case study biomass_final
TRANSCRIPT
![Page 1: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/1.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 1
INDEX
1. INTRODUCTION 1.1.1. National electricity policy 2002………………………………………………..2
1.2. Achievement………...…………………………………………………….………3
1.3Installation cost…………………………………………………………………….3
2. Case Study: Biomass power Project in Andhra Pradesh 2.1 Overview………………………………………………………………………… 4
2.2 Factors influencing the programme ……………………………………………..4
2.3 Fuel procurement …………………………………………………………………4
2.4 Fuel processing/preparation……………………………………………………….5
2.5 Investment ……………………………………………………………………….5
2.6 Parameters of main equipment …………………………………………………5
2.7 Problems and constraints ………………………………………………………..6
2.8 Power generation. …………………………………………………………………6
3. Case Study: Biomass based Power Project at Kothara, Gujarat 3.1 The demonstration project: Blazing a new trail …………………………………..8
3.2 Tree species ……………………………………………………………………….8
3.3 Cost break-up ……………………………………………………………………..8
3.4 Location …………………………………………………………………………...8
3.5 Capacity details …………………………………………………………………...9
3.6 Power from a Mad Tree……………………………………………………………9
3.7 Learning and experience ………………………………………………………...10
4. Case study: Kasai Village electrification with 100% biomass 4.1 Location………………………………………………………………………….11
4.2 Participation of the local community…………………………………………….11
4.3 Village Energy Committee……………………………………………………….11
4.4 Project execution and capacity building …………………………………………11
4.5 End-users and benefits of the project…………………………………………….11
5. Case study: Energy recovery from urban wastes in India 5.1 Potential for urban waste ………………………………………………………..12
5.2 Municipal solid-waste based power project at Hyderabad …………………….12
5.3 Process of pelletization ………………………………………………………….13
5.4 Phase II – 6.6 MW power project………………………………………………...13
5.5 Design of the boiler………………………………………………………………13
References……………………………………………………………………..14
![Page 2: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/2.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 2
BIOMASS AS A RENEWABLE ENERGY SOURCE IN INDIA
1. INTRODUCTION
Biomass has always been an important energy source in India. Although, the energy
scenario in India today indicates a growing dependence on the conventional forms of
energy, about 32% of the total primary energy use in the country is still derived from
biomass and more than 70% of the country’s population depends upon it for its energy
needs.
The Government of India, through its Ministry of Non-conventional Energy Sources
(MNES), has been aware of the potential and role of biomass energy in the Indian context
and, hence, has initiated a number of programmes for promotion of modern technologies
for its use in various sectors of the economy to ensure derivation of maximum benefits.
Biomass power generation in India is an industry that attracts investments of over Rs.600
crores ever y year, generating more than 5000 million units of electricity and yearly
employment of more than 10 million man-days in the rural areas. The three main
technologies being promoted by the MNES for productive utilization of biomass are
bagasse-based cogeneration in sugar mills, biomass power generation, and biomass-
gasification for thermal and electrical applications.
The Government of India has a well-framed national policy with objectives to promote
biomass power generation systems. Requisite clauses are inserted in the Electricity Act,
2003.
There is an installed capacity of 302 MW through biomass gasification and 437 MW
through cogeneration till March 2005. Case studies of a few of the installed plants are
collected and analyzed to consolidate the value of learning and experience.
1.1.1. National electricity policy 2005
a) The National Electricity Policy aims at achieving the following objectives:
b) Access to Electricity – available for all households in the next five years,
c) Availability of power – demand to be fully met by 2012. Energy and peaking
shortages to be overcome and spinning reserve to be available,
d) Supply of reliable and quality power of specific standards in an efficient manner and
at reasonable rates,
e) Per capita availability of electricity to be increased to over 1000 units by 2012,
f) Minimum lifeline consumption of 1 unit/household/day as a merit good by 2012,
![Page 3: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/3.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 3
g) Financial turnaround and commercial viability of electricity sector, and
h) Protection of consumers’ interests.
1.2. Achievements
A power-generation capacity of about 302 MW has been commissioned through 54 projects,
as on March 2005. A further capacity addition of about 270 MW through 39 projects is
reported to be under implementation. The biomass materials that have been used for power
generation in these projects include rice husk, cotton stalk, mustard stalk, Prosopis juliflora
(Vilayati babul), poultry litter, bagasse, cane trash, etc. State-wise distribution of the
commissioned plants and the plants under implementation is given in Table 1 below (as on 31
March, 2005). :
Table 1 Details of power projects commissioned and under implementation
State Commissioned capacity Under implementation capacity
No. of projects (MW) No. of projects (MW)
Andhra Pradesh 37 194.2 11 70.25
Chhatisgarh 2 11.0 5 51
Gujrat 1 0.5 - -
Haryana 1 4 - -
Karnataka 5 36 11 61
Madhya Pradesh 1 1 - -
Maharashtra 1 3.5 1 6
Punjab 1 10 1 6
Rajasthan 1 7.8 4 29.10
Tamilnadu 4 34.5 6 48.50
Uttarpradesh - - - -
Total 54 302.5 39 271.85
Source: Booklets on Renewable Energy - No.2 ‘Biomass” published by Ministry of Non-
conventional Energy Sources, Government of India
1.3 Installation cost
The typical capital cost for biomass power projects range from Rs.3.00 crores/MW to Rs.4.00
crores/MW. The cost of generation depends upon the cost of biomass, the plant load factor,
and the efficiency of the conversion.
![Page 4: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/4.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 4
2. Case Study: Biomass power Project in Andhra Pradesh
2.1 Overview
This case study is about a multi-biomass based on direct combustion grid-connected power
plant using steam turbine. Biomass based power projects are promoted in Andhra Pradesh by
Ministry of Non- Conventional Energy Sources (MNES), Non-Conventional Energy
Development Agency (NEDA) and Government of Andhra Pradesh. The first project was
commissioned in 1996 and most of the plants are established in 2001. The present installed
capacity in the State is 206 MW. The typical size of the plants is 6 MW. In ever y district of
the State, these plants are in operation.
2.2 Factors influencing the programme
The State has a favorable tariff regime. The third-party sale is permitted. There are lower
wheeling charges and availability of multiple biomass is abundant. Later the regulator has
prohibited the third-party sale, but allowed the MNES tariff rate from the year 2000. The tariff
was revised to Rs.2.88 per kWh in place of Rs.3.46. Again the rate was enhanced to Rs.3.18
from Rs.2.88 with the intervention of court. The Plant Load Factory (PLF) was pegged to
80%. Due to these factors there was a loss of interest for developers to set up new plants. The
project was commenced in June 2000 and completed by December 2001.
2.3 Fuel procurement
Different types of biomass was utilized and the procurement methods are as follows:
a) Rice husk from rice mills
b) Bagasse from sugar plants
c) Jute stick from farmers
d) Casuarinas trees from Agro-Farming
e) Cotton and red gram stalks from farmers
f) Woody biomass from farmers
g) Groundnut shell from oil mills
h) Jute waste from jute mills
The plant was installed by Varun Power Projects (P) Ltd. The capacity of the plant was 6 MW.
The project is first of its kind without much industrial experience. The plant is located at
Chilakapalem, at Srikakulam District in Andhra Pradesh.
The selection of appropriate location is done with the following criteria:
![Page 5: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/5.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 5
a) Ensuring the availability of biomass resources, in surplus
b) Only one plant in the district
c) Adequate availability of ground water resources
d) Location of the plant adjacent to the existing grid of 132 KV sub-station
e) Location of the site on the National Highway connecting Howrah, Chennai
f) Ensured logistic requirement, including biomass mobilization
2.4 Fuel processing/preparation
Only rice husk was fired as it is without processing. All wood biomass was chipped in to
smaller pieces using chipping machine. Bushy wastes like stalks are cut into small pieces
using biomass shredder.
2.5 Investment
The project is set up at a total cost of Rs.2440 lakhs including land, buildings, plant and
machinery and fixed deposit collected by IREDA Means of finance:
Term Loan Rs. 1827 lakhs
Equity Rs. 613 lakhs
The project was funded by IREDA. Subsequently due to increase in the cost of biomass fuel,
reduction in tariff, the company shifted the loan to a commercial bank to reduce the interest
cost.
Equipment packages:
a) Turbo generator and auxiliaries
b) Boiler and Auxiliaries
c) Fuel handling system
d) Cooling water circulation system
e) Ash handling system
f) Compressed Air System
g) RO/DM Water treatment system
h) Air conditioning and Ventilation
i) Fire protection
j) Power evacuation and auxiliary power distribution system
k) Controls and instrumentation
l) Civil and structural works
2.6 Parameters of main equipment
![Page 6: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/6.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 6
a) Boiler configuration is as follows.
b) 495 Deg.C, 65 kg /cm - 27 TPH Travelling grate fired boiler 2
c) Turbine configuration is given bellow.
d) 495 Deg. C, 65 kg /cm - fully condensing type – 9000 rpm machine
2.7 Problems and constraints
a) New kind of industry and market
b) Fuel processing.
c) Continuous and constant fuel feeding rate
d) Fuel required, size of the fuel to feed is up to a maximum of 20 mm.
e) Woody and bushy biomass is needed to be processed for required size
f) Because of volumes in nature, low bulk density procurement of biomass to the site
adds high overhead expenses
g) Biomass ash is highly alkaline in nature. It r enquires frequent cleaning and
maintenance of the tubes.
h) Being grid connected to rural sub-stations, occurring of high grid fluctuation, it
demands continuous attention.
i) High moisture content of the fuel results in low boiler efficiency
j) Frequently reducing and varying tariff rate maintains high PLF
k) PLF has been pegged to 80%
2.8 Power generation.
The unit operates at more than 80% of PLF. The average power generation rate, over a period
of three years, is 438 lakhs of unit per annum. 1.1 kg of biomass per kWh, is considered as
base for tariff calculation. The details of power generation are provided in the following table
2:
Table 2 Details of power generation
Sl. No Year Units generated in lakhs
1 2002-2003 428
2 2003-2004 471
3 2004-2005 415
4 Average 438
*The average PLF (Plant Load Factor) is 83 .3%
![Page 7: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/7.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 7
A view of the Biomass storage and conveyer system of the biomass power plant in
Andhra Pradesh
![Page 8: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/8.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 8
3. Case Study: Biomass based Power Project at Kothara, Gujarat
3.1 The demonstration project: Blazing a new trail
The Gujarat Energy Development Authority (GEDA) took up Energy Plantation Programmes
in the wastelands of Kuch in a major way since the early 1980s. These programmes are multi-
dimensional in nature with linkages to energy supply, food and fodder, soil regeneration,
ecological development and local employment generation.
3.2 Tree species
The tree species for plantation were Acacia nilotica, Prosopis juliflora, Acacia tortillas,
Eucalyptus, Subabul and Casurina. These are hardy specimens that can survive in harsh
climates, poor soils and minimal water conditions. At the same time, they are also able to
regenerate the soil. By their very name, energy plantations mean that they are grown for
cyclical harvesting whereby the trees, once they attain specific height, are cropped or coppiced
periodically for their biomass, a sustainable resource. Biomass yields from energy plantations
usually range from 4-8 tonnes per ha per year. GEDA’s energy plantations in district Kuch
cover 1450 ha at different agro-climatic locations in villages Moti Sindhodi, Lathedi, Vingabe
and Kosha in taluka Abdasa.
3.3 Cost break-up
The total project cost is Rs.200 lakhs, with plant and machinery at Rs.160 lakhs and civil work
at Rs.30 lakhs. The project objective is to feed a minimum of 500 kW electric power into the
grid at Kothara Sub-station. The salient features are as under in table 6.13
Table 6: Salient features
3.4 Location
When the proposal for a demonstration power project was mooted, village Kothara was
selected as the project site from among two other sites, Moti Sindhodi and Nalia, for the
![Page 9: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/9.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 9
various advantages it offered. Biomass feedstock comes here f rom the Kuch Energy
Plantation sites. The project has a status of a National Demonstration Project with a significant
R&D component.
The Kothara Biomass Power Plant is located in village Kothara, taluka Abdasa, district Kuch.
Kothara is 80 km from Bhuj, the district headquarters, and at a distance of 1.2 km from the
GEB gridline of Kothara’s 66 Sub-station. This closeness to the gridline is one of the most
critical plus points for the selection of Kothara site since grid connectivity
costs were eliminated and the project investment based on a preliminary survey came down
drastically. The analysis also brought down the transmission costs considerably since T & D
losses were very low. The recurring expenditure also dropped considerably. Kothara is located
at a distance of average 20 km from each of the GEDA Energy Plantation sites at Moti
Sindhodi, Lathedi and Kosha. This reduces transportation costs of the feedstock to the power
plant site. The database generated will help study the techno-economic feasibility of large
capacity biomass-based generation on grid parallel operation with GEB. Kothara was also
selected because the load at the GEB Sub-station at Kothara was the minimum amongst the
other sub-stations in the taluka, and it allowed easy and more viable grid connectivity.
The fact that the land for the Power Plant was available on easy terms very near the Sub-
station (1.2 km) also considerably reduced the cost of the transmission line installation for the
project and therefore, made Kothara an attractive proposition.
3.5 Capacity details
The demonstration plant is equipped with a single unit of 500 kW gasifier. It has state-of-the
art electrical including control panels, transformer, synchronizing equipment with complete
safety systems for grid paralleling. The plant is equipped with extensive instrumentation, data
logging and laboratory materials. It is the first such project in the country and will prove
conclusively that if such projects are set up in appropriate locations with proper organizational
infrastructure, rural areas can benefit from them on a long-term basis.
3.6 Power from a Mad Tree
Prosopis juliflora or gando bawal (the mad tree) was introduced in Kuch in the 1950s and
1960s to check the spread of the Little Rann of Kuch. Now the problem is the thorny tree’s
unrestricted spread in the shrinking pasturelands of Banni, which is losing its pastures at the
rate of 2673 ha per year to the gando bawal, as data from Indian Remote Sensing Satellites has
shown. The gando bawal is a highly aggressive tree. It coppices well – annual average growth
![Page 10: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/10.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 10
has been recorded to be up to 3-5 meters. It thrives in difficult physical conditions, and due to
its ability to strike root and flourish in highly degraded soils.
3.7 Learning and experience
a. Due to several reasons, the project did not sustain:
b. Collection and transportation of thorny biomass from a large geographical area,
c. Poor quality of the local grid,
d. Constrains due to dual-fuel mode, particularly 30% of the diesel cost and certain
logical problems of organizing it to the site,
e. Miss-match of the existing load and installed capacity.
It is, therefore, proposed to go for a 100% gasifier based power generation system and to
improve the quality of the grid.
![Page 11: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/11.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 11
4. Case study: Kasai Village electrification with 100% biomass
4.1 Location
Kasai is a remote tribal village in the Betul District of Madhya Pradesh in India. In Madhya
Pradesh, eleven such villages were selected to electrif y using biomass gasifier system under
the electrification programme of the Ministry of Non-conventional Energy Sources (MNES).
4.2 Participation of the local community
a. Participation of the local community was ensured after detailed group discussions at
the initial stages of the project.
b. Active participation is essential for wood collection and day-to-day operation and
maintenance of the system.
c. Community participation in overall system management.
4.3 Village Energy Committee
a. A Committee comprising 11 members (of which five women) were constituted.
b. A village energy fund was created by contribution from all the users.
c. A sum of Rs.120/- per month per household was collected to meet the expenditure on
operation and maintenance of the system.
d. A Village Energy Committee (VEC) was set up by the Gram Panchayat.
e. The VEC was responsible for operation and maintenance of the system.
f. Fixation and collection of user charges and overall management.
4.4 Project execution and capacity building
A 10 kWe 100% biomass based power generation project was executed in May 2005 and
commissioned within two months by the local Forestry Department.
4.5 End-users and benefits of the project
a. Lighting of households, school, and streets.
b. Bring music systems and television into the village for entertainment.
c. 10 ha of land around the village is planted with fast growth species to ensure
sustainable biomass supply.
d. Oil expellers to produce bio-oil from Jatroppha seeds is under planning stage.
e. Flour mill, water pump, milk chilling units is also being planned.
![Page 12: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/12.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 12
5. Case study: Energy recovery from urban wastes in India
5.1 Potential for urban waste
India’s population as per census 2001 is 1027 million, of which 285.35 million reside in 5161
urban areas. It constitutes 27.8% of the total population of the country.
The problem of urban waste management is notable for only because of large quantities of
waste involved, but also due to its spatial spread across 5161 urban local bodies, and the
enormity and variety of problems faced in setting up of systems for collection, transportation,
and disposal of waste. According to a recent estimate, about 42 MT (million tonnes) of solid
waste (1.15 lakh tonnes per day) and 6000 million cubic meter of liquid waste are generated
every year by our urban population. The composition of the urban waste in given in table 10
below:
Table 10: Composition of urban waste
This translates into a potential for generation of over 1700 MW of power from urban waste in
the country.
5.2 Municipal solid-waste based power project at Hyderabad
A waste-to-energy plant was taken by M/s SIL (Selco International Ltd) in 1999 based on the
RDF (refuse derived fuel) technology, for production of RDF pellets, which can be used as an
alternative to coal for energy production. While a project for production of RDF pellets was
taken in 1999 as Phase I of the project, the second phase of the project for utilization of RDF
for generation of power was completed in November 2003. The total cost of the project is
about Rs.43.50 crores. The plant was commissioned in November 2003, and has been
operational since then with maintenance shutdown for 1-3 days per month.
Phase I (Pelletization project)
This plant is located next to the Gandhamguda municipal waste dump, which receives 1300
MT of garbage every day from Hyderabad city. The installed capacity of the plant is 1000
TPD (tonnes per day), and it has the capacity to produce 200-250 TPD of fuel pellets. The
calorific value of fuel pellets produced in the first phase was of the order of 3000 kcal/kg
(kilocalories per kilogram), and pellets were reported as having ash content
![Page 13: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/13.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 13
of less than 10%. Technology for production of RDF and fuel pellets from MSW was obtained
from TIFAC (Technology Information Forecasting and Assessment Council) and DST
(Department of Science and Technology). SIL is processing about 500 MT of MSW for
production of about 150 TPD of RDF fluff.
5.3Process of pelletization
a. Solar drying yard: a rotary dryer fired with MSW has also been installed for drying of
MSW, especially during monsoon, to improve removal of inerts.
b. Manual segregation of large objects.
c. Sieving for removal of grit and soil.
d. Air classification: this equipment aids the removal of heavy components such as bricks
and stones.
e. Size reduction: by shredding large pieces of biomass and other organic waste
f. Screening: final screening for removal of more soil and grit.
5.4Phase II – 6.6 MW power project
The salient features of the project and its performance are as follows:
5.4.1Feeding mechanism
The fuel is spread from side of the boiler. The rotary spreaders and its blades are designed to
suit the RDF spreading. The drag-chain conveyor is also specially designed for conveying the
RDF. Second conveyor with half an hour storage silo and three screw feeders with variable
frequency drives has also been installed as a standby fuel-feeding system.
5.5 Design of the boiler
The special design features are as follows:
a) The boiler tubes are protected with special alloy coating. This alloy has a high thermal
conductivity and protects the boiler tubes from corrosion and erosion.
b) This was also filed for an Indian patent.
c) Secondary air is pre-heated and sent into the boiler at various points for proper burning
of RDF.
d) Air-cooled condenser has been employed in place of conventional water-cooled
condenser.
e) The initial ash fusion starts at a temperature of 860 ºC, hence low- furnace temperature
has to be maintained, and the boiler is designed accordingly to prevent clinker
![Page 14: Case Study Biomass_FINAL](https://reader031.vdocument.in/reader031/viewer/2022020115/542adc60219acd87798b4916/html5/thumbnails/14.jpg)
CASE STUDY: BIOMASS IN INDIA 2011
Page 14
formation.
References:
1. http://powermin.nic.in/rural_electrification/definition_village_electrification.htm
2. Mr. A Mohan Reddy, Zenith Corporate Services, Hyderabad, at One-day Business
Meet on Biomass Energy and Co-generation (Non-Bagasse) Projects for Industries on
22.12.05 organised by Haryana Renewable Energy Development Agency.
3. NH Ravindranath, HI Somashekar, S Dasappa and CN Jayasheela Reddy 2004 on
Sustainable biomass power for rural India: Case Study of biomass gasifier for village
electrification – a Special Section of S&T to rural areas.
4. Gujarat Energy Development Agency (GEDA), Suraj Plaza-II, Sayajiganj, Vadodara-
390005, Ph:+91-265-363123, Fax:+91-265-363120, Email: [email protected]
5. Akshay Urja (an MNES publication), Vol.1, Issue 5 (Sep-Oct.2005)
6. ‘Biomass Gasifier illuminates Gosaba Island, Sundarbans’, published in Success Story
section in Akshay Urja, of Nov-Dec.05, Vol.I.
7. ‘Energy recovery from urban wastes in India’ by AK Dhussa, Director, MNES, in
Technology section in Akshay Urja, of Nov.-Dec.05, Vol.1 Issue