CAPACITY REQUIREMENT PLANNING
By
Sure ravikumar
![Page 2: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/2.jpg)
Capacity Requirements Planning
• Capacity Requirements Planning is a computerized technique for projecting resource requirements for critical work stations.– Inputs:• Planned order releases• Routing file•Open orders file
–Outputs:• Load Profile for each work center
![Page 3: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/3.jpg)
Definitions• Planned Order Releases: Information from the
Material Requirements Planning which tells when you should start the order so it can be completed on time.
Routing Files: Information that details the requirements of equipment and labor to complete the order as needed in the required time frame.
Open Orders Files: Information regarding the orders that are currently started and need to be completed.
![Page 4: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/4.jpg)
Capacity Requirements Planning
• A tool for:– determining capacity that is available and required.– Alleviating bottleneck work centers.
• Helping planners make the right decisions on scheduling before problems develop.
• Verifies that you have sufficient capacity available to meet the capacity requirements for MRP plans.
![Page 5: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/5.jpg)
What is Capacity?• The work that the system is capable of doing in a
period of time.• It must be determined at different levels:– plant – department– work center.
• It is normally stated in standard hours of work.
![Page 6: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/6.jpg)
What is Capacity?• Capacity = (no. of machines or workers) x (no. shifts)
x (utilization) x (efficiency)
• Best operating level is the percent of capacity utilization that minimizes average unit cost. – Usually 80% with a 20% cushion
![Page 7: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/7.jpg)
Utilization and Efficiency• Utilization is the percent of available time spent
working.
• Efficiency is how well a machine or worker performs compared to a standard output level.
![Page 8: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/8.jpg)
Utilization and capacity
• Utilization=Actual Charged/ Schedule Available Hours
• Efficiency= Standard Hours Earned/ Actual Hours Charged
![Page 9: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/9.jpg)
Reason to use CPR• Bottleneck Management -– The throughput of all products processed is
controlled by bottlenecks.– Work centers need to be scheduled at a rate to
prevent bottlenecks.– To eliminate bottlenecks, a time buffer inventory
should be established.
![Page 10: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/10.jpg)
Basic Strategies for Timing Capacity
• CRP provides information to determine the timing of capacity expansion. The basic strategies in relation to a steady growth in demand are:– Capacity Lead Strategy– Capacity Lag Strategy – Average Capacity Strategy
![Page 11: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/11.jpg)
Capacity Lead Strategy• In anticipation of demand, capacity is increased.
• This is an aggressive strategy and is used to lure customers away from competitors.
![Page 12: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/12.jpg)
Average Capacity Strategy
• Average expected demand is calucated and capacity is increased accordingly
• This is the most moderate strategy
![Page 13: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/13.jpg)
Capacity Lag Strategy • Increased capacity after demand has
increased• This is a conservative strategy and may result
in loss of customers• You assume customers will return after
capacity has been met
![Page 14: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/14.jpg)
Capacity PlanningHow much to increase capacity demands
depend upon a number of factors, including:
• Anticipated demand – volume & certainty
• Strategic objectives
• Costs of expansion and operation
![Page 15: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/15.jpg)
Adjustments to CapacityIncrease capacity by:
• Adding extra shifts
• Scheduling overtime or weekends
• Adding equipment and/or personnel
Reduce load by:
• Reducing lot sizes
• Holding work in production control
• Subcontracting work to outside suppliers
![Page 16: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/16.jpg)
Adjustments to CapacityReduce capacity by:
• Temporarily reassigning staff
• Reducing the length of shifts
• Eliminating shifts
Increase load by:
• Releasing orders early
• Increasing lot sizes
• Making items normally outsourced
![Page 17: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/17.jpg)
Capacity Planning• Best operating is seldom at 100% and varies with
industry.
– In industries where demand is highly variable, large capacity cushions are common.
– Companies with less flexibility and higher costs maintain small cushions – under 10%.
– Overbooking is common with some industries such as airlines.
![Page 18: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/18.jpg)
Economies of Scale• Economies of scale is the best operating level.
• Economies of scale is the point where it costs less per unit to produce high levels of output.
– Occurs when fixed costs are spread over large number of units
![Page 19: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/19.jpg)
Diseconomies of Scale• Occurs at a certain level of output.
–When fixed costs increase with number of units being produced, examples:
• Higher rework
• More equipment breakdown
![Page 20: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/20.jpg)
What is CRP Used For?
• To determine the capability of a system or resource to produce a quantity of output in a particular time period. For example:– Should the hospital hire more registered
nurses to care for the projected patient load?– Should the hospital build more rooms for
patients?– What is the projected finish time for the
current projects?
![Page 21: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/21.jpg)
CRP Produces Load Profile• CRP uses the information to produce a load profile
for each machine or work center. A load profile:
– Compares released orders and planned orders with the capacity of the work center.
– Identifies under loads and overloads.
![Page 22: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/22.jpg)
What is a load?• Load refers to the standard hours of work
assigned to a facility.
![Page 23: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/23.jpg)
What is the load percent?
Load percent is the ratio of load to capacity
Load percent=load/capacity
![Page 24: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/24.jpg)
Engineering Calculations (Capacity)
Numbers of hours = 40 Shifts = 1Efficiency = 100%Utilization = 4/5 = 80%Capacity = 40 x 1 x 0.8 x 1.00 = 32 hours
Project 1 capacity = 4 (weeks) x 32 = 128Project 2 capacity = 2 (weeks) x 32 = 64Project 3 capacity = 4 (weeks) x 32 = 128Project 4 capacity = 3 (weeks) x 32 = 96
![Page 25: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/25.jpg)
Engineering Calculations (Load)
Project 1 = 30 x 4 hours per mile = 120 hours(start by February 15th – must be completed by March 15th)
Project 2 = 20 x 4 hours per mile = 80 hours(start March 16th – must be completed by April 1st)
Project 3 = 5 x 4 hours per mile = 20 hours(start April 2nd – must be completed by May 1st)
Project 4 = 15 x 4 hours per mile = 60 hours(start by May 2nd – must be completed by May 23rd)
![Page 26: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/26.jpg)
Engineering Calculations (Load %)
• Project 1 = 120/128 = 94%–Can be completed
• Project 2 = 80/64 = 125%–Can not be completed
• Project 3 = 20/128 = 16%–Can be completed
• Project 4 = 60/96 = 63%–Can be completed
![Page 27: Capacity requirement planning sure 12mt07ind019](https://reader036.vdocument.in/reader036/viewer/2022062420/55b9af02bb61ebf6578b460b/html5/thumbnails/27.jpg)
Summary• To operate at maximum capacity, companies must
use the resources available. If resources under underutilized, the profit margin will not be maximum.
• Using capacity requirements planning helps a company identify potential problems, such as eliminating the possibility of overworking the current staff, overloading machines, losing customers because the work could not be completed as scheduled, paying penalties for late delivery.