capital project cost reporting. project goals documentation of project approval approval path based...
TRANSCRIPT
Project Goals
• Documentation of project approval• Approval path based on reporting structure and
individual approval limits• POs against an overspent project to be stopped• Detailed comparisons of approved AFE budget and
cost breakdown• Reporting on project spending
Project Goals (cont)
• Reporting of internal maintenance labor by project• Process to capture and approve project scope
changes– Allows for easy tracking of scope changes– Allows for incremental approvals of project costs
• Document the date project is closed• Single system solution
Description Budget Costs Costs @ Comp AFE Budget
Engineering
Conceptual Engineering $ 441,500 $ 424,360 $ 424,360 $ (17,140)
Detailed Engineering $ 1,025,643 $ 1,138,684 $ 1,138,684 $ 113,041
Engineering Support $ 52,879 $ 58,879 $ 58,879
.
Total Engineering $ 1,467,143 $ 1,615,923 $ - $ 1,621,923 $ 154,780
Procurement
Major Equipment $ 1,100,000 $ 930,108 $ 2,300 $ 932,408 $ (167,592)
PO-Vessel Peterson
PO - Exchanger
Misc Equipment (filters, specialty valves etc.
Structural Steel & Foundation Material $ 27,988 $ - 27,988 $ 27,988
PO - Structure
PO- Pipe Supports
Piping Material $ 338,034 $ 209,281 $ - $ 209,281 $ (128,753)
Instrument Material $ 34,155 $ - $ 35,863 $ 35,863
Electrical /Instrumentation Material $ 7,486 $ - $ 7,486 $ 7,486
Insulation/Paint
Catalyst/Chemicals
Spare Parts/Critical Spares
Stores Materials $ 8,443 $ - 8,865 $ 8,865
Rentals $ 1,659 $ 2,500 $ 4,159 $ 4,159
Total Equipment & Materials $ 1,438,034 $ 1,219,120 $ 4,800 $ 1,226,050 $ (211,984)
Construction
Civil / Underground $ -
Structural Steel $ -
Mechanical $ 2,390,580 $ 1,393,019 $ 1,843,499 $ 3,236,518 $ 845,938
Piping Contractor
Pump Installation Contractor
Insulation /Painting $ -
Electrical/Instrumentation
Electrical Contractor A
Construction Support $ 24,868 $ 10,000 $ 41,842 $ 41,842
Total Construction $ 2,390,580 $ 32,482 $ 1,853,499 $ 3,278,360 $ 887,780
PR and WO Mods
• An ‘AFE #’ field was added to both the PRs and the WOs in Maximo.– The AFE # has been programmed to carry forward to the PO and the
invoice as they are created
• PRs with an AFE # are only approved by the project owner– Encourage users to tie PR/PO cost to AFE– Eliminate redundant approvals
• When a project work request is rolled to a WO the AFE # is added by the scheduler– Finance reviews all new WOs to assure AFE # are being added
correctly
Project Reporting
• Monthly Management Review– Sub set of all ongoing projects – Project owners are required to go over the Maximo generated spending
reports– Report tracks both actual spending and committed cost
• Before a project can be closed all POs and WOs must be closed. – Requires owner to assure POs have been invoiced and labor has been
charged to the WOs
• Maximo will not allow a PO to be approved if the AFE is over spent– Controlled by workflow at time of PO approval
• Tax department is using the Maximo generated spending reports for multiple tax fillings
Change in Project Scope
• Project scope and price increases must be communicated to and approved by management.– The AFE revision is added to the approved spending and the new total
amount is used to determine the approval path. i.e. If the revised project total breaks the $1 million level it will go to the next management level for approval.
– Multiple revisions can be done • Allows the AFE to be generated when long lead time items are ordered• AFE is then revised to meet project milestones
AFE Automation ScriptsScript Name Launch Point Code
BWO_AFE_GRAND_TOTALS
Update of BWO_AFE or Action assigned to AFE revision workflow
Calculates the totals for each cost breakdown category
Show in system
BWO_AFEREV_CREATE
Update of BWO_AFEREV
mbo.setValue("AFEREV",mbo.getThisMboSet().max("AFEREV") + 1,2);
AFE_REV_TOTAL_COST
Update of BWO_AFEREV
Calculates the totals for each cost breakdown category for revisions only
Show in system
MOC EscalationsEscalation ID Description Condition
BWO_AFE_TOT Notifies the AFE originator that PO’s have comsumed at least 95% of the AFE approved spending
:BWO_AFE_2_AFE_SUMMARY.afe_rev_po_commit_percent >= 95
BWO_AFEREV_WF Submits an AFE revision into workflow
status in ('NEW','WAPPR','REJECT') and submit = 1 and bwo_aferevid not in (SELECT OWNERID FROM WFASSIGNMENT WHERE ASSIGNSTATUS = 'ACTIVE' AND OWNERTABLE = 'BWO_AFEREV')
BWO_AFE_EX_ADM
Notifies the CEO executive assistant that an AFE is awaiting approval
status = 'WAPPR‘ and bwo_current_approver = 'CRYSTAL.MAGGELET'