capstoneposter 36x48 supernova
TRANSCRIPT
The group would like to thank Professor Jack Reilly, Teaching
Assistants Steve Yang, Bo Li, and Yiwei Zhou, and our mentor
Michael Kowalczyk for their continuous support of this project.
Acknowledgements
External Transportation Improvements for Washington Avenue & Fuller Road Mixed Use Site
Brett Cutler, Robert Fohrenbach, Shahira Hussein, Sofia Kyle, Alexander Lin
Civil Engineering Capstone Design, Spring 2015
Traffic ModelingSummary
Alternatives Analysis & Final Design Choices
Trip Generation and Distribution
Geometric Design
The site is located just west of the SUNY Albany Campus, south
of Washington Avenue and I-90, and east of I-87. The scope of
work is to improve traffic conditions on a realignment of
Washington Avenue, the intersection of Washington Avenue and
Fuller Road, and the intersection of Fuller Road and Tricentennial
Drive.
Mixed-use development is a type of development where multiple
building types are situated closely together on a single site. As a
result, the users of the roadways adjacent to the site will vary with
time of day, straining the network at certain peak hours.
The existing intersections suffer from heavy traffic volumes and
delays of over 80 seconds per vehicle. Additionally, pedestrian
access is either missing or insufficient.
The current design of intersections cannot accommodate the
current traffic, let alone the additional traffic that will be attracted by
the development of the site. In order to reduce congestion and
accommodate the community’s vision for development,
transportation improvements must be made.
Lighting, Drainage, and Safety
High pressure sodium bulbs will illuminate
our roadways. They have a very long lamp life
with minimal reduction in light level over time.
Catch basins will be placed at low points of
elevation to collect water and debris. Signs will be
placed to inform users of the new conditions.
These provisions will keep the system safe and
operational for many years.
EstablishmentWD AM
IN
WD AM
Out
WD PM
In
WD PM
Out
Sat Peak
In
Sat Peak
Out
Sun Peak
In
Sun Peak
Out
Dorms 10 24 25 17 18 20 18 20
Library 191 199 100 100 100 100 100 100
Theater 190 190 205 205 275 275 275 275
Athletic Center 26 23 18 26 11 9 15 12
Winery - - 163 77 196 92 - -
Restaurant 169 123 182 169 137 121 175 143
Hotel 20 30 28 24 22 27 24 21
Total (veh/hr) 606 589 721 618 759 644 607 571
Traffic was forecasted in
conjunction with the Institute
of Transportation Engineers
Trip Generation Manual, 8th
edition, and further adjusted to
match realistic expectations of
trip generation. Trips were
distributed onto our network
using TransCAD and gravity
distribution models.
The additional traffic generated by the mixed use site was added
to existing traffic volumes. The overall geometry of the network
was modelled in SYNCHRO 6 and SimTraffic. This method
provides Level of Service (LOS) for both individual lane groups
and each intersection overall. Level of Service measures how well
an intersection operates, and is expressed as a letter grade from A
to F. The final combination of design alternatives is the only
solution that achieves LOS C (desirable) or LOS D (acceptable) for
the worst case condition: Saturday PM Peak Hour.
IntersectionLOS at Estimated
Time of
Completion (ETC)
LOS 30 years after
ETC
Washington Avenue and Fuller Road
Existing Signalized
IntersectionF F
Realignment and Grade
Separation of Washington Ave
Over Two Lane RoundaboutC D
Fuller Road and Tricentennial Drive
One-Lane Roundabout
with Slip RampB C
New Signalized
IntersectionE F
Supernova Lane (new site access)
Right Turn Only LanesA A
A list of feasible alternatives were considered and analyzed for
their ability to meet this project’s objectives. A summary of key
features is shown below. Design choices are bolded.
Washington Avenue and Fuller Road1. The null alternative would result in continued deterioration of
the intersection's functionality.
2. Improving the existing signalized intersection, even with
construction of additional lanes, would not sufficiently improve
traffic operations.
3. Realigning Washington Avenue would allow for successful
construction of a two-lane roundabout. A four-lane bridge
spanning over this roundabout would remove eastbound
and westbound through traffic on Washington Avenue. This
alternative improves overall level of service, reduces conflicting
lane movements, and decreases emissions by reducing the
amount of idling cars.
Fuller Road and Supernova Lane1. Supernova Lane, a new construction that provides access to
the site, will be restricted to right turns in and out.
Disallowing left turns reduces conflict and improves traffic flow.
This alternative will allow for free flow of traffic at the estimated
time of completion, as well as 30 years into the future.
2. A new signalized intersection was considered, but is unnecessary
as it is more expensive to construct.
Fuller Road and Tricentennial Drive1. The existing one-lane roundabout experiences a large
southbound right turn movement, which reduces the efficiency
of its operation.
2. A slip ramp on Fuller Road allows vehicles coming
southbound to turn right onto Tricentennial Drive, without
entering the roundabout.
3. A new signalized intersection would result in an unacceptable
amount of delay per vehicle, and is more expensive to construct.
Overall cost estimation of project: $18.1 million
Intersections
Fuller
Ro
ad
Supernova Lane
Fuller
Ro
ad