case study brighton pier 2012
TRANSCRIPT
© GTL Partnership Ltd • Tel +44 (0)1403 741 166
Client: The Noble Organisation, Gifford & CMP
Site: The Brighton Palace Pier – Boat Deck Replacement
Location: Brighton, East Sussex, United Kingdom
Project Description
Brighton Palace Pier is a Grade II listed
building that opened in 1899. The pier stem
and head total approximately 540m in
length and the pier head itself comprises
structure from three distinct time periods.
The central core comprises Victorian cast
iron piles. To the north east corner is an
area known as the boat deck built in the
1930’s. In the mid 1990’s the pier head was
extended with new structure that
surrounded the original pier head. The 36
piles to the 1930’s boat deck are rolled steel
joists. Interestingly GTL’s initial involvement
came from the fact that the original
Victorian piles were screw piles.
GTL were commissioned to design, supply
and install a piling solution for the boat deck
replacement project. The clients engineer
had originally planned to utilise helical piles,
however, GTL were able to provide an
alternative unique solution that would
ensure buildability and provide cost savings
to the client. The new solution had never
before been used in this environment and
under such constraints anywhere in the UK.
Specific working restrictions made this
particular project a challenge. The Pier itself
is a commercially operating pier that
attracts large numbers of public visitors. The
design was developed to negate the need
for access / working from the sea to reduce
any potential delay due to poor weather and
also mitigate potential health and safety
hazards.
A structural working platform was constructed
below the pier deck to enable access to install
the piles. This obviously created working
height, logistical and load restrictions;
therefore, the piles were designed in
manageable sections.
Geotechnical Ground Conditions
GTL, in partnership with Whitworth Peck,
reviewed the available soils data which
revealed that the site was underlain by thin
seabed gravels overlying Upper Chalk. The
chalk was typically described as a very
weak/weak low and medium density chalk.
On this basis, GTL treated the chalk
encountered as “rock chalk”
Pile Design
The scheme required 24 bearing piles each
consisting of a 406.4mm x 20mm thick
circular hollow section installed in conjunction
with a limited access segmental auger.
© GTL Partnership Ltd • Tel +44 (0)1403 741 166
Compression loads varied, peaking at
1,300kN. In addition, there were significant
shear and moment loads, with some minor
tension loads.
The working platform was positioned 10m
above the seabed and only 5m below the
pier deck. The first pile section, 5m long,
was placed within a specially designed piling
gate and suspended above the sea while the
other sections were connected via a flanged
connection and lowered through the piling
gate. This process was repeated until there
was sufficient pile length to transfer the load
from the working platform to the seabed.
The CHS pile was then rotated into the chalk
bed with a rotary piling rig to a depth of 5m.
Additional sections were then added to
achieve the designed embedment of the CHS
pile. The centre of the CHS was then drilled
out by a segmental auger piling rig and the
pile was progressed to 15m design depth. The
pile shaft was then grouted and the centre of
the pile was reinforced with an Ischebeck bar.
Acknowledgements
Senior Management
Gavin Rixon – Project Director
Barnaby Tanner – Commercial Director
John Whitworth – Geotechnical Consultant
Karsten Richter – Lead Design Engineer
Mark Stacey – Construction Manager
Thanks to all of Mark’s team who worked
under extremely challenging conditions and in
harsh weather to deliver a successful project,
one that GTL is rightly proud of.
GTL used Oasys software in particular ALP
(Analysis of Laterally Loaded Piles) to predict
the pressures, horizontal movements, shear
forces and bending moments induced in the
pile when subjected to lateral loads, bending
moments and imposed soil displacements.
Associated Articles
http://www.ramboll.co.uk/projects/viewproject?pr
ojectid=4725E946-5B12-4A39-A692-EF5E8D937CEF