cba example application 2012

Upload: manuel-ferniza

Post on 04-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 CBA Example Application 2012

    1/38

    EXAMPLES OFAPPLICATIONS FOR THECBA-32P

  • 7/29/2019 CBA Example Application 2012

    2/38

    What is a Circuit Breaker?

    A circuit breaker is an automatically operated electrical switch

    designed to protect an electrical circuit from damage caused by

    an overload or a short circuit.

    Unlike a fuse, which operates once and then has to be replaced,

    a circuit breaker can be reset (either manually or automatically)

    to resume normal operation. Essentially, a circuit breaker is a

    safety device.

  • 7/29/2019 CBA Example Application 2012

    3/38

    What is a Circuit Breaker Analyzer?

    A Circuit Breaker Analyzer (CBA) is an electrical test

    equipment designed to perform timing and other tests such

    motion analysis on any circuit breaker.

    A wide range of tests have been developed to verify the

    conformity of each of the electrical and mechanical properties

    of a circuit breaker in order to meet the design criteria.

    Some of these tests are acknowledged and documented by

    international standards (IEM, ASTM, etc.). Some are still underdevelopment and promise great expectations.

  • 7/29/2019 CBA Example Application 2012

    4/38

    What is a Circuit Breaker Analyzer?

    CBA-32P is mainly designed to perform timing and motionanalysis but it is also an excellent multifunctional oscilloscopethanks to its compatibility with several accessories.

    By means of the accessories, the following measurement tests

    can be performed:- breaker travel and velocity

    - main and arcing contact resistance curve

    - voltage, current, pressure, temperature, etc.

    - insertion resistance during the opening and closinga times of the breakers auxiliary contacts

    The tests are executed under the control of CbaWin, runningunder any Windows.

    http://www.zensol.com/brochure/MULTIFUNCTIONAL_CBA.pdfhttp://www.zensol.com/brochure/MULTIFUNCTIONAL_CBA.pdf
  • 7/29/2019 CBA Example Application 2012

    5/38

    How to get started? In order to execute the test, the circuit breaker has to be set off line.

    The CBA-32P is connected via cables to both the computer and the breaker :

    To the computer via optical fiber communication module

    to the contacts of the circuit breaker via contact cables

    to the control cabinet (open and close coils) via the command cables

    Command-signals are sent from the CBA-32P to the control cabinet and the contacttiming is measured through the cables.

    The contacts may have up to three possible states visualized in the CbaWin software:

    Open (0)Resistive (0.5)Close (1)

    All recorded data are automatically and instantaneously transferred to the CbaWinsoftware which analyses the data and displays the results of the tests in graphics andtabular formats.

  • 7/29/2019 CBA Example Application 2012

    6/38

    EXAMPLE 1 : Timing Tests -Inoperative resistor

    The insertion resistor does not work.

    The spring on the moving contact is

    broken and blocks the piston.

    The broken spring has been replacedwith a new one and the device hasbeen reassembled.

  • 7/29/2019 CBA Example Application 2012

    7/38

    EXAMPLE 1 : Timing TestsRebounds

    Abnormal rebound on an auxiliary

    (resistive) contact. The head on the

    semi-mobile contact is loose.

    The auxiliary moving contact has beendisassembled and the problem has been identifiedas a loose head. The head has been tightened andimmobilized with loctite and punching, followedby reassembly of the mechanism.

  • 7/29/2019 CBA Example Application 2012

    8/38

    EXAMPLE 1 : Timing TestsDead Tank Missing Main contact

    Case of an inoperative main contact onone phase (B), showing an open circuiton a close operation.

    Disassembling the defective parts its been

    possible to observe that a shaft, connecting the

    actuating rod to the moving contact, had fallen

    causing the contact piston to separate from the

    actuating rod. The shaft has been replaced.

  • 7/29/2019 CBA Example Application 2012

    9/38

    EXAMPLE 1 : Timing TestsDead Tank Bad damping

    This timing diagram suggests a lack ofdamping at the end of the travel.

    The damage was due to a defectivedashpot.

  • 7/29/2019 CBA Example Application 2012

    10/38

    EXAMPLE 1 : Timing TestsValve in wrong position

    The body of the valve has been installedat 90 with respect to its normal position,hence causing delays in the admission ofcompressed air. The closing time ofcontacts A-1 and A-2 results longer thanusual, as observed on their signals.

    The body of the valve has beendisplayed in the correct configuration.The closing time of contacts A-1 andA-2 now corresponds to the one of A-3 and A-4, as observed in the newgraphic.

  • 7/29/2019 CBA Example Application 2012

    11/38

    EXAMPLE 1 : Timing Tests Adjustmentscrew of hydraulic command incorrectly set

    An adjustment screw is incorrectlyset, creating a 25 ms difference onone phase.

    The problem has been solved afteradjusting the screw.

  • 7/29/2019 CBA Example Application 2012

    12/38

    EXAMPLES 1 : Timing Tests Hydraulicactuator - Short circuit time

    The admission restriction of thehydraulic actuator is such that the shortcircuit time on phase C is longer than theother phases.

    The admission restriction of thehydraulic command has been adjustedin order to obtain synchronousoperation for all the phases.

  • 7/29/2019 CBA Example Application 2012

    13/38

    EXAMPLE 1 : Timing TestsPneumatic Breaker Isolation time

    Phase C is much quicker than the twoother phases.

    The restriction on the inverter switchhas been adjusted in order to obtaincomparable times between phases.

  • 7/29/2019 CBA Example Application 2012

    14/38

    EXAMPLE 1 : Timing Tests ShieldedBreaker

    The travel course is not completed, (112mm instead

    of 180mm). The piston starts moving 30 to 35

    milliseconds after the main piston while the normal

    delay is 20 milliseconds.

    The problem is solved by increasing the appropriatediaphragm orifice by 0.020 inches. The prematurereopening of the resistor was due to the main contactclosing later. Besides, the curve shows a problem withthe upper piston (DpC) of the main contact on Phase C.This piston was overhauled prior to the timing test.

  • 7/29/2019 CBA Example Application 2012

    15/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    The circuit breaker tested in this example is a PK8D - ALSTOM

    (800KV - 24 contact breaker)

    The steps to execute the test are the following:

    -1. Preparation of the breaker

    -2. Installation of cables by human operators

    -3. Connection of CBA-32P

    -4. Execution of the test with test plans-5. Presentation and discussion of the results

    -6. Conclusions

  • 7/29/2019 CBA Example Application 2012

    16/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    1. Preparation of the breaker: securing the site

    The first step consists in the isolation of the breaker from the electricnetwork by means of disconnectors, which are displayed on each side of the

    circuit. After isolation, the breakers are closed in order to ground the entire circuit.

    In order to guarantee the maximum safety for the operators, it is highlyrecommendable to put the ground on each side of the breakers.

  • 7/29/2019 CBA Example Application 2012

    17/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Detail of disconnectors:

    They isolate the circuit

    from the line.

    High voltagebreaker

    Current

    transformers

  • 7/29/2019 CBA Example Application 2012

    18/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    2. Installation of the cables

    Operators proceed to the

    installation of the cables

    on the breaker

    The installation is

    typically performed with

    the help of a bridge

  • 7/29/2019 CBA Example Application 2012

    19/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Yellow cable Red cable

    Black cable

    To the inputs of the CBA-32PExtensions for the connection of

    the CBA-32PContact cables

  • 7/29/2019 CBA Example Application 2012

    20/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    3. Cables for the CBA-32P:

    Command

    cable

    Extensions cables

    Contacts cable

  • 7/29/2019 CBA Example Application 2012

    21/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Overview of the CBA-32P connection and components:

    Portablecomputer

    24 contact CBA-

    32P

    Grounding of

    the CBA-32P

    Command

    6 analog inputs

    Optical fibre link

  • 7/29/2019 CBA Example Application 2012

    22/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Optical fibre connection:

    The optical fibre cable

    puts in communication the

    CBA-32P and the

    computer

  • 7/29/2019 CBA Example Application 2012

    23/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Connection of the command cables:

    The green cable commands the

    opening of the breaker

    Control cabinet

    The red cable commands the closing

    of the breaker

  • 7/29/2019 CBA Example Application 2012

    24/38

    EXAMPLE: Time-travel tests on HVcircuit breaker

    Connection of the CBA-32P:

    The command cable mustbe connected here

    Contacts cablesOptical fibre

    Command cable

  • 7/29/2019 CBA Example Application 2012

    25/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Execution of the test: loading a test plan

  • 7/29/2019 CBA Example Application 2012

    26/38

    EXAMPLE2 : Time-travel tests on HVcircuit breaker

    Execution of the test: creation of a test link

    Test link

  • 7/29/2019 CBA Example Application 2012

    27/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Test of the optical fibre link:

  • 7/29/2019 CBA Example Application 2012

    28/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Execution of a cable test:

    Contact cable test

  • 7/29/2019 CBA Example Application 2012

    29/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Execution of a test for the cables connected to the breakers:

  • 7/29/2019 CBA Example Application 2012

    30/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Launching a test:

    Launch the test

  • 7/29/2019 CBA Example Application 2012

    31/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    5. Presentation and discussion of the results:

    Bad fixation of the cables (the

    black clip is probably

    disconnected)

    The black clip falls during theclosing of the main contacts

  • 7/29/2019 CBA Example Application 2012

    32/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Closing test on a 24 contacts

  • 7/29/2019 CBA Example Application 2012

    33/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Opening test

  • 7/29/2019 CBA Example Application 2012

    34/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Close-Open test

  • 7/29/2019 CBA Example Application 2012

    35/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Problem on the A phaseContacts A01-A02 : We notice the

    apparition of the insertion resistance on

    the close side that could derive from a too

    long safety time. The contact traces of

    resistances have to be separated. In thisway, it will be possible to see the

    complete resistance traces. If necessary,

    the safety time can be readjusted. This

    operation will require the dismantlement

    of the resistances cables, and hence, to

    work on the timing diaphragms.

    In this case, the problem could be also

    solved by increasing the timing. This is

    possible since the opening time of this

    contacts is quicker than the others on the

    same phase.

  • 7/29/2019 CBA Example Application 2012

    36/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Open-Close-Open test

  • 7/29/2019 CBA Example Application 2012

    37/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    Problems on phase B

    The isolation time of phase B is too

    long: the timing of the pneumatic

    inverter switch (52bb) is too long. Inorder to work on the timing, the

    breaker has to be dismantled.

    Note: A good way to test the 52bb

    on the three phases is to perform an

    O-C test with a delay of 20 ms

    between the O and the C. Thismeans that the breaker has to be in a

    close status till the end of the test.

  • 7/29/2019 CBA Example Application 2012

    38/38

    EXAMPLE 2 : Time-travel tests on HVcircuit breaker

    The results of any test can be visualized in Tabular report,

    as follows: