capital project budget reporting formmedia.budget.uconn.edu/2016/10/heatingplantemergency... ·...
TRANSCRIPT
TYPE BUDGET:
PROJECT NAME:
APPROVED APPROVED APPROVED PROPOSED
PLANNING REVISED PLANNING DESIGN FINAL
BUDGETED EXPENDITURES 9/2/2011 6/25/2014 8/5/2015 10/28/2015EVPACFO
CONSTRUCTION -$ 1,500,000$ 1,625,000$ 1,700,000$ DESIGN SERVICES 55,000 125,000 200,000 200,000 TELECOMMUNICATIONS - - - - FURNITURE, FIXTURES AND EQUIPMENT - - - - CONSTRUCTION ADMINISTRATION - 125,000 150,000 150,000 OTHER AE SERVICES (including Project Management) 5,000 75,000 235,000 185,000 ART - - - - RELOCATION - - - - ENVIRONMENTAL - 20,000 - - INSURANCE AND LEGAL - 10,000 5,000 5,000 MISCELLANEOUS - 20,000 30,000 30,000 OTHER SOFT COSTS 5,000 20,000 - -
SUBTOTAL 65,000$ 1,895,000$ 2,245,000$ 2,270,000$
PROJECT CONTINGENCY 70,000 605,000 255,000 230,000
TOTAL BUDGETED EXPENDITURES 135,000$ 2,500,000$ 2,500,000$ 2,500,000$
SOURCE(S) OF FUNDING
UCONN 2000 PHASE III 135,000$ 2,500,000$ 2,500,000$ 2,500,000$
TOTAL BUDGETED FUNDING 135,000$ 2,500,000$ 2,500,000$ 2,500,000$
BOT 10.28.15
CAPITAL PROJECT BUDGET REPORTING FORM
901697
FINAL
HEATING PLANT UPGRADE - EMERGENCY POWER SYSTEM UPGRADE
TYPE BUDGET:
PROJECT NAME:
APPROVED APPROVED PROPOSED
PLANNING REVISED PLANNING DESIGN
BUDGETED EXPENDITURES 9/2/2011 6/25/2014 8/5/2015BY EVPACFO
CONSTRUCTION -$ 1,500,000$ 1,625,000$ DESIGN SERVICES 55,000 125,000 200,000 TELECOMMUNICATIONS - - - FURNITURE, FIXTURES AND EQUIPMENT - - - CONSTRUCTION ADMINISTRATION - 125,000 150,000 OTHER AE SERVICES (including Project Management) 5,000 75,000 235,000 ART - - - RELOCATION - - - ENVIRONMENTAL - 20,000 - INSURANCE AND LEGAL - 10,000 5,000 MISCELLANEOUS - 20,000 30,000 OTHER SOFT COSTS 5,000 20,000 -
SUBTOTAL 65,000$ 1,895,000$ 2,245,000$
PROJECT CONTINGENCY 70,000 605,000 255,000
TOTAL BUDGETED EXPENDITURES 135,000$ 2,500,000$ 2,500,000$
SOURCE(S) OF FUNDING
UCONN 2000 PHASE III 135,000$ 2,500,000$ 2,500,000$
TOTAL BUDGETED FUNDING 135,000$ 2,500,000$ 2,500,000$
BOT 8.5.15
CAPITAL PROJECT BUDGET REPORTING FORM
901697
DESIGN
HEATING PLANT UPGRADE - EMERGENCY POWER SYSTEM UPGRADE
TYPE BUDGET:
PROJECT NAME:
APPROVED PROPOSED
PLANNING REVISED PLANNING
BUDGETED EXPENDITURES 9/2/2011 6/25/2014BY EVPACFO
CONSTRUCTION -$ 1,500,000$ DESIGN SERVICES 55,000 125,000 TELECOMMUNICATIONS - - FURNITURE, FIXTURES AND EQUIPMENT - - CONSTRUCTION ADMINISTRATION - 125,000 OTHER AE SERVICES (including Project Management) 5,000 75,000 ART - - RELOCATION - - ENVIRONMENTAL - 20,000 INSURANCE AND LEGAL - 10,000 MISCELLANEOUS - 20,000 OTHER SOFT COSTS 5,000 20,000
SUBTOTAL 65,000$ 1,895,000$
PROJECT CONTINGENCY 70,000 605,000
TOTAL BUDGETED EXPENDITURES 135,000$ 2,500,000$
SOURCE(S) OF FUNDING
UCONN 2000 PHASE III 135,000$ 2,500,000$
TOTAL BUDGETED FUNDING 135,000$ 2,500,000$
BOT 6.25.14
CAPITAL PROJECT BUDGET REPORTING FORM
901697
REVISED PLANNING
HEATING PLANT UPGRADE - EMERGENCY POWER SYSTEM UPGRADE
HEATING PLANT UPGRADE POWER SYSTEM Project Budget (Revised Planning)
06/25/2014
Central Utility Plant (CUP)