Page 1: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

Capital Projects Reportt o t h e

Board of Trustees of the

Sierra Sands Unified School District

January 15, 2015

1

Page 2: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

BURROUGHS HIGH SCHOOL

· Address 500 E. French Ave. Ridgecrest, CA 93555

· Project Manager

MaasSteve Hubbard

· Architect Westberg + White Tustin, CA

· Construction Manager

ProWest PCM

Fast Facts

Complete renovation of the permanent instructional spaces throughout the campus along with the addition of a new Administration Building at the front of the campus and a new Concessions/Restroom Building adjacent to the existing stadium. Work will include replacement of all existing HVAC systems, site paving improvements, a new and enlarged student parking lot, and modern audio visual and technology infrastructure.

• Total Project Budget . . . . . . . . . . . . . . . . . . . . $31,909,274

• Project Square Footage (GSF) . . . . . . . . . . . . 178,202 SF

• Funding Source . . . . . . . . . . . . . . . . . . . . . . . . 80% DOD, 20% District Funds

• Construction Start . . . . . . . . . . . . . . . . . . . . . . June 2015

• Targeted Completion . . . . . . . . . . . . . . . . . . . . 06/30/17

Sustainable FeaturesMeets requirements of the National Environmental Policy Act

PROJECT STATUS REPORT

2

Page 3: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

PROJECT STATUS REPORTDSA REVIEW AND APPROVAL

Fast Financial Facts

• Total Project Budget . . . . . . . . . . . . . . . . . . . . .$31,909,274• Construction Budget . . . . . . . . . . . . . . . . . . . . $22,410,282• Expenditures To Date. . . . . . . . . . . . . . . . . . . . $ 5,303,488

• Percent Complete of Project Cost . . . . . . . . . 17%• Percent Complete of Construction . . . . . . . . . 0%

3

Project Update

• DSA for back-check of construction documents nearing completion; expected approval remains January 15, 2015.

• Preliminary Plans of Admin Building and the Concessions Building as Custom Permanent Modular Construction conducted approved by the District staff and Principal.

• Construction Manager’s cost estimate expected by January 15, 2015.

• Project remains on schedule for early bidding as a methodology to maintain the Project Schedule which targets commencement of construction in June 2015.

• CEQA Categorical Exemption now complete and ready for submission upon DSA approval.

• CDE final application remains pending approval by DSA and final CEQA determination.

BURROUGHS HIGH SCHOOL

Page 4: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

SCHEDULE: 12 MONTH

4

BURROUGHS HIGH SCHOOL

•DSA Submittal 11-04-15

•DSA Plan Check Duration – 8 weeks 01-15-15

•Bid Advertisements (twice) 02-10-15 and 02-17-15

•Bidding Period 02-10-15 thru 03-10-15

•Bid Notices of Intent 03-12-15

•Board Approval of Awards 03-12-15

•Notices to Proceed 03-14-15

•Submittal Review 03-14-15 thru 05-29-15

•Construction Start 06-01-15

Page 5: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

MURRAY MIDDLE SCHOOL

· Address 200 E. Drummond Ave. Ridgecrest, CA 93555

· Project Manager

MaasSteve Hubbard

· Architect IBI Group Bakersfield, CA

· Construction Manager

ProWest PCM

Sustainable Features

·Meets requirements of the National Environmental Policy Act

Fast Facts

New construction of a complete middle school campus to house the students from the existing Murray Middle School including Classroom Building, Music and Art Building, Library, Gymnasium, Multi-purpose Room and Administration Building, along with playing fields and a central campus courtyard.

• Total Project Budget . . . . . . . . . . . . . . . . . . . . $39,542,838• Project Square Footage (GSF) . . . . . . . . . . . . 65,425 SF (as revised)• Funding Source . . . . . . . . . . . . . . . . . . . . . . . . 80% DOD, 20% District Funds• Construction Start . . . . . . . . . . . . . . . . . . . . . . July 2015• Targeted Completion . . . . . . . . . . . . . . . . . . . . 9/30/2017

PROJECT STATUS REPORTCONSTRUCTION DOCUMENTS PHASE

5

Page 6: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

PROJECT STATUS REPORTCONSTRUCTION DOCUMENTS PHASE

Fast Financial Facts

• Total Project Budget . . . . . . . . . . . . . . . . . . . . .$39,542,838• Construction Budget . . . . . . . . . . . . . . . . . . . . $24,510,544• Expenditures To Date. . . . . . . . . . . . . . . . . . . $ 6,893,580

• Percent Complete of Project Cost . . . . . . . . . 17%• Percent Complete of Construction . . . . . . . . . 0%

Project Update

• Construction Documents Phase commenced; DSA submittal scheduled for February 15, 2015.

• Architect continues working with regulatory agencies to maintain prior approvals.

• Budget constraints continue to be critical, Project Team continues to work to minimize costs related to extent and nature of site utilities and earthwork for site development

• Design of Food Service, Technology and Facilities Services being reviewed, modified and approved by District representatives.

• CEQA – Additional DTSC-required sampling on site conducted and results obtained; coordination continues among DTSC, consultant, District staff, and Navy personnel in order to expedite and optimize schedule and funding; public meeting to be scheduled.

• Relocation of the Base boundary fence scheduled for January 2015; Navy review and approval remain pending.

• Threat force protection consultant continues completed performance criteria for Custom Permanent Modular construction; Navy and DSA reviews to be concurrent.

MURRAY MIDDLE SCHOOL

6

Page 7: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

SCHEDULE: 12 MONTH

MURRAY MIDDLE SCHOOL

7

•DSA Submittal 02-15-15

•DSA Plan Check Duration – 12 weeks 05-06-15

•Bid Advertisements (twice) 05-07-15 and 05-14-15

•Bidding Period 05-07-15 thru 06-12-15

•Bid Notice of Intent 06-14-15

•Board Approval of Awards 06-21-15

•Notices to Proceed 06-22-15

• Site Construction Start 07-15-15

•Commence design of modular units 6-22-15

•DSA completion of review of modular unit design 10-22-15

Page 8: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

HVAC REMEDIATION

· Address Various

· Project Manager

MaasSteve Hubbard

· Architect RBB Architects Los Angeles, CA

· Construction Manager

TBD

Fast Facts

Remediation of prior substandard construction and installation of HVAC units. Work at school sites that have not yet benefitted from Modernization projects includes structural, mechanical and electrical retrofitting of existing HVAC units to properly respond to existing conditions and to correct prior substandard work. Due to budget constraints, work now includes Monroe Middle School, Mesquite Continuation School, and Burroughs High School.

· Total Project Budget . . . . . . . . . . . . . . . . . . . . $7,024,500· Project Square Footage (GSF) . . . . . . . . . . . . Varies· Funding Source . . . . . . . . . . . . . . . . . . . . . . . . Facilities Hardship /Siemens· Construction Start . . . . . . . . . . . . . . . . . . . . . . June 2015· Targeted Completion . . . . . . . . . . . . . . . . . . . . August 2015

Sustainable Features·Meets requirements of the National Environmental Policy Act

PROJECT STATUS REPORTCONSTRUCTION DOCUMENTS

8

Page 9: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

PROJECT STATUS REPORTCONSTRUCTION DOCUMENTS

Fast Financial Facts

• Total Project Budget . . . . . . . . . . . . . . . . . . . . .$7,024,500• Construction Budget . . . . . . . . . . . . . . . . . . . . $4,917,150• Expenditures To Date. . . . . . . . . . . . . . . . . . . . $ 796,580

• Percent Complete of Project Cost . . . . . . . . . 11%• Percent Complete of Construction . . . . . . . . . 0%

9

Project Update

• DSA in review of correction of all prior BHS Open A# work and incorporation into the Modernization

• DSA for Plan Check and approval of Monroe complete

• Detailed cost estimates for Monroe construction documents complete; Project Budget Report based on projected Monroe cost estimate; estimates for Mesquite and Burroughs based on Monroe cost estimate.

• Applications for State Facilities Hardship funds remain in process; CDE representative prepared to submit interim funding request documents in order to qualify for wait list; letter from DSA delineating minimum acceptable level of remediation remains outstanding.

• Agreement reached with Monroe and Burroughs Principals and other District staff regarding appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015.

HVAC REMEDIATION

Page 10: Capital Projects Report · appropriate scheduling and logistics of construction as relate to school use and occupancy; construction to commence in June 2015. HVAC REMEDIATION. SCHEDULE:

SCHEDULE:

10

HVAC REMEDIATION

•DSA Submittal, Phased Intake 08-03-14 thru 03-17-15

•DSA Plan Check Duration – 12 weeks each Phase 08-03-14 thru 06-03-15

•Bid Advertisements (twice) 04-07-15 and 04-14-15

•Bidding Period 04-07-15 thru 05-12-15

•Bid Notices of Intent 05-14-15

•Board Approval of Awards, first phases 05-21-15

•Notices to Proceed, first phases 05-22-15

•Construction Start, first phases 06-04-15