scaffold hoist to save money on scaffold erection

TRANSCRIPT

Page 1: Camac smart installation

CAMAC SMART installation

Page 2: Camac smart installation

We must introduce the CAMAC SMART in the scaffold or placing the scaffolding around the SMART .

Page 3: Camac smart installation

Level the first mast. It is very important for avoiding erection problems

Page 4: Camac smart installation

Fix the first mast to the scaffold using the anchorage.

Page 5: Camac smart installation

Install the wire-winder next to the base. We should give 7 rounds for getting tension on the inside springs. Afterwards connect the cable to the machine.

Page 6: Camac smart installation

Connect the hand control to the machine. It will be used only for installation process.

Page 7: Camac smart installation

Assemble the second mast, use the screws to fix it. Use the hand control to lift the machine when you need it.

Page 8: Camac smart installation

Before start up the CAMAC SMART check that all switches are not active or pressed.

Top limit switch

Safety switch

Bottom limit switch

Floor switch

Page 9: Camac smart installation

Follow the erection by assembling more masts

and one anchorage every 3 meters.

Page 10: Camac smart installation

Anchorages are fixed on the mast using this plate.

Floor stop. Can be fixed anywhere on the mast.

Its used for fixing the stop positions according the

scaffold levels.