cba example application 2012
TRANSCRIPT
-
7/29/2019 CBA Example Application 2012
1/38
EXAMPLES OFAPPLICATIONS FOR THECBA-32P
-
7/29/2019 CBA Example Application 2012
2/38
What is a Circuit Breaker?
A circuit breaker is an automatically operated electrical switch
designed to protect an electrical circuit from damage caused by
an overload or a short circuit.
Unlike a fuse, which operates once and then has to be replaced,
a circuit breaker can be reset (either manually or automatically)
to resume normal operation. Essentially, a circuit breaker is a
safety device.
-
7/29/2019 CBA Example Application 2012
3/38
What is a Circuit Breaker Analyzer?
A Circuit Breaker Analyzer (CBA) is an electrical test
equipment designed to perform timing and other tests such
motion analysis on any circuit breaker.
A wide range of tests have been developed to verify the
conformity of each of the electrical and mechanical properties
of a circuit breaker in order to meet the design criteria.
Some of these tests are acknowledged and documented by
international standards (IEM, ASTM, etc.). Some are still underdevelopment and promise great expectations.
-
7/29/2019 CBA Example Application 2012
4/38
What is a Circuit Breaker Analyzer?
CBA-32P is mainly designed to perform timing and motionanalysis but it is also an excellent multifunctional oscilloscopethanks to its compatibility with several accessories.
By means of the accessories, the following measurement tests
can be performed:- breaker travel and velocity
- main and arcing contact resistance curve
- voltage, current, pressure, temperature, etc.
- insertion resistance during the opening and closinga times of the breakers auxiliary contacts
The tests are executed under the control of CbaWin, runningunder any Windows.
http://www.zensol.com/brochure/MULTIFUNCTIONAL_CBA.pdfhttp://www.zensol.com/brochure/MULTIFUNCTIONAL_CBA.pdf -
7/29/2019 CBA Example Application 2012
5/38
How to get started? In order to execute the test, the circuit breaker has to be set off line.
The CBA-32P is connected via cables to both the computer and the breaker :
To the computer via optical fiber communication module
to the contacts of the circuit breaker via contact cables
to the control cabinet (open and close coils) via the command cables
Command-signals are sent from the CBA-32P to the control cabinet and the contacttiming is measured through the cables.
The contacts may have up to three possible states visualized in the CbaWin software:
Open (0)Resistive (0.5)Close (1)
All recorded data are automatically and instantaneously transferred to the CbaWinsoftware which analyses the data and displays the results of the tests in graphics andtabular formats.
-
7/29/2019 CBA Example Application 2012
6/38
EXAMPLE 1 : Timing Tests -Inoperative resistor
The insertion resistor does not work.
The spring on the moving contact is
broken and blocks the piston.
The broken spring has been replacedwith a new one and the device hasbeen reassembled.
-
7/29/2019 CBA Example Application 2012
7/38
EXAMPLE 1 : Timing TestsRebounds
Abnormal rebound on an auxiliary
(resistive) contact. The head on the
semi-mobile contact is loose.
The auxiliary moving contact has beendisassembled and the problem has been identifiedas a loose head. The head has been tightened andimmobilized with loctite and punching, followedby reassembly of the mechanism.
-
7/29/2019 CBA Example Application 2012
8/38
EXAMPLE 1 : Timing TestsDead Tank Missing Main contact
Case of an inoperative main contact onone phase (B), showing an open circuiton a close operation.
Disassembling the defective parts its been
possible to observe that a shaft, connecting the
actuating rod to the moving contact, had fallen
causing the contact piston to separate from the
actuating rod. The shaft has been replaced.
-
7/29/2019 CBA Example Application 2012
9/38
EXAMPLE 1 : Timing TestsDead Tank Bad damping
This timing diagram suggests a lack ofdamping at the end of the travel.
The damage was due to a defectivedashpot.
-
7/29/2019 CBA Example Application 2012
10/38
EXAMPLE 1 : Timing TestsValve in wrong position
The body of the valve has been installedat 90 with respect to its normal position,hence causing delays in the admission ofcompressed air. The closing time ofcontacts A-1 and A-2 results longer thanusual, as observed on their signals.
The body of the valve has beendisplayed in the correct configuration.The closing time of contacts A-1 andA-2 now corresponds to the one of A-3 and A-4, as observed in the newgraphic.
-
7/29/2019 CBA Example Application 2012
11/38
EXAMPLE 1 : Timing Tests Adjustmentscrew of hydraulic command incorrectly set
An adjustment screw is incorrectlyset, creating a 25 ms difference onone phase.
The problem has been solved afteradjusting the screw.
-
7/29/2019 CBA Example Application 2012
12/38
EXAMPLES 1 : Timing Tests Hydraulicactuator - Short circuit time
The admission restriction of thehydraulic actuator is such that the shortcircuit time on phase C is longer than theother phases.
The admission restriction of thehydraulic command has been adjustedin order to obtain synchronousoperation for all the phases.
-
7/29/2019 CBA Example Application 2012
13/38
EXAMPLE 1 : Timing TestsPneumatic Breaker Isolation time
Phase C is much quicker than the twoother phases.
The restriction on the inverter switchhas been adjusted in order to obtaincomparable times between phases.
-
7/29/2019 CBA Example Application 2012
14/38
EXAMPLE 1 : Timing Tests ShieldedBreaker
The travel course is not completed, (112mm instead
of 180mm). The piston starts moving 30 to 35
milliseconds after the main piston while the normal
delay is 20 milliseconds.
The problem is solved by increasing the appropriatediaphragm orifice by 0.020 inches. The prematurereopening of the resistor was due to the main contactclosing later. Besides, the curve shows a problem withthe upper piston (DpC) of the main contact on Phase C.This piston was overhauled prior to the timing test.
-
7/29/2019 CBA Example Application 2012
15/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
The circuit breaker tested in this example is a PK8D - ALSTOM
(800KV - 24 contact breaker)
The steps to execute the test are the following:
-1. Preparation of the breaker
-2. Installation of cables by human operators
-3. Connection of CBA-32P
-4. Execution of the test with test plans-5. Presentation and discussion of the results
-6. Conclusions
-
7/29/2019 CBA Example Application 2012
16/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
1. Preparation of the breaker: securing the site
The first step consists in the isolation of the breaker from the electricnetwork by means of disconnectors, which are displayed on each side of the
circuit. After isolation, the breakers are closed in order to ground the entire circuit.
In order to guarantee the maximum safety for the operators, it is highlyrecommendable to put the ground on each side of the breakers.
-
7/29/2019 CBA Example Application 2012
17/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Detail of disconnectors:
They isolate the circuit
from the line.
High voltagebreaker
Current
transformers
-
7/29/2019 CBA Example Application 2012
18/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
2. Installation of the cables
Operators proceed to the
installation of the cables
on the breaker
The installation is
typically performed with
the help of a bridge
-
7/29/2019 CBA Example Application 2012
19/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Yellow cable Red cable
Black cable
To the inputs of the CBA-32PExtensions for the connection of
the CBA-32PContact cables
-
7/29/2019 CBA Example Application 2012
20/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
3. Cables for the CBA-32P:
Command
cable
Extensions cables
Contacts cable
-
7/29/2019 CBA Example Application 2012
21/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Overview of the CBA-32P connection and components:
Portablecomputer
24 contact CBA-
32P
Grounding of
the CBA-32P
Command
6 analog inputs
Optical fibre link
-
7/29/2019 CBA Example Application 2012
22/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Optical fibre connection:
The optical fibre cable
puts in communication the
CBA-32P and the
computer
-
7/29/2019 CBA Example Application 2012
23/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Connection of the command cables:
The green cable commands the
opening of the breaker
Control cabinet
The red cable commands the closing
of the breaker
-
7/29/2019 CBA Example Application 2012
24/38
EXAMPLE: Time-travel tests on HVcircuit breaker
Connection of the CBA-32P:
The command cable mustbe connected here
Contacts cablesOptical fibre
Command cable
-
7/29/2019 CBA Example Application 2012
25/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Execution of the test: loading a test plan
-
7/29/2019 CBA Example Application 2012
26/38
EXAMPLE2 : Time-travel tests on HVcircuit breaker
Execution of the test: creation of a test link
Test link
-
7/29/2019 CBA Example Application 2012
27/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Test of the optical fibre link:
-
7/29/2019 CBA Example Application 2012
28/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Execution of a cable test:
Contact cable test
-
7/29/2019 CBA Example Application 2012
29/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Execution of a test for the cables connected to the breakers:
-
7/29/2019 CBA Example Application 2012
30/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Launching a test:
Launch the test
-
7/29/2019 CBA Example Application 2012
31/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
5. Presentation and discussion of the results:
Bad fixation of the cables (the
black clip is probably
disconnected)
The black clip falls during theclosing of the main contacts
-
7/29/2019 CBA Example Application 2012
32/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Closing test on a 24 contacts
-
7/29/2019 CBA Example Application 2012
33/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Opening test
-
7/29/2019 CBA Example Application 2012
34/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Close-Open test
-
7/29/2019 CBA Example Application 2012
35/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Problem on the A phaseContacts A01-A02 : We notice the
apparition of the insertion resistance on
the close side that could derive from a too
long safety time. The contact traces of
resistances have to be separated. In thisway, it will be possible to see the
complete resistance traces. If necessary,
the safety time can be readjusted. This
operation will require the dismantlement
of the resistances cables, and hence, to
work on the timing diaphragms.
In this case, the problem could be also
solved by increasing the timing. This is
possible since the opening time of this
contacts is quicker than the others on the
same phase.
-
7/29/2019 CBA Example Application 2012
36/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Open-Close-Open test
-
7/29/2019 CBA Example Application 2012
37/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
Problems on phase B
The isolation time of phase B is too
long: the timing of the pneumatic
inverter switch (52bb) is too long. Inorder to work on the timing, the
breaker has to be dismantled.
Note: A good way to test the 52bb
on the three phases is to perform an
O-C test with a delay of 20 ms
between the O and the C. Thismeans that the breaker has to be in a
close status till the end of the test.
-
7/29/2019 CBA Example Application 2012
38/38
EXAMPLE 2 : Time-travel tests on HVcircuit breaker
The results of any test can be visualized in Tabular report,
as follows: