castle village report

Upload: marshall-bravestar

Post on 04-Jun-2018

257 views

Category:

Documents


3 download

TRANSCRIPT

  • 8/13/2019 Castle Village Report

    1/41

    Castle Village

    Retaining Wall Collapse

    April 2007

    Board of Inquiry Report

  • 8/13/2019 Castle Village Report

    2/41

    ChairpersonLeslie Torres, Esq. Assistant Commissioner for Enforcement

    Vice-Chairperson

    Christopher Santulli, P.E. Borough Commissioner, Manhattan

    Members

    Dan Eschenasy, P.E. Deputy Assistant Commissioner for Safety and Emergency Operations

    Robert LiMandri First Deputy Commissioner

    Lisa Orrantia, Esq. Assistant General Counsel

    Mark Sanabria Executive Director, Office of Internal Audits and Discipline

    Manher Shah, P.E. Executive Engineer

    Russell Steinberg, Esq. Supervising Attorney, Office of Internal Audits and Discipline

    Basil Szpylka, R.A. Deputy Borough Commissioner, Queens

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    3/41

    Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

    Principal Companies and Individuals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

    Background on Castle Village and the Retaining Wall. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

    Mueser Rutlege Study Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    URS Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    Findings/Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

    Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

    Endnotes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

    Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

    Summary of Testimony . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

    Documents Received. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

    TABLE OF CONTENTS

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    4/41

    On Thursday, May 12, 2005, at approximately 4:00p.m., a portionof a 65 foot high stone retaining wall on the side of a bluffrising above the Hudson River just north of the GeorgeWashington Bridge suddenly collapsed. Minutes later a second

    larger collapse followed. A 150 foot section of the 800 foot longwall now covered portions of the Henry Hudson Parkway andRiverside Drive, a number of parked cars, and the adjacentsidewalk. The wall is owned by Castle Village Owners Corporation,a five building, 575 unit co-operative housing complex locatedon the top of the hill behind the wall. The collapse causedmassive delays on the Henry Hudson Parkway and surroundingroads. Fortunately, there were no deaths or even injuries.

    Because of the magnitude of the collapse and because its causewas not readily apparent, Commissioner Patricia J. Lancaster,FAIA, of the New York City Department of Buildings, conveneda Board of Inquiry on May 24, 2005. The Board of Inquiry was

    charged with conducting an independent investigation into thepossible causes of the walls sudden collapse, with gathering theevidence the Board needed to make its findings, and with makingrecommendations to the Commissioner to prevent similaroccurrences in the future.

    The Board interviewed numerous individuals, including themembers of Castle Villages Board of Directors; CastleVillages property manager Frank Nadal; engineers employedby Castle Villages consultant, Langan Engineering; and variouseyewitnesses. The Board reviewed numerous documentssubmitted by Castle Village and Langan that set forth the history

    and maintenance of the wall since 1985, when Castle Villagebecame a co-operative housing corporation. Members of theBoard also visited the collapse site. The Board also retained twoengineering firms, United Research Services (URS) and MueserRutledge Consulting Engineers (Mueser), to assist it inconducting the investigation.

    URS found that the most likely cause of the collapse of theretaining wall was structural failure resulting from an increasedpressure that developed behind the wall due to the build up ofgroundwater throughout the years. The Board concurs in thisfinding. Neither of the two documented repairs that Castle

    Village undertook at the recommendation of engineeringconsultants was sufficient to address the destabilization posedby the increased pressure. First, in 1985 when the wall shifted and a bulge occurred, Mueser Rutledge was hiredby Castle Village to recommend and oversee a repair. The Board finds that while this repair (installation of wallanchors and bolts) may have addressed the localized issue, it did not address the groundwater pressure build up.The second construction work occurred in 2004 when Castle Village accepted Langan Engineerings first phasedesign for installation of a new surface drainage system in the yard at the top of the wall. The Board finds thatwhile this surface drainage system failed, this failure did not have a significant adverse effect on the wall.

    EXECUTIVE SUMMARY

    A view of pre-collapsed section looking down onRiverside Drive and Henry Hudson Parkway North.

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    View of bowing wall on May 12, 2005.

  • 8/13/2019 Castle Village Report

    5/41

    The infiltration and pressure posed by the groundwater were fargreater than this surface drainage system would have divertedeven had it worked as intended.

    Effective repair and maintenance is critical to structural stability

    of all retaining walls. The wall had been a major matter ofconcern to Castle Villages Board of Directors since theapartment complex became a co-operative in 1985. Repeatedinspections and investigations showed cracking and wallmovement, bulging of sections of the wall, stones falling fromthe wall, tilting of the balusters at the top of the wall, andvoids and sinkholes in the park located at the top of the hill beingheld up by the wall. In 2002, Castle Village hired LanganEngineering to monitor the wall. Langan told Castle Village ina report dated January 6, 2003 that portions of the wall werebulging and were moving toward the west, away from the hill thatthe wall was holding back.

    While Castle Village solicited 15 different reports from variousengineering firms during the 20 years before the collapse toevaluate and study the walls many problems, it did not performany substantial work after the 1985 repair except for theinstallation of the failed drainage system in 2004. The Boardfinds that these efforts do not constitute effective repair andmaintenance.

    Further, when sinkholes and voids reappeared behind the wall inearly 2005 and Castle Village learned the new drainage systeminstalled the previous summer had not arrested the wallsdecline, the co-operative failed to take effective action. On April13, 2005, Langan informed Castle Village that the upper sectionof the wall had further destabilized by moving up to seven incheswestward during the previous eight months and that this sectionof the wall was critical. Langan wrote Frank Nadal, CastleVillages property manager:

    Our judgment is that there probably is ongoing deep seatedglobal movement of an approximately 50 ft section of theretaining wall. This critical section (i.e., cracks reopening andlarge sinkholes within the terrace) requires immediate attention;we recommend installing a restraining system to stabilize thiscritical section.1

    Nevertheless in the following month, as the wall continued todeteriorate, neither Langan nor Castle Village took effectiveemergency action. Even on May 4, 2005, eight days before the

    collapse, when Langans monitoring points indicated that parts of the wall had moved an additional nine inchessince April, no emergency was declared. While this information and Langans conclusion set forth in its April 13letter that the wall needed immediate bracing warranted a sense of urgency, Langan did not notify theDepartment of Buildings of the existence of an imminent threat to public safety. While it is true that a few days

    EXECUTIVE SUMMARY

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    2002 picture shows curvature of wall.

    Cracks in re-pointed mortar on January 26, 2002.

    Sink hole surrounding drainage catch basin onApril 19, 2005.

  • 8/13/2019 Castle Village Report

    6/41

    before the collapse Urban Foundations, a Castle Village contractor, hired an expediter to approach theDepartment of Transportation for permission to close a lane of Riverside Drive so that the wall could be braced,Langan and Castle Village appeared to treat the situation as an ordinary problem, one that could be dealt within the ordinary course of business. When the Department of Transportation asked for an engineering report to

    justify the lane closure, Langan wrote that the 70 ft high stone wall is exhibiting distress due to lateralmovement. This language was insufficient to put the Department of Transportation on notice that failure of thewall might be imminent. Neither Langan, Castle Village, nor any of its agents acted with a sense of urgency orgave an indication that public safety was at risk. They simply went through the normal permitting process.

    On the morning of the collapse, when Langan visited the site to address Castle Villages mounting concerns, anengineer from Langan told Castle Village to tie the leaning concrete balustrade columns to some trees to preventthem from toppling off onto the sidewalk and roadway below. This demonstrated that Langan and Castle Villageboth knew there was an imminent threat to public safety. They again failed to implement adequate safetymeasures to protect the public from the rapidly deteriorating situation, in this instance evidenced by both theleaning balusters and by the walls precipitous westward movement over the previous weeks.

    Castle Village had a non-delegable duty under the New York City Building Code to maintain the wall in a safe

    condition. It failed to do so. Castle Villages manager Frank Nadal; Nadals employer Goodstein ManagementInc.; and Langan Engineering all failed to properly address the seriousness of the situation in April and May 2005when they knew that significant changes had taken place after sinkholes and sidewalk joints re-opened andsections of the wall accelerated their westward movement. The Board finds that Castle Village and its agentsNadal, Goodstein Management and Langan all failed to notify the City of the obvious and imminent threat topublic safety posed by the walls extremely deteriorated condition.

    In early May, when Langans monitors showed that a section of the wall had moved almost two feet westwardsince 2002, Langan still took no effective emergency measures and failed to notify the Buildings Department.Two feet of movement of the upper section of the wallapproximately nine inches between April 11 and May 4is significant. URS has calculated that the factor of safety for the pre-collapse May 2005 geometry of the wall isapproximately 1.0 or less than 1.0. As the factor of safety approaches 1.0 or less, failure occurs. The Board findsthat Langan should have known this portion of the wall had dramatically destabilized and that the wall was atrisk of imminent failure.

    As a result of its investigation, the Board recommends the following actions to the Commissioner of Buildings:

    1) The New York State Education Department licenses and oversees professional engineers.George Derrick and Gregory Biesiadecki, the engineers from Langan who worked on the CastleVillage project who were aware of the walls movement and condition in March andApril 2005, should be referred to the New York State Education Departments Officeof Professional Discipline for consideration of any appropriate disciplinary action basedon their failure to exercise a reasonable standard of care and their failure to alert theDepartment of Buildings that the movement of the wall in the Spring of 2005 hadaccelerated and that this presented a danger to the public.

    2) The Department of Buildings does not license engineers; however it does afford engineersprivileges that may be revoked. Title 1, 21-02, of the Rules of the City of New York allowsthe Department of Buildings to revoke a Professional Engineers right to professionallycertify that his or her submissions are code and zoning compliant. George Derrick and GregoryBiesiadecki, the engineers from Langan who worked on the Castle Village project, shouldbe referred to the Buildings Special Investigations Unit to determine whether proceedingsshould be commenced under the provisions of 21-02 based on their involvement in the project.

    EXECUTIVE SUMMARY

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    7/41

    3) Section 26-234 of the Administrative Code states that those engaged in building operationshave a duty to report dangerous or unsafe conditions to the Department of Buildings. CastleVillage; its managing agent Goodstein Management; Goodsteins employee Frank Nadal, theproperty manager; Langan Engineering; and Langan engineers George Derrick and Gregory

    Biesiadecki should each be cited with a New York City Environmental Control Board violation fortheir failure to comply with section 26-234 by bringing the dangerous condition of the wall tothe attention of the Department of Buildings.

    4) The Department of Buildings should propose legislation to require owners to engage a New YorkState licensed architect or engineer to perform periodic inspection of retaining walls thatfront a public way. A model for this type of regulation is Local Law 10 of 1980, as amendedby Local Law 11 of 1998, which sets forth a facade inspection/repair regulatory scheme forbuilding facades. The legislation would require a cyclical inspection report and a schedulefor any needed repair and maintenance to be filed with the Department of Buildings. Criteriafor the inspection and reporting process should include factors such as wall height, wallcomposition, and proximity to a public way.

    Furthermore, related to its investigation, the Board acknowledges the following prior actions on the part ofthe Department of Buildings:

    1) Pursuant to Section 26-235 or 26-243 of the Administrative Code, the Department ofBuildings issued an Emergency Declaration the day after the collapse stating that repairwork on the wall was to commence immediately in order to remedy the dangerous conditionand protect public safety.

    2) Castle Village Owners Corporation was ordered to permanently repair the collapsed portionof the retaining wall and permanently stabilize the remaining portion of the wall. Furthermore,the Department of Buildings monitored this process to ensure that all work conformed to theNYC Building Code, other applicable laws, rules, and regulations, and that all requisite permits

    were obtained to perform the necessary work.3) Castle Village Owners Corporation was ordered to monitor the movement of the retaining

    wall until it provides the Department of Buildings with a report from a professionalengineering firm certifying that the wall is safe.

    4) Sections 27-127 and 27-128 of the Building Code explicitly require an owner to maintain itsbuildings in a safe condition, and impose responsibility on the owner to do so. Castle Villagefailed to discharge this duty and was properly served with a notice of violation and found guiltyat the Environmental Control Board for its failure to maintain its property in a safe condition.

    EXECUTIVE SUMMARY

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    8/41

    The following is a list of the principal companies and individuals involved with the Castle Village retainingwall collapse and the investigation that followed.

    Castle Village Owners Corporation (Castle Village)A co-operative ownership association that owns the site and is responsible for the maintenance

    of the retaining wall.Goodstein Management, Inc. (Goodstein)A property management company that manages the Castle Village complex for the Castle VillageOwners Corporation.

    Frank Nadal, P.E.The property manager for the Castle Village complex and an employee of Goodstein Management.

    Langan Engineering & Environmental Services (Langan)An engineering firm that was retained by Castle Village to evaluate, inspect, makerecommendations about, and repair certain areas of the Castle Village grounds, drainage systems,and the retaining wall.

    George Derrick, P.E.A partner at Langan Engineering who was responsible for the Castle Village project and whoself-certified the application with the New York City Department of Buildings to performdrainage modifications at the Castle Village site in 2004.

    Gregory Biesiadecki, P.E.A project manager at Langan Engineering who supervised the work at the Castle Village site.

    New York City Department of Buildings (Buildings or the Department)Agency responsible for enforcing the Building Code and the Zoning Resolution. Buildingshas regulatory authority over retaining walls located within the property lines of private owners.

    Board of Inquiry (the Board)

    Entity convened by the Department of Buildings Commissioner Patricia J. Lancaster, FAIA.Responsible for investigating the cause of the collapse and for making recommendations regardinghow to prevent similar collapses.

    Mueser Rutledge Consulting Engineers (Mueser)Consultants retained by DOB to:1. Collect information on the construction of the wall;2. Collect information on inspections and repairs to the wall made prior to the collapse;3. Interview eyewitnesses to the collapse;4. Collect photographs taken by various parties prior to and after the collapse; and5. Prepare a report summarizing all the collected information

    United Research Services (URS)

    Engineering firm retained by Buildings to review Muesers findings and provide an analysisof the technical reasons for the walls collapse.

    PRINCIPAL COMPANIES AND INDIVIDUALS

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    9/41

    THE CASTLE VILLAGE RETAINING WALL

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    A. Construction of Castle Village and the Retaining Wall

    Castle Village is located in the historic Washington Heights section ofManhattan in an area bordered on the west by Riverside Drive and theHenry Hudson Parkway, to the south by West 181st Street, to the east

    by Cabrini Boulevard, and to the north by Alex Rose Place. Restingatop one of Manhattans highest points at 200 feet above sea level,Castle Villages seven acres include five apartment towers, a parkinggarage, and a large park that was supported by the retaining wallthat collapsed in 2005. This site is close to the original location ofFort Washington, built in 1776 along with Fort Lee in New Jersey, toprevent British troops from sailing up the Hudson River.

    In the 1880s, the Paterno family emigrated from Italy and settled inWashington Heights. John Paterno started a real estate business, andafter his death in 1899, his sons Charles and Joseph continued topurchase and develop real estate.2 The Paterno brothers were involvedin the construction of several apartment houses on the Upper WestSide of Manhattan.3 In 1905, Dr. Charles Paterno purchased the propertythat would eventually become the Castle Village site.4 He builta four-story castle on the property between 1905 and 1910.5 The castleserved as Dr. Paternos home and offered a panoramic view of theHudson River from its location high above what would later becomethe Henry Hudson Parkway.6 On the west side of the property, a stoneretaining wall that would eventually measure 800 feet long and65 feet high separated the castle from the street below.7

    Dr. Paterno purchased the adjacent property and constructed theHudson View Gardens co-operative housing complex in WashingtonHeights in 1924.8 Based on the success of Hudson View Gardens,

    Dr. Paterno demolished his castle and built Castle Village, whichconsisted of five fourteen-story residential towers with nineapartments on each floor.9 The architect was George Fred Pelham, Jr., and the buildings were some of the earliestapartment towers to employ reinforced concrete construction.10 In 1940, Castle Village received the certification ofexcellence in design for an apartment building from the New York Chapter of the American Institute of Architects.11

    The Castle Village complex was operated at first as rental apartments.12 It was converted into a co-operativeownership association in the 1980s.13 Presently, Goodstein Management manages the property for the CastleVillage Owners Corporation.

    The precise date when construction of the wall began and its original dimensions are unknown. Part of the wallappears to have been built when the original castle was constructed for Dr. Charles Paterno between 1905and 1910. A 1939 advertisement in the New York Herald Tribune for the Castle Village apartment complex

    described the wall on the westward side of the new apartment complex as 800 feet long, 65 feet high, and 25 feetthick at the base.14 Based on available records and research, it is likely that the wall was built in stages between1905 and the late 1930s. The available research also indicates that a tunnel was created within the wall, andthat a stone staircase providing access to the road below was built in the section of the wall that collapsed. 15

    This staircase was removed and filled in, most likely when the apartment complex was built in the 1930s.

    In 1927, Robert Moses proposed his West Side Improvement plan, which involved designing andconstructing the Henry Hudson Parkway.16 Construction of the Parkway began in 1933 and was completed in1937.17 It stretched from West 72nd Street in Manhattan to the Bronx-Westchester border and was built alongwith the Henry Hudson Bridge and Riverside Park.18

    Paterno Castle

    Castle Village complex

    Castle Village site

  • 8/13/2019 Castle Village Report

    10/41

    B. Castle Villages Evaluations of the Retaining Wall

    Retaining walls are structures that separate lower land areas from higher, retaining soil (backfill) that wouldotherwise collapse into a more natural shape. Common materials for retaining walls in New York City are stone,brick, and concrete. They may be reinforced by the use of ties, which are metal bars inserted through the wall

    that are usually anchored into rock or other material behind the wall. Retaining walls must be designed and builtto withstand the lateral pressure exerted by the backfill behind them, or they will eventually fail. Retaining wallsmade from stone must be maintained so that their strength is not weakened. Common maintenance issues forstone retaining walls are weakening by freeze-thaw cycles, tree roots or other vegetation growing in the wall, anddeterioration of any mortar holding stones in the wall together. Retaining walls usually have weepholes insertedthrough them which are designed to allow rain or ground water accumulating behind the wall to drain through,thereby preventing additional pressure from building up behind the wall. If the lateral pressure behind a wallis greater than the pressure that the wall was built to withstand, or if a retaining wall is weakened by weatheringor other forces so that its strength falls below the lateral pressure behind it, the wall is at risk of failing.

    The first available inspection records of the Castle Village retaining wall date back to 1985, the year thatCastle Village converted to a co-operative. At that time, Mueser Rutledge Consulting Engineers was hired

    by Castle Village to monitor the wall.19

    Concerns over the walls structural stability were expressed by Mueserand recommendations for repair were made and implemented.20 On November 4, 1985, Mueser prepareda report recommending rock anchoring and support repairs to the below grade tunnel.21 Rock anchors and

    bolts were installed on certain stones and repairswere made to the tunnels.22

    Inspections in the 1990s also cited problems withthe wall, including spalling, loose and displacedstones, deteriorating mortar, cracking, and leaks.23

    A physical condition survey conducted byAntonucci and Lawless Architects and Engineers,LLP in 1994 reported twelve to eighteen inchesof settlement in the park area behind the wall.24

    The settlement was caused either by the filling ofvoids left in the backfill during the originalconstruction, and/or by new or enlarged voidscreated by the walls westward movement.25 Fouryears later, a 1998 report by Cutsogeorge & ToomanArchitects, PC, indicated that approximately sixcubic feet of stone had spalled from the wall.26

    A sidewalk shed was erected to protect the public.27

    On July 3, 2002, Castle Village awarded a contractto Langan Engineering & Environmental Servicesto perform topographic surveying services

    and inspection services. The scope of the contractwas later expanded to include monitoringand evaluation of the retaining wall. Langan beganmonitoring the wall in November 2002. Langansinspection records cite wall cracks, water seepage,missing mortar, and fallen wall stones. To monitorthe movement, optical laser survey control pointswere installed along the length of the wall.28

    THE CASTLE VILLAGE RETAINING WALL

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    View of deformation in lower portion of wall on May 9, 2005.

    View of rock anchors and rock bolts installed in 1986.

  • 8/13/2019 Castle Village Report

    11/41

    In 2003 and 2004, the wall was the subject of a seriesof evaluations by Langan Engineering. During thisevaluation period, Langans monitoring pointsshowed that a portion of the wall was movingwestward away from the land it was holding back.Langan expressed concern with this section of thewall (the same section that ultimately collapsed).Langan developed a rating system of I to III,representing a spectrum of no immediate concernto critical level of concern. In a report dated

    January 6, 2003, Langan gave that portion of thewall an overall condition rating of II, meaning thatit showed moderate to heavy deterioration andpresented a possible stability or safety concernover the next twelve months.29 Langan gave theportion of the wall that did not collapse an overall

    condition rating of I, i.e. little to moderatedeterioration and an unlikely stability or safetyconcern during the following twelve months.30

    Frank Nadal of Goodstein Management, in hiscapacity as property manager for Castle Village,negotiated with Langan Engineering on behalfof Castle Village the scope of any wall repairs.31

    Langan recommended that Castle Village replacethe walls drainage system.32 Castle Village andFrank Nadal accepted Langans recommendationand approved the installation of the new drainagesystem on January 22, 2004.33 Langans engineersdesigned the new system.34 After a biddingprocess, Morris Park Contracting Corporation wasselected by Castle Village to perform the work.The drainage system was installed betweenSeptember and November of 2004.

    On April 5, 2005, Frank Nadal called Langan torequest that it restart survey monitoring of thewall after he noticed that sinkholes were againforming above it.35 On April 11, 2005, engineersfrom Langan inspected the wall. They observednew cracks in its lower portions, new sinkholes at

    the terrace level, and separation in the newlyinstalled sidewalks. On April 13, 2005, Langanprovided Castle Village with a memorandumthat recommended further stabilization andstated that a particular section of the wallrequired immediate attention. Bracing and wallrestraining system recommendations andsketches were also provided.36

    THE CASTLE VILLAGE RETAINING WALL

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    View of fallen rocks on May 9, 2005.

    View of a sinkhole next to the park sidewalk and fissures in the parksoil (both above the wall) created by the wall pulling away westwardon May 12, 2005 prior to the collapse.

    Measurement of 8 inch lateral displacement of sidewalks onMay 12, 2005 prior to the collapse.

  • 8/13/2019 Castle Village Report

    12/41

    THE CASTLE VILLAGE RETAINING WALL

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    Figure 1The above drawing representsa cross section of the Castle Villageretaining wall after construction.

    Figure 2The darker outline in this drawing showshow the Castle Village retaining wall hadmoved and the deformed shape it hadtaken in the months prior to its collapse.

    Figure 3This drawing shows the lower portionof the wall once the bulging front facehas been removed and illustrates howthe wall was in imminent danger ofcollapse without that support.

    Figures Not Drawn to Scale

    distance in feet

    25 20 15 10 5 0 25 20 15 10 5 0

    distance in feet

    25 20 15 10 5 0

    distance in feet

    wall withfront faceof lowerretaining wallcollapsed

    On April 14, 2005, Langan received authorization from Frank Nadal to prepare contract documents for therepair and rehabilitation of the retaining wall. Langan selected Urban Foundations Engineering to install

    raker braces at the base of the wall to stabilize it. Raker braces required a street closure permit from theNew York City Department of Transportation (DOT) because the rakers would have blocked a portionof Riverside Drive. On May 9, 2005, at the request of Urban Foundations, a firm Castle Village hired to assistwith obtaining a lane closing permit, Langan drafted a letter dated May 9, 2005 to DOT stating that the70 foot high wall is exhibiting distress37; however, DOT has no record of the receipt of this letter. An expediterhired by Urban Foundations did go to DOT on May 11 to obtain a street closing permit. 38 A site survey by DOTwas necessary and the DOT representative and Urban Foundations agreed to visit the site on May 13, twodays later, to conduct the survey.39

  • 8/13/2019 Castle Village Report

    13/41

    THE CASTLE VILLAGE RETAINING WALL

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    RETAINING WALL EVENTS APRIL - MAY 2005*

    Urban Foundationswent to DOT toobtain street

    closure permitand agreed

    to meet for thesurvey on May 13.

    Langan draftedletter to DOTrequesting

    a street closurepermit to install

    raker braces.

    5APRIL

    11APRIL

    13APRIL

    14APRIL

    9MAY

    11MAY

    12MAY

    At 4pm a section ofthe lower retaining

    wall collapsed

    followed by thecollapse of the

    160 foot sectionof the center ontoRiverside Drive andnorthbound HenryHudson Parkway.

    Langaninspected walland observednew cracks,

    sinkholes, andseparation in

    sidewalks.

    UrbanFoundationsEngineering

    to install rakerbraces at the

    base of the wallto stabilize it.

    Castle Villagerequested

    monitoring of

    the wall aftersinkholes were

    observed. Langan recommendedbracing and

    wall restraining system.

    Langan recommended furtherstabilization and stated that

    a particular section of the wall

    required immediate attention.

    Langanprepared

    documents forthe repair andrehabilitationof retaining

    wall.

    Between 2002 and May 12, 2005, the day the wall collapsed, Langan had recorded that the wall movedapproximately two feet away from the land behind it.40 The movement accelerated rapidly during April andMay of 2005 and during that time period Langan went to the site to take measurements once every fewdays instead of once every few months as it had done previously.41 The portions of the wall that did not

    collapse showed very little movement.

    * Inspections, both formal and informal, were conducted by Langan or Castle Village everyfew days during this period and were not limited to the dates in the timeline above.

  • 8/13/2019 Castle Village Report

    14/41

    C. Events of May 12, 2005

    On the morning of May 12, 2005, representativesfrom Langan including Gregory Biesiadeckivisited the Castle Village site at the request of

    Frank Nadal, who was concerned about evidenceof further movement and destabilization.42

    Langan suggested that Castle Village tie the topstone balusters above the wall, which were nowleaning over the edge, to the large trees in thegarden.43 George Melendez, Castle Villagessuperintendent, and his staff started performingthe tiebacks in the afternoon.44 Before they couldfinish, at about 4 p.m., they heard rumbling.45

    They looked over the edge of the wall and saw thatthe lower section of the wall had collapsed.46 Whenpolice and fire emergency responders arrived, they

    told Castle Villages employees to immediately getaway from the top of the wall, and they complied.

    Riverside Drive was now covered with dirt androcks. Carlos Pellecier, the doorman at anapartment building next to the wall, dialed 911 toreport the incident.47

    About ten minutes later, police officers andfirefighters arrived and blocked traffic on thehighway.48 They surveyed the area and noticedthat there were cars buried beneath the fallendebris.49 As they peered into the cars to determineif anyone was trapped inside, they heardrumbling.50 Another portion of what remained ofthe retaining wall was starting to collapse. Theyran to safety as the remainder of this section ofthe wall fell behind them.51

    Approximately 150 feet of the wall was now gone.52 The collapse caused a large amount of soil and debris(stones from the wall, boulders, dirt, benches, trees, and other objects) to fall down on the sidewalkand roadways below thus blocking a portion of Riverside Drive and the northbound Henry Hudson Parkway.53

    The NYPD and FDNY responded by closing the Henry Hudson Parkway in both directions and re-routed traffic.They conducted search and rescue operations using thermal imaging and search dogs to determine if anyone

    had been trapped beneath the rubble. A safety zone was established to protect first responders; localresidents were evacuated while engineers from Buildings checked the stability of the buildings and theremaining portions of the wall.

    The New York City Office of Emergency Management (OEM) directed the Department of Design andConstruction (DDC) to immediately hire contractors and engineers to make the site safe. DDC procuredan emergency contract to remove excess soil and debris from the top of the retaining wall; it performedcertain structural work to temporally prevent a further collapse; it monitored the wall using electronicsensor equipment; and it placed barricades on the sidewalk and street. OEM also brought in portable lights

    THE CASTLE VILLAGE RETAINING WALL

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    Contractors on site at collapsed portion of wall working to preventfurther collapse.

    Retaining wall collapse on May 12, 2005

  • 8/13/2019 Castle Village Report

    15/41

    for overnight operations. DOT establisheddetours for northbound travelers and NYPDprovided escorts for trucks and heavy equipmenttraveling to and from the collapse site.

    DOT, the Department of Sanitation, theDepartment of Parks and Recreation, and privatecontractors provided over 70 pieces of heavyequipment to haul rocks and debris from the siteto landfills in Queens and Staten Island and toa barge in Manhattan.54 The contractors workingfor DDC secured the area by cutting back the soilin the collapsed area to a safe slope. The slopewas reduced to less than 45 degrees to ensure thatno further sliding would occur.

    The Department of Buildings issued an

    emergency declaration on May 13 (amended onMay 16) to remove debris, to stabilize the wall,to provide a monitoring program for the wallsstabilization, and to protect against rainwater.

    By Saturday evening, May 14, engineers from theBuildings Department determined that theevacuated apartments in the adjoining buildingswere safe for occupancy during the clean-up.The Department of Environmental Protectionbriefly shut down a water-main that passedthrough the collapse zone to prevent furtherundermining of the wall by water if there were anybroken water lines. The Department of Parksremoved downed trees and was on hand tomitigate any impacts on the parkway below.Engineers from DDC and Buildings assessed thestability of the wall and ordered the removalof additional portions that were unstable.The exposed slope was covered in tarps whilelarge gravel and sewer drains were clearedto prevent water and mud accumulations andto prevent mudslides in case of rain.

    A seven-foot safety wall, comprised of two rows

    of 4500 lb. concrete blocks, was erected toprevent additional sliding of dirt or rocks onto theroadway. On Sunday evening, May 15, the New YorkState Department of Transportation, City DOT, andNYPD determined that two northbound lanes ofthe Henry Hudson Parkway were safe. Vehicleswere permitted in the area after 10:00 pm.

    THE CASTLE VILLAGE RETAINING WALL

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    Contractors dig back top portion of collapse to prevent furthersliding of debris.

    Safety blocks installed to protect roadway.

  • 8/13/2019 Castle Village Report

    16/41

    A. Mueser Rutledge Engineering Study Prepared for the Board of InquiryBuildings retained Mueser Rutledge Consulting Engineers (Mueser) to perform a study of the retainingwall and the factors that led to its collapse. Mueser was selected due to its expertise, availability, andprior knowledge of the wall.

    In 1985, Castle Village had hired Mueser to perform an engineering study of the wall and to recommendrepairs. On subsequent occasions Mueser submitted bids to Castle Village to supply engineering services;however, Mueser was never again selected by Castle Village to provide services. Buildings retained UnitedResearch Services (URS) to provide a peer review of Muesers report and to reach conclusions as to thevarious technical and engineering reasons for the walls collapse.

    Neither pre-construction plans nor as-built drawings of the original wall construction were available.The construction of the wall appears to have conformed to the standards used in the early part of thelast century.55 Using field measurements, photographs, historical data, and information from Langansreports and drawings, Mueser developed a model of a probable cross section of the original wall.56

    In addition to its mathematical analyses, Mueser also collected information pertaining to the constructionof the wall, interviewed witnesses and collected information on the inspections and repairs to the wall prior

    to the collapse.

    i. Prior Inspections and Repairs to the WallExcluding Langan involvement, inspections and repairs to the retaining wall from 1985 to 2002 are as follows:

    A letter written by John Flynn, an engineer, in 1985 where he expressed concerns with the conditionof the retaining wall.57

    A November 4, 1985 report from Mueser recommending rock anchoring and repairs to thebelow-grade tunnels. Rock anchors and bolts were installed (though URS determined theywere not anchored in bedrock) and the tunnels were repaired.58

    The engineering firm of Antonucci and Lawless, in a report dated April 14, 1994, performeda visual inspection of the wall and noted spalling and loose fascia stones.59

    Cutsogeorge and Tooman Architects, in a report to Castle Village dated June 24, 1998, notedspalling of wall fascia stones and recommended that sidewalk scaffolding be installed forpublic safety. Scaffolding was erected and was in place on the day of the collapse. 60

    ii. Summary of Information Collected from InterviewsMueser conducted multiple eyewitness interviews. The eyewitness accounts indicate that the lower partof the wall collapsed first. The collapse of the lower portion of the wall was described as a delamination,or a peeling away of the walls faade. The loss of support after the first collapse triggered a second, much largercollapse of the upper portion of the retaining wall. The eyewitnesses indicated that the trees went downvertically, thereby establishing that the whole mass came down in one solid drop. For further eyewitnessaccounts, see Muesers report on pages 39 through 46.

    iii. Langan Engineerings InvolvementIn 2002, Castle Village solicited proposals for inspection of the wall, and selected Langan. Langan establishedlocation points on the wall for monitoring and monitored the wall from November 2002 through the day of thecollapse. Langan performed site topography development and completed a geotechnical subsurfaceinvestigation. In addition, Langan designed a new drainage system for the land above the wall andsupervised the contractor hired to install it.61

    BOARD OF INQUIRY REVIEW OF EVENTS AND ENGINEERING STUDIES

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    17/41

    iv. Langans Wall Monitoring ProgramIn 2002, Langan established a rating system for the retaining wall. Areas showing little or no structuraldistress were given a rating of I; areas showing moderate structural distress were given a rating of II.No area was given a rating of III, i.e. showing heavy structural distress.62 The part of the wall that collapsed

    was given a rating of II.Langan monitored the wall beginning in November 2002 and ending when the wall collapsed on May 12, 2005.Six survey lines were established in order to monitor the wall. Four of six survey lines showed little or nomovement. However, at two locations Langan denominated pilasters four and five, where the wallultimately collapsed, did show significant movement of approximately two feet westward during the timethat Langan was monitoring it. There was also an acceleration of movement in the wall that coincideswith the high rainfall that occurred in March and April of 2005.63

    BOARD OF INQUIRY REVIEW OF EVENTS AND ENGINEERING STUDIES

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    3/20

    03

    6/20

    03

    9/20

    03

    12/200

    3

    3/20

    04

    6/20

    04

    9/20

    04

    12/200

    4

    3/20

    05

    feet

    surveydates

    12/200

    2

    WALL DISPLACEMENT

    May1

    2,20

    05

    upper portionof wall

    2.0

    1.5

    1.0

    .5

    0

    lower portionof wall

    The above diagram shows the westward movement of the section of the wall that collapsed. The movement noticeably

    accelerated during the months immediately before the collapse. On May 12, 2005, the day of the collapse, the wall hadmoved two feet westward from its position in 2002 when the wall monitoring began.

  • 8/13/2019 Castle Village Report

    18/41

    B. Summary of the URS Engineering Study prepared for the BoardThe Board retained URS to review and analyze the cause of the wall collapse based on the information containedin Muesers study. URS concluded that the wall developed tension cracks along the lower portion of the wallduring and after construction.

    URS reviewed the movement of the wall prior to the collapse and concluded that if the balustrade had originallybeen constructed plumb, portions of the wall had moved two feet westward from its plumb position prior toCastle Villages retaining of Mueser in 1985.64 URS further concluded that between 2002 and 2005 at two ofLangans survey points, the top of the wall moved an additional 1.25 to 2 feet and the lower portion moved anadditional .7 to 1.2 feet.65 These measurements were consistent with the bulging of the lower portions of the wall(which collapsed first) that was observed before the wall collapsed. URS thus concluded that the wall couldhave displaced a maximum of 4 feet prior to the final survey made before the wall collapsed.66

    URS also reviewed the drainage system. It concluded that prior to 2004, the wall essentially had no workingdrainage system.67 Small catch basins were present, but they directed the water towards the face of the wallrather than away from it.68 Weepholes in the wall were clogged with debris and there was no drainage systembehind the wall; therefore water was not able to flow through them.69 While some of the groundwater flowed

    through the wall and weathered the stones and mortar, any groundwater that did not flow through wouldhave been trapped by the impermeable bedrock that sloped downward behind and under the wall. URS concludedthat the trapped groundwater had resulted in additional pressure to the walls lower portion.70 URS furtherconcluded that the 2004 drainage modifications did not have a substantial negative impact on the pressure

    behind the wall from accumulated water.71

    URS also concluded that the pressure from the groundwaterresulted in a gradual weakening of the lower portion of the wall.72

    Installation of rock anchors and bolts in 1986 in some of thestones comprising the wall may have arrested some movement,but even if the anchors and bolts had been inserted into bedrock,which was not the case, they would not have had a significantimpact on the walls stability.73 Groundwater built up overtime causing pressure on the wall to increase and eventuallycaused the cracking and deformation that led to the wallscollapse.74 On May 12, 2005, the result of this pressure wasa delamination of stones in the vicinity of Langans survey pointsdenominated pilasters 3, 4 and 5 in the lower wall which fellto the street below. The upper portion of the retaining wall,extending from pilaster 3 to pilaster 7, collapsed shortlyafterward due to a loss of support from the lower wall whichhad previously fallen. URS calculated that the geometry of thewall just prior to collapse suggested a factor of safety of 1.0 orless, indicating failure.75

    BOARD OF INQUIRY REVIEW OF EVENTS AND ENGINEERING STUDIES

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    Three anchors in pilaster with large crack in lowerportion.

  • 8/13/2019 Castle Village Report

    19/41

    C. Summary of Other Engineering Evaluations

    Board members visited the site as a group on July 1, 2005. Several Board members also made subsequentindividual visits. In addition to commissioning Muesers report and the report from URS, the Board examineddocuments and reports, reviewed the history of the sites engineering evaluation since 1985 and took

    testimony from parties with an interest in, or knowledge of, the wall (see appendix). The following is a summaryof the engineering evaluations conducted on behalf of Castle Village.

    BOARD OF INQUIRY REVIEW OF EVENTS AND ENGINEERING STUDIES

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    ENGINEER DATE OBSERVATION RECOMMENDATION RESULT

    John Flynn August 28,1985

    Deterioration and cracking of the walland deterioration of the tunnels

    None stated None documented

    Mueser RutledgeConsulting Engineers

    November4, 1985

    The wall and the underground tunnelsshow signs of structural distress

    Repair and monitoring of thosestructures

    Sections of wall were pinnedand fascia stones repaired

    Antonucci andLawless Architectsand Engineers

    April 14,1994

    Signs of spalling, deterioration, rootinfiltration, water leaks, and 12-18inches of settlement in the landabove the wall

    Monitoring, cleaning of drainsand pipes, replacement of sewercovers, and the addition of moreweepholes

    None documented

    Cutsogeorge andTooman Architects June 24,1998 Severe deterioration of the wallresulted in spalling of six cubic feetof debris to the sidewalk below. Rootinfiltration severely compromisingwalls stability

    Sidewalk scaffolding to protectpublic from spalled stones;necessary removal of allvegetation from face of wall;repoint mortar

    Sidewalk scaffolding erectedby Castle Village; not knownif vegetation was removed;mortar repointed by PhoenixWaterproofing (unconfirmed)

    Mueser RutledgeConsulting Engineers

    March 17,1999

    Writes proposal for retaining wallinspection services.

    None None

    Cutsogeorge andTooman Architects

    1999 Drainage and structural problemsstill found at the site

    A geotechnical engineer neededto conduct investigation

    Geotechnical engineer GregoryPillori hired to study the wall

    Gregory Pillori September1999

    Sinkholes noted in the ground abovethe wall; drainage system foundunable to handle water runoff

    Sinkholes should be filled anddrainage improved; concernsexpressed about walls stability

    No action documented

    LanganEngineering

    January 7,2002

    Wrote proposal for evaluating wallthat was accepted on July 3, 2002

    The wall needed to be monitoredfor possible movement

    Langan was hired to performthe monitoring

    Mueser RutledgeConsulting Engineers

    March 27,2002

    Wrote a proposal for retaining wallinspection services that was notaccepted

    None Not accepted

    LanganEngineering

    January 6,2003

    Wall cracks, water seepage, missingmortar, fallen stones, and settlementof walkways above wall

    Further monitoring of parts of thewall showing structural distresswas needed

    Wall monitoring performed byLangan

    LanganEngineering

    August 8,2003

    Site drainage was inadequateexisting drains did not discharge tothe NYC sewer system

    A completely new drainage systemwas designed

    Drainage system installed thefollowing year

    LanganEngineering

    December16, 2003

    New drainage system proposed alongwith repairs to walkways above wall

    Castle Village approved the workon January 22, 2004

    Work performed betweenAugust and November 2004

    Langan

    Engineering

    September

    14, 2004

    During installation of drainage system,

    Langan expresses concern about thestability of the walls parapet

    Concrete deadmen and tieback

    anchors needed at top of wall toincrease the parapets stability

    Work performed as part of

    drainage system installation

    LanganEngineering

    April 13,2005

    More sinkholes and depressionsappear; Langan finds deep-seatedglobal movement of 50 section ofthe wall

    The critical section of the wallneeded to be restrainedimmediately

    Langan chooses exterior rakerbrace. Contractor hired toinstall brace; wall collapsesbefore work could be done

    LanganEngineering

    May 12,2005 (dayof collapse)

    Frank Nadal called Langan to the siteafter noticing sinkholes and cracks insoil above the wall

    Langan advised Castle Village totie the top part of the wall totrees directly behind it

    Castle Village in process oftying wall to trees when wallcollapses

  • 8/13/2019 Castle Village Report

    20/41

    URS found that the most likely cause of the collapse of the retaining wall was structural failure resulting from anincreased pressure that developed behind the wall due to the build up of groundwater throughout the years. TheBoard concurs in this finding. Neither of the two documented repairs that Castle Village undertook at therecommendation of engineering consultants was sufficient to address the destabilization posed by the increased

    pressure. First, in 1985 when the wall shifted and a bulge occurred, Mueser Rutledge was hired by Castle Villageto recommend and oversee a repair. The Board finds that while this repair (installation of wall anchors and bolts)may have addressed the localized issue, it did not address the groundwater pressure build up. The secondconstruction work occurred in 2004 when Castle Village accepted Langan Engineerings first phase design forinstallation of a new surface drainage system in the yard at the top of the wall. The Board finds that while thissurface drainage system failed, this failure did not have a significant adverse affect on the wall.The infiltration and pressure posed by the groundwater were far greater than this surface drainage system wouldhave diverted even had it worked as intended.

    Effective repair and maintenance is critical to structural stability of all retaining walls. The wall had been a majormatter of concern to Castle Villages Board of Directors since the apartment complex became a co-operative in1985. Repeated inspections and investigations showed cracking and wall movement, bulging of sections of thewall, stones falling from the wall, tilting of the balusters at the top of the wall, and voids and sinkholes in the

    park located at the top of the hill being held up by the wall. In 2002, Castle Village hired Langan Engineering tomonitor the wall. Langan told Castle Village in a report dated January 6, 2003 that portions of the wall werebulging and were moving toward the west, away from the hill that the wall was holding back.

    While Castle Village solicited 15 different reports from various engineering firms during the 20 years before thecollapse to evaluate and study the walls many problems, it did not perform any substantial work after the 1985repair except for the installation of the failed drainage system in 2004. The Board finds that these efforts do notconstitute effective repair and maintenance.

    Further, when sinkholes and voids reappeared behind the wall in early 2005 and Castle Village learned the newdrainage system installed the previous summer had not arrested the walls decline, the co-operative failed totake effective action. On April 13, 2005, Langan informed Castle Village that the upper section of the wall hadfurther destabilized by moving up to seven inches westward during the previous eight months and that thissection of the wall was critical. Langan wrote Frank Nadal, Castle Villages property manager:

    Our judgment is that there probably is ongoing deep seated global movement of an approximately 50 ft sectionof the retaining wall. This critical section (i.e., cracks reopening and large sinkholes within the terrace) requiresimmediate attention; we recommend installing a restraining system to stabilize this critical section. 1

    Nevertheless in the following month, as the wall continued to deteriorate, neither Langan nor Castle Village tookeffective emergency action. Even on May 4, 2005, eight days before the collapse, when Langans monitoringpoints indicated that parts of the wall had moved an additional nine inches since April, no emergency wasdeclared. While this information and Langans conclusion set forth in its April 13 letter that the wall neededimmediate bracing warranted a sense of urgency, Langan did not notify the Department of Buildings of theexistence of an imminent threat to public safety. While it is true that a few days before the collapse Urban

    Foundations, a Castle Village contractor, hired an expediter to approach the Department of Transportation forpermission to close a lane of Riverside Drive so that the wall could be braced, Langan and Castle Village appearedto treat the situation as an ordinary problem, one that could be dealt with in the ordinary course of business.When the Department of Transportation asked for an engineering report to justify the lane closure, Langan wrotethat the 70 ft high stone wall is exhibiting distress due to lateral movement. This language was insufficient toput the Department of Transportation on notice that failure of the wall might be imminent. Neither Langan,Castle Village, nor any of its agents acted with a sense of urgency or gave an indication that public safety was atrisk. They simply went through the normal permitting process.

    FINDINGS/CONCLUSION

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    21/41

    On the morning of the collapse, when Langan visited the site to address Castle Villages mounting concerns, anengineer from Langan told Castle Village to tie the leaning concrete balustrade columns to some trees to preventthem from toppling off onto the sidewalk and roadway below. This demonstrated that Langan and Castle Villageand both knew there was an imminent threat to public safety. They again failed to implement adequate safety

    measures to protect the public from the rapidly deteriorating situation, in this instance evidenced by both theleaning balusters and by the walls precipitous westward movement over the previous weeks.

    Castle Village had a non-delegable duty under the New York City Building Code to maintain the wall in a safecondition. It failed to do so. Castle Villages manager Frank Nadal; Nadals employer Goodstein ManagementInc.; and Langan Engineering all failed to properly address the seriousness of the situation in April and May 2005when they knew that significant changes had taken place after sinkholes and sidewalk joints re-opened andsections of the wall accelerated their westward movement. The Board finds that Castle Village and its agentsNadal, Goodstein Management and Langan all failed to notify the City of the obvious and imminent threat topublic safety posed by the walls impending collapse.

    In early May, when Langans monitors showed that a section of the wall had moved almost two feet westwardsince 2002, Langan still took no effective emergency measures and failed to notify the Buildings Department.

    Two feet of movement of the upper section of the wallapproximately nine inches between April 11 and May 4is significant. URS has calculated that the factor of safety for the pre-collapse May 2005 geometry of the wall isapproximately 1.0 or less than 1.0. As the factor of safety approaches 1.0 or less, failure occurs. The Board findsthat Langan should have known this portion of the wall had dramatically destabilized and that the wall was atrisk of imminent failure.

    FINDINGS/CONCLUSION

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    22/41

    As a result of its investigation, the Board recommends the following actions to the Commissioner of Buildings:

    1) The New York State Education Department licenses and oversees professional engineers.George Derrick and Gregory Biesiadecki, the engineers from Langan who worked on the CastleVillage project who were aware of the walls movement and condition in March and

    April 2005, should be referred to the New York State Education Departments Officeof Professional Discipline for consideration of any appropriate disciplinary action basedon their failure to exercise a reasonable standard of care and their failure to alert theDepartment of Buildings that the movement of the wall in the Spring of 2005 hadaccelerated and that this presented a danger to the public.

    2) The Department of Buildings does not license engineers; however it does afford engineersprivileges that may be revoked. Title 1, 21-02, of the Rules of the City of New York allowsthe Department of Buildings to revoke a Professional Engineers right to professionallycertify that his or her submissions are code and zoning compliant. George Derrick and GregoryBiesiadecki, the engineers from Langan who worked on the Castle Village project, shouldbe referred to the Buildings Special Investigations Unit to determine whether proceedings

    should be commenced under the provisions of 21-02 based on their involvement in the project.

    3) Section 26-234 of the Administrative Code states that those engaged in building operationshave a duty to report dangerous or unsafe conditions to the Department of Buildings. CastleVillage; its managing agent Goodstein Management; Goodsteins employee Frank Nadal, theproperty manager; Langan Engineering; and Langan engineers George Derrick and GregoryBiesiadecki should each be cited with a New York City Environmental Control Board violation fortheir failure to comply with section 26-234 by bringing the dangerous condition of the wall tothe attention of the Department of Buildings.

    4) The Department of Buildings should propose legislation to require owners to engage a New YorkState licensed architect or engineer to perform periodic inspection of retaining walls that

    front a public way. A model for this type of regulation is Local Law 10 of 1980, as amendedby Local Law 11 of 1998, which sets forth a facade inspection/repair regulatory scheme forbuilding facades. The legislation would require a cyclical inspection report and a schedulefor any needed repair and maintenance to be filed with the Department of Buildings. Criteriafor the inspection and reporting process should include factors such as wall height, wallcomposition, and proximity to a public way.

    Furthermore, related to its investigation, the Board acknowledges the following prior actions on the part ofthe Department of Buildings:

    1) Pursuant to Section 26-235 or 26-243 of the Administrative Code, the Department ofBuildings issued an Emergency Declaration the day after the collapse stating that repairwork on the wall was to commence immediately in order to remedy the dangerous condition

    and protect public safety.

    2) Castle Village Owners Corporation was ordered to permanently repair the collapsed portionof the retaining wall and permanently stabilize the remaining portion of the wall. Furthermore,the Department of Buildings monitored this process to ensure that all work conformed to theNYC Building Code, other applicable laws, rules, and regulations, and that all requisite permitswere obtained to perform the necessary work.

    RECOMMENDATIONS

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    23/41

    3) Castle Village Owners Corporation was ordered to monitor the movement of the retainingwall until it provides the Department of Buildings with a report from a professionalengineering firm certifying that the wall is safe.

    4) Sections 27-127 and 27-128 of the Building Code explicitly require an owner to maintain its

    buildings in a safe condition, and impose responsibility on the owner to do so. Castle Villagefailed to discharge this duty and was properly served with a notice of violation and found guiltyat the Environmental Control Board for its failure to maintain its property in a safe condition.

    RECOMMENDATIONS

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    24/41

    1Langan Memo to Frank Nadal, p. 1 (April 13,2005).

    2Gray, Christopher, Streetscapes/Castle Villageand Hudson View Gardens in Upper Manhattan,The New York Times, September 10, 2000,Section 11, p. 7.

    3Id.

    4 Dr. Charles V. Paterno, Washington Heights& Inwood Online, http://www.washington-heights.us/history/archives/dr_charles_v_paterno_48.html. (AccessedMarch 30, 2007)

    5Id.

    6Id.

    7Id.

    8Id.

    9Id.

    10Id.

    11Id.

    12Chan, Sewell et al, Official Hope to Reopen2 Traffic Lanes at Collapse Site, The New YorkTimes, May 15, 2005, Section 1, p. 37.

    13Id.

    14Towers and Battlements It Sees, Bosomd High

    in Tufted Trees, The New York Herald Tribune,May 28, 1939, p. 51.15

    A Boy in His Rowboat Picked Castle VillageSite, The New York Herald Tribune, May 28,1939, p. 51.

    169A West Side (Joe DiMaggio) Highway HistoricOverview,http://www.nycroads.com/roads/west-side.(Accessed March 30, 2007).

    17Id.

    18Id.

    19Mueser, Investigation Report-Phase I, p. 5(April 6, 2007).

    20Id.

    21Id.

    22Mueser at 5, 6.

    23Mueser at 6.

    24Id.

    25Id.

    26 Mueser at 7.27

    Barron et al., Years before Landslide, ResidentsComplained of Walls Instability, The New YorkTimes, May 14, 2005, Section A, p. 1.

    28Mueser at 9.

    29Mueser at 10-11.

    30Id.

    31Id.

    32Mueser at 12.

    33Mueser at 13.

    34Mueser at 15.

    35Mueser at 20.

    36Id.

    37Langan Letter to DOT, p.1 (May 9, 2005).

    38May 11, 2006, Testimony Transcript, p. 46.

    39May 11, 2006, Testimony Transcript, p. 24.

    40 Mueser at 21, 56.41

    Mueser at 47.42

    January 6, 2006, Testimony Transcript, p.54-56.43

    November 15, 2005, Testimony Transcript, p. 90-94.

    44January 6, 2006, Testimony Transcript, p. 55-56,59-60.

    45Id.

    46November 15, 2005, Testimony Transcript, p.100.

    47August 2, 2005, Testimony Transcript, p. 9.

    48Id. at 32, 40 and 46.

    49Id.

    50Id. at 32 and 47.

    51Id. at 33, 41 and 47.

    52Chan et al, at 37.

    53Id.

    54 Chan et al, at 37.55

    Mueser at 56.56

    Insert note for drawing location.57

    Mueser at 4.58

    Mueser at 5.59

    Mueser at 6.60

    Mueser at 7.61

    Mueser at 9-21.62

    Mueser at 10-11.63

    Mueser at 12.64

    URS, Castle Village Retaining Wall Collapse-Phase II, p. 2-2, 6-1 (April 26, 2007).

    65URS at 2-2.

    66URS at 2-2.

    67URS at 2-3.

    68

    URS at 6-1.69URS at 6-1.

    70URS at 6-1.

    71URS at 6-2.

    72URS at 6-2.

    73URS at 6-2.

    74Id.

    75URS at 4-6.

    ENDNOTES

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

    Leslie Torres left her position at the Department of Buildings on April 6, 2007.

    Photo CreditsPage 3, Photo 1: MRCE Report to the Board of Inquiry, Photo Taken by MRCE in 2002, Plate Number 13

    Page 3, Photo 2: MRCE Report to the Board of Inquiry, Photo Taken by Langan 5/12/05, Plate Number 5

    Page 4, Photo 1: MRCE Report to the Board of Inquiry, Photo Taken by Castle Village 4/19/05, Plate Number 14

    Page 4, Photo 2: MRCE Report to the Board of Inquiry, Photo Taken by Castle Village 1/26/02, Plate Number 2

    Page 4, Photo 3: MRCE Report to the Board of Inquiry, Photo Taken by MRCE in 2002, Plate Number 5

    Page 8, Photo 1: www.answers.com/topic/castle-village

    Page 8, Photo 2: http://gis.nyc.gov/doitt/cm/CityMap.htm

    Page 8, Photo 3: www.washington-heights.us/history/archives/dr_charles_v_paterno_48.html

    Page 9, Photo 1: URS Report to the Board of Inquiry, Photo Taken by Langan in November 2002, URS Figure Number 18

    Page 9, Photo 2: MRCE Report to the Board of Inquiry, Photo Taken by Castle Village 5/9/05, Plate Number 21

    Page 10, Photo 1: MRCE Report to the Board of Inquiry, Photo Taken by Castle Village 5/9/05, Plate Number 22

    Page 10, Photo 2: MRCE Report to the Board of Inquiry, Photo Taken by Langan Engineering 5/12/05, Plate Number 12Page 10, Photo 3: MRCE Report to the Board of Inquiry, Photo Taken by Langan Engineering 5/12/05, Plate Number 10

    Page 13, Photo 1: Retaining Wall Collapse 5/12/05

    Page 13. Photo 2: MRCE Report to the Board of Inquiry, Photo Taken by Thornton-Tomasetti, Plate Number 2

    Page 14, Photo 1: MRCE Report to the Board of Inquiry, Photo Taken by Thornton-Tomasetti, Plate Number 3

    Page 14, Photo 2: Photo Taken by MRCE 5/14/05

    Page 17, Photo 1: MRCE Report to the Board of Inquiry, Photo Taken by Castle Village 5/9/05, Plate Number 20

  • 8/13/2019 Castle Village Report

    25/41

    APPENDIX

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    26/41

    Carlos Pellecier Doorman at 1380 Riverside Drive

    On August 2, 2005, Carlos Pellecier testified before the Board of Inquiry. Mr. Pellecier has been employed as thedoorman at 1380 Riverside Drive for 24 years. 1380 Riverside Drive is the building directly next to the CastleVillage retaining wall. According to Mr. Pellecier, during his tenure as the doorman he has had many

    opportunities to observe the wall and the surrounding areas. Each night before starting his shift,Mr. Pellecier patrolled the area beneath the wall. During these nightly patrols, he searched for suspiciouspersons, collected trash and debris, and investigated resident complaints. He recalled several residentcomplaints about the wall including dampness along the bottom portion, cracks, and falling rocks. He alsoremembered that at some point drainage work was performed at the top of the wall and that there wasvisible bulging in the middle-to-bottom portion of the wall.

    At approximately 4:00 p.m. on May 12, 2005, Mr. Pellecier was sitting in the lobby eating when a loud boomstartled him. He testified that the sound appeared to be emanating from the retaining wall area. To him, itresembled the sound of an oversized truck hitting an overpass. He decided to investigate when he noticed smokefilling the air and left his post to do so. He then discovered that the lower portion of the retaining wall hadcollapsed. Mr. Pellecier described the wall after the first collapse as a slice shaved off the bottom of the wall.

    After observing the collapse, Mr. Pellecier immediately returned to his post and dialed 911. The police andfirefighters arrived on the scene shortly after the emergency call. The remainder of the wall collapsedsoon afterwards. According to Mr. Pellecier, he and approximately 11 emergency personnel were standing inclose proximity to the retaining wall during the second collapse. He further explained that prior to thesecond collapse, he felt a rumbling and that the time lag between the first and second collapsewas approximately 10 to 12 minutes.

    Following the second collapse, Mr. Pellecier ran away to avoid falling debris. He observed that as thebottom portion of the wall slid down to the highway, a tree, a park bench, and rocks were projected over thetop of the wall. Immediately afterwards, he ran to the corner of 181st Street and Riverside Drive andremained there until he was comfortable that there would be no further collapse. Mr. Pellecier then returned to1380 Riverside Drive and advised the tenants to vacate immediately.

    Joseph Byrne New York City Firefighter

    On August 2, 2005, Joseph Byrne testified before the Board of Inquiry. Mr. Byrne has been a firefighter with theNew York City Fire Department for eighteen years. On May 12, 2005, he responded to a call about a partialcollapse of a retaining wall near 181st Street and the Henry Hudson Parkway. Upon arrival, he noticed thata wall had collapsed on top of a couple of vehicles parked on Riverside Drive. This prompted him to check insidethe vehicles in order to ensure that nobody was trapped in the vehicles. At some point after his arrival, Mr. Byrneheard a rumble that prompted him to run. He witnessed the second collapse occurring behind him as he ran.

    Brian Masterson New York City Firefighter

    On August 2, 2005, Brian Masterson testified before the Board of Inquiry. Mr. Masterson has been a firefighter

    with the New York City Fire Department for fifteen and one half years. Mr. Masterson responded with Joseph Byrneto a collapse at the intersection of 181st Street and the Henry Hudson Parkway on May 12, 2005. Upon his arrival,he noticed that a portion of the retaining wall had collapsed and sent debris to the street below that covereda couple of cars. He was looking at the top of the wall and noticed that it started to waver. Approximately twoto three minutes later, he observed the second collapse. He described the second collapse as the whole wallletting loose all at once and falling vertically. As the wall collapsed, Mr. Masterson ran away to avoid the debris.He noticed water coming out from behind the wall after it fell.

    SUMMARY OF TESTIMONY

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    27/41

    Because he was uncertain about what portion of the wall was going to fall next, Mr. Masterson evacuated theadjoining building south of the wall. Prior to the collapse, Mr. Masterson drove by the retaining wall on manyoccasions over the past 15 years. Throughout those 15 years, he noticed that the wall was bulging outwardsbut he does not recall ever receiving a complaint from the public about the wall.

    Jonathan Wally New York City Police Officer

    On August 2, 2005, Jonathan Wally testified before the Board of Inquiry. Mr. Wally has been a police officerwith the New York City Police Department for three years. At approximately 4:00 p.m. on May 12, 2005, Mr. Wallyresponded to a call that a wall collapsed near the junction of the Henry Hudson Parkway andRiverside Drive. Upon arrival, he noticed that the lower half of the retaining wall collapsed onto the roadway.Rocks and dirt from the initial collapse flattened about five or six cars. He began checking the cars for peopletrapped inside. Approximately five minutes after his arrival, the second part of the wall collapsed. The secondcollapse occurred over approximately a 20 second period of time. The collapse caused Mr. Wally to run northon the ramp, but he hesitated and reverted south. After the wall fell, he noticed that there was a pipeleaking water. Mr. Wally patrolled the area surrounding the retaining wall daily in the past and did notnotice any rocks or pebbles that fell from the wall.

    Donna Rounds President, Castle Village Owners Corporation

    Donna Rounds testified before the Board of Inquiry on October 21, 2005. Ms. Rounds is the president ofthe Castle Village Owners Corporation. She began her presidency in 2004. As the president, she is responsiblefor presiding over the monthly meetings and reviewing management reports and documents.

    Ms. Rounds testified that she did not have much personal or physical contact with the retaining wall.She stated that she only observed the wall during the period when Langan was making proposals regardingthe retaining wall. Also, when she occasionally went to the Riverside Park along the Hudson River she wouldcross the bridge beneath the wall that carried pedestrians over the Henry Hudson Parkway.

    While Ms. Rounds was president, Langan was contracted to monitor the retaining wall. She testified that

    Langan was chosen because they were impressed by the comprehensive program presented to them by Langanthat involved the use of laser monitoring to check for any movement of the wall. She stated that Castle Villagewas concerned about movement and spalling of the face of the wall. During the monitoring program, Langanreported to Castle Village every three months. In one of their reports, Langan recommended that the drainagesystem in the land above the wall needed to be replaced. Due to Langans recommendation, Morris ParkContracting Corporation installed the drainage system in the fall of 2004 under the supervision of Langan.

    Prior to the collapse, Ms. Rounds was not concerned that the wall was in danger of falling. In April of 2005,Frank Nadal brought his concerns about subsidence in the area above the wall to her attention. Cracks hadstarted to appear close to the wall and along the sidewalks on the grounds above the wall. Because of theseconcerns, Castle Village contacted Langan about the cracks and remained in contact with Langan on a regularbasis. Langan suggested that the wall needed to be pinned back to stabilize it. However, before that could bedone it needed a brace installed at its base to provide immediate stabilization. Langan was authorized to solicitbids for the stabilization work. The wall collapsed before any work could be done. Ms. Rounds testified that it isher understanding that they were waiting for the appropriate city permits before Langan could begin working.

    Ms. Rounds testified that she did not witness the wall collapse. Once alerted to the situation, she calledCastle Villages attorneys and notified their insurance carriers. She scheduled a meeting with Langan andthey discussed the stabilization of the slope. Upon the citys request that they hire an engineering firm foroversight of Langan as a peer reviewer, they hired Weidlinger Engineering to oversee the monitoring work

    SUMMARY OF TESTIMONY

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    28/41

    that was being done by Langan. Weidlinger is also doing the preliminary design for the new wall that willeventually replace the wall that collapsed.

    According to Ms. Rounds testimony, Castle Village never refused to comply with any of Langans suggestionsabout the wall. She also testified that maintenance of the wall was never subject to any monetary constraints

    because Castle Village had refinanced their underlying mortgage and had a large capital reserve. She testifiedthat Castle Village executed all of Langans recommendations.

    James Berlin Board Member, Castle Village Owners Corporation

    On October 21, 2005, James Berlin testified before the Board of Inquiry. Mr. Berlin is a retired physics andcomputer science teacher and a resident of Castle Village for the past twelve years. He has served in somecapacity with the Castle Village Owners Corporation every year since 1998 with the exception of the 2000-2001term. Mr. Berlin attends all meetings, serves as a member of the admissions committee, and attends meetingswith architects and engineers hired by Castle Village.

    Mr. Berlin testified that approximately four or five years ago, a rock fell out of the wall. The wall was repairedwith mortar and, as a precaution, a sidewalk bridge was installed underneath that section of the wall.

    Mr. Berlin does not recall personally receiving any complaints about the condition of the wall.

    On the day of the collapse, Mr. Berlin was in his apartment. His apartment does not face the wall and thereforehe was unaware that it had collapsed. He last observed the wall on May 10, 2005, during his daily walk.He testified that he has taken daily walks since 1998 and that, on occasion, he would walk past the retainingwall. He noticed some bulging, but he never reported this observation to Langan. In addition, Mr. Berlin recalledthat an indentation near the bottom of the walk had increased in size over the years.

    Mr. Berlin was present for most of the meetings between Langan and Frank Nadal. He was present when Langancame to investigate the cracks in the ground above the wall in April of 2005. According to Mr. Berlin, the cracksunder investigation measured two inches. He mentioned that Gregory Biesiadecki was the Langan engineerwho conducted the April 2005 investigation.

    According to Mr. Berlin, Castle Village authorized all of Langans recommendations regarding the constructionof a new drainage system. He recalls Langan advising Castle Village that a new drainage system would preventsome of the changes that were taking place on the grounds and also reduce the hydrostatic pressure behindthe retaining wall. Castle Village relied on Langans expertise and followed their recommendations.

    On the morning of May 12, 2005, Mr. Berlin was informed that the gap between the sidewalk slabs hadincreased by over one inch over the past two days. He conveyed this information to Langan.

    Gail Berson Board Member, Castle Village Owners Corporation

    On October 21, 2005, Gail Berson testified before the Board of Inquiry. Ms. Berson has lived in Castle Villagesince 1968. She testified that she has served in some capacity with the Castle Village Owners Corporationfrom 1987 to 1992 and from 2002 to the present.

    Ms. Berson testified that she never received any complaints about the condition of the retaining wall.She testified that she did observe tilting of the sidewalks on the Castle Village property near the retainingwall. She was satisfied with the work Langan Engineering performed. However, Ms. Berson testified that shehad little direct contact with Langan or involvement with issues regarding the retaining wall.

    Ms. Berson testified that she was in her apartment at the time of the walls collapse. While she did hear soundsthat she associated with the collapse of the wall, she did not personally observe it.

    SUMMARY OF TESTIMONY

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    29/41

    George Melendez Castle Village Superintendent

    On October 28, 2005, George Melendez testified before the Board of Inquiry. Mr. Melendez is the superintendentat Castle Village and is responsible for maintenance of its grounds and buildings. On May 12, 2005, he was askedto tie the parapet of the retaining wall to the trees behind it. Several other Castle Village employees were

    assisting him. As he was performing this work, he heard a loud rumbling noise. As he looked over the parapetdown to Riverside Drive, he saw that a portion of the wall had collapsed. Police officers and firefightersresponding to the scene ordered him to move away from the wall, which he immediately did. As he wasleaving the area, the top part of the wall collapsed.

    Gregory Biesiadecki Langan Engineering

    On November 15, 2005, Gregory Biesiadecki, a Senior Associate at Langan Engineering, testified before theBoard of Inquiry. Mr. Biesiadecki is a licensed New York State Professional Engineer and he has experience withstone masonry retaining walls. Prior to working for Langan, Mr. Biesiadecki worked at Mueser RutledgeConsulting Engineers for 14 years. During this time, Mueser Rutledge was hired to install tiebacks to secure theCastle Village retaining wall. He was not involved with the Mueser Rutledge retaining wall project and he did not

    see any Mueser Rutledge report regarding the Castle Village wall until after he began working for Langan.Mr. Biesiadecki testified that, based on his professional opinion, the tiebacks installed by Mueser Rutledgein 1986 had been installed according to the accepted standards of the industry.

    Mr. Biesiadecki testified that he became involved with the Castle Village retaining wall in 2002 when LanganEngineering was asked to do a topographic survey of the grounds. Castle Village became concernedwith conditions at the top of the wall and contacted Langan to complete an inspection. Langan was neverasked to determine the safety factor or the stability of the wall. In his opinion, there probably were othercriteria that Castle Village could have requested within this inspection to provide a more comprehensiveappraisal of the condition of the wall. Due to the large amount of information that would have beenneeded to calculate the safety factor of the wall, Mr. Biesiadecki was not surprised that Castle Villageonly asked for a global assessment of the wall.

    The initial January 2002 proposal included a site inspection, record search, topographic survey, inspection ofthe retaining wall, and preparation of a report based on their findings. This proposal was modified in June 2002,at which time Langan was asked to discontinue the other work and simply perform a site survey. Mr. Biesiadeckitestified that in August 2002, Langan was asked to propose an inspection of the wall. Langans subsequentproposal to Castle Village included investigatory work, which Castle Village denied because it was determined tobe too expensive. In September 2002, Langan submitted a revised proposal to inspect the wall which included thepreparation of a report and setting up a one year monitoring program. This revised proposal would have costCastle Village less than $20,000 while the original proposal would have cost $30,000. Langans primary contactperson at Castle Village was Frank Nadal, who is also a licensed engineer.

    Mr. Biesiadecki explained that the wall monitoring program was a twelve month process. Langan establisheda baseline reading in November 2002 and took additional readings at the three-month, six-month andtwelve-month marks. They established six stations along the 600-foot length of the wall. A series of fivelaser targets at varying heights of the wall were established at each station.

    Langan issued an initial monitoring report dated January 2003. In their report, Langan assigned sections of thewall a numerical rating from one to three. Some sections were given a rating of one, which indicated faircondition. Other sections were given a rating of two, which indicated possible stability and safety concerns.No area was given a rating of three, which indicated probable stability and safety concerns. In assigningratings to the various sections of the wall, Langan looked at such criteria as the overall number of cracks, thesize of the cracks, the positioning of the cracks, and protrusions found in the masonry. Langan established

    SUMMARY OF TESTIMONY

    B

    O A R D

    O F

    I N Q U I R Y

    R E P O R

    T / C A S T L E

    V I L L A G E

    R E T A I N

    I N G

    W

    A L L

    C O L L A P S E

  • 8/13/2019 Castle Village Report

    30/41

    a trend in