Short Midline

4 Tracks - Southern

3 Tracks

Page 16: Caltrain modernization program update 8 10-2012

Blended SystemGrade Crossing & Traffic Analysis

Page 17: Caltrain modernization program update 8 10-2012

• 40 at-grade crossings

• Identify relationship between:– Train service levels– Gate down time– Local traffic

• Analyze future scenarios (2035):– Impacts from Caltrain versus future growth– Difference between service plan options

• Improvement recommendations

Study Purpose & Goals

Page 18: Caltrain modernization program update 8 10-2012

Key Tasks and Status

Page 19: Caltrain modernization program update 8 10-2012

Discussion